Method Of Statement
1
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
CONTENTS
1 . INTRODUCTION.................................................................................... 3
2 . SCOPE .................................................................................................. 3
3 . REFERENCE DOCUMENTS ................................................................... 3
4 . Work Location ..................................................................................... 3
5 . WORK PREPARATION .......................................................................... 4
5.1 . GENERAL PREPARATION................................................................ 4
5.2 . LIFTING OPERATIONS - GENERAL.................................................. 5
5.3 . FORMWORK – GENERAL............................................................... 5
5.4 . CONCRETE MIX DESIGNE............................................................... 5
5.5 . MATERIALS.................................................................................... 6
5.6 . CONCRETE CASTING...................................................................... 6
5.7 . EXCAVATION, BACKFILLING & COMPACTION................................ 7
6 . RISK ASSESMENT................................................................................. 8
7 . MANPOWER........................................................................................ 8
8 . EQUIPMENTS....................................................................................... 8
9 . WORK EXCUTION................................................................................ .9
9.1 . Valve box for 48” line, (TV124)......................................................9
9.2 . PIPE SUPPORTS FOR 16 INCH AMNA RELIEF LINE (ST 5 – 6)........ 14
2
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
1 . INTRODUCTION
Due to unavoidable incident that happen on Ras Lanuf Terminal previously which affects the Tank
Farm area, Storage tanks and associated piping’s, Harouge Oil Operation will be replacing the
concrete Valve box for 48” line, (TV124). This 48” valve box was badly affected and concrete valve
box has been demolished. The 48” valve was already replaced, therefore, concrete valve box is
necessary to have access to this valve.
Furthermore, two relief lines shall also needed to be installed/constructed connecting Storage Tank
no. 5 to 6, (AMNA) line and another relief line to connect from Storage Tank no. 13 line to Storage
Tank no. 10 (MESLA) line by-pass.
2 . SCOPE
This Method statement describes in details the sequences of work activities and the assigned
resources (all necessary manpower , equipments and materials )to be implement in the
construction of the mentioned 48" 124 TV valve box (sludge removal , excavation, formwork ,
casting concrete) and 16" relief line pipe supports (survey work layout and elevation, excavation,
formwork , casting concrete) .
3 . REFERENCE DOCUMENTS
Contract Schedule A Scope of work
Bonatti As-Built Drawings Valve Boxes 36/2 – 36/3 – 36/6 Details.
ACI 305 American Concrete Institute ,Specification for Hot Weather Concrete.
ACI 318 American Concrete Institute ,Building Code Requirements for Structural Concrete and
Commentary.
ASTM A82 Standard Specification for Steel Wire , Plain ,for Concrete Reinforcement.
4 . Work Location.
Work site will be at Libya –RasLanuf Tank Farm to Complete procurement and construction of civil
works at Ras Lanuf Tank Terminal.(see sketch No#01)
3
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
5. WORK PREPARATION.
5.1 GENERAL PREPARATION
Work area will be provided with all signage and warning equipments relevant to
work type for example traffic cones , plastic chain , signage indicate work site and
signage to indicate excavation work.
Work area shall be clean and safe for all work activities , transportation , manpower
and machinery movement around the site.
During the work time only essential personnel are allowed to have access the work
area.
Supervision team and Safety supervisor should implement all necessary actions and
precautions to guarantee safe work activities.
All risk and hazardous conditions and situations are to be detailed and
mitigated in the risk assessment.
4
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
New trial mixed shall be conducted for new concrete design, must be grade C40 tested
after 28 days, as per ACI 318 requirements, mixed design must be approved, trail mix
must be conducted and witness by the client (HOO).
5
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
5-5. MATERIALS
All aggregate (fine & coarse ) cement must be properly stored to avoid contamination of
foreign materials.
A- Cement
Cement must be sulphuric resistant , Portland cement (ASTM type II) .
Source : ALMERGEB – ALKHOMS – LIBYA.
B- Aggregate
Crushed Gravel must be hard , durable, clean and free from adherent coating such as
clay.
