Professional Documents
Culture Documents
AC 150-5320-5B - Airport Drainage PDF
AC 150-5320-5B - Airport Drainage PDF
DA TE: 111110
ADVISORY
CIRCULAR
DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION
SUBJECT: AIRPORT DRAINAGE
•
AC 150/5320-58 Page I
•
• CONTENTS
Paragraph Page
• Chapter 1. INTRODUCTION
1. Characteristics of Airport Drainage --------------------------------------- 1
2. Purpose of Airport Drainage --------------------------------------------- 1
I
Chapter 2. HYDROLOGY
3. Rainfall------------------------------------------------------------------ 3
Figures 1 through 5 Rainfall Frequenc~· liaps --------------------------- 6
Figure 6 Intensltr Cur,es for Storms in ''lcinlty of Example Site ________ 8
Paragraph Page
Chapter 1. INTRODUCTION
1. CHARACTERISTICS OF AIRPORT DRAINAGE. of, any depressed or low spots on the site
a. An airport should have smooth, well- must be drained, and all surface runoff must
drained operational areas with sufficient sta- be accumulated and directed into adequate
bility to permit the safe mO\·ement of aircraft outfalls.
under all weather conditions. The design of e. Enough tests should be taken to identify
adequate drainage is important because it af- all soil types because texture, permeability, and
fects the stability and usability of extensive capillarity have a pronounced effect upon their
areas: yet, these areas are subject to varying drainability. Because of its effect on the sta-
soil and drainage conditions, and also have rel- bility of soils and on the ultimate design of
ati,·el~· flat grades. the airport, the water table should be accurately
b. The drainage system should be built be- determined o.-er the entire area. ,vhen a high
fore or during the grading operations because water table does exist, provision should be
draining and grading are interrelated. A made for controlling or lowering it-or al-
drainage system cannot be expected to function ternatirnly raising the pavement grades-see
properly unless the airport area has been cor- paragraph 21.
rectly graded to di.-ert the surface runoff into f. In designing a drainage system, it is im-
the system. In the absence of adequate sta- portant to determine expected precipitation at
bilization or pavement, drainage does not as- the airport site. Intensity-frequency or pre-
sure an all-weather airport, but it does shorten cipitation data may be obtained and developed
the interrnl of nonuse. from information in several publications as
c. The large area that must be drained on noted in paragraph 3.
an average airport requires an economically g. Localized climatological data should be
designed drainage system to realize the full studied and ad rice sought on average frost pen-
rnlne of the im·estment made. Sound engi- etration and recommended minimum depth of
neerinp: principles must be applied in the uti- storm sewer installations for the area. For
lization of all a rnilable data, such as: topo· some localities, records of a.-erage accumulated
graphic maps: soil reports; determinations of snowfall would be pertinent to the drainage
water tables: intensity, frequency, and dura- design.
tion of precipitation: climate and temperature
reports: and nature of the area surrounding 2. PURPOSE OF AIRPORT DRAINAGE.
the particular site.
d. The topography of the site and the off- a. The purpose of airport drainage is to dis-
site areas affect the final layout of the runways, pose of water which may hinder any actiYity
taxi"·ays, aprons, and buildings. The location necessary to the safe and efficient operation of
and size of these facilities will control the the airport. The drainage system should col-
grading and the extent of drainage required. lect and remO\·e surface water runoff from each
It is important that the grading of the air- area, remove excess underground water, lower
port be such that all shoulders and slopes drain the water table, and protect all slopes from
away from runways, taxiways, and all parnd erosion.
areas. After final elerntions on the airport b. Natural drainage normally does not meet
ham been determined, all surface flow of water these requirements. Constructed drainage fa-
onto the site must be intercepted and disposed cilities must be sufficient to prO\·ide for present
Chap 1 Par 1
Page 2 AC 150/5320-58
requirements and any future enlargements of serious hazards to air traffic at airports. The
the system. This may mean the installation most dangerous consequences of inadequate
of a portion of a drainage system to supple- drainage systems are saturation of the sub-
ment the natural drainage on the site or it may grade and subbase, damage to slopes by erosion,
call :for a complete system to drain the entire loss of load-bearing capacity of the paved sur-
airport area. A proper understanding of all faces, and excessive ponding of water.
contributing drainage factors determines the d. Aprons and other paYement should be
extent of the facilities required on each par- sloped away from buildings so that there will
ticular airport. be no possibility of fuel spillage flowing toward
c. An inadequate drainage system can cause buildings.
