Professional Documents
Culture Documents
BBC Programme Business Case Template and Guidance October 2019
BBC Programme Business Case Template and Guidance October 2019
<Agency Name>
<Programme Name>
Prepared by:
Prepared for:
Date:
Version:
Status:
Document ID
Document owner
Issue date
Filename
Document History
Version Issue date Changes
Document Review
Role Name Review Status
Programme Manager
Document Sign-off
Role Name Sign-off Date
Senior Responsible
Owner/Project Executive
<Agency name>: <Programme Name>
Contents
On completion of PBC development, update this ToC after deleting the Guidance sectionsi
Before you start: Programme Business Case (PBC) overview <go to PBC
planning guidance>.....................................................................................................4
Executive Summary....................................................................................................6
The Strategic Case – making the Case for Change <go to guidance>....................10
The Economic Case – Exploring the Preferred Way Forward <go to guidance>.....17
Annexes.....................................................................................................................30
Annex 2:....................................................................................................................32
Annex 3…..................................................................................................................33
Annex X:....................................................................................................................34
Commercial Case......................................................................................................62
Financial Case...........................................................................................................66
Management Case....................................................................................................68
Annex 4: References.................................................................................................78
This document provides both a template and guidance for completing a Programme
Business Case (PBC). It sets out good practice for a programme business case, but
organisations and writers need to test the relevance at each step. Some sections will not be
relevant for some cases, and in other instances, topics should be addressed which are not
included in this document. The primary driver must be whether the information is
required to inform the next decision-point; for a PBC, this is Cabinet:
Agreement in principle to the preferred way forward
Approval to develop subsequent tranche and/or project-based business cases
(Detailed Business Case or Single-Stage Business Case, as appropriate).
Purpose of the Programme Business Case
A Programme Business Case follows from the Programme Strategic Assessment (SA),
which justifies the need to invest in change.
The primary purpose of the Programme Business Case is to support the decision to invest in
a programme of change that optimises potential value for money. It provides an early
opportunity for the organisation and key stakeholders to influence the direction of the
investment proposal, and to avoid the agency putting too much effort into developing
investment proposals and options that should not proceed. A PBC:
confirms the need to invest and the case for change, the strategic context and how the
proposed investment fits within that strategic context (update to SA)
recommends a preferred programme and a preferred way forward for further
development of the investment proposal
identifies the key asset and non-asset-based projects and activities that will support the
programme outcomes, including proposed programme tranches
seeks the approval of decision-makers to the preferred way forward, and to develop
subsequent project/tranche business cases (Detailed or Single Stage, as appropriate).
The PBC should be revisited at the start of each project/tranche business case. Each
business case should provide an update on any material changes to the programme drivers,
benefits, approach, timeline or costs since the completion of the previous business case.
Executive Summary
Write this last, and keep it short! The executive summary is the key output for decision-
makers around whether to invest (approval in principle to proceed) and in what
solution(s)/options. It should meet the needs of decision-makers by setting out the key
aspects of the business case in a concise and accessible form. Structure the summary to
follow the five-case model, to allow better comparison between business cases. The
executive summary can be the basis for other documents (eg communication, engagement
with others, information to stakeholders) but may need tailoring, especially if commercials
that may be sensitive are included.
Introduction
If there is no executive summary, retain the Introduction and Next Steps sections.
Text
In plain English, describe the investment proposal in one or two sentences. State what
decision-makers are being asked to consider or decide.
What is it purchasing, in broad terms, and what will be delivered?
What is the initiative type? Cost pressure, expansion of existing service, regulatory
initiative, completely new investment…
If it contributes to one or more of the five priority areas, outline which one(s) and how.
This Programme Business Case seeks formal approval to state briefly and clearly what
decisions are sought
Strategic Case
Summarise the strategic context for the proposed investment from the Strategic
Assessment, with particular reference to supporting strategies, programmes and plans.
The Strategic Case summarises and updates the strategic context for the investment
proposal and the case for change as detailed in the Programme Strategic Assessment.
The strategic context for this investment is…
Investment ………….
Objective Two
Existing
Arrangements
Business
Needs
etc
Economic Case
Set out the key findings of the analysis of programme options and the overall conclusions,
including a description of the preferred programme and the project mix. Include range-based
estimates of the indicative costs and benefits of the proposed programme.
We strongly recommend a workshop-based approach to getting consensus on these areas.
Note that Investment Logic Mapping (ILM) workshops with a facilitator accredited by the
Department of Treasury and Finance, Victoria, Australia, are mandatory for high-risk
programmes and projects.1
1
https://www.dtf.vic.gov.au/support-departmental-users/book-investment-management-standard-facilitator
Commercial Case
Provide an assessment of the likely commercial viability of the proposal. Outline the
procurement strategy and highlight the potential for non-traditional procurement, where
applicable. Most programmes will have a number of procurements, with various deals. It is
unlikely that there will be a potential deal at a programme level; deals may be at a tranche
level or for individual projects, of which there may be many within many tranches.
The Commercial Case outlines the proposed deal(s) in relation to the preferred way forward.
List and briefly describe the key material procurements
Provide an initial outline of the commercial case to provide decision-makers with some
assurance on the likely commercial viability of the proposal, potential suppliers, and where
those suppliers may be utilised. This is particularly relevant for innovative or more complex
services where there may be little market depth and experience. List here the key
procurements that are likely to be required as part of the programme; the detailed
consideration of the commercial case takes place at the Detailed Business Case stage for
the individual tranches/major projects within the programme.
Financial Case
The Financial Case demonstrates that the overall programme is affordable and outlines the
funding requirements for the programme tranches identified in the management case below.
Provide the rough-order cost estimates and an assessment of the ability of the organisation
to meet these. Decision-makers will expect a best-possible indication of the funding required
and its affordability. Ensure the primary funding sources for the programme are identified,
including mixes between different organisations. Identify funding gaps and areas where
decision-makers will need to make further funding decisions.
Management Case
Summarise the key programme management arrangements and key programme milestones.
Identify the overall methodology and the approach that will be taken to manage the
programme on an on-going basis.
The Management Case addresses the achievability of the proposal and planning
arrangements required to both ensure successful delivery and to manage programme risks.
The programme governance structure and initial programme milestones are provided below.
Next Steps
This programme business case seeks approval from decision-makers to start the preferred
programme of work and to proceed with developing:
There are multiple options for the next steps. Specify here what has been discussed and
agreed with Treasury and/or Ministers and/or Cabinet, for example:
Detailed (or Single Stage) Business Case for the first tranche
Indicative [and then Detailed] Business Cases for [specify] high risk/high value
project(s)
Direct to Detailed Business Case(s) for [specify]
This decision is made by [name of body] and will be formally recorded in [name of formal
record].
Strategic Context
Summarise the strategic context for the proposed investment, with particular reference to
supporting strategies, programmes and plans. Source this information from the previous
Strategic Assessment and update for any changes. Note that strategy does not necessarily
refer just to an organisation’s strategy, but could also refer to a government strategy, a
sector strategy, a functional/systems strategy (e.g. GCDO).
The strategic context provides an overview of the organisation and the outcomes that it is
seeking to achieve, or contribute to, through its operations.
Organisational Overview
Provide a brief outline of the organisation, of what it is seeking to achieve, current activities,
available resources and the environment in which it operates. Current planning documents
should also be referenced wherever possible.
The summary of the operating environment should also consider what externally-driven
factors are driving the need to invest.
Source this information from the previous Strategic Assessment and update for any
changes.
