Oman Ras Markaz Crude Oil Park Project

Project No.: 180515005

Document Distribution Form


Date: 17-Nov-2019 Ref. No. 9686-TR-CPP-EG-2370
180515005-EN-DDF-
From: CPP Rec. No. Page: 1 of 1
2399
Subject: ALARM AND TRIP SCHEDULE
I A Position: Name: Results:
Project Manager Kong Deren
Interface Manager/ Project
 Zhang Yongxiang
Engineer
Lead Planning Engineer Mohit Dhiman
Document Control Engineer Aaron Pascual
Engineering Contract Manager Han Yongjia
Lead QA/QC Engineer Mahima Tripathi
 Lead Process Engineer Manoj Kumar Hargude
Lead Piping Engineer Kishore Kumar
Lead Civil Engineer Li Chuanghua
Lead Electrical Engineer Arumuga Perumal
Lead Instrument Engineer Malledevaru
Lead Safety Engineer Naganjaneyulu Kowur
Lead Rotating Engineer Sagar Rathi
Lead Static Engineer Aravind Sujay Jayadev
Lead Telecom Engineer Liu Yongjun
Lead Structure Engineer Gautam Sanker
Lead Cathodic Protection Engineer Naveen Anna
Rajesh Prabhakarrao
Lead Architecture Engineer
Bejurwar
Lead Pipeline Engineer Ratnadeep Khobragade
Lead HVAC Engineer Romano More
Lead Plumbing Engineer Mohsin Javed
For P.M Review:

Please update the document’s according to CPP received documents.

Note: A-Action; I-Informed.


Illustrations:
1. The reprography shall be signed and ticked for the designated department of person after the P.M gives the
instructions.
2. Document Controller shall file the form after the designated department person fill up the results.

CPPEAD-IMS-OP-06/F09 | Version 2.1 | 05-Jun-2018 IMS/OSHMS