Par 2 Chap 1
AC 150/5320-SB Page 3
Chapter 2. HYDROLOGY
3. RAINFALL. maps, useful in practical problems reqmrmg
rainfall-frequency data. It is an outgrowth of
a. The determination of the amounts of
seYeral previous "reather Bureau publications
rainfall and runoff to be used as a basis for
on this subject and contains an expression and
design of a drainage system is the primary
generalization of the ideas and results in ear-
step to be considered by the designer. The
lier papers. It is di rided into two parts:
rate of storm runoff which will flow into the
system must be established in the preliminary (1) The first part presents the rainfall
design stage. At some locations this may in- analyses. Included are measures of the quality
Yoh·e rainfall plus melting sno.Y or ice. of the rnrious relationships, comparisons w·ith
preyious works of a similar nature, numerical
b. The importance of the rainfall-intensity
examples, discussions of the limitations of the
factor is well known to drainage engineers, pa;-
results, transformation from point to areal fre-
ticularly in its relationship to total runoff. In-
quency, and seasonal rariation.
nstigations haYe shown that results of studies
regarding the probable intensity, frequency, 121 The second part presents 49 rainfall-
and duration of rainfall in particula1· locations frequency maps based on a comprehensfre and
are more likely to be correct and consern:i.tiYe integrated collection of up-to-date statistics,
if they are obtained from the records of many sernral related maps, and seasonal rnriation
stations rather than from the record of one diagrams. The rainfall-frequency (isoplm·ial)
station. Single stations seldom giYe a true pic- maps are for selected durations from 30 min-
ture of the rainfall-frequency regime for rnr utes to 24 hours and return periods from .1 ~o
ious locations. The use of many stations in a 100 years.
region to determine the pattern and rn lue of Rainfall-frequency data for Puerto Rico and
the rainfall-frequency Yalues tends to mini- the Virgin Islands, Hawaii and Alaska can be
mize the limitations of a small sample in both obtained from ESSA-,Yeather Bureau Tech-
time and space. nical Papers No. 42, "Probable ~laximum
c. l\Iany inrnstigations and studies haw been Precipitation and Rainfall-Frequency Data for
conducted to find a basis for making reason- Puerto Rico and the Virgin Islands, "dated
able estimates of the intensities, frequencies, 1961; Ko. 43, "Rainfall-Frequency Atlas of
and durations of rainfall for different loca- the Hawaiian Islands," dated 1962: and Ko. 47,
tions. A pre,·iously used publication by D. L. "Probable Maximum Precipitation and Rain-
Yarnell, "Rainfall Intensity-Frequency Datat fall-Frequency Data :for Alaska," dated 1962,
has now been replaced by more recent studies. respectiYely.
Rainfall-frequency data :for the rnited States, d. The preferred source of precipitation-fre-
Puerto Rico, the Virgin Islands, Hawaii, and quency information :for the eastern two-thirds
Alaska can be obtained from a series of of the conterminous United States is ESSA-
,veather Bureau Technical Papers. Data for ,veather Bureau Technical Paper Ko. 40.
