AN TYRES

DETAILS AND ESTIMATE


Existing building
Proposed Design
Proposed Design
Elevation Specification
Building Costing
S NO DESCRIPTION QUANTITY PRICE PER UNIT AMOUNT
01 A.C.P 3mm wooden sheet 32 sqft Appx. Rs. 250 Rs. 8,000
(for invisible part)
02 A.C.P 3mm wooden sheet 210 sqft Appx. Rs. 290 Rs. 60,900
(for visible part)
03 LED glowing letters 16 sqft Appx. Rs. 850 Rs. 13,600

04 Inner electrical works and ceiling lights and wall sconces - Rs. 8,500

05 Scaffolding - - Rs. 4,000

06 Bathroom 7’x4’ = 28 sqft Rs. 900 Rs. 25,200


07 Transport - - Rs. 2,000

08 Architect fees 336 sqft of elevation work Rs. 30 Rs. 10,080


09 Total amount - - Rs. 1,23,280
Terms And Condition
All the images shown in rendered image are shown just for the representative purpose.
Actual design of the building may vary with respect to the site conditions and material
availability.
Architect fee of Rs 10,080 and 50% of the building cost (Rs. 61,500) should be paid in
advanced before the execution.
The construction time will be 10-14 days depending upon the site condition.