Sala Concerte Danemarca

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Design of a Concert Hall, Denmark

Max Baagoe Rasmussen, MSc, Civ. Eng., NIRAS, Copenhagen, Denmark; Mikkel Bramsen, MSc, Civ. Eng., NIRAS,Aarhus,
Denmark; Henrik Schiichter Andersen, MSc, Civ. Eng., NIRAS, Copenhagen, Denmark. Contact: mib@niras.dk
DOI I0.27 49/10168661 1X12910257 1027 58

Abstract
This paper describes the process of
designing a concert complex: from
the architectural visions of a flying
concrete meteor to the static calcula-
tions that made it happen. Because
of differential settlements from the
non-uniform underground conditions,
hydraulic jacks have been introduced
so that upward and downward adjust-
ments are possible for the concert
hall. Furthermore, the whole building
is covered by a complex two-sYstem
cable facade, where each cable sYs-
tem affects the other. Finally, dynamic
investigations have been conducted
for the huge balcony structures.
Keywords: concert hall; cable facade;
hydraulic jacks; post tensioning; con-
crete structure. Fig. l: Concert hall

Introduction
In 2009, the new Danish Concert Hall
won the IABSE Denmark's Struc-
ture's Award 2009,the European Steel
Design Award (ECCS) and many
other awards. From the beginning of
the project, it was questioned whether
it was possible to construct a flying
concert hall supported by slender col-
umns. Over the course of the project,
the architectural and acoustic solutions
have been uncompromising and have
challenged engineering calculations.
The building is situated in Copenha-
gen and is in fact an unPrecedented
spectacular building (Fig. 1)'

Fig. 2: DR Town
Architectural Visions
The concert hall is one of four seg- and function. The whole town is char- author Peter H@egh's "Smillas's Sense
ments, called DRTown (Danish Radio) acterised by transparency, light and of Snow", where a meteor has landed
(Fig.2) All segments were designed as openness. The purpose was to create a in glacial ice in Greenland, inspired the
an overall plan, but separate architec- climate where media production of the architect to cover the whole building
tural competitions were held for each future and creativity are united in an in a semi-transparent blue projection
segment. The four segments are con- inspiring environment. screen. Behind this screen the "flying
nected by an inner street. The idea meteor" is partially visible.
The architectural idea with the concert
for the project arose from the Middle hall is that, in an area where the sur-
E,astern Kasbah, which is a mix of roundings are very neutral and where
covered squares, markets, streets and
Description
a neighbouring environment has not
shops, where each neighbourhood has yet been created, the highest value that The meteor is the main concert hall
its own special character. can be created is the opposite-some- in the whole concert complex. It can
In much the same way, the buildings thing spectacular. This, together with accommodate an audience of uP to
in DR Town have their own identitY inspiration from the Danish national 1800 people (Fig.3).The meteor looks

Structural Engineering International U20LI Technical Report l0'7


Fig. 4: The meteor covereti with the shell cladding'View from the
Fig. 3: Inside the concert hall
foyer