the conterminous United States are giYen in Rainfall-frequency data for the ele,·en ,vestern
ESSA-,Yeather Bureau Technical Paper Ko. States can be obtained from the physiograph-
40, "Rainfall Frequency Atlas of the United ically adjusted precipitation-frequency maps
States," dated ~lay 1961. Technical Paper Ko. currently being prepared by the ESSA·
-10 is intended as a cmwenient summary of ,Yeather Bureau. These maps haYe been com-
empirical relationships, "·orking guides, and pleted for the States of Arizona, Xe"· )fexico,
Chop 2 Par 3
Page 4 AC 150/5320-58
Colorado, Utah, ,vyoming, )Iontana, Idaho, hour basis for currn plotting purposes, there-
,vashington, and Oregon. Maps for Kernda fore, the scaled quantity must be multiplied
and California are currently being prepared by the ratio between 1-hour and the %-hour
and should be aYailable shortly. The maps for duration (1.37 X (60 + 30) =2.74"). Plot this
the ·western United States are only for the 6- intel.lsity on coordinate paper (using inches
and 24-hour duration Yalues and relations giYen per hour as ordinates and duration in min-
in Technical Paper Ko. 40 must be used to ob- utes as abscissas). Similarly, scale the inten-
tain the Yalues for the shorter durations (see sity for Chicago for a 1-hour rainfall to be ex-
paragraph g below). Rainfall-frequency values pected once in 5 years from Chart 10, for a
for Puerto Rico and the Yirgin Islands, Ha- 2-hour rainfall from Chart 17, and convert the
waii and Alaska can be obtained from ESSA- latter value to a 1-hour basis. As Technical
,veather Bureau Technical Papers Xos. 42, 43, Paper No. 40 does not have short-duration rain-
and 47, respectirnly. It should be recognized fall charts, i.e., for 5, 10, and 15 minutes, it is
that there may be. some locations where the necessary to use the ,veather Bureau dHeloped
ya]ues from the generalized charts may be relations~1ip between a 30-minute rainfall on
either an ornr or an underestimate. If the en- the one hand and 5-, 10-, and 15-minute
gineer suspects this to be the case, he should amounts on the other. This relationship is as
inrnstigate all possible sources of data for follows:
additional information to rnrify or rerise the Duration (minutes) 5 10 15
published Yalues. Possible data sources are Ratio 0.37 0.57 0.72
the local ESSA-"'eat her Bureau Office, the
State Highway Office, State Hydrographers Thus, the Chicago 30-minute amount of 1.37
Office, City Engineer·s Office, and perlwps local can be reduced to a 5-minute amount by multi-
drainage districts or utility companies. Such plying 1.37 by 0.37 or 1.37 X 0.37 = 0.51";
locally derh·ed data should not be used to similarly, 1.37 X 0.57 = 0.78" for the IO-min-
ornrride the data from the '\Veather Bureau ute amount, and 1.37 X 0.72 = 0.99" for the
Technical Papers unless there is ample e,·i- 15-minute amount. Then convert these Yalues
dence that the latter data is clearly not appli- to a 1-hour basis as described aboYe. Accord-
cable to the local situation. ingly, the 5-, 10-, 15-, and 30-minute, I-hour,
and 2-hour intensities giYe 6 points on the co-
e. The rainfall intensity-duration cunes re-
ordinate paper and a smooth cune can be
quired for design purposes, in the conterminous
drawn through the points to construct the
United States, can be deriYed from the charts
5-year cun-e. This curYe will indicate the in-
in Technical Paper Ko. 40. Figures 1 to r, are
tensity of rainfall to be expected for any time
examples of the charts in that paper. It is not
interrnl from 5 minutes to 2 hours for a storm
intended that these figures be used for deter-
that might occur once in 5 years. The same
mining intensity as the scale was kept quite
procedure should be followed to construct
small for illustration purposes. Return periods
curYes for 2 and 10 years. Figure 6 is a
of 2, 5, and 10 years are sufficient for airport
graph exemplifying this procedure.