Demonstrate how the proposal contributes to relevant national, regional, sector and
organisational strategies. Take a wellbeing approach where appropriate and refer to the
Living Standards Framework (LSF). Where the proposal is part of a larger portfolio of related
programmes or projects, outline the inter-dependencies.
Outline how the proposal will help to achieve the business goals, strategic aims and plans of
the organisation. The proposed investment should contribute to, and be consistent with,
organisational strategic business planning.
Source this information from the previous Strategic Assessment and update for any changes
Include a summary of the stakeholder analysis to date, including an influence/interest grid for
key stakeholder groups. More detail, including the stakeholder map, management plan and
communications plan, can be included in the annexes and referenced here. Source this
information from the previous Programme Strategic Assessment and update for any changes
Provide evidence of support from key stakeholders of the need to invest.
The key stakeholders that have an interest in the expected outcomes or can influence the
investment proposal have been identified:
List and briefly describe their role, interest and influence
The process used to date to engage with key stakeholders and to build support for the need
for change has been to:
Summarise stakeholder engagement to date
Summarise stakeholder support/commitment
Text
Investment objectives specify the desired outcomes for a proposed investment. They need to
be SMART (specific, measurable, achievable, relevant and time-bound) to inform the later
assessment of potential options in Action 7 and to provide the basis for determining the
investment’s success. We recommend a facilitated ‘case for change’ workshop process to
develop and agree the investment objectives, to ensure that key stakeholders are engaged
early and have an opportunity challenge and shape the direction of the investment proposal.
Note that ILM workshops focus on problems and benefits, not Investment Objectives.
Benefits do not map directly to Investment Objectives, which may be broader (eg maintain
current level of service, minimise impact on customers…)
Facilitated case for change/Investment Logic Mapping (ILM) workshops were held with key
stakeholders in Mmm and Mmm yyyy to identify the existing business problems, likely
benefits expected from the investment, and the programme investment objectives.
Where applicable The outputs from the ILM workshops are attached as annexes; the agreed
problem statements have been used to inform the development of the programme
Investment Objectives.
The key stakeholders identified and agreed the following key investment objectives:
For each objective, provide a snapshot of the current state, using a wellbeing approach
where appropriate. For example where an existing service is being replaced, this could
include current costs and measures of the existing services. Including metrics provides a
base to help measure the distance of travel from the status quo.
Where an ILM was undertaken, ensure that the existing arrangements capture all of the
evidence supporting the problem statements agreed at the ILM workshop.
Existing
Arrangements
Business
Needs
Investment ………….
Objective Two
Existing
Arrangements
Business
Needs
Investment ………….
Objective xxx
Existing
Arrangements
Business
Needs
The potential business scope and key service requirements were identified and assessed by
stakeholders at the facilitated case for change workshop held on [dd mmm yyyy] ….
Table xx: Potential business scope and key service requirements
Service Scope Assessment
Requirements
(in decreasing
order of
relevance Intermediate
Minimum Scope Maximum Scope Out of Scope
compared to the Scope
investment
objectives)
Stakeholders identified the following benefits at the facilitated workshop on [dd mmm yyyy]
Table xx: Analysis of primary potential benefits Consider grouping by Living Standards
Framework (LSF) domain, eg (example)
Domains Benefit
Sustainable delivery of patient care: text
Improved patient experience and outcomes: text
Cultural Identity
text
Civic
engagement and
governance
text
Jobs and earnings
text
Cultural Identity
text
Civic
engagement and
governance
More information on the use of the Living Standards Framework, and the icons for the
domains, are in the guidance later in this template.
More detailed information is provided in Annex XX.
Risk is an uncertain event or circumstance that, if it occurs, has a negative effect on at least
one programme objective. The most significant risks that might prevent, degrade or delay the
achievement of the investment objectives are identified and analysed below. All risks will be
monitored, managed and updated as the programme progresses.
Table xx: Initial risk analysis
Comments & Risk Management Strategies
Main Risks
(Mitigations)
1 IF (xxx happens) THEN (impact) For the key strategic level risks, outline key mitigations
2 Reference, and include as an annex, a subset of the
Risk Register with more information (max 2 pages,
landscape)
3
4
5
Optimism bias is the tendency of people starting an endeavour to assume that it will
succeed, even when the outcome is uncertain. Thus programmes and projects tend to
underestimate timeframes and costs and overestimate benefits, productivity and outcomes.
This means that the analysis may not reflect the possibility of cost overruns, changing
business drivers or implementation timing delays.
Consider Quantitative Risk Assessment (QRA) to give quantitative estimates of risks and
their potential impact on programme costs and estimates, including required contingency.
Note QRA is mandatory for High Risk projects at the Detailed/Single-Stage Business Case
stage, but strongly recommended for the Programme Business Case.
Based on the nature of the investment proposal, the expected net benefits should be
reduced by [xx]% to reflect the effects of optimism bias. This loading will be progressively
reduced as the accuracy of the estimates for proposal costs and benefits improves.
The long-list must include an option that provides the baseline for comparing marginal costs
and benefits of by other options. This is the “Do Nothing” option; the programme does not
proceed. The “Status Quo” option requires maintaining the current level of services without
the programme proceeding; neither may be a viable option: for example, risk of service
delivery failure, or escalating maintenance costs.
The long-list must also include a realistic ‘do minimum’ option based on the core functionality
and essential requirements for the programme.
Repeat the above analysis of programme choices (by dimension) then score the choices
against the investment objectives and critical success factors, to determine the preferred
programme. The preferred programme is constructed from the preferred choices under
each of the five dimensions.
Format for the stakeholder assessment of choices.
Repeat this table for each of the five dimensions of choice, to show how the preferred way
forward is derived:
Scale, Scope and Location
Programme Solution
Service Delivery
Programme Implementation
Programme Funding
Table xx: Assessment scores for programme dimension options. Keep this as brief as
possible. If this table gets unwieldy, summarise here and state The full analysis of options
against Assessment criteria is attached as Annex X.
Note: this is a possible template: the values in the table below are illustrative only
Table xx: High-level cost benefit analysis
Rough Benefit Cost Analysis Notes Option 1: Option 2: Option 3: Do Option 4: Do
(summary) Do Nothing Do Minimum Intermediate Aspirational
Assumptions
The assumptions and tools used to justify each of the line items above are summarised
below:
List here the key assumptions (note financial assumptions are in Indicative costs and
benefits, below)
Describe the approach used to develop the rough order cost benefit analysis should be
described together with key financial assumptions. Consider the Treasury’s wellbeing
approach to cost benefit analysis: treasury.govt.nz/information-and-services/nz-
economy/living-standards/our-living-standards-framework/wellbeing-approach-cost-benefit-
analysis
Procurement Strategy
Outline the organisation’s procurement strategy and either provide a reference or attach it as
an Annex.
On the basis of the relative value of the procurement and the potential risk to the
organisation, the preferred approach to the supplier market is …
The initial assessment of the attractiveness of the proposed procurement to the supplier
market is…
Subject to approval, the organisation proposes to approach the market with a(n) Expression
of Interest (EOI)/Request for Information (RFI)/Other, based on the preferred way forward
above.
Required services
The required goods and/or services in relation to the preferred way forward are:
List here the key procurements that are likely to be required as part of the programme; the
detailed consideration of the commercial case takes place at the Detailed Business Case
stage for the individual major projects within the programme.
The specific goods and services required in each tranche will be defined in the respective
project or tranche business cased
Contract provisions
The contract procurements and key procurement milestones will be determined for each
procurement required. The overarching programme approach is:
Contract lengths:
…
Key contractual clauses
…
The indicative procurement timeline is aligned with the preferred programme approach as
described above. The key procurement milestones include:
list
Detail for this is not required until the Single-Stage or Detailed Business Case – but it is
useful to start to think about where the risks might be shared. Seek guidance from the
New Zealand Infrastructure Commission2.