of the staircase section in terrain. The curve height of 1,5 m, and also enable
like it is flying 30 m above the ground, tension forces to be transferred from
mainly resting on three slender stair- bottom of the concert hall is designed
as a large post-tensioned concrete slab, the leaning staircase 1 to the stiffer
cases. The main concert hall itself is and verticil staircase 3. Staircase 1
designed with a verY comPlex geom- which ipart from functioning as the
floor of the concert hall also ensures would not be stable without this sup-
etrv based on acoustic requirements' oort. In addition to this, the bottom
ThL load-bearing structure is like a the horizontal stability of the staircases
(Fig 6). olare ol the caisson slab structure is
walnut shell surrounding the hall and
bost-tensioned by horizontal cables
defining its acoustics and architec- The post-tensioned concrete slab is a 2 (tensioned to 2,5 MN), on average Per
ture. The structure consists of a steel m high caisson slab supporting the stage every 800 mm, to obtain the neces-
struclure covered by concrete. work- and inner seating areas. It spans 34 m sary strength and stiffness of the slab'
ing as a composite structure, but also across the foyer connecting staircase 1 The stiffness of the staircases does not
r"iu"s as the acoustic barrier against to staircase 3. The slab is constructed influence the cable forces.
the surroundings. To make this con- as a caisson slab to reduce weight. The
crele sphere look like a meteor' the structure consists of 300 mm thick top The remaining Part of the bottom of
surfaces are covered with a thin and bottom plates, and interior walls of the concert hall is made of large geo-
glass-fibre-reinforced concrete shell 300 to 500 mm thickness everY 5 m' metrically challenging steel structures'
cladding. The large open foyer area
Main oost-tension cables are inte- which are suPPorted bY the concert
is located right under the PrimarY hall shell structure. The concrete plat-
concert hall (Frg. 4). In the basement srated lnto the entire 48 m through
both staircases and the slab struc- form is spray-moulded on trapezoidal
there are three smaller concert halls/
ture. Two cables are located in each sheets thit are supported by the steel,
studios. Everything is covered by the
wall (each tensioned to 3,4 MN). The after which the structures function as a
blue screen, which is supported by an
almost invisible vierendeel steel frame cables partly suPPort the slab bY a composite structure.
structure.

Concert Hall
The concert hall itself is conslructed
as a concrete shell, "the meteor"' This
huse concrete shell measures 65 x 68 m
utrd is 34 m high. Its perimeter consists
of lining walls that are up to 18 m high
and 20b mm thick. Below the lining
walls a perimeter ring duct is located-
which, bisides working as torsion-stiff
supporting structure for the lining
wilis, also works as a ventilation duct'
The concert hall almost floats in the air
and is only supported by three stair-
cases and six imall columns (Fig' 5)'
As an example of the uncompromising
architecture, one of the staircase tow-
ers is designed to be tilted, such that
the reaction from the concert hall is
located far from the centre of gravity Fig. 5: Plan view

Structural Engineering International U2017


108 Technical RePort
a static load on 1,5o/" of gravity in any
horizontal direction. Due to the high
mass of the raised concert hall. seismic
loads are considered. which are the
design load for some supporting struc-
tures and directions.
The roof is concrete cast as shotcrete
on corrugated steel plates, which are
placed between the purlins.
This huge concert hall is not self-sup-
porting before the roof is cast, and
works as a shell construction (Fig.9):
hence temporary supports are placed
below the perimeter ring duct in the
construction phase.
Below the concert hall are located
studios 2, 3 and 4, to accommodate
540,7'70 and 240 persons, respectively
(Fig.10).T\ese studios are designed as
Fig. 6; Cross section a "box-in-box" solution, which means
that a steel box has been built in a
room limited by concrete walls. This
solution was chosen because of the
acoustics.
Balcony s Hat-sectron

Hydraulic Jacks
Apart from the three staircases below
the floating concert hall, there are six
Perimeter ring duct column supports to the north. These
columns are again supported by post-
Fig.8: Framework tensioned high concrete beams that
Fig.7: Balconies and lining walls
lead the forces past the 24 m wide
studio 2.
The top of the concert hall is covered a "hat-section" that fulfils the require-
This highly statically indeterminate
with a concrete slab, which is suP- ments. Because of varying heights and
structure is sensitive to creep, shrink-
ported by 12 individual steel trusses varying loads, the dimension of the hat-
age and differential settlements of the
with a maximum length of 47 m and a section also varies (Fig. B)
foundation. The non-uniform under-
height of 3,2 m to match. The girders ground conditions cause differential
Wind load is the dominating horizon-
are supported along the walls on steel settlements and with this a possibly
tal load. Seismic loads in Denmark are
columns. Steel was chosen to minimise
very low due to weak and rare seismic critical redistribution of the load, par-
the weight of the whole roof structure
activity in the area, and is calculated as ticularly regarding the columns.
and as a frame on which the concrete
roof and walls could be cast. The steel
truss structure also allows free pas-
sage in the large technical area that
is located between the ceiling and the
roof.
Between the columns, pre-fabricated
concrete panels are erected with
protruding bows, and the joints are
grouted (Fig. 7). Shear dowels are
welded to the steel columns, such that IiI:-
the connections to the concrete work g:
as a composite structure. !i-=:-: 3
)
The steel columns have different func-
7.1:":: 1
tions. They have to span between the ffi'.
perimeter ring duct and the roof, and
8,.
T.
resist the wind forces; work as a frame-
II
7
work for the concrete column that is cast 3.,
Kir
in the steel-section; and furthermore.
allow connection of the concrete lining
wall elements. The solution was to use Fig. 9: Horizontal stress distribution of the top of concert hall

Structural Engineering International u20ll Technical Report 109


with 88 brown fibre-reinforced con-
crete shells. All the shells are at differ-
ent angles and varying distances from
the concrete surface. The shells are sup-
ported by a secondary steel frame' This
iecondary frame is erected directly on a
variety of different primary steel frames,
of which the largest is 30 mz. The con-
nections between the primary lrames
and the concrete walls are achieved by
High bean a geometric complex support system'

_lL ___

litI Facade
lll,".li--,*i.
The facade has multiPle PurPoses.
To enable the outside viewer to see
Fig. 10: Longitudinal sectnn
the flying meteor through the facade,
the siruCture has to be as light and
transparent as possible. To cover the
The column reactions are glven m wholi complexiit took 15 000 m2 of
Fig. 12. The intentional column reac- this semi-transparent blue screen'
tions are the dead load plus half of the At night, the blue screen.works as a
Iive load. In the operational period, it is proiection screen, and pro1ectors posl-
'tion"O
ensured that the maximal design loads on the neighbouring buildings
are not exceeded. Column C6 has the and in sPecial towers Project both
same intentional and design load.There- moving and still images onto the blue
fore this column is critical as regards s.te"tt. Itt this way, the exterior of the
overloading, and it should be ensured concert hall is able to change character
that the load value is never exceeded. according to the event inside. Besides
Aftei the temPorarY supports are this, all foyer areas are to have large
removed, an inspection of the pressure glass facades.
in the iacks is carried out. Then the jacks To l-ulfil these requirements. a steel
are locked. During the construction frame surrounds the concert hall' The
period, until the commissioning of the structure consists of an external and
Fig. 11: Hydraulic jack
ioncert hall, all the jacks gradually an internal facade with an inter-space
increased the load until the intentional of approximatelY 2 m. On the exter-
column reactions were oblained (Fig. /3). nal facade the blue screen is attached,
In order to take this unwanted extra and on the internal facade the glass is
The pressures in thejacks were checked
load into account, hydraulic jacks are attached.
every month during the first year after
olaced between columns and the con-
commission. During the next year the
fert hall in the six supports to the north
insoections were reduced to every sec-
(Fig. 11) to ensure that the columns are The Facade Steel Cage
ond month. This was continued everY
not being overloaded.
6 months, and after 6 years when there
The main structure of the facade con-
The hydraulic jacks make it possible will be no more creep in the concrete
sists of an optimised steel cage, which
to adjust the column tops by up to +75 structures, the inspection will end.
is 50 m high,100 m long and 60 m wide
mm with a caPacitY of uP to 800 t Per
The hydraulic jacks function as fixed and consists of SHS260-Profiles'
column, thereby controlling the exact
mechanical supports during the peri-
force in each column. As requested by the architect, all are
ods between adjustments.
box se-ctions, which have been welded
The permanent deformations from together, with very few exceptions' It is
creep, shrinkage and differential set- a iequirement that all facade profiles
tlements are taken into account by Shells are placed either vertically or h.ori-
adjustments of the jacks in the first zont;ily, for which reason the stability
6yearsoftheoperationalperiodofTomaketheconcerthalllooklikea
sphere is covered is handled solely by vierendeel effect
the structure. meteor, the concrete
with the stress concentration in the
column beam junctions'
It was the architect's requirement that
Column C1 C2 C3 C4 C5 C6
the steel structures were to appear
Dead load 4t26 1147 2374 3412 4217 1000 with no other finish but Paint' The
1 000
Intentional load 4450 1860 2490 3600 4350 welded seams in the welded sections
DL+0,5xLL and joints therefore seem unground
1000
Desisn load 59'76 2805 3191 4532 s609
8000 2000
with a resulting rough aPPearance,
8000
Jack capacitY 8000 8000 8000 together with the characteristic con-
crete surlaces.
Fig. 12: Column reactions