drainage calculations and sufficient for com-
parisons between such periods. To construct f. Similar proeedures can be followed in
intensity-duration cun-es such as shown in Fig- Puerto Rico and the Virgin Islands, Hawaii,
ure 6, begin by spotting the airport location and Alaska, using charts from the appropriate
on the 30-minute, I-hour, and 2-hour charts "·eather Bureau Technical Papers to obtain
for 2, 5, and 10 years in Technical Paper No. Yalues for 30 minutes, 1, and 2 hours. The
40. Then read the intensities by scaling be- 5-, 10-, and 15-minute values can be approx-
tween the isolines, linear interpolation between imated using the ratios with 30-minute rain-
adjoining isolines is sufficient. For example, fall values cited earlier.
the 5-year, 30-minute rainfall chart (Chart 3) g. The more detailed rainfall-frequency
reYeals that the intensity at Chicago would be charts for the 11 ,vestern States, referred to in
1.37 inches. This must br conwrted to a 1- paragrnph d abm·e, should be used to obtain
Par 3 Chap 2
AC 150/5320-58 Page 5
the rainfall intensities for the more rnriable durations, it is necessary to compute ralues
conditions found in the mountainous areas of for the shorter durations for our purposes.
,vestern United States. These studies provide This can b edone by using Figure 2 of Tech-
detailed maps which depict the rnriation in nical Paper No. 40. (First note, however, that
rainfall-frequency mines in this portion of these charts show values in tenths of an inch,
the country. These maps were dewloped to so they must be converted to inches.) For
depict the rainfall-frequency rnlues for a,·erage example, read the 5-year, 6- and 24-hour
conditions along orographic barriers and in amounts for the airport location from the
mountain valleys. At some locations, where charts and plot these amounts on Figure 2.
the topography departs significantly from Lay a straight-edge across the two points
arerage conditions, ralues determined from and read the values for 1- and 2-hour dura-
the generalized chart may be either an under tions at the proper intersections. Estimate the
or overestimate. Locally a,·ailable data for 30-minute rainfall by multiplying the one-
these locations could be considered by the en- hour value by 0.79. Then proceed to com·ert
gineer to modify rnlues obtained from the the 30-minute rnlue to 5-, 10-, and 15-minute
generalized charts. Such locally derived data values by using the ratios given in paragraph
should not be used, howe,·er, unless there is e abm·e. Then convert the values to a I-hour
ample evidence to show that the local situation
intensity and construct a 5-year cune in the
insists that such data are more applicable than
manner described in paragraph e.
that in the generalized charts. The following
procedure will need to be used to convert the h. The use of the data, de,·eloped as de-
information in the charts :for the 11 "'estern scribed in either paragraph e or g above, is
States to a more useable form. As the charts taken up later in Chapter 5 and is the basis
prm·ide rnlues for only the 6- and 24-hour for estimating runoff.
Chap 2 Par 3
.,, .,,
a
a
~
.., .
(Q
°'
r;rr1<c1t
6 8
- 8...._,rrf.
6
6
~, 12(,"
, 4 I • ' ('I' , ; . '\' . _8 \ I2 POSS111LE THEN SCALE THE INTUISITY FOR THE POINT IN
•)4 4 6 8 I L'1~,\ I
,,,, f,rl e.,. 6 1•\ r' , t .s, 12[\"
6.,
( ·~,,
. ,- - ..::,-~! .• ( \,l-.'\,12 ,,,\JM,' J ( i 14 ~JC,
I"'
_,'.-'< 's·--,,
~.
/',(12
QUESTION BY INTERPOLATION BETWEEN THE TWO ISOtiYETAL
LIN(S ON EITHER SIDE Of THE POINT TO ILLUSTRATE, THE
r,, ,,7'14 /; /• / ,\ I,\ [
? ,' ,
I \ 1~·,
1
6
8
e. j{(,.,,
"{\ ~8
,
,'- ·
1.
' ,14"
I
.,
.\',
·
. . , 'I' .•, ''-16
, ' •
~ ~1i )(J• /
l '
TO 8( CONVERTED TO A I· HOU!! BASIS FOfl PL OTTING PUR ,
't 6 · .'
I· ;
1
I \ ,(
1 ,', I, ~·21
'· f-'
r'r·: >r"/·) /i,•.
