TIME BAR CHART (APPROX.

SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF 2 (TWO) NOS. PASSENGER LIFT FOR THE PROJECT "LABAID CANCER HOSPITAL".

SL Days
Task Name
no 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46

1 Plumling, Scaffolding, Main guide rails installation

Separator Beam Fixation, Counter guide rails installation &


2
Bracket fixation
Civil Work For Lintel (Door Front Wall) Depends on client

Door header and sill installation, Motor Setting & Cabin


3
Assembling

Rope Fixing, Filler Fixing, Speed Governor Setting, Inverter-


4
Controller Setting and Wiring
Civil Work For Tiles Work Depends on client

5 KTS, LOP, LIP & Other Wiring & Slow Speed

6 Bamboo Remove, Servicing

7 High Speed Operation and Commissioning Work

8 Handover

Note: Above mentioned time bar chart might vary 02-05 working days, Total work and Handover might depends on civil finishing work.

For Super Star Engineering Ltd

Shyamal Das
General Manager