Determining Economic Life of Earth Movin PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Determining Economic Life of Earth Moving Equipment by

Using Life Cycle Cost Analysis: Case Study

Pedram Kheirkhah Sabet Ghadam1, Mehdi Ravanshadnia2, Saeed Ramezani3

Abstract: The purpose of this paper is to demonstrate how the standard economic life model for equipment replacement can be slightly
modified to determine the economic life of earth moving equipment, taking into account the declining utilization of construction equipment
over its life. Specifically, new construction equipment is highly utilized to meet base load demand while older construction equipment is
used to meet peak demands, such as during the rush hour. The objective of this paper is to determine the economic life of earth moving
equipment using life cycle cost analysis for operation and maintenance (O&M) costs. Nonlinear utilization trend was used to estimate more
accurate operation time in real situations. Economic engineering techniques were implemented for calculating time value of money,
inflation and equivalent annual cost (EAC) of O&M. In addition, SPSS software was used to trend a nonlinear regression for estimating
future costs. Moreover, the data mining evaluation used in the case study made it possible to propose ways to use loader resources more
optimally. The study took place in construction projects with huge volume of earth moving applications in Iran. Meeting the project
schedules required a fleet of 73 loaders. The model of loaders used in this case study was WA-470 Komatsu. The recommendations
resulting from the study were implemented and, substantial savings were reported.

Keywords: life cycle cost, replacement age, economic life, construction equipment, loader, earth moving.

1. INTRODUCTION Firstly, to propose an LCC model for earth moving equipment


specifically earth moving plant.
Construction equipment is one of the significant resources in Secondly, to determine economic life of the earth moving
construction projects like dam, highway and railway which involve equipment.
huge amounts of earth moving applications. Operation and Finally, to develop a cost operation regression into nonlinear
maintenance costs of construction equipment make a considerable trend with a higher R square, to determine economic life of 73
amount of the project total cost. Most of these costs have a hidden WA-470 Komatsu loaders during a case study.
nature, like operation, training, software, inventory, test and
support cost. Project managers mostly pay attention to the
acquisition cost, and do not evaluate life cycle cost of equipment in 2. BACKGROUND
their account evaluations. However, studying life cycle cost of
equipment as a decision support tool could give the manager the LCC is a concept originally developed by the U.S. Department of
opportunity to make a more appropriate and accurate decision. Defense (DoD) in the early 1960s to increase the effectiveness of
Otherwise, the hidden cost could lead to project loss. government procurement (Barringer and Weber 1996). Many
One of the key decision areas in optimizing equipment studies have been carried out on optimizing equipment
maintenance and replacement is determining economic life of maintenance and replacement with LCCA. A study on determining
equipment by using life cycle cost analysis (LCCA). Notably in the economic life of 2000 Montreal’s bus services led to saving
air line industry, the life cycle cost of an aircraft can be five times approximated $4 million per year (Simms et al. 1984). A model
more than its initial purchase. An advertisement by Compaq proposed by Shen and Smith (2006) on life cycle cost (LCC)
Computer Corp. states that 85% of computer costs are usually factors as one of the design optimization criteria used genetic
hidden, going to administration (14%), operations (15%), and the algorithm (G.A) to optimize functional design and life cycle cost of
bulk-about 56%-to asset management and service and support mechanical systems. Hinow and Mevissen (2011) chose the right
(Campbell and Jardine 2001). maintenance strategy by using genetic algorithm and its application
Therefore, life cycle costing is increasingly being used in for life cycle cost optimization. To reduce LCC of the construction
construction projects around the world due to several reasons project, one way is find out how to provide equipment required for
namely competition, increasing operation and maintenance costs, project implementation by deciding which part of the equipment
and, budget limitations, expensive equipment or systems, rising should be bought, leased or rented. For this purpose, Ravanshadnia
inflation, and increasing awareness of cost effectiveness among et al. (2010) presented a multi-stage decision making model.
product, equipment, and system users. Besides, some studies have been done in order to estimate life
The major objectives of the present study were: cycle cost parameters. Seo (2006) presented an approach to
estimate products LCC with hybrid genetic algorithm and artificial
1 M.Sc. Student, Construction Management, Islamic Azad University neural network (ANN). Also, There is a lot of research carried out
Science and Research Branch-Tehran, Iran; Email: on LCC of plants and managing their spare parts (Mitchell et al.
Pedramphoenix@gmail.com 2011, Jaafari and Mateffy 1990, Collier and Jacques 1984).
2 Assistant Professor, Dep. of Construction Management, Islamic Fleischer et al. (2007) presented a generic and comprehensive
Azad University Science and Research Branch-Tehran, Iran; Email: approach for estimating the distribution function of machine
ravanshadnia@yahoo.com, www.ravanshadnia.com warranty cost. Carpentieri et al. (2007) proposed a model to
3 Research Associate, Maintenance of Logistic Research Center determine the optimal spare parts volume in order to minimize the
Institute, Email: ramezani.sr@gmail.com
operating cost and the lost production cost for unavailability. Most These conflicts are illustrated in the Figure 1, in which fixed
of the research in the field of LCC utilization in civil engineering is costs (such as operator and insurance charges) are also depicted by
devoted to infrastructure projects like bridge and transportation the horizontal line. Fixed costs will not affect the economic life
projects. Decisions on scenarios for maintaining infrastructures decision, so it can be omitted from the analysis (Jardine and Tsang
have to be based on life cycle cost analysis (Kong and Frangopol 2006).
2004). A research carried out by Papagiannakis and Delwar (2001) The asset’s economic life is the time at which the total cost is
described the development of a computer model that performs life minimized.
cycle cost analysis of road way pavements, analyzing the cost of
both agency and the user. For more realistic life cycle cost
estimation for bridges, Chang and Shinozuka (1996) provided a 4. DETERMINING ECONOMIC LIFE OF
frame work which seismic retrofit and damage repair cost have CONSTRUCTION EQUIPMENT
been considered.
4.1 Selecting Equipment

