No Project Activity Location Event Cause Impact Recommendations Action Plan Status
What Went WRONG
1. Example:
Telok/Tapis Fast Crew Kemaman Putra Andika 2 detained Improper monitoring by Schedule crew boat run To provide To provide
Boat by local Marine Dept due vessel owner/agent to had to be cancelled and weekly/monthly weekly/monthly
to one of her statutory keep updated all ship deferred to other day update from update from
certificate expired certificate in good order owner/agent for owner/agent for
monitoring purposes monitoring
purposes
To have a
reminder to
monitor the
validity via
calendar.
2. Telok/Tapis/ Supply Kemaman Long time standby due to IF BUNKERING AT Cannot meet the boat IF BUNKERING AT To provide early
Damar Boat / MGO problem PORT (Inability of port run schedule and PORT (need to have Bunkering
Crew Boat and bunker supplier to deferred to other day early bunker Delivery Delivery Number
provide berth and supply Number for booking so confirmation
MGO at the same time) confirmation with port and bunker
and bunker supplier surveyor to
ensure bunkering
IF BUNKERING VIA IF BUNKERING VIA can be proceed
BUNKER BOAT (Difficult BUNKER BOAT once got berthing
to find the exact time for (cargo loaded onboard
both of our supply boat supply boat from / to To advice
and bunker boat to meet offshore must not offshore team to
at the same time for close sounding hole to properly plan on
bunkering) ensure bunkering can cargo loaded on
be proceed at to supply boat
anytime)
3. Telok/Tapis/ Supply Kemaman A lot of special boat run A lot of unexpected High consumption of To plan properly for To explore option
Damar Boat / movement urgent cargo and crew MGO which is very any urgent cargo or of delay supply or
Crew Boat movement costly and difficult to crew crew boat to wait
get last minute facilities for urgent cargo
from KSB or crews so
loading or crew
Page 1 of 6
EMEPMI 2013 PROJECT LESSON LEARNT - <DEPARTMENT>
No Project Activity Location Event Cause Impact Recommendations Action Plan Status
mob can be
arrange in one
time
4. Telok/Tapis / Crew Boat Kemaman Unsafe crew embark and No proper gangway for Cause complaint from To provide 2 unit To prepare our
Damar disembark the crew boat crew boarding the crew the crew gangway (1 unit long own steel step or
boat especially during gangway and 1 unit hire the crew
crew boat alongside short gangway) and boat that
double banking proper steel step for complete with
every crew boat proper steel step
and gangway
5. Telok/Tapis / Supply Kemaman Standby at Anchorage Engine problem that Cannot meet boat To ensure surveyor to To ensure vessel
Damar Boat for maintenance and caused vessel unable schedule and delay in do proper during is in very good
documentation problem serve TLO and sometime cargo delivery survey before hire condition before
just few days after on hire hire
6. Telok/Tapis / Yard and Kemaman Improper Storage and Small storage area and too Space supposedly for To ensure full To have proper
Damar Office Late Disposal of long waiting time for project item cannot be documentation is in storage place
Schedule Waste approval from HQ used due to stored the place before sent schedule waste
schedule waste schedule waste to and to reduce
base waiting time for
dispose it.
7. Telok/Tapis / Yard and Kemaman Cargo not belong to TLO Vendor / contractor do not Space supposedly for Vendor / contractor to To ensure
Damar Office stored in yard have yard inside KSB TLO project item have yard or instruct Vendor /
cannot be used due their agent to keep it contractor to
have yard or
instruct their
agent to keep it
PMT to give
instruction to not
allow contractor
to stored their
equipment inside
TLO yard
8. Telok/Tapis / Yard and Kemaman Account blocked by port Payment problem and port All facilities cannot be Base to regularly To prepare
Damar Office do not provide early booked communicate with port mechanism or
Page 2 of 6
EMEPMI 2013 PROJECT LESSON LEARNT - <DEPARTMENT>
No Project Activity Location Event Cause Impact Recommendations Action Plan Status
information with regards to to ensure account is system as what
account ok have been
performed now to
ensure base
have info and
ensure fast
action when
receive port
invoice
9. Telok/Tapis / Discharge Kemaman Improper rigging Not enough own rigging Complain from offshore To have enough own To discuss and
Damar and equipment ie; our own equipment to and client rigging equipment to have proper plan
Loading asset requested and accommodate to all accommodate to all for rigging
Activity from vendor projects Delay in cargo delivery project equipment and
to offshore use only certified
rigging
equipment
To ensure team at
SKOB, Pasir Gudang Implementation
to provide only of check list form
certified rigging to ensure only
equipment certified item sent
to offshore
10. Telok/Tapis / Discharge Kemaman Late loading and Not enough port facility Late cargo delivery to To provide ample time To give early
Damar and discharge activity and constraint by offshore for base to prepare all notice and
Loading government regulation arrangement ie; enough time
Activity booking and before discharge
arrangement before and loading
and during loading activity to ensure
best arrangement
can be plan and
done
11. Telok/Tapis / Discharge Kemaman Late delivery of cargo to Late confirmation on duty Delay in project due to To plan properly and To ensure PMT
Damar and offshore due to bonded payment late delivery of project make early has agreed and
Loading item item confirmation for duty approve for duty
Activity payment to avoid last payment in early
minute problem time.
Page 3 of 6
EMEPMI 2013 PROJECT LESSON LEARNT - <DEPARTMENT>
No Project Activity Location Event Cause Impact Recommendations Action Plan Status
Page 5 of 6
EMEPMI 2013 PROJECT LESSON LEARNT - <DEPARTMENT>
No Project Activity Location Event Cause Impact Recommendations Action Plan Status
Page 6 of 6