Construction of Boundary Pillar

Engineer's Estimate

Unit Rate Current Amount


Sl # Item Code Description of Items Unit Quantity Ref
(Tk) Rate (Tk) (Tk)
Mobilization &
1 01.4 sqm 400.00 128.00 154.88 61,952.00 PWD
Demobilization
2 04.180 Site Development sqm 200.00 30.35 30.35 6,070.00 BWDB
Earthwork in Foundation
2 02.1.3 Excavation cum 160.00 96.00 116.16 18,585.60 PWD

3 02.10.2 Sand Filling cum 150.00 1,043.00 1,262.03 189,304.50 PWD


4 03.1 1 layer Brick Flat Soling sqm 57.00 355.00 429.55 24,484.35 PWD
5 44-200 Casting Yard cum 200.00 660.54 660.54 132,108.00 BWDB
6 07.4.4.1 Concrete cum 17.00 10,203.00 12,345.63 209,875.71 PWD
7 07.4.4.2 Formwork sqm 285.00 373.00 451.33 128,629.05 PWD
400-Grade Deformed Bar
8 08.1.2 100kg 35.50 8,699.00 10,525.79 373,665.55 PWD
(fy=400Mpa)
Carriage including
9 08-150-60 loading, unloading & cum/km 125.00 687.52 687.52 85,940.00 BWDB
stacking

Labour charge for placing


10 NA each 182.00 LS LS 20,000.00 NA
the pillars in position

Total 1,250,614.76

Note:
Note: PWD Rate 2014 with inflation rate @6.5% per year
BWDB Rate: 2016-2017