Fine Aggregate (Sand) must be clean and washed , not contain harmful materials which
have bad effect on strength or durability of concrete or any substances, which may attack
the reinforcement , Desert sand will on be used.
Source : EJDABYA – LIBYA.
C- Water
Potable water shall be used for mixing concrete.
Source : Harouge Oil Operation – RasLanuf.
D- Admixture
Sikament-163 (High Range Water Reducing Concrete Admixture) used as a highly
effective water-reducing agent and super plasticizer for the production of high quality
concrete in hot climates.
The dual action of Sikament-163 promotes accelerated hardening with high early and
ultimate strengths.
Application Dosage : (0.6-2.5)% of Cement Wight.
Complies to: ASTM C-494 Type F and B.S. 5075 Part 3 for super plasticizer.
E- Reinforcing Steel
All reinforcing steel must be new and free from rust/corrosion .
Reinforcing tie must be number 18 minimum size, if smaller must be double warp.
5-6. CONCRETE CASTING
- Concrete casting must be done in segment, so as maximum concrete free fall inside
the formworks must not more than 1500mm in height.
- Concrete placement must be done not more than 600mm in thickness and spread
around the form equally.
- Proper treatment on the concrete joint prior additional concrete must casted,
roughening the old concrete surface , cleaning and application of bonding
agent/grouted.
- Proper scaffold must be prepare around the formworks for casting concrete .
6
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
- An experience and skilled team shall only allowed to casting concrete, to follow the
approved concrete mix design quantities .
- Proper concrete vibrator must be provided and inspected before casting concrete.
- An experience and skilled concrete vibrator operator shall only allowed to operate the
equipment, to avoid segregation of mix.
- Concrete curing must be properly observe, by means of water curing, a hessian burlap
must be warp to keep the concrete moist all the time.
- All concrete defects must be treated prior application of water proofing membrane,
and must be applied after concrete attain its required compressive strength, minimum
of 7 days.
7
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
6- RISK ASSESMENT.
The following items identify the anticipated inherent risks associated with
carrying out the works.
Transportation of equipments / Materials
Personnel / materials hit by vehicles.
Operative falling/tripping.
Excavation.
Falling Objects
Manual handling
Form work (Shuttering and steel fixing)
Casting Concrete.
Scaffolding/ Ladders
H2S-Gas
Weather.
See annex.1 Risk Assessment.
7. MANPOWER.
During the work time only essential personnel are allowed to have access the work area.
Site Manager
Civil Engineer
Safety Officer
Site Supervisor
Banksman
Crane operator
Truck driver
Carpenter
Steel Fixer
Mason
Plasterer
Skilled Labours (5 Nos.)
8. EQUIPMENTS.
All the equipments , devices and tools to be used for this work activities shall be certified
and in good conditions.
Crane 40T
High-Up Truck
Dump Truck
Concrete Mixer
Concrete Vibrator
Air Compressor
Level Instrument
8
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
Hand tools
Electric saw
Steel cutter
Steel benter
Fire extinguisher
Scaffold / ladder
Grinding Machine
Welding Machine
Healthy
9. WORK EXCUTION.
9-1 . Valve box for 48” line, (TV124).
According to Valve box sketch (Contract Drawings) the dimensions of valve box will be :
From outside to outside , Length = 4500 mm, Width = 3500 mm and Depth = 4950 mm
Steel Cover = 50 mm , Thickness of walls = 250mm , Thickness of floor slab = 300 mm
Dimensions of valve foundation = 1800 mm Length X 1640 mm Width X 300 mm Depth
Type of Box Cover = Primed And Painted Steel Structure.
9
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
10
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
2 – Provide containment wall (Barrier) and divert the flow of oil from pressure relief valve to
avoid contamination of work area (see sketch No#02).
3 - Removing of all sludge inside the pit to get clean and safe area for work.
4 - Provide adequate support, reinforced the pipe line with suitable materials ,I beam and
pre-casted concrete foundations (see sketch No#03) .
