Project Evaluation and Review Technique (PERT)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Project Management CT 200 Eng.

Asmaa Soliman

Project Evaluation and Review Technique (PERT)

Duration:

 Optimistic Time (OT) = The Shortest Duration of Activity


 Pesimistic Time (PT) = The Longest Duration of Activity Given
 Mor Likely Time (MLT) = The Best Duration of Activity

𝑻𝒐 + 𝟒 ∗ (𝑻𝑴. 𝒍) + 𝑻𝒑
1. Expected Time for activity (Te) =
𝟔

2. σ (C.p) only = 𝑻𝒑 − 𝑻𝒐
𝟔
Calculated
3. v=σ²(C.p) only

4. 𝑻𝒐𝒕𝒂𝒍 𝑻𝒊𝒎𝒆 −𝑬𝑵𝑫 𝒐𝒇 𝒕𝒉𝒆 𝒑𝒓𝒐𝒋𝒆𝒄𝒕


Z =
∑𝝈𝟐 𝒄.𝒑 𝒐𝒏𝒍𝒚

5. Insert Chart and Get the Probability as follow:


Project Management CT 200 Eng. Asmaa Soliman

Case (1):
Project Management CT 200 Eng. Asmaa Soliman

Case (2):
Project Management CT 200 Eng. Asmaa Soliman

Case (3):
Project Management CT 200 Eng. Asmaa Soliman

Solved Example

Required
1. What is the probability if the total time (22 week)?
2. What is the total time if the probability (65%)?

Step (1): Draw the Network

Solution
Project Management CT 200 Eng. Asmaa Soliman

Step (2): Determine the Expected Time

Step (3): Determine the Total Time of the Project and Critical Activities

Step (4): Determine σ and σ² for Critical Activities


Project Management CT 200 Eng. Asmaa Soliman

Step (5): Get the Required: