Professional Documents
Culture Documents
Lesson 9: Benefit/Cost Analysis and Public Sector Economics: Prof - Jessica Maria Paz S. Casimiro, Ce, Enp, Disds
Lesson 9: Benefit/Cost Analysis and Public Sector Economics: Prof - Jessica Maria Paz S. Casimiro, Ce, Enp, Disds
Lesson 9: Benefit/Cost Analysis and Public Sector Economics: Prof - Jessica Maria Paz S. Casimiro, Ce, Enp, Disds
Conventional B/C:
𝒃𝒆𝒏𝒆𝒇𝒊𝒕𝒔 −𝒅𝒊𝒔𝒃𝒆𝒏𝒆𝒇𝒊𝒕𝒔
B/C=
𝒄𝒐𝒔𝒕𝒔
Selection guideline:
∆𝐵
If 𝐶 ≥ 1.0, choose the higher-cost alternative, because its extra cost is
economically justified.
∆𝐵
If < 1.0, choose the lower-cost alternative.
𝐶
Interpretation:
The Open Channel alternative is the design to be justified. The AW
equivalent of all costs will be utilized. Benefits will consist of the
savings generated due to the selection of the Open Channel design. This
is a form of implied benefits based on usage cost estimates.
Calculation:
The Open Channel design has the higher-cost alternative, it
must be incrementally justified against the sanitary sewers
design:
AWOC = 53,000,000(A/P,8%,20) = 5,398,050
AWSS = 26,000,000(A/P,8%,20) = 2,648,100
∆𝐶 = 5,398,050 − 2,648,100 = 2,749,950
Benefit: annual savings generated due to Open Channel design
∆𝐵 460,000−30,000
= = 0.16 < 1.0
𝐶 2,749,950
Solution:
The AW method is appropriate for unequal life comparison. The higher-
cost alternative which is Project I will be compared to Project II. The
incremental B/C will determine whether the additional cost is justified.
AWI =750,000(A/P, 9%,35)+120,000 = 190,977
AWII = 625,000(A/P,9%,25)+110,000= 173,629
Project I Project II
Capital investment, $ $750,000 $625,000
Annual M&O, $ per year 120,000 110,000
Annual Benefit 245,000 230,000
Useful life of project 35 25
Interpretation:
The AW method is appropriate for unequal life comparison. The higher-cost
alternative which is Project I will be compared to Project II. The incremental B/C
will determine whether the additional cost is justified. One project must be
selected.
Calculation:
AWI =750,000(A/P, 9%,35)+120,000 = 190,977
AWII = 625,000(A/P,9%,25)+110,000= 173,629
∆𝐵 245,000 − 230,000 15,000
= = = 0.86 < 1.0
𝐶 190,977 − 173,629 17,348
Decision:
The lower-cost alternative Project II should be selected.
Alternate solution: B/C analysis
Project I Project II
Capital investment, $ $750,000 $625,000
Annual M&O, $ per year 120,000 110,000
Annual Benefit 245,000 230,000
Useful life of project 35 25
Analysis:
Calculation:
Both projects have B/C ratios greater than 1
Project I
245,000
and are therefore economically justified
B/C = 190,977 = 1.28 since B/C for both are greater than 1 but
Project II Project II has higher B/C.
230,000 However, the additional cost of Project I is
B/C=173,629 = 1.32
not economically justified.
Decision:
Select Project II.
Incremental B/C: Multiple alternatives
Steps:
1. Determine the equivalent total cost for all alternatives: Use PW, AW or FW
equivalencies.
2. Order the alternatives - smallest to largest.
3. Determine the total benefits ( and any disbenefits estimated) for each alternative.
4. Direct benefits estimation only: Calculate B/C for the first ordered alternative. If B/C
< 1.0, eliminated it. By comparing each alternative to DN in order, we eliminate all
that have B/C < 1.0. The lowest-cost alternative with B/C ≥ 1.0 becomes the
defender and the next higher cost alternative is the challenger in the next step. (For
analysis in the spreadsheet, determine the B/C for all alternatives and retain only
acceptable ones.
5. Calculate incremental cost (∆𝐶) and benefits ∆𝐵 using the relations:
(∆𝐶) = challenger cost – defender cost
∆𝐵 = challenger benefits – defender benefits
6. Calculate the ∆𝐵/𝐶 for the first challenger compared to the defender. If ∆𝐵/𝐶 ≥
1.0, the challenger becomes the defender and the previous defender is eliminated.
Conversely, if ∆𝐵/𝐶 <1.0, remove the challenger and the defender remains against
the next challenger.
7. Repeat Steps 5 and 6 until only one alternative remains. It is the selected on.
Incremental B/C (∆𝐵/𝐶)
There are two types of benefits- direct benefits, and implied
benefits based on usage cost estimates.
If alternatives are unacceptable, the DN alternative is the choice.
All costs are considered positive in B/C calculations.
The terms defender and challenger alternative are used in this
procedure, as in ROR analysis.
If relative usage cost are estimated for each alternative, rather
than direct benefits, ∆𝐵 may be found using the relation:
∆𝐵 76−52 24
Defender D, Challenger C: = = = 0.83 < 1.0 eliminate C, retain D
𝐶 72−43 29
∆𝐵 84−52 32
Defender D, Challenger F: = = = 0.84 < 1.0 eliminate F, retain D
𝐶 81−43 38
Like ROR and B/C analyses, the CEA requires the ordering (ranking) of
alternatives prior to selection and the use of incremental analysis for
mutually exclusive alternative selection.
Steps for Cost-effectiveness analysis
(CEA)
1. Determine the equivalent total costs C and effectiveness
measure E, and calculate CER measure for each project.
2. Order projects from the smallest to the largest CER value.
3. Determine the cumulative cost for each project and
compare with the budget limit b.
4. The selection criterion is to fund all projects such that b is
not exceeded.
Example 5. Cost-effectiveness analysis
9.48/257
The cost in $/year and effectiveness measure in items salvaged
per year for four mutually exclusive service sector alternatives
have been collected as shown. (a) Calculate the CER for each
alternative. (b) Use the CER to identify the best alternative.
Step 1 Step 2
Cost C, Salvaged
Alternative CER Rank
$/year Items/year , E
W 355 20 17.75 3rd
X 208 17 12.23 2nd
Y 660 41 16.09 Highest
Z 102 7 14.57 Lowest
Step 3
Ethical Challenges in the Public
Sector
The results of the B/C or CEA analysis are routinely depended upon by
public officials and staff members to assist in making public planning
decisions.
Three of the foundation elements upon which engineers should use their
recommendations to decision-makers.
1. Impartiality
2. Consideration for wide range of circumstances.
3. Use of realistic assumptions.
Note: You are expected to come up with a UNIQUE solution to the above problems. This
can only be done if you work independently. Compare your answer with those in the
Solution Manual. If you copied from the manual, your solution will not be unique, of
course!