PRECOMMISSIONING CHECK LIST

ELECTRICAL
EARTHING SYSTEM

Form : EARTHING SYSTEM

Unit NO :
User Group :

Estimated Time (MH) : Expended Time (MH) :

DW NO :

Subsystem :

ITEM CHECK LIST

1 Check all earth bars installation and tagging against drawings.


Check earthing cables installation depth and tagging against
2
drawings.
3 Check earthing cables cross section against drawings.
Check all connections are tight, clean and coated with an
4
approved anti-corrosive grease.
5 Check earthing networks segregation (IS)
6 Check earth rods correct installation
7 Produce marked-up drawings in accordance with installation.
Check Lightning air terminal installed as per the
8
Drawings/Specification.
9 Check connection earth cable/ electrode before backfilling.
10 Check continuity electrode-earth bar/ plant earth ring.
11 Check continuity electrode-earth pit to earth bar.
12 Check continuity of equipment loop protection conductors.
13 Check visual inspection before backfilling.
14 Check thermal connection insulation.
15 Check thermal connection before backfilling.
16 Check riser conduit installation with related drawing.
17 Check compression of connections.
18 Check insulation of compression connections.
19 Check dispatcher continuity and drawing.
20 Check earthing/ lightning Well (Pit) location as per drawings.
Check for corrosion on the exposed part of the electrod.
21
(greasing)
22 Produce a defect list for punch list issue.

N/A Not Applicable P Not accepted (Punch)  Checked & Accepted

REMARKS:

CONTRACTOR TPI / COMPANY

Sign
Name
Date