2
https://treasury.govt.nz/information-and-services/nz-economy/infrastructure/nz-infrastructure-commission
The purpose of this section is to set out the Programme financial implications of the preferred
way forward.
The following assumptions have been made in determining these initial estimates:(or include
as an Annex and reference here if there are a significant number of financial assumptions).
List
Funding sources
It is proposed that the additional funding required ........ is sought/provided from the following
sources: ...........
Overall affordability
The proposed whole of life cost of the programme is $xxxm over the X years of the expected
lifetime of the programme.
The [Commissioner(s)/Chief Executive(s)/Senior Responsible Owner (SRO)] has/have
signified his/her/their agreement to the required level of funding required… The
Commissioner’s/Chief Executive(‘s/s’)/SRO’s letter is attached.
Governance arrangements
Outline governance arrangements (this may need an organisational chart):
Programme Board membership
Senior Responsible Owner
Project Executive for [project]
Representatives of corporate functions:
Programme structure
Include the programme organisational chart
The most recent programme plan (dd Mmm yyyy) is attached as Annex X.
Risk management
The Senior Responsible Owner is responsible for ensuring that arrangements for the
management of risk are in place, together with the appointment of a risk manager at the
appropriate time. The risks must be regularly and frequently reviewed and the register
updated throughout the course of the programme.
A Risk Management Strategy & Framework and a Risk Register have been developed and
will be progressively updated as more detailed analysis is undertaken.
Note that this may be a reference to the use of existing organisational programme
management frameworks and standards.
3
https://treasury.govt.nz/information-and-services/state-sector-leadership/investment-management/think-
investment-possibilities/risk-profile-assessment
Annexes
Attach as annexes additional supporting detail where noted in the Programme Business
Case document (examples below – these may not all be required, and other documents may
be more appropriate). Where the annex is an extract (eg risk register) or summary (eg plan),
note that the full version is available on request.
Commissioner’s letter
Supporting strategy and planning documents
Summary of stakeholder communication and engagement plans
Investment Logic Mapping deliverables, eg Investment Logic Map
High-level requirements analysis describing what the investment is to deliver (where
applicable)
Detailed options analysis
Programme blueprint and projects dossier
Summary Programme plan (Gantt chart) (1page)
Organisational Change management strategy
Benefits strategic alignment showing alignment to strategy
Draft outline/high-level Benefits (and Disbenefits) profiles
Economic and Financial analysis
Summary of risk register
<signature(s)>
Title(s)
Annex 2:
Table xx: Primary benefits
The benefits above will be used to undertake the options analysis in the Economic Case. Other expected secondary benefits are shown below.
Table xx: Secondary benefits and disbenefits
By domain: Description & possible measure(s)
Quantitative or Direct or
Secondary Benefit and Who Benefits?
Qualitative? Indirect?
disbenefit name
Annex 3…
Annex X:
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 33
GUIDANCE – DELETE ON COMPLETION OF PBC
For state sector agencies, any agency-specific questions should be addressed to your
Treasury Vote team or departmental Monitoring Agency.
These Actions develop the Programme Business Case, which provides a tool for transparent
and evidence-based decision-making and a framework for the coordination, delivery,
monitoring and evaluation of the programme’s resultant outputs, outcomes and benefits.
34 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
Note that the process and level of effort will vary depending on the nature of the organisation, the decision being
sought and the expectations agreed in the Point of Entry document meeting.
1. Ensure the mandate and brief for the programme have been completed
2. Complete the Treasury Risk Profile Assessment (RPA)4 and send to Treasury.
3. Draft the Point of Entry/Scoping document(PoE) 5 and arrange a meeting with the business case reviewer
to agree the process, the level of effort and any additional assurance requirements for the completion of
the Strategic Assessment (if required) and Programme Business Case (including Gateway Review,
Regulatory Impact Analysis and Independent Quality Assurance).
o Include in the Programme Business Case a summary update on the strategic case elements already
completed, and complete the remaining actions not undertaken in the Programme Strategic Assessment.
o If significant time has elapsed or any material changes have been identified since the completion of the
Programme Strategic Assessment, update the RPA and undertake a further PoE for the development of
the Programme Business Case
o Update the stakeholder management plan. This will inform the choice of attendees for stakeholder
workshops.
o Arrange and conduct a case for change workshop with key stakeholders to agree investment objectives
and scope. Additional workshops may be required to identify and analyse benefits, risks, service
requirements, constraints and dependencies.
o Note that Investment Logic Mapping (ILM) workshops with a facilitator accredited by the Department of
Treasury and Finance, Victoria, Australia, are mandatory for high-risk programmes and projects. 6 The first
two workshops are required (Problem Definition workshop and Benefit Definition workshop).
7. Arrange and conduct the workshops needed to identify a wide range of options and to assess these to
determine the preferred way forward; draft the Economic Case after the workshop(s).
8. Share the early draft of the Programme Business Case with senior management and key stakeholders to
obtain feedback and agreement to the proposed way forward; run this as a workshop.
9. Revisit and complete the Economic Case section following the workshop
10. Consult with the agency’s/agencies’ Commercial, Financial and (e)PMO teams; collect information for the
Commercial, Financial and Management cases and draft these cases.
12. Present the final draft Programme Business Case (and any supporting documentation required) for review,
including to central agency reviewers and to a Gateway review panel if required. Incorporate feedback.
4
https://treasury.govt.nz/information-and-services/state-sector-leadership/investment-management/think-
investment-possibilities/risk-profile-assessment
5
www.treasury.govt.nz/publications/guide/better-business-cases-significant-investment-proposal-point-entry
6
https://www.dtf.vic.gov.au/support-departmental-users/book-investment-management-standard-facilitator
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 35
GUIDANCE – DELETE ON COMPLETION OF PBC
13. Finalise the Programme Business Case, seek final sign-off from the Senior Responsible Owner and any
other required internal sign-off, and submit for approval to proceed with the programme.
14. The Programme Business Case should be revisited at the start of each project/tranche business case.
Each project/tranche business case should provide an update on any material changes to the programme
drivers, benefits, approach, timeline or costs since the completion of the previous business case.
15. Use the Programme Business Case to support post evaluation and benefit realisation
16. Feed findings back into the strategic planning process for the future development of the strategy and
strategic portfolio.
<back to template>
36 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
Purpose
The purpose of this action is to demonstrate alignment of the proposed investment with wider
national or sectoral priorities and goals, policy decisions, other multi-agency programmes (if
relevant) and with the sponsoring organisation(s) strategic intentions.
What’s expected?
This action builds on the initial analysis undertaken in Action 1 as part of the Strategic
Assessment. This action includes:
An organisational overview
Alignment to strategic intentions
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 37
GUIDANCE – DELETE ON COMPLETION OF PBC
Organisational overview
The scope of the organisational focus will determine the scope of the investment proposal.
For the purposes of BBC, ‘an organisation’ can be a single agency or can include multiple
agencies, business units or groups of people structured and managed to meet a need or to
achieve common goals.
Provide a brief snapshot of the organisation, of what it is seeking to achieve, current
activities, available resources and the environment in which it operates.