3. LCC AND DETERMINING ECONOMIC LIFE Firstly, the equipment is selected and life cycle cost analysis is
used to determine its economic life. To have reliable results
3.1 Life Cycle Cost Model requires that the selected construction equipment be adequate in
numbers. The cost and time data should also be reliable.
Life-cycle costing (LCC) analysis considers all costs associated
with equipment’s life cycle. Accordingly, this article proposes
equation 1 for calculating life cycle cost of earth moving 4.2 Understanding Organization Information
equipment: System
This model is concerned with estimating construction
equipment cost over the life span of the equipment. Thus, the earth Furthermore, at a minimum, a life cycle costing data bank should
moving equipment life cycle cost is expressed by: incorporate information such as user pattern records, descriptive
LCCe = VAC + TC + IOC + IC + FC + MCC records (hardware and site), cost records, and procedural records
(1) (operation and maintenance). Although data for life cycle cost
+ RC + GOC + TC + DTC + SCC
analysis can be obtained from many sources, their amount and
Where: quality may vary quite considerably. Therefore, prior to starting a
LCCe is the earth moving equipment life cycle cost. life cycle cost study, it is important to carefully examine factors
VAC is the equipment acquisition cost. such as data bias, data applicability, data availability, data
TC is the tire cost. comparability to other existing data, data orientation toward the
IOC is the cost of intermediate overhauls. problem under consideration, and data coordination with other
LC is the lubricant cost. information. Some of the important sources for obtaining cost-
FC is the fuel cost. related data include (Dhillon 1999, Dhillon 1989).
MCC is the cost of maintenance and checkup.
RC is the repair cost.
GOC is the cost of general overhauls. 4.3 Collecting Operation Time Data
TC is the tax
DTC is the downtime cost. The calculation using the classic economic life model assumes that
SCC is the cost of sleep capital. equipment is being replaced with similar equipment. It also
assumes that the equipment is used steadily year by year. Most of
the equipment is not used steadily year to year. New equipment
3.2 Economic Life Model might be used frequently and, older equipment only to meet peak
demands.
There are two key conflicts in establishing the economic life of To reach this goal, it must first be established how often the
capital equipment: equipment is used as it ages to find out when it is the best time to
(1) The increasing operations and maintenance costs of the replace aging equipment according to the underlying mathematical
aging asset. model. The utilization data will trend, and can be described by the
(2) The declining ownership cost in keeping the asset in equation of a straight line(Y=a-bX), polynomial or exponential
service, since the initial capital cost is being written off over a where Y is hours/year and X is the equipment age.
longer time period.