POSl'S
I 6 ·,_...,
· • ' . 1 · '·. ' 1 .I( . . ,', '•'
,1" • r '. , I ' ' 24 THUS THE SCALED QUANTITY Of 1 16 INCH[ S MUST BE
M_:'· , \,8; I '1 18
·r -~ ·' a , I '. I '.!-r i , . ~4 . , ; ; ~.,-: j' ? ~ IIIJLTIPLIED BY 60• JO OR 2 R£SULTING IN 1J6°X 2 •272'
¥i~ff;;..,..,,_J) ·~
r ' (
11 I _. · . _J,) , 22
<.-~ ~i ) >~ -. I .-\-r-; ~ :z_ 11)( • 2 PLOT THIS INTENSITY ON COOROINA7E PAP[R ( USING
j -~ - 8 ; 6 j~ ,(I , f
1
lI
~
,2 . L IMGH(S P(R HOIJR AS QROINATES A~ TIMES IN IMMUT[S
8 I4 '~ ' 24 - 26 14 16 • '/ -~
6' 6
24 AS AIISCISSAS ). SIMILARLY SCALE THE INTENSITY FOR
54... CH1GAGO FOIi /. HOUR RAINFALL TO BE EXPECTEO ONCE
I 2 I 4 I- I
f ,, , 2 4 ...-·, 22 26 . 2' 2 ~. · 24 18 "".'.:.,- ' ) 1 l
12
141618'
2 ,
22 tdonce1n5yeo
rs.
2
12 28·~
24~6•',/218 ·JJe IN 5 YEARS fROlol FIGURE 2 ANO FOLLOW TIil: ABOVE
PllOGEDURE, TH(N US( FIGURE l fOfl TWO HOUR RAIN,
.
. fol I, in inches.
- te rain to bf! e,:pec e One-hour ro,rifall, ,n inches, to be expected once 1n 5 years FALL
Thirty -minu F gure
1 1 Figure 2
ALSO, CONVERT THE JO MINUTE INTENSITY TO 5-,IO-,
ANO 15 MINUTE INTENSITIES AS INDICATED ABOVE, CONVERT
NOTES TO I HOUR BAS IS ANO Pl.OT. FIGURE 6 ILLUSTRATES 2
TH£ WEATHER BUREAU O(V[LOPED RELATIONSHIPS FOR SHORT 5 ANO 10 YEAR flTENSITY DURATION CURVES CONSTRUCTED
DURATIOtl RAINFALLS THE AVERAGE RELATIONSHIP 8[TW(EN IN THIS IIANNER
I jI 30 MINUTE RAINFALL ON T/if CJ,£ HANO AMJ 5-, 10-,ANO 15-
15 f'J1/ / .' 15 1.r5
;7ir--J., \ ( • , ·SI.., 7·~ ':\. .. ".i 15 MIMJTE RAINFALL ON THE OTHER CAN 8[ OBTAINED
l /) 2/·,1(?·(-,v- .,r,1<2
I 5 FROM TH[ FOLL OWING
15 I 5/ (' 1( t \~ 4+'{
DURATION (MIN) 5 10 15
'1~ ~ • ~
. ) \l '{.~ . ';) C;' RATIO 0)7 0 57 0 72
\ .,/ ,
15 , /r,. . i
,). .- ii \ 2 5
THUS A GEOGRAPHICAL POINT ON FIGURE I WHICH INOICATES
, '\ 1'5 \' ,2\/ )_, ¥'. A THIRTY MINUTE RAINFALL or I 6 INCHES ONCE IN 5 YEARS
t· ,.;·.
