Montecarlo Limited Budget Change Request: General Details

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Montecarlo Limited

Budget Change Request

General Details
Request No. : BF/3240/MOC/BCR/0008
Vertical : Building & Factories Project : 3240-Dakshinkhanda Building Project
Department : Project Requester : Anshu Kumar
Position : General Manager Title : For Inter department change of staff and for
extension of staff
Location : 3240 Date : 04-Jan-2021
Estimate Time Impact : 3 month Estimate Cost Impact : 524049
Required Implementation Date : 04-Jan-2021 Status : Approved by Project Head
Full Description of changes For Inter department change of staff and for extension of staff and card holder
Justification & Benefits It will help smooth work progress.
Consequences of date not it will be very difficult for site team for smooth progress.
being met
Change Impact TM - Project - EHS-148500
Assessment WelderS3 -59874
HelperS3-49500
MechainicS3-81675
Survey - AsistantS3-49500
Helper27000
Helper81000
Helper27000
Total 524049
Comments & Status History
Approved by PH System Administrator (Project Head) on 07-Jan-2021
Auto approved by system after 1 days
Approved by HOD System Administrator (HOD) on 06-Jan-2021
Auto approved by system after 2 days
Submitted By Anshu Kumar (Project Manager) on 04-Jan-2021
Attachment(s)
Sr. No File Name(s)
1 CRN For Staff 3240 Revised.xlsx

Note: This is electronic system generated report.