Mechanical Cartridge Seal

Air Pressure Test


Procedures

Fluid Containment and


Control Specialties for
Industry
Step # 1
Mechanical
Seal

Test Rig

Test Bung Test


Sleeve/
Housing

Gather all necessary equipment for Testing


Fluid Containment and
Control Specialties for
Industry
Step # 2

Process End

Atmospheric
End

Put the completed cartridge seal


onto the test rig as shown
Fluid Containment and
Control Specialties for
Industry
Step # 2 Cont

Nuts

1/16” Gap

Adjust the heights of the nuts, so that the seal is


about 1/16” above the bottom test plate.

Fluid Containment and


Control Specialties for
Industry
Step # 4

Test
Bung

Sleeve
O’Ring

Put the test bung into the end of the sleeve. Ensure
that there is an o’ring in the sleeve.

Fluid Containment and


Control Specialties for
Industry
Step # 4 Cont

Test Bung installed into the cartridge sleeve.

Fluid Containment and


Control Specialties for
Industry
Step # 5

Test
Sleeve/Housing

Install Test Sleeve/Housing


over the end of the seal as shown.

Fluid Containment and


Control Specialties for
Industry
Step # 5 Cont

Test Sleeve/Housing installed .

Fluid Containment and


Control Specialties for
Industry
Step # 6

Assemble the top half of the air test rig.

Fluid Containment and


Control Specialties for
Industry
Step # 6 Cont

Install the nuts to the test rig and tighten.

Fluid Containment and


Control Specialties for
Industry
Step # 6 Cont

Fluid Containment and


Control Specialties for
Industry
Step # 7

Attach the compressed air line and proceed with the


air test.

Fluid Containment and


Control Specialties for
Industry
Air Test Procedure

• Test Pressure: 25 psi of air

•Test Duration of 5 Minutes


•Acceptable Air Loss of 2 psi Maximum
•When the seal is first pressurised allow the test pressure to
settle and stabilise (this may take a few seconds).