11
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
5 - provide shoring or benching around the valve box as temporary supporting during work
activities to protect workers if collapse occur.
- Option #02 Continue with excavation to get the undisturbed soil materials, provide a
polythene sheets 200 microns and lean concrete.
8- Casting Lean concrete with minimum thickness of 100mm and grade C25 .
9- Prior casting structural concrete for slab and wall (will be grade C40 tested after 28 days,
as per ACI 318 requirements), mixed design must be approved, trail mix must be conducted
and witness by the client, and must be followed in the entire construction works :
B - Provide a sump pit with dimensions of , 300mmX300mm in size and 250mm depth , and
location to be determined on site.
C- Provide a keyway on joint between floor slab and wall.(see sketch No#04)
12
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
D - Annular space between pipe and pipe sleeves will be properly sealed with sika materials
or approved equivalent approved by HOO engineer.
E - Concrete casting must be done in segment, so as maximum concrete free fall inside the
formworks must not more than 1500mm in height.
F - Concrete placement must be done not more than 600mm in thickness and spread
around the form equally.
G - Proper treatment on the concrete joint prior additional concrete must casted, roughening
the old concrete surface , cleaning and application of bonding agent/grouted.
H- Proper scaffold must be build around the formworks of valve box for casting concrete .
I - An experience and skilled team shall only allowed to casting concrete, to follow the
approved concrete mix design quantities .
J - Proper concrete vibrator must be provided and inspected before casting concrete.
K - An experience and skilled concrete vibrator operator shall only allowed to operate the
equipment, to avoid segregation of mix.
L - Concrete curing must be properly observe, by means of water curing, a hessian burlap
must be warp to keep the concrete moist all the time.
M - All concrete defects must be treated prior application of water proofing membrane, and
must be applied after concrete attain its required compressive strength, minimum of 7 days.
10- Steel valve pit cover and steel members including ladder will be fabricated and coated
by epoxy coating materials and HOO approve procedures.
11- Backfilling materials shall be of selected fill, free from rocks/ stones larger than 500mm
in size and foreign materials.
12 - Backfilling & compaction around the valve bit must be done in layers 150 mm lift and
tested up to 92% based on modified proctor density, after bituminous coating application has
been properly dried.
13 – Around the pipes shall be backfilled with clean sand materials 300mm around the
pipes, prior additional backfilling with fill materials, sand will be compacted by means of
water flooding.
13
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
construction of new concrete support (preferably pre-cast) for the new line,
construct/installed as per drawing reference number 1401/3/50/100 sheet 1&2,
1401/3/54/100 sheet 1&2 & detailed drawing number SK100918-1013.
HOO will supply the required 16 inch pipe saddle support embedded on concrete
foundation; strapped type pipe saddle support’s location shall be site determined (total –
21 nos.).
14
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
15
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
Construction of new concrete supports (preferably pre-cast) for the new line,
construct/install as per drawing reference number 1401/3/50/102, 1401/3/54/102 and
detail drawing SK100918-1013.
HOO will supply the required 16 inch pipe saddle supports to be embedded on concrete
foundation ; strapped type pipe saddle support’s location shall be site determined
(total – 2 nos.).
16
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
According to drawings (Drawing No. SK 220918 - 0344 New MESLA 16"RELIEF LINE TO ST-10
INSPECTION BOX), dimensions of inspection box from inside to inside will be :
Length = 3000 mm , Width = 1375 mm , Depth = (Field determined ) Walls thickness = 150mm, floor
slab Thickness = 300 mm, Type of Cover = chequered plate removable cover.
Drawing No. SK 220918 - 0344 New MESLA 16"RELIEF LINE TO ST-10 INSPECTION BOX.
17
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
Drawing No. SK 220918 - 0344 New MESLA 16"RELIEF LINE TO ST-10 INSPECTION BOX.
18
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
19
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
20
Method Of Statement
CONSTRUCTION OF 16” AMNA, MESLA RELIEF LINE
PIPE SUPPORTS and 48” TV124 VALVE BOX
21