4.4 Collecting LCC Data

When making decisions about capital equipment whether for


Annual cost

replacement or new acquisition, all associated costs should be


reflected on. In section 3.1 an LCC model was proposed for the
earth moving equipment.
One of the advantages of this model is that since various costs
like oprator wage, overhead, compulsory insurance, inventory and
CMMS-computerized maintenance management system- (Zalud
and Lanc 1972, Green and Knorr 1989) do not have a significant
relationship with equipment age, they are asumed as a fixed cost
and will not be calculated for determing economic life, but those
Figure 1: Economic-life problem
are part of the budget.
Nevertheless, it should be noted that there is no universal C1=Operations and maintenance (O&M) cost of a equipment
model for estimating all LCC elements. in its first year of life
Ci=O&M cost of a equipment in its ith year of life, assuming
payable at the start of the year, i=1,2, 3, . . . , n
4.5 Discounted Cash Flow Analysis (Interest, r=Discount factor
Inflation, NPV, Discounted Cash Flow Analysis, Sn=Resale value of equipment of age n years
EAC, Tax) n=Replacement age
C(n)=Total discounted cost for a chain of replacements
4.5.1 Interest and Inflation every n years
Which r=i/1+i in this equation.
When economic calculations are made, it is acceptable to work in To be fair, all possible cycles for the alternatives over the
terms of either nominal dollars-dollars having the value of the year same period of time must be compared.
in which they are spent or received-or in real dollars-dollars having
present-day value-. Provided that the correct cost of capital is used
in the analysis, the same total discounted cost is obtained whether 4.5.4 Equivalent Annual Cost
nominal or real dollars are used. This does assume that inflation
proceeds at a constant annual rate. The economic life model gives a dollar cost that is a consequence
To illustrate the method for obtaining the cost of capital, all of an infinite chain of replacements, or by modification for the first
calculations must be done in present-day. Therefore, the real N cycles. To ease interpretation of this total discounted cost, it is
interest must be calculated according to the following equation; useful to convert the total discounted costs associated with the
If=I+f+I.f. where If is real interest rate, f is inflation rate and I is economic life to an Equivalent Annual Cost (EAC) which is shown
interest rate (Dhillon 2010). in equation 3 (Campbell and Jardine 2001).
n
A+ Ci r i - S n r n
4.5.2 NPV
EAC ( n ) = i =0 ×i (3)
1- r n
In most cases, with replacement problems it is usual to assume that where
interest is payable once per year and so Present Value equation is A=Acquisition cost
used in the present-value calculations (Dhillon 2010). Ci=O&M costs of equipment in its ith year of life, assuming
payable at the start of year, i=1, 2, . . ., n
r=Discount factor
4.5.3 Discounted Cash Flow Analysis Sn=Resale value of equipment of age n years
n=Replacement age
It becomes economically justifiable to replace an aging equipment
C(n)=Total discounted cost for a chain of replacements
with a new one. Since it is usually years between replacements, every n years
rather than weeks or months as it often is for component preventive
replacement. The fact that money changes in value over time must
be considered. This is known as discounted cash flow analysis. The 4.5.5 Tax
Figure 2 shows the different cash flows when replacing equipment
on a 1-, 2-, and 3-year cycle. In most cases, economic life calculations would be conducted on a
before-tax basis. This is always the case in the public sector, where
tax considerations are not applicable. However, in privet sector, tax
must be calculated. Equation 4 shows the form of the EAC model
for after-tax, taking into account corporation tax and capital cost
allowance (Campbell and Jardine 2001).