Structural Engineering International U20ll.


110 Technical RePort
5000 Dynamics
4500
^
tr 4000
All five southern balconies in the
; 3500
concert hall are large steel structures
.€ 3ooo
fi zsoo with a special geometry. Theoretical
: 2ooo dynamic modal analysis was carried
E lsoo out for the platform steel and a lowest
E
o 1000
soo eigenfrequen cy of 4,3 Hz was found for
0 the corresponding vertical oscillation.
99€rrrrrrr€
O-Of,OOCOOOO
OOCOOOOOCOO
NNNNNdNNNNN
Furthermore, an independent check
x=-=aa9.*q-: was undertaken of peak accelerations
+oo€o@r9nso and dynamic impact on the structure.
NFNFCN:ONiO

Date If a peak acceleration limit of 15%


Fig. 13: Inspection of pressure in jacks of gravity was decided upon, and a
fundamental frequency >3,4 Hz with
relative damping of 0,06 was recom-
mended, <3,0}{2 would be very critical.
The structure was analysed for rhyth-
mic crowd loading, simulating persons
jumping in a time history study, and
maximal accelerations below L5"/o of
gravity were found. It is important to
calculate the exact eigenfrequency and
damping for the structure because the
acceleration is sensitive to these val-
ues. Therefore, subsequently frequency
measurements were carried out by a
to ensure the integrity
full-scale test
Fig. 14: Internal facade with pre-tensioned Fig. 15: Glass facade and comfort of the structure under
rods rhythmic load. The test included a
huge mass that hung from the platform
steel. The mass was released and the
The columns in the facade are stabi- where the cables lean at an angle of platform started to vibrate (Fig. U).
lised with a beam every 15 m. In order 45" (Fig.15). This glass/cable structure Eigenfrequency of 5,2 Hz and relative
to give the structure lightness, stiffen- resists the wind forces on the glass as a damping of at least 0,04 were measured
ing with diagonals has not been carried membrane effect-like the strings in a in this test. This result satisfied the
out. Naturally, the result is that all beam tennis racquet. The mounting and pre- requirement of eigenfrequency >3,4
column joints are made moment-stiff tension of 150 kN of the cable system Hz. A time history analysis showed
as a welded solution. Due to the fact take place only after the mounting of that the acceleration was 13% of grav-
that columns with a length of 15 m in the horizontal pre-tensioned rods, the ity for the high eigenfrequency of 5,2
this structure are sensitive to stability result of which is that the force in the Hz and a relative damping of 0,04. It
problems, the columns are further sta- pre-tensioned rods changes. is, of course, still difficult to say exactly
bilised with pre-tensioned rods every 5 what the true eigenfrequency for the
To determine the interaction and ten-
m. Each rod is tensioned to a force of structure is, because at the time when
sion procedure for the stabilising ten-
50 to 250 kN depending on its position the full-scale test was made the struc-
sion rods and the cable grid for the
in the structve (Fig.14). ture was not completely cast together,
glazed facade, which are both supported
so the mass and stiffness were still sub-
The columns are placed with a spacing by the same steel structure, a variety of
ject to change. It is also well known
of 9,8 m in the internal facade and 4,8 complex step-by-step calculations have
been accomplished (Fig. 16).
that damping increases in a room with
m in the external facade.
people, compared with room without
Between the facade and the concert The large tension coming from the people.The true dynamic impact on the
hall, another steel structure supports cable grid at its perimeter is supported structure can therefore actually only
the glass roof above the foyer. The by the bending in the large beams. be realized by a full-scale test during
joints towards the concert hall are
designed as acoustic damped bearings
and have a natural frequencv lower
than 10 Hz.