The key areas of focus are:
the main outcomes, impacts and objectives that the organisation is trying to achieve
the nature and scope of the organisation’s activities and services (outputs), key
stakeholders and customers
the current environment and context, including how the organisation intends to respond
to changes and possible risks. Consider:
o Strengths, Weaknesses, Opportunities and Threats analysis (SWOT)
o external drivers for the investment proposal – these can be political, economic,
social/ demographic, technological, legislative, environmental, and/or commercial
(PESTLE).7
Note that all new spending initiatives to be submitted for Budget Bid must demonstrate
alignment with the Government’s overall priorities, present a strong intervention logic and
evidence, show cost and impact understanding and provide a strong narrative on how the
assumed outcomes of the initiative will impact on wellbeing, for example through use of
the Living Standards Framework8. Wherever possible, the initiatives should also
demonstrate cross-agency and cross-portfolio collaboration.
7
PESTLE(C) and SWOT analysis tools: https://treasury.govt.nz/information-and-services/state-sector-
leadership/investment-management/better-business-cases-bbc/bbc-methods-and-tools
8
www.treasury.govt.nz/information-and-services/nz-economy/living-standards/our-living-standards-framework
38 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
Required evidence
There should be clear linkages and references to the Think Phase of the Investment
Lifecycle, through the organisation’s strategic planning and portfolio management process,
showing how this programme contributes to these strategies.
Identify the linkages to organisational strategic planning documents and other project
documents, for example:
white papers and overall business strategy
service models, e.g. models of care in the health sector, service plans
investment plans, e.g. Long-Term Investment Plan (LTIP), Asset Management Plan(s),
Information Systems Strategic Plan (ISSP)
corporate strategies, e.g. cybersecurity strategy
detailed asset planning information, e.g. asset condition assessments, geotechnical
assessments, Master Site Plans
documents prepared elsewhere in the project, e.g. business needs analysis, high-level
user requirements, results of Discovery/Feasibility exercises.
Do not repeat the detailed content of existing business planning documents - provide a brief
summary and references, rather than repeating the content.
Development of these business planning documents is not part of the business case
process; they provide necessary context and overarching strategy. Information from them is
required as input for analysis. If these documents do not exist, the SRO and the organisation
executive should consider whether the organisation is ready to proceed to business case, or
should initiate work outside the programme to address strategic planning gaps.
<back to template>
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 39
GUIDANCE – DELETE ON COMPLETION OF PBC
Note that Investment Logic Mapping (ILM) workshops with a facilitator accredited 9by
the Department of Treasury and Finance, Victoria, Australia, are mandatory for high-
risk programmes and projects.
There is no restriction on the number of investment objectives, but five or fewer helps to
make the analysis manageable and focussed (ie on the vital few); some proposals may
require either fewer or more. A large number of investment objectives, or single objective
statements that encompass multiple outcomes, can undermine the clarity and focus of the
proposal.
The objectives should be SMART (specific, measurable, achievable, relevant, and time-
bound) to inform the assessment of potential options in Action 7 and to provide the basis for
determining the investment’s success.
Defining good investment objectives
Good investment objectives should be:
Customer-focused and distinguishable from the means of provision
Focus on what needs to be achieved rather than the potential solution
Not so narrowly defined that they preclude important options, and
Not so broadly defined that they cause unnecessary work at the options analysis stage.
In practice, well-defined investment objectives typically address one or more of the following
five generic investment rationales:
To improve effectiveness. For example, by improving the quality of services, improving
access or better targeting these services to meet demand.
To improve efficiency. For example, by improving the relationship between the quantity
of inputs employed and the quantity, quality and timeliness of services delivered.
To reduce costs. For example, by reducing the underlying costs of the inputs employed
to deliver existing services.
To meet statutory, regulatory or organisational requirements. This can include
complying with new or changing legislative requirements (or organisational policies)
To re-procure services or avert service failure. For example, at the end of an existing
contract or where an enabling asset is no longer fit for purpose.
9
https://www.dtf.vic.gov.au/support-departmental-users/book-investment-management-standard-facilitator
40 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
Example: where an existing service is being replaced, this could include current costs and
measures of the existing services. Wherever possible, include metrics to provide a base to
help measure the distance of travel from the status quo.
Depending on the type of investment proposal, this analysis could include describing the
existing arrangements and explain how services are currently organised, provided and
supplied. Include any relevant contextual details about stakeholders, competitors, suppliers,
customers, service performance, and asset availability, utilisation and condition. An
evidential base should be provided to support the problems and opportunities that are
described.
This description also forms the basis for specifying the ‘Do nothing’ or ‘Status quo’ option in
Action 7; this is the baseline for measuring successful change.
Suggested evidence
Demonstration that analysis of the current state, investment objectives and underpinning
business needs are defined clearly and supported by key stakeholders and customers (eg
results of workshops).
Where appropriate, a wellbeing approach should be used to help evidence the performance
of the existing arrangements. Refer to the benefits table below for the identification of the
main benefits.
<back to template>
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 41
GUIDANCE – DELETE ON COMPLETION OF PBC
investment proposal to be considered successful. These can vary from the core or minimum
scope, through to the most aspirational:
The minimum scope required to deliver the essential or core service requirements (the
must haves)
The intermediate scope required to deliver essential and desirable service
requirements, and
The maximum scope required to deliver the essential, desirable and aspirational
service requirements.
Desirable requirements may typically be considered if they represent good marginal
value for money. The aspirational requirements (or “nice to haves”) are generally only
considered further if they are affordable.
Suggested evidence
Evidence should include clear statements of business outcomes and service outputs
together with demonstration that key stakeholders understand and agree scope. What is out
of scope should also be clear, understood and documented.
Methods and tools to gather the evidence for Action 3 and Action 4
There are a variety of methods and tools that are available to help the strategic case or
specific actions within the strategic case. https://treasury.govt.nz/information-and-
services/state-sector-leadership/investment-management/better-business-cases-bbc/bbc-
methods-and-tools
<back to template>
42 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
All significant benefits should be identified from the perspective of the benefits to New
Zealand (ie wellbeing) unless otherwise agreed with the reviewer. This recognises the wider
perspectives of public value decision-makers when making resource allocation choices.
Sources of wellbeing indicators, measures and data
To demonstrate wellbeing benefits, Treasury has provided access to Wellbeing indicators,
measures and data sources to baseline the current state, and to describe investment
objectives and benefits:
www.treasury.govt.nz/information-and-services/nz-economy/living-standards/our-living-
standards-framework/measuring-wellbeing-lsf-dashboard
Another potential (but not exhaustive) resource is Indicators Aotearoa New Zealand (IANZ):
www.stats.govt.nz/indicators-and-snapshots/indicators-aotearoa-new-zealand-nga-
tutohu-aotearoa
Case study/worked example
The Treasury also has a set of indicators, measures and data sources (the 'Horowhenua
District indicators'), drawn from IANZ and used by a district council for strategic planning.
Horowhenua District Council led a successful community conversation exercise involving iwi,
communities, elected members and community networks in 2018 to identify what residents
and ratepayers loved the most about their communities and those attributes that would
define neighbourhoods of the future. With participation in this conversation reaching over
10% of the population, Horowhenua District Council selected indicators that were the most
meaningful to measure the wellbeing aspiration in the district. Horowhenua District Council is
working with community leaders to develop a baseline and further refine the indicators.
On request, Treasury’s Investment Management & Asset Performance team can provide the
'Horowhenua District Council’ example (of domains, measures, indicators and data sources)
to agencies with projects in the Government Investment Portfolio.
The Treasury is not particularly endorsing these indicators as having more significance than
others – they are simply presented as a 'worked example'. The main value is in
understanding the process of how they were identified. There’s also value in being able to
see the associated measures and data sources, for agencies to get a sense of how they
might achieve this for the indicators they end up choosing for their own Wellbeing narrative.