j
MAY BE REDUCED TO 5 MIIIUTES BY MUlTl!'LYlflG 1.6 BY
0)7,.592 INCHES OR 10 MINUTES AS 16 8Y 057•912
INCHES OR TO 15 MINUTES AS I 6 XO 72 • 1152 INCHES
5 . ~
I • / . . \ • • •
15 . /)•·
2 " I5
',-fit. . If ACTUAL WEATHER BUREAU Rl:COROS OR SUPPLEMENTAL
15
_.. 4 )~ 1(~ ~ RECORDS ARE NOT AVAILABLE FOR THE POINT IN QUESTION
) 5 15 THEN THE CHARTS IN THE TECHNICAL f',tPER NUMBER 4 0
'RAINFALL FREQUENCY ATLAS or THE UNITED STATES'
Two·hour ,oinfoU, in inches, to be elpected Ol'\Ce m 5 yea,,
MAY BE USEO TO CONSTRUCT INTENSITY CURVES SUCH AS
Figure 3 SHOWN IN FIGURE 6 INDEED FIGURES 1,2,l,4, 5 WERE
CONSTRUCTED FROY TECHNICAL PAPER NUll8[R 40 ANO
SERVE TO ILLUSTRATE TH[ METHOD or DEVELOPING AN
INTENSITY· DURATION Cl/RV[ OR CURVES FIRST SPOT THE
AIRPORT LOCATION UN()(R CONSl()(RATION ON rtGUR[ I
130 MINUTE RAINFALL,INCHES, TO BE EXPECTED ONCE
IN 5 YEARS.I LOCATING TH[ POINT AS ACCURATELY AS
>
n
-......
u,
0
9a
...
u,
~
,, a. • ?
... F1G1rnF.s 1, 2 1 Ilainfall frequency maps. u,
UI
•
•
·--
t"I )I,
:r
.,, t"'I
-
Q
' '
"' I I "'0
.
....,_
"'...
....?
tlJ
•. ',i\• ·
6 . .86
4 6 •.• ,- 6 .{,1~ .6,6 8 t I 2 " I 4
6~- .' •. 6 _ 8_ , a ~, J -1&-,-aJ!_E·, I. 4.
6;;.j'~YI~. .T I\~--,.1 \.. ( -' 8 ~-,, , I ,18 . ~ ••
-l4
I6
.-\ 12("·.,,__1,:,'·-;,- .j"1 t'!..,' . \ ) il .'.'.' 2 ;t-, ,;
8/J \~.
e
•
.a(/
/ )
\\ \ ·
I
\14'
-0
I ~.J.f.i
\,1.,;.·x'
\,, 12
">,...14 ,2.
1
'2 . .1ll
It ii I
~ t:~6,,,,/;: ~i .i
". J•. ,,/ i . ., .·. I
11r ~,/
/~ r.
:~I"\
\ .,
-2
-18
2 4 -2 2
26
8 6 ~ -•. i('J'(6,;\'. ·J' 1! ,) I ) - 1' \
!)'. - · Y, ~
_,, . • I,. 216
16 • '~( 611, '· / / 'lJ 28
8""·- , 1 t ,' • I 8 - - - '.'i'J-U,f1, . ' \
6 6 I I.
'&,· . /I~L . I\6 -- . 2 \ .
\ 22 16 . fl-ift.~)2.
3
-· 3
6 - 2.6
-· '1:r'f..,e, , It' 22 18 22 ·18. <6·- - 3 • 32
I I2 14· 1': 24 2.6 ' ' ., 26 22 2 4 36 1 , ,
3.8
I6 · 2 ' 2. 8 2 2 ' 2 2'' 24 5 4' 3 8 2.l 3 3
· •I8 22
ona~hour roinfotl, ,,., inche, 1 to be e-..p,ected ()nee '" 2 years One-hour rainfall, in inches, to be expected once in IO years.
Fi9ure 5
Figure 4
1
.w
1
n. ,,
IQ
FrntJRF,R 4 and. Rn!nfnll frequeney mnpR. ...
...
!!
~
.
