Project Evaluation and Review Technique (PERT)
Project Evaluation and Review Technique (PERT)
Project Evaluation and Review Technique (PERT)
Asmaa Soliman
Duration:
𝑻𝒐 + 𝟒 ∗ (𝑻𝑴. 𝒍) + 𝑻𝒑
1. Expected Time for activity (Te) =
𝟔
2. σ (C.p) only = 𝑻𝒑 − 𝑻𝒐
𝟔
Calculated
3. v=σ²(C.p) only
Case (1):
Project Management CT 200 Eng. Asmaa Soliman
Case (2):
Project Management CT 200 Eng. Asmaa Soliman
Case (3):
Project Management CT 200 Eng. Asmaa Soliman
Solved Example
Required
1. What is the probability if the total time (22 week)?
2. What is the total time if the probability (65%)?
Solution
Project Management CT 200 Eng. Asmaa Soliman
Step (3): Determine the Total Time of the Project and Critical Activities