Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

 

BPM 305 (TMA01) – PROJECT SCHEDULING AND CONTROL (MOHAMED ALI B1210887)

S/
S/N
No: St
Stru
ruc
ctur
tural El eme
ement
nts
s Ti
Times
mesii n
ng
g Le
Len
ngt
gth
h Widt
Width
h Heigh
eightt Qu
Quan
antti tty
y Uni
nitt Rat
ate
e ($) Amoun
mountt ($
($))
(1) Suspended Floor Slab

Sc reeded and finish 13. 00 13.00 169. 00 m2 3.50 591.50

Concrete 13. 00 13.00 0.25 42.25 m3 185. 00 7816.25

Formwork
Soffit 13. 00 13.00 169. 00 m2 41.00 6929.00
Sides (Assume s ame rate as 4 13. 00 0.25 13.00 m2 41.00 533.00
soffit as the thickness is more
than 100-200mm high for drop
panels)

Reinforcement
Number of bars = 13000/300
= 43 + 1 = 44 nos (4 x 44 x
13 x 0.888) ÷ 1000 = 2.0156

2.02 tonne 1450.00 2929.00

Total 18,798.75

(2) Drop Panel 

Concrete 4 1.50 1.50 0.15 1.35 m3 185. 00 249.75


4
Formwork 4/4/ 1.50 24.00 m 11.50 276.00 4

Reinforcement
 Assuming similar to slab :
Number of bars = 1500/300 =
5 + 1 = 6 no
noss (4 x 6 x 1.5 x
0.888) ÷ 1000 = 0.032
0.03 tonne 1450.00 43.50
1.5
Total 569.25 24

(3) Column

Concrete 4 0.40 0.40 3.10 1.98 m3 205. 00 406.72

Formwork 4/4/ 0.40 3.10 19.84 m2 53.00 1051.52


4
Reinforcement 4
R10
Nnumber of R10 bars
bars = 0.4
3100/300 = 10 + 1 = 11 nos 3.1
(4 x 11 x 4 x 0.4 x 0.616) ÷ 19.84
1000 = 0.043
0.04 tonne 1450.00 58.00

Y20
(4 x 6 x 3.10 x 2.466) ÷ 1000
= 0.183 0.18 tonne 1450.00 261.00

Total 1,777.24

21,145.24
Overall Total 21,145.24
Ov
Overall
erall Area 13 m x 13 m 169 m 2
Therefore the cost per m2 is 21,145.24 ÷ 169 = $125.12

Page 18 of 22

You might also like