112
c.,
INTENSITY CURVES FOR STORMS IN VICINITY OF EXAMPLE SITE 0,
9 9
I- --+--------t------t------1---- --·-·+- .. -t------. ··1----------+------l
.......--+-----+--.......·--+--- - 1-- -----+-·-··--··-+-- ·-·-·-·-+--·· ·• .... ··-----t-----·-1
8
1-----l---
I---+· --+---+----+--- ... --
-------+------+------- -
. --- -t==- 8
t--+---+---+ · - t - - - - - -•···· ..... - ------+-·- ---+----- --··· - -·---+- -----1
- - - - - - + - - - - - i - - · ·------+--···
1-- -+----+ +------+-------+---- ····+---·---+ ------ .. ·----+-· -----------1
7
; 7~
0
:r
.,
~
.., t---t--'-t----11---t-----------------------------+-----t-----+-----+-----16
Q. 6
------· ·---- -----
---- -~------- -----·----
----- -- ---- -----~- - - - -
--------- - - ---~------ -··-- ···-- ----·---
.c:: ---+---~----,
---+-------
u -- .. --+--····-·· -+-----1------1
-C
5 1--=-~-l-l---l----+-----+----+-----4f-----+----------+-----+-----+-----4'-----+------15 --- ~--- ------ ____.......____......,
.=
-D _\.~l\.
11 ~l-tM-~l-8 I I· I l ! r
C: 4
0
a:
-,...
0 ·----+-·--+--·
!
"'C
3
.=
2
I I___I _I I }=:I;;;tsts:L.J
,....._....... ---. I 4 I l d· -+-
~
---+-· - - ·----
-
Duration Of Rainfall In Minutes u,
0
u,
~ "'N
II
"Cl
Frn1rnr. fi. Intensity curve,; for storms in vicinity of exnmple site.
?
u,
N "'
AC 150/5320-58 Page 9
Chap 3 Par 4
Page 10 AC 150/5320--SB
to proYide capacity in the drainage system for cordance with the respecti,·e areas. For ex-
direct runoff. The calculation of and proYision ample, if a drainage area to an inlet consists
for ponding between runways, taxiways, and of 1h acre of asphalt pa ,·ement ha dng a co-
aprons should usually be considered as a safety efficient of 0.90 and 2 acres of impenious soil
factor-for temporary accommodation of run- with turf having a coefficient of 0.35, the aver-
off from storm return periods longer than 5 age coefficient for the total area is equal to
years. [(0.90 X 0.5) + (0.35 X 2.0)] -;-(0.5 + 2.0) or
Ponding of more than a temporary nature 0.46.
may be acceptable on the air.port site other
than between runways, taxiways, and aprons. TABLE I. Value of factor "C"
Such ponding may indeed be essential because
of limitations in offsite outfalls. Type of surface I Factor "C"
5. RUNOFF COEFFICIENT.
a. The runoff coefficient or factor as it is For all watertight roof surfaces ________ , • 75 to . 95
For asphalt runway pavements _______ -! . 80 to . 95
sometimes designated, is the percentage of rain- For concrete runway pavements ______ -! . 70 to . 90
fall on a gi,·en area that flows off as free water. For gravel or macadam pavements _____ ; .35 to. 70
This percentage will seldom reach 100 percent, For impervious soils (heavy)* ________ .: • 40 to . 65
ernn with steep slopes, because imperdous sur- For impervious soils, with turf* ________ i • 30 to • 55
faces absorb some moisture and small depres- For slightly pervious soils*------------1 .15 to .40
For slightly pervious soils, with turf* __ -: . 10 to . 30
sions and irregularities hold back additional For moderatelv pervious soils* _________ : .05 to .20
amounts. During a storm, the percentage of For moderately pervious soils, with turf* ! • 00 to . 10
runoff will increase gradually as the soil be-
comes saturated, the impe1Tious areas become
thoroughly wet, and all depressions become *For slopes from 1 percent to 2 percent.
filled. Then the percentage will remain fairly
constant, Yarying directly with the intensity of 6. TIME OF CONCENTRATION.
the rainfall. The composite effect of all those a. According to the theory underlying the
factors must be taken into consideration. Rational Method, maximum discharge at any
b. Many authorities lun-e presented estimates point in a