There is a lot of overlap between the indicators used in IANZ and The Treasury’s LSF
Dashboard, and the two products are closely related. Agencies can use indicators from both
products to help build their Wellbeing narrative. However, these are both a high-level view of
wellbeing. Where appropriate, agencies should also consider whether other more granular or
relevant indicators may be needed to best describe impacts (benefits/disbenefits) at a
business case (micro-economic) level.
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 43
GUIDANCE – DELETE ON COMPLETION OF PBC
Health (primary)
Cultural Identity
Civic engagement
and governance
Environment
Housing
Income
Jobs
Social connections
Subjective
wellbeing
Time use
44 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
<back to template>
Disbenefits have negative impacts on stakeholders also need to be identified and analysed
here. Provide a similar analysis table.
Where benefits may are contingent on other events, they should be classified with risks.
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 45
GUIDANCE – DELETE ON COMPLETION OF PBC
This analysis will be revisited and updated in further business cases (eg Detailed Business
Case) and be based on the preferred option.
Additionally, there is a demonstrated, systematic, tendency for individuals to exhibit ‘optimism bias’
when preparing spending proposals. The effects of optimism bias can be mitigated by making explicit
adjustments to key assumptions and variables, for example by increasing proposal estimates,
reducing projected benefits, or by assuming benefits are delayed.
The amount of optimism bias typically depends on the nature of the investment proposal and the
accuracy of the estimates for proposal costs and benefits. As the business case development
proceeds and estimates are refined, the level of optimism bias can be expected to reduce and
incorporated as a contingency in the contracted project. This means that the business case analysis
may not fully reflect the possibility of cost-overruns, changing business drivers or implementation
timing delays. Tools such as Quantitative Risk Assessment (QRA - see link below) are useful to
identify and counter optimism bias.
Guidance:
BBC – techniques to quantify risk and uncertainty
UK government Green Book: supplementary guidance on Optimism Bias
<back to template>
Identify constraints
Constraints are limiting parameters within which the investment must be delivered. These
can include relevant Government policy decisions, initiatives or rules, or constraints on
available resources (eg availability of internal subject matter experts (SMEs), market
limitations). Affordability constraints can include funding envelopes or limits on the amount of
either operating or capital expenditure that can be incurred.
Constraints on the programme need to be described, considered and managed from the
outset, since they will limit the range and scale of investment options that can be considered
for further assessment.
46 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
Programme assumptions need to be identified and managed from the outset. If any
assumption proves to be incorrect, at any stage during the programme duration, this may
impact on the validity of the programme or its expected benefits. Any material change in
assumption(s) should trigger a review of the advisability of proceeding with the programme.
Note that the assumptions in this section are broader than the financial assumptions that are
considered in the Financial case.
Required evidence
Demonstration that the benefits, risks, constraints, dependencies and assumptions are
clearly defined and are understood and agreed by the key stakeholders.
Benefits thinking may be preliminary but should be documented in a format that can be
expanded over time.
<back to template>
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 47
GUIDANCE – DELETE ON COMPLETION OF PBC
Required evidence
The business case should describe the critical success factors and describe the approach
that was used to identify and agree them.
<back to template>
48 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 49
GUIDANCE – DELETE ON COMPLETION OF PBC
50 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 51
GUIDANCE – DELETE ON COMPLETION OF PBC
52 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
Case study: for a service improvement programme where the ‘scope’ for change has been defined
in terms of organisational coverage: the number of departments and functions that might be
affected by the change.
The workshop identified and appraised the options as follows:
Programme Do nothing Do Intermediate Intermediate Do maximum
minimum option option
1 Service 1.0 all 1.1 Dept A 1.2 Dept A 1.3 Dept A 1.4 All Dept
scope – as departments (Front FO plus FO plus A, B, C, D, E
outlined in Office Dept B and Depts B,C,D
strategic only) C
Case Carried Carried Preferred Carried Discount
forward forward way forward forward
Once the preferred way forward for potential scope has been identified:
5. Identify ‘potential solutions’ for improving organisational capabilities within the
programme’s preferred way forward for potential scope, ranging from business-as-
usual (BAU) through to the ‘do minimum’ and ‘do maximum’ and intermediate options.
These options focus on the outputs, activities and potential projects required.
6. The ‘do minimum’ solution must be a realistic option that meets the ‘core’ requirements
and essential business needs for the programme. The ‘Do maximum’ solution must not
exceed the agreed scope for the programme as defined in the strategic case (which
must be revisited if it does). Limit intermediate options to those that have key
differences in relation to their desirable and optional outputs and activities.
Be innovative and think in terms of what other organisations have achieved, what is
likely to work, and what is available in the marketplace.
i. Carry out a SWOT analysis for each option – note advantages and
disadvantages and how well it meets the agreed investment objectives and
CSFs.
ii. Discount unrealistic options. Carry forward possible options, including ‘Do
nothing’ and ‘Do minimum’ solutions.
iii. Identify the preferred way forward (PWF) – the ‘solution’ that is considered most
likely to optimise value.
Solutions identified for a programme that are more ambitious than the ‘do
minimum’ must be justified on their potential for delivering additional value.
Case study: for a service improvement programme where the ‘service solution’ relates to the
number of outputs and activities – potential projects – that might be required within the programme.
The workshop identified and appraised the options as follows:
Programme Do nothing Do Intermediate Intermediate Do
minimum option option maximum
2 Service 2.0 Current 2.1 Core: 2.2 Core & 2.3 Core & 2.4 Core &
solution – in services QMS + desirable desirable desirable
relation to training plus: plus: plus:
the preferred New IT Refurbished New offices
scope office
(option 1.2 Carried Carried Carried Preferred Discount
above) forward forward forward way forward
Once the preferred way forward for potential service solution has been identified:
7. Identify potential options for ‘service delivery’ of the programme’s preferred way
forward in relation to potential scope and service solution.
These options focus on the delivery of the outputs, activities and potential
projects required.
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 53
GUIDANCE – DELETE ON COMPLETION OF PBC
In this instance the ‘Do minimum’, Intermediate and ‘Do maximum’ choices relate to the
varying levels and degrees of ‘ambition’ for service delivery, so a ‘Do maximum’ is not
necessarily required.
Be innovative and challenge whether the organisation is currently sourcing and
delivering the services it provides in the most efficient and cost-effective way:
All state sector proposals requiring Cabinet approval that have whole-of-life costs
in excess of $25 million must consider non-traditional procurement options for
service delivery, including public private partnership (PPP). For more detail see
Annex 1 and contact the New Zealand Infrastructure Commission for advice.
State sector programmes – if there are options with structural implications for
government (eg setup of a new Department/Departmental Agency) you must
engage early with the State Services Commission, which provides advice and
guidance in this area: www.ssc.govt.nz/mog
i. Carry out a SWOT analysis for each option – note advantages and
disadvantages and how well it meets the agreed investment objectives and
CSFs.
ii. Discount unrealistic options. Carry forward possible options, including ‘do
nothing’ and ‘do minimum’ service options.
iii. Identify the preferred way forward (PWF) – the method of ‘service delivery’ that is
likely to provide the optimal outcome in terms of programme and operational
delivery.
Case study: for a service improvement programme where ‘service delivery’ relates to how the
required outputs and activities or potential projects might be provided within the programme.
The workshop identified and appraised the options as follows:
Programme Do nothing Do Intermediate Intermediate More
minimum option option ambitious
3 Service 3.0 Current 3.1 In- 3.2 3.3 Mix in- 3.4
Delivery – in arrangement house Outsource house and Strategic
relation to the s outsource partner
preferred Carried Carried Discount Preferred Discount
scope and forward forward way forward
solution(option
s 1.2 and 2.3
above)
Once the preferred way forward for potential service delivery has been identified:
8. Identify potential options for implementation of the programme’s preferred scope,
service solution and method of service delivery.