Glass Facade
In all of the foyer areas, the internal
facade are mounted with glass pan-
els in a diagonal grid of 1,7 x 7,1 m.
Again, in order to give lightness to the
structure, the glass panels are mounted Fig. 16: Facade steel. (a) Glass roof steel. (b) Horiz.ontalpre-tensioned rods. (c) Cable net
directly onto a diagonal cable net, in foyer areas

Structural Engineering International U2011 Technical Report 111


Fig. 17: Fttll-scale dynamic test of balconies

Fig.20: Casting of walls

a concert with the true mass, stiffness tuned mass dampers (TMD). After
and damping. This has not been done, the complex dynamic interaction was
but the above investigations and analy- monitored during actual use, some of
sis showed that the eigenfrequency is the longest stairs in the foyer areas
definitely larger than 3,4 Hz and the were prepared to be installed with up
damping is at least 0,04. Hence, the to three 500 kg tuned mass dampers.
vibrations turned out to be a non-issue.
Erection
The slender walkways, stairs and esca-
Fig. 18: Perimeter ring lators are suspended in the foyer area. The sequence for the concert hall
In order to meet the architect's high started by erecting the three stair-
requirements for slenderness of the up cases and columns. Then the perimeter
to 2J m long spans, these steel struc- ring duct was cast all the way around
tures were prepared with openings for (Fig. 18) simultaneously with the large

Fig. 19: Erecting sequence Fig.21: Construction of lacade

I12 Technicai Report Structural Engineering International U20L1,


concrete slab between the staircases. and high strength concrete, steel and
Steel columns and roof trusses were cables were mainly used everywhere. SEI Data Block
erected on top of the perimeter ring
and the concert hall was cast (Figs. 19 The very slender facade construction Owner:
and 20). At the same time, the steel was designed to handle large deforma- Danish Broadcasting Corporation (DR)
for the platform structures had to be tions. and the interaction between the
different facade systems made it neces- Architectttral des ign:
hoisted into the hall and hung on the Ateliers Jean Nouvel
perimeter ring.Then the walls sary to solve complex non-linear stabil-
ind rool'
were cast, and after completing most ity effects in many different load cases. Structural design:
of the roof and the structure was found The interaction in the facade is in fact NIRAS A/S
stable, all the temporary supports were exceptional. From the very beginning,
Acoustical design:
removed. Construction of the facades the main target for all structures in the Nagata Acoustics
then commenced (Fig. 21). concert hall was to meet the require-
ments of the architectural design and Main contractor:

Conclusion
the acouslics. These requiremenls M.T. H@jgaard
made it necessary to arrive at complex Cable facade contractor:
It was indeed a challenge to design the
concrete and steel solutions and chal_ Waagner Biro
concert hall. Use of finite element pro- lenged the static, dynamic and fabrica-
tion tasks. Steel (t): 3500
grams and computers in general were
Concrete (m3): 18 000
a crucial factor. The planning of how Overall, it was a pioneer project that Post tension cables (m): 2200
all structures would work together in increased the expectations for what is Reinforcement steel (t): 3600
this huge concert complex was a com- possible to build in future and heloed
Total cost (EUR million): 220
plicated job. Every single corner of this to place Copenhagen on the archiiec-
building was considered and discussed. tural and structural world map. Service date: January 2009

Being a Member of TABSH brings you together...

Companies,
increase their access to visibility within the worldwide structu ra I engi neeri ng
community, and to new i nform ation, new pers pectives and new contacts.

..tell you r colleague.

www.iabse.org

Structural Engineering International 1lZ0lI


Technical Report 113

You might also like