ESTIMATED INSTALLED COST FOR PE MANHOLE & INSPECTION CHAMBERS

DIA 1.0 Meter Manhole Chambers DIA 800 mm Manhole Chambers DIA 600 mm Inspection Chambers
8.0 Meters 7.5 Meters 7.0 Meters 6.5 Meters 6.0 Meters 5.5 Meters 5.0 Meters 4.5 Meters 4.0 Meters 3.5 Meters 3.0 Meter 2.5 Meters 2.0 Meters 2.0 Meters 1.5 Meters 1.0 Meters 1.5 Meters 1.25 Meters 1.0 Meters 750 mm
PE Manhole 172332 163962 150260 141890 124250 97950 89400 80850 72300 63750 55200 46650 37350 24196 19116 12445 9750 8250 6750 6066

Fittings 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 350 350 350 350

Excavation 2727 2727 2169 2169 2169 1655 1655 1655 1180 1180 1180 735 735 735 735 735 735 735 320 320

Backfilling 7288 7038 6788 6288 6038 5788 5209 4959 4709 4500 4500 3157 2104 1052 1052 1052 1052 1052 802 802

Load Bearing Ring 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900 1900

SFRC Frame & Cover 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100 2100

Total Installed Cost 186847 178227 163717 154847 136957 109893 100764 91964 82689 73930 65380 55042 44689 30483 25403 18732 15887 14387 12222 11538

ESTIMATED INSTALLATION / CONSTRUCTION TIME (INCLUDING CURING DAYS) FOR PE MANHOLE CHAMBERS VERSUS RCC/BRICK MASONRY MANHOLE CHAMBERS

PE Manhole 3 Days 3 Days 3 Days 3 Days 2.5 Days 2.5 Days 2.5 Days 2 Days 2 Days 1.75 Days 1.75 Days 1.5 Days 1.5 Days 1.0 Day 1.0 Day 1.0 Day 0.50 Days 0.50 Day 0.50 Day 0.50 Day

RCC/Brick Masonry 29 Days 29 Days 29 Days 29 Days 27 Days 27 Days 27 Days 25 Days 25 Days 25 Days 25 Days 22 Days 20 Days 17 Days 17 Days 17 Days 5 Days 5 Days 5 Days 5 Days