These options focus on the sizing, sequencing and phasing of the potential
outputs, activities and projects required.
The agreed programme tranches and projects in the tranches are usually determined
through a series of workshops and meetings with stakeholders where the mix is
considered, evaluated, costed, deemed impossible, relitigated to make the tranches
affordable and achievable etc.
The mix of projects
As part of this action, identify the projects that best achieve the investment objectives and
service requirements, yet lie within the boundaries of the scope parameters and critical success
factors identified for the programme.
The following criteria may also be helpful in determining and recommending the mix of projects
within a programme:
54 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
Proximity to delivery: Projects close to completion (particularly where there is a high degree
of confidence in the achievement of investment objectives) could be allowed to continue and
included within the programme, in order to deliver quick wins
Dependencies: Projects which are dependent on particular programme outcomes may be
grouped together.
Achievement of investment objectives: Projects likely to contribute significantly to the
programme investment objectives should be included within the programme.
Organising into tranches
Typically, programmes are planned as a series of sequential tranches which meet elements of
the business needs at defined points in the future. Completion of each tranche is also an
opportunity to review the Programme Business Case as a basis for seeking confirmation to
continue to invest in the mix of projects and activities within the programme; consider
completion of each tranche as a potential off-ramp.
The recommended programme tranches show intermediate future states and outline which of
the programme outcomes will be realised at the end of each tranche.
Develop a programme roadmap that identifies the programme tranches and each tranche’s
contributions to investment objectives, costs and benefits at the end of each tranche.
There is no need to identify all projects and activities across all tranches. For the first
tranche, projects should be identified in some detail, because the Programme Business
Case is seeking approval to commence business case development for these projects.
In this instance the ‘do minimum’, intermediate, and ‘do maximum’ relate to the varying
levels and degrees of ‘ambition’ for implementation, so a ‘do maximum’ does not
necessarily apply.
Create tranches that provide synergies, holistic fit and sufficient critical mass for
delivering economies of scale, and size accordingly
Focus on the critical path for delivering the required outputs and activities and
sequence accordingly
Design and build projects that optimise benefits delivery while managing the risks
and phase accordingly
Consider the requirement for off-ramps.
i. Carry out a SWOT analysis for each option – note advantages and
disadvantages and how well it meets the agreed investment objectives and
CSFs.
ii. Discount unrealistic options for implementation. Carry forward possible
options, including ‘Do nothing’ and ‘Do minimum’ service options.
iii. Identify the preferred way forward (PWF) – the approach to the sizing,
sequencing and phasing of potential projects that is most likely to deliver
successful outputs and outcomes.
Case study: for a service improvement programme where ‘implementation’ options relate to how
the required outputs and activities might be delivered over time.
The workshop identified and appraised the options as follows:
Programme Do Do Intermediate Intermediate Do
nothing minimum option option maximum
4 Implementation 4.0 4.1 Tranche 1 4.2 Tranche 1 4.3 Single N/A
– in relation to Project A: Project A: tranche
QMS & refurbished Project A:
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 55
GUIDANCE – DELETE ON COMPLETION OF PBC
Once the preferred way forward for implementation has been identified:
9. Identify possible ‘funding options’ for resourcing of the programme’s preferred scope,
service solution, method of service delivery and implementation.
These options focus on the range of different ways in which the programme’s
projects and activities could be funded, including both traditional and innovative
sources of finance.
In this instance the ‘Do minimum’, intermediate, and ‘Do maximum’ relate to the varying
levels and degrees of ‘ambition’ for funding the service, so a ‘Do maximum’ does not
necessarily apply.
i. Carry out a SWOT analysis for each option – note advantages and disadvantages
and how well it meets the agreed investment objectives and CSFs.
ii. Discount unrealistic options for implementation. Carry forward possible options,
including ‘Do nothing’ and ‘Do minimum’ service options.
iii. Identify the preferred way forward (PWF) – the funding option that is most likely
to meet the requirements of the programme, to optimise value for money and be
affordable.
Case study: for a service improvement programme where potential projects and activities could be
funded in their design, build and operational phases through a number of sources.
The workshop identified and appraised the options as follows:
Programme ‘do Do Intermediate Intermediate Do
nothing’ minimum option option maximum
5 Funding – in 5.0 5.1 Public 5.2 Private 3.3 Mixed
relation to the funding finance public &
preferred private
scope, N/A Carried Discount Preferred
solution, forward way forward
method of
service
delivery and
implementatio
n (options 1.2,
2.3, 3.3, 4.2
above)
A wide range of possible solutions should be considered under each of the five dimensions.
There is no set limit on the number of composite options that may be generated – but to
avoid undue analysis effort, impractical options can be discarded as part of the workshop
process (take a note of the reasoning).
The options framework is a useful tool; even in this very simplified case study, over 20 main
options have been considered – for scope, solution, service delivery, implementation and
funding – and indirectly over a thousand possible combinations of different options.
56 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
The individual tables can be merged to form a single page summary of the options that have
been considered – a useful format for senior management.
End of options framework insert
Annex 2 shows a worked example of an options framework. This one is for a project, but the
same principles apply.
Required evidence
The business case should:
reference any Feasibility Study or Discovery work undertaken
describe the approach that was used to identify and assess the programme options
and the stakeholder roles involved.
The full long-list assessment should be documented and included as an annex to the
Programme Business Case; this enables the reviewer to assess the level of analysis and
thinking underlying the preferred way forward.
What’s expected?
The suggested steps are:
10. Identify the key dimensions of choice
Key dimensions of choice for programmes are typically within the scope and solutions (or
capabilities to be developed)
11. Identify possible options within each dimensions
Systematically identify possible options within the selected dimensions where there are
choices.
12. Assess options against the programme’s investment objectives and critical success
factors
Discard options that are plainly unrealistic or uneconomic by rejecting any option that does
not fully meet all of investment objectives and critical success factors. The extent or depth of
the options assessment should be tailored to the relative size, impacts, and risks of the
proposal. The assessment should be based information that is readily to hand.
13. Develop programme options
From the options that meet all the investment objectives and critical success factors
construct at least three options by combining the options from the various dimensions.
14. Evaluate the programme options
For each of the programme options, a rough order cost benefit analysis should be provided
including indicative monetary and non-monetary costs and benefits. Costs and benefits
should be widely ranged to avoid creating unrealistic expectations. The relative risks
associated the delivery of each option should also be considered.
Methods and tools for gathering the evidence for Actions 6 and 7
We recommend a series of facilitated workshops with key stakeholders to agree the critical
success factors and the long-list of programme options. The options framework is a
particularly useful tool to relatively quickly identify and assess a large number of potential
options across the five dimensions.
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 57
GUIDANCE – DELETE ON COMPLETION OF PBC
Methods and tools identified in this guidance, and others that can be used in this and other
stages of the business case: https://treasury.govt.nz/information-and-services/state-sector-
leadership/investment-management/better-business-cases-bbc/bbc-methods-and-tools
<back to template>
What’s expected?
The programme option that optimises costs, benefits and risks should be recommended as
the preferred option.
For the preferred option the programme’s tranches should be identified. By their very nature
programmes will progressively deliver the identified investment objectives over time.
Typically, programmes are planned as a series of sequential tranches which elements of the
business needs at several defined points in the future. The recommended programme
tranches show intermediate future states and outline which of the programme outcomes will
be realised at the end of each tranche.
A programme schedule or roadmap should be developed that identifies the programme
tranches together contributions to investment objectives, costs and benefits at the end
of each tranche.
There is no need to identify all projects across all tranches. However, all key activities
or work packages should be identified. For the first tranche, projects should be
identified because the programme business case is seeking approval to commence
business case development for these projects.
Short-listing options
From the long-list, the Programme Business Case should filter to identify a minimum of three
to four shortlisted options for further appraisal. These should include:
‘Do nothing’ or ‘Status quo’ or ‘BAU’ option – the benchmark for considering the relative
value for money of alternative options
The ‘Do minimum’ option – a realistic way forward that also acts as a further
benchmark for value, in terms of cost justifying further intervention
The ‘recommended’ preferred way forward at this stage
One or more possible options based on realistic ‘more ambitious’ and ‘less ambitious’
choices that were not rejected at the long-list stage.
Avoid going into ‘solution mode’ – that is, take care to avoid ‘rigging’ and ‘retro-fitting’ options
that have been pre-determined. The programme should seek guidance from its reviewers if it
finds itself in this position.
58 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 59
GUIDANCE – DELETE ON COMPLETION OF PBC
The costs should include some allowance for the uncertainty of cost and risk (‘optimism bias’
and the ‘cost of risk’) and together with the benefits should be rejected to provide indicative
net present values for the short-listed options.
Suggested evidence
Engagement with key stakeholders on the process to determine the shortlist should be
described.
The approach to developing the programme schedule and roadmap should be described.
The approach used to develop the rough order cost benefit analysis should be described
together with key assumptions.
60 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
The level of detail at this stage will be high level: sufficient to provide decision-makers with
an early view of key factors that may affect the commercial viability of the proposal.
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 61
GUIDANCE – DELETE ON COMPLETION OF PBC
62 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
Consider capturing the following details for the programme and its projects:
The business areas affected by the procurement(s)
The business environment and related activities
The business objectives relevant to the procurement(s)
The scope of the procurement(s)
The required service streams
The required outputs, including phases, performance measures and quality attributes
The stakeholders and customers for the outputs
The options for variation in the existing and future scope for services
The potential developments and further phases that may be required.
<back to template>
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 63
GUIDANCE – DELETE ON COMPLETION OF PBC
Operational phase: following acceptable delivery of the service up to the close of the
primary contractual period
Extension phase: post primary contract period.
<back to template>
64 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
Personnel implications
Identify any personnel implications for the programme. Public sector organisations are often
obliged to involve their staff and their representatives in a process of continuous dialogue
during significant projects involving considerable internal change. This is also best practice in
terms of human resources policies.
<back to template>
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 65
GUIDANCE – DELETE ON COMPLETION OF PBC
Financial Case
Completing the financial case requires the following actions for the preferred option identified
in the economic case:
Step 6 Ascertaining affordability and funding requirement
Action 19 Prepare financial model and the financial appraisals
The level of detail at this stage will be high level: sufficient to provide decision-makers with
an early view of key factors that may affect the financial viability of the proposal.
What’s expected?
Decision-makers will expect a best-possible indication of the funding envelope and its
affordability, based on the information available, to provide an early indication of key factors
that may affect the affordability of the proposal. Identify the primary funding sources for the
programme, including mixes between different organisations, fees recovery and other
sources. Identify funding gaps and areas where decision-makers will need to make further
funding decisions.
Provide an initial assessment of the overall affordability of the preferred programme option
and possible funding sources and requirements. This can include:
the current financial situation of the organisation
an overview of resources available for implementing the proposal, including an
assessment of the ability of the organisation to provide on-going support
any capital and revenue constraints
statements of strategic or in-principle support from stakeholders.
66 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
For more detail refer to the Detailed Business Case guidance, Action 19:
http://www.treasury.govt.nz/statesector/investmentmanagement/plan/bbc/guidance
<back to template>
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 67
GUIDANCE – DELETE ON COMPLETION OF PBC
Management Case
Step 7: Planning for successful delivery
Completing the management case requires the following actions:
Step 7 Planning for successful delivery
Action 20 Plan programme management – strategy, framework & plans
Action 21 Plan change management – strategy, framework & plans
Action 22 Plan benefits realisation – strategy, framework & plans
Action 23 Plan risk management – strategy, framework & plans
Action 24 Plan programme assurance and post-project evaluation – strategy, framework &
plans
The level of detail at this stage will be high level: sufficient to provide decision-makers with
an early view of the organisation’s capability to deliver the programme.
68 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 69
GUIDANCE – DELETE ON COMPLETION OF PBC
Ownership of the Programme Business Case and responsibility for its development must be
retained by the Programme Board. Organisations may outsource to get specialist skills for its
completion, but must retain intellectual ownership of the thinking.
Evidence required
There must be evidence that:
Programme management processes and arrangements are already in place within the
organisation (eg through an Enterprise Programme Management Office) and plans are
in place to apply these arrangements to the programme - or -
The organisation has considered the requirement to introduce a programme
management methodology and has plans that show how this will be done.
70 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
The benefits realisation strategy should set out arrangements for the identification of
potential benefits, their planning, modelling and tracking. It should also assign responsibility
for the actual realisation of those benefits throughout the key phases of the programme.
At the Programme Business Case stage of a programme the following should be available
for the PBC to reference; if these were created earlier (eg as part of the Strategic
Assessment process) revisit and update to reflect any changes and additional information
available:
Benefits map: identifies benefits and relationships and linkages to intended outcomes.
All anticipated benefits identified in the strategic case and appraised in the economic
case sections of the Indicative Business Case must be accounted for in the register.
This is also a good time for a workshop to identify emerging benefits (or disbenefits)
Strategic alignment: how outcomes and benefits align to strategy.
Initial benefits profiles, including (preliminary) identification of measures
Benefits Realisation Plan, including:
o business ownership agreed with the owners
o identification of key risks to each benefit’s delivery
o likely delivery dates
o monitoring and reporting plans
Evidence required
There must be evidence that planning for benefits realisation is underway and benefits
delivery arrangements are outlined.
All benefits identified in the strategic case and appraised in the economic case sections of
the Programme Business Case must be accounted for in the register.
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 71
GUIDANCE – DELETE ON COMPLETION OF PBC
Programmes must capture all identified risks within a register that indicates how they will be
managed and mitigated. The register should be regularly and frequently reviewed and
updated throughout the programme; all the risks identified in the strategic and economic
case sections of the Programme Business Case must be accounted for in the register.
Programme Assurance
Gateway Reviews are mandated for significant projects and programmes in organisations in
scope for Cabinet Office Circular CO(19)6 10which have been assessed as High Risk (through
completion and review of a Risk Profile Assessment) and thus require Gateway reviews.
Engage with the Treasury’s Investment Reviews team early, to ensure that Gateway or
other Investment Reviews can be scheduled for appropriate points in the programme:
investmentreviews@treasury.govt.nz
Programme assurance provides independent and impartial assessment that the
programme’s investment objectives can be delivered successfully, and improves the
prospects of achieving intended outcomes and benefits.
These programmes also require an Operational & Benefits Realisation review, and must
report to Cabinet on the achievement of benefits one year after go-live (refer CO(19)6).
Quality Assurance
Other forms of assurance include: Independent Quality Assurance; Independent Technical
Assurance; security assurance.
ICT-enabled programmes and projects must develop an Assurance Plan and agree this with
the Government Chief Digital Officer (GCDO).
