Project : Aqaba Screening Project

Day : Thu
Date : 07.01.2021
Department : Electrical
Tasks Done by Today
1
Cable Ladder Support Fabrication and Installation at Level 58.975
2
Fixing nd releveling the Cable ladder damaged by truck at level 36.135 under conveyor 502

3
Painting The Conduit Mounting Accessories
4
Engineering : Follow Up the Lighting Panel With Supllier
5

Next Working day

1
Engineering: Finalizing the Dedusting and Marshalling Submittal with VoltAutomation
2
Engineering : Follow Up the Lighting Panel With Supllier
3
Assembly the Lighting Junction Box for T09 Stair case
4

Issues/ Requirements

Staff

Name Daily Working


Hours Over Time Hours
1
Supervisor 8
2
Technician (1) 8
3
helper (2) 8
4

10

11

12

Resp. Engineer: Ahmad Dagamseh