NPV ( k ) = A 1
td 1 + 2
i (
itA 1 d (1 d )
2 )
k 1

i + d 1+ i (i + d )(1 + i) k
(4)
k
S k (1 t ) (1 t )
+ Cj
(1 + i) k j =1
(1 + i) j 1
where
i=Interest rate
d=Capital Cost Allowance rate
t=Corporation tax rate
Figure 2: Equipment-replacement cycles A=Acquisition cost
Equation 2 can calculate cash flow on n year cycle to decide Sk=Resale price
which of n alternatives would be best (Jardine and Tsang 2006). Cj=O&M cost in the jth year
n NPV(k)=Net Present Value in the kth year
Ci r i + r n ( A - S n ) A(1-d/2)(1-d)k-1 is the nondepreciated capital cost
C1 ( n ) The equivalent annual cost (EAC) is then obtained by
C ( n) = = i =1 (2) multiplying the NPV(k) by the Capital Recovery Factor
1- r n 1- r n
where i (1 + I ) k
(5)
A=Acquisition cost (1 + i )k 1
4.6 Trending Regression Graph loaders were being used according to their ages, and the operation
time in year which was scheduled could be expressed by equation
In the next step, the trend for Operating and Maintenance (O&M) Y=2863.2e-0.051x. However, in reality owning to reasons which will
costs must be established. The equation on straight line would be be evaluated in the conclusion, loaders older than 4-year performed
Y=ax+b where Y=cost/hour, and x=cumulative operation hours. less than scheduled operation time in year which is shown in the
In most cases, both a linear and polynomial relationship exist Figure 3. Also the real operation time data were trended, and this
for Y(x). However, a polynomial equation will give a better fit to a equation Y=4000.3e-0.134x can describe it.
particular series of data. These polynomial equations can be
generated by using a standard statistical package such as Minitab
or SPSS.

Operation hours in year


If the economic replacement age of a loader is set at n years,
then C(n) can be evaluated using the previously cited data and
converting the annual utilization to annual cost by integrating the
cost trend Y(x) over the appropriate utilization range.

4.7 Resale Value in Present Year

To draw the total cost graph, resale value in the present year will
be required. To solve this problem, finding the exact resale values
of equipment based on their ages is vital. So, expert views must be
used through a questionnaire.
Figure 3: Equipment operation time trend
The Figure 3 shows the trend line that was fitted to the
relationship between loaders’ utilization (hours/year) and loaders’
4.8 Determining the Economic Life of Equipment
ages. The reason for this relationship was that new loaders were
highly utilized to meet base load requirements while the older
As mentioned in section 3.2 by using the economic life model, in
loaders were used to meet peak demands.
addition to the results of the pervious steps during the model
process, the economic life is determined.
5.4 Collecting LCC Data
4.9 Sensitive Analysis
In this step, all the costs that were mentioned in the proposed LCC
model (section 3.1) were collected. As the projects that the
Finally, in the last step, a sensitive analysis is carried out for some
company was working on were related to public sector, tax was not
parameters which are identified during the model process, like
considered in the calculation of economic life.
interest rate, inflation rate, before and after tax consideration and
cost parameters in LCC model.
5.5 Discounted Cash Flow Analysis (Interest,
Inflation, NPV, Discounted Cash Flow Analysis,
5. CASE SUDY EAC, Tax)
5.1 Selecting Equipment
In this study, the inflation rate was 9.5 % and the interest rate was
12% because of unstable economics and lots of risk due to the
To implement the step by step framework, a large size construction
changing costs. Then by using the equation in section 4.5.1 the real
company was selected. This company owned several construction
interest became 22.64%.
equipment such as loaders, dozers, trucks, etc. which were studied to
Finding out the real interest rate, all costs were easily
determine the optimal replacement age for earth moving equipment
converted to net present value. Also EAC and total discounted cost
and to minimize total discounted cost. In this case, it was needed to
were calculated by equation 2, 3 in section 4.5.
modify the classic economic model and examine the total cost of the
group of similar equipment rather than individual units. Therefore,
73 WA-470 Komatsu loaders which were being used in construction
5.6 Trending Regression Graph
projects in Iran were selected. This number of WA-470 Komatsu
loaders was adequate for the purpose of the study. In addition, their
A plot of the trend in O&M cost would look like the Figure 4.
cost and time operation data were accessible and reliable.
Each equipment’s O&M cost is represented by a dot on the graph.
Equipment 1-73 is identified in the diagram. The polynomial line
was the trend that has been fitted to the dots. The equation
5.2 Understanding Organization Information System
calculated by SPSS is Y=1.366E-07x3-0.002x2+23.037x+65071.
All of the cost and maintenance data were managed by CMMS
software. The cost and time operation data were used through this
research.