Engage with the GCDO early to ensure that the programme meets its requirements in
terms of assurance: GCDO@dia.govt.nz
<back to template>
10
https://dpmc.govt.nz/publications/co-19-6-investment-management-and-asset-performance-state-services-
html
72 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 73
GUIDANCE – DELETE ON COMPLETION OF PBC
the process of developing subsequent business cases (Single Stage or Indicative then
Detailed or direct to Detailed, as appropriate and agreed).
The consideration of procurement options is carried out at Action 7 of the PBC where
evaluation of a wide range of realistic options for meeting the identified service needs is
required. The suggested approach is to consider possible options against five dimensions:
scale, service solution, service delivery, implementation and funding. The resulting options
for implementing the preferred solution may range from the procuring agency self-performing
the delivery of all required assets and services to the provision of all services by a private
sector provider through assets developed and owned by that provider.
An initial qualitative assessment of PPP procurement is required. This should consider the
characteristics of the project and assess whether PPP procurement is likely to be suitable
and offer greater value for money. Further detail of those characteristics which should be
considered at a minimum are set out below.
If PPP procurement is to be included as a short-list option, additional consideration is
required as part of the Detailed/Tranche Business Case before PPP procurement is
presented to Cabinet. This additional consideration includes consultation with joint Ministers
(the Minister of Finance and Minister responsible for the procuring entity) and engagement
with potential interested parties through market sounding.
Two additional components (Actions 8a and 8b) are required to be added to Action 8 to
provide for this additional analysis.
Action 8a: Market Sounding
Early market engagement and procurement planning is particularly important for innovative
or more complex services where there may be little market depth and experience (eg PPPs).
Engaging with a representative sample of potential private sector partners (the market) early
in the planning process for a project can provide real value to a procuring entity as it can help
inform the opportunity for all parties – both in terms of readying the market for the project as
well as helping the procuring entity resolve the optimal scope and scale of the project.
While care must be taken to ensure that appropriate probity processes are observed, market
sounding provides the procuring entity an opportunity to gain a better understanding of the
appetite of the market for the project as well as any preferences or challenges the market
may have with certain scope and scale permutations.
The procuring entity must ensure that it is well prepared for the market sounding process and
that it presents a coherent and considered opportunity to the market. If the procuring entity is
not well prepared and has not considered a range of options or attempts to use the market
sounding process to ‘crowdsource’ innovation or intellectual property then it is likely to
damage the market’s appetite for the project.
Action 8b: Endorsement by joint Ministers
If, on the basis of the initial qualitative assessment and market sounding, PPP procurement
is considered a short-list option then joint Ministers should be consulted prior to submission
of the Programme Business Case to Cabinet. This provides Ministers with full visibility of the
analysis and assumptions which underpin the project and allow them to consider whether
there are any project or external factors which may also impact the likely success of PPP
procurement. For example, if the timing of another project, for which a different agency is
considering PPP procurement, may clash then Ministers may consider intervening.
If joint Ministers agree that PPP procurement is an appropriate option, further analysis will be
required as part of the preparation of the DBC. The IBC or PBC should short-list two
procurement options for further evaluation in the DBC which include PPP procurement and
74 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
the preferred form of conventional procurement. This is important as the preferred form of
conventional procurement will form the basis for the calculation of the Public Sector
Comparator (PSC) and will ensure a second option is available if further analysis as part of
the DBC results in PPP procurement being discarded.
<back to guidance>
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 75
GUIDANCE – DELETE ON COMPLETION OF PBC
Option Title
Option 0 Do Nothing SCO1 Do Nothing
Option 1 Intermediate SCO3 Intermediate SOL2 Integrated Regionally SDO3 Partially managed (led by commercial IMP2 Phased by site
Scope - Regional supplier)*
Option 2 Intermediate SCO3 Intermediate SOL3 Integrated Nationally SDO3 Partially managed (led by commercial IMP2 Phased by site
Scope - National supplier)*
Integration
Option 3 Maxim um Scope - SCO4 Maximum SOL2 Integrated Regionally SDO3 Partially managed (led by commercial IMP2 Phased by site
Regional Integration supplier)*
Option 4 Maxim um Scope - SCO4 Maximum SOL3 Integrated Nationally SDO3 Partially managed (led by commercial IMP2 Phased by site
National Integration supplier)*
* A capability analysis of the [MINISTRY} will be
conducted to see if SDO4 Partially managed (led
by [MINISTRY]) is a possibility. Based on present
incomplete information this does not appear to be
a viable option.
76 | Better Business Cases: Guide to Developing the Programme Business Case November 2019
GUIDANCE – DELETE ON COMPLETION OF PBC
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 77
GUIDANCE – DELETE ON COMPLETION OF PBC
Annex 4: References
Department of Prime Minister and Cabinet (2001), Cabinet Office Circular CO (15) 05, Investment
Management and Asset Performance in the State Services: https://dpmc.govt.nz/news/new-cabinet-office-
circular-published-co-15-5-investment-management-and-asset-performance-state
HM Treasury (2003), Green Book: Appraisal and Evaluation in Central Government, Treasury Guidance
updated July 2011: https://www.gov.uk/government/publications/the-green-book-appraisal-and-evaluation-
in-central-governent
Ministry of Business, innovation and Employment (2011), Mastering Procurement: A Structured Approach
to Strategic Procurement, March 2011: https://www.procurement.govt.nz/procurement/guide-to-
procurement/
Ministry of Business, Innovation and Employment (2019), The Government Rules of Sourcing, October
2019: https://www.procurement.govt.nz/procurement/principles-and-rules/government-procurement-rules/
Smith, Courtney A and Flanagan, Joe (2001), Making Sense of Public Sector Investments: the five case
model in decision-making, Radcliffe Publishing Limited, (ISBN 1 85775 432 8)
The Treasury (2013) Better Business Case guidance, templates and supporting documents:
http://www.treasury.govt.nz/statesector/investmentmanagement/plan/bbc/guidance
The Treasury (2018) The Treasury’s CBAx tool: https://treasury.govt.nz/information-and-services/state-
sector-leadership/investment-management/plan-investment-choices/cost-benefit-analysis-including-public-
sector-discount-rates/treasurys-cbax-tool
The Treasury (2018) Cost benefit analysis including public sector discount rates:
https://treasury.govt.nz/information-and-services/state-sector-leadership/investment-management/plan-
investment-choices/cost-benefit-analysis-including-public-sector-discount-rates
The Treasury (2013) Regulatory Impact Assessments (2019):
https://treasury.govt.nz/publications/legislation/regulatory-impact-assessments
https://treasury.govt.nz/publications/guide/guide-cabinets-impact-analysis-requirements
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 78
GUIDANCE – DELETE ON COMPLETION OF PBC
Acknowledgements
This document was created using material provided by HM Treasury in the United Kingdom and the Welsh
Government (Llywodraeth Cymru), licensed under the terms of the Open Government Licence v3.0
(http://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/).
The Five Case Model is the best practice standard recommended by HM Treasury for the preparation of business
cases, published as The Green Book:
https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/685903/The_Green
_Book.pdf.
© Crown Copyright
This work is licensed under the Creative Commons Attribution 4.0 International licence. In essence, you
are free to copy, distribute and adapt the work, as long as you attribute the work to the Crown and abide by the other
licence terms.
To view a copy of this licence, visit https://creativecommons.org/licenses/by/4.0/. Please note that no departmental or
governmental emblem, logo or Coat of Arms may be used in any way which infringes any provision of the Flags,
Emblems, and Names Protection Act 1981.
Attribution to the Crown should be in written form and not by reproduction of any such emblem, logo or Coat of Arms.
November 2019 Better Business Cases: Guide to Developing the Programme Business Case | 79
i