5.3 Collecting Operation Time Data

As mentioned in part 3.3, in the selected construction company,


Cost per hour

Annual cost
Figure 4: The trend of O&M cost

Figure 6: Optimal replacement age with and without


5.7 Resale Value in Present Year downtime and sleep capital costs

Resale value was calculated by experts’ view with a questionnaire


and the results were used for determining economic life as the 6. COMPARISON OF NONLINEAR VS LINEAR
ownership cost after converting to EAC. REGRESSION

In this study, unlike most studies, two nonlinear regressions were


5.8 Determining the Economic Life of Equipment used to estimate operation time and cost per hour which depend on
equipment age. This issue helps to estimate more accurate
The result of the model showed that the economic life of a WA- downtime and sleep capital costs. As shown in the Table 1, Table 2
470 Komatsu loader was 7-year, with an annual cost (EAC) of and Table 3 the R square factor is higher than linear regressions
109,986 $. This amount would be sufficient to buy, operate, and which gives this opportunity to the manager to make more accurate
sell the loader on a 7-year cycle as the Figure 5 illustrates. This is decision.
the optimal decision. Note that the amount in the annual budget to
fund replacements will be calculated based on the number and age Table 1: SPSS Output, Comparison Exponential vs Linear
of loaders and based on a 7-year replacement cycle. Regression for Estimating the Operation Time
Regression R R Square Equation
Exponential 0.937 0.878 Y=4000.3e-0.134x
Linear 0.854 0.730 Y=-196.0x+3344.9
Annual cost

Table 2: SPSS Output, Polynomial Regression for Cost/Hour


Model summary
R R-Square Adjusted R-Square Std. Error of the estimate
0.888 0.77 0.778 200044.270
ANOVA
Sum of df Mean square F Sig.
squares
Regression 9.52112 3 3.174E12 79.303 0.000
Figure 5: Optimal replacement age Residual 2.561E12 64 4.002E10
Total 1.208E13 67
Coefficients
5.9 Sensitive Analysis Standardized
Unstandardized coefficients
coefficients t Sig.
The results of the sensitive analysis of LCC parameters proved that B Std. Error Beta
economic life increased after omitting downtime and sleep capital Sat 23.038 39.187 0.338 0.588 0.559
cost. As the Figure 6 shows, without considering the downtime and Sat**2 -0.002 0.003 -0.784 -0.581 0.563
sleep capital cost and due to the fact that the real operation time did Sat**3 1.366E-7 0.000 1.351 1.624 0.109
not reach to the scheduled operation time. Economic life of WA- (Constant) 65071.776 132578.357 0.491 0.625
470 Komatsu loader was determined to be 9-year. Notes: The independent variable is sat.
Table 3: SPSS Output, Linear Regression for Cost/Hour Carpentieri, M., Guglielmini, A. and Mangione, F. (2007). “A life cycle
Model summary cost framework for the management of spare parts.” 14th CIRP
Conference on Life Cycle Engineering, 4, 473-478.
R R-Square Adjusted R-Square Std. Error of the estimate
Chang, S. E. and Shinozuka, M. (1996). “Life cycle cost analysis with
0.807 0.652 0.646 252572.478 natural hazard risk.” Journal of Infrastructure systems, ASCE, 2(3),
ANOVA 118-126.
Sum of squares df Mean square F Sig. Collier, C. A. and Jacques. D. E. (1984). “Optimum equipment life by
Regression 7.871E12 1 7.871E12 123.38 0.000 minimum life-cycle costs.” Journal of Construction Engineering and
Residual 4.210E12 66 6.379E10 Management, ASCE, 110(2), 248-265.
Total 1.208E13 67 Dhillon, B. S. (1989). Life cycle costing: Techniques, models, and
Coefficients applications, Gordon and Breach Science Publishers, New York,
America.
Unstandardized Standardized
Dhillon, B. S. (1999). Design reliability: Fundamentals and applications,
coefficients coefficients t Sig. Boca Raton, FL: CRC Press, Florida, America.
B Std.error Beta Dhillon, B. S. (2010). Life cycle cost for engineering, CRC press Taylor&
Sat 54.964 4.948 0.807 11.108 0.000 Francis group, USA.
(Constant) -250540.707 72448.766 0.807 -3.458 0.001 Fleischer, J., Wawerla, W. and Niggeschmidt, N. (2007). “Machine life
Notes: The independent variable is sat. cycle cost estimation via Monte-Carlo simulation.” 14th CIRP
Conference on Life Cycle Engineering, 4, 449-453.
Green, H. and Knorr, R. E. (1989). “Managing public equipment.” The
APWA Research Foundation, 105-129.
7. CONCLUSIONS
Hinow, M. and Mevissen, M. (2011). “Substation maintenance strategy
adaptation for life cycle cost reduction using genetic algorithm.”
In this study, 73 WA-470 Komatsu loaders were evaluated. Results Journal of IEEE, 26(1), 197-204.
showed that average of scheduled time for loaders older than 4- Jaafari, A. and Mateffy, V. K. (1990). “Realistic model for equipment
year were 60483 hours in year, but in real situation, operation time replacement.” Journal of Construction Engineering and Management,
was 37643 hours in year. Besides, the economic life of loaders was ASCE, 116(3), 514-532.
determined 7-year which after omitting down time and sleep Jardine, A. K. S. and Tsang, A. H. C. (2006). Maintenance, replacement
capital cost economic life was calculated 9-year. Also, 10 loaders and reliability, CRC press Taylor&Francis group, USA.
were older than 9-year, which caused the cost of downtime and Kong, J. S. and Frangopol, D. M. (2004). “Cost reliability interaction in
sleep capital only for one year to be 450,000 $ for them only for life-cycle cost optimization of deteriorating structures.” Journal of
Structural engineering ASCE, 130(11), 1704-1712.
one year. Finally, data mining evaluation proved that lack of
Mitchell, Z., Hildreth, J. and Voster, M. (2011). “Using the cumulative cost
suitable maintenance strategy and not replacing loaders in the
model to forecast equipment repair costs: two different
economic age lead to contractor’s inability to perform based on methodologies.” Journal of Construction Engineering and
schedules besides a huge extra hidden cost during the project Management, ASCE, 137(10), 817-822.
performance. Papagiannakis, T. and Delwar, M. (2001). “Computer model for life-cycle
Using a nonlinear trend to estimate operation time caused cost analysis of roadway pavements.” Journal of Computing in civil
downtime and sleep capital costs to be calculated more engineering, 15(2), 152-156.
realistically. Also, in order to estimate cost per hour, the regression Ravanshadnia, M., Mohamadi, A. and Rajaie, H. (2010). “An Integrated
was trended more accurately with the higher R square than the group decision making model to determine buy, hire, or lease
linear one. Therefore, implementation life cycle cost analysis could construction equipment.” The International Conference on
Construction and Real Estate Management ICCREM2010,
give managers this opportunity to make more accurate decisions
Queensland, Australia.
about construction equipment. In addition, by determining
Seo, K. K. (2006). “A methodology for estimating the product life cycle
economic life of equipment, contractors could save considerable cost using a hybrid GA and ANN model.” Springer-Verlag Berlin
amount of budget during project implementation. Heidelberg, 4131, 386-395.
Shen, Z. and Smith, S. (2006). “Optimizing the functional design and life
cycle cost of mechanical systems using genetic algorithms.” The
References International Journal of Advanced Manufacturing Technology, 27(11-
12), 1051-1057.
Barringer, H. P. and Weber, D. P. (1996). Life cycle cost tutorial, Fifth Simms, B. W., Lamarre, B. G., Jardine, A. K. S. and Boudreau, A. (1984).
international conference on process plant reliability, Gulf Publishing “Optimal buy, operate and sell policies for fleets of vehicles.”
Company, TX: Houston, America. European Journal of Operational Research, 15(2), 183-195.
Campbell, J. D. and Jardine, A. K. S. (2001). Maintenance excellence Zalud, F. H. and Lanc, J. (1972). “Automobile reliability: A key to lower
optimizing equipment life cycle cost decisions, Marcel Dekker Press, overall transport costs.” Proceedings of the 14th International
Basel, Switzerland. Automobile Technical Congress of FISITA, 6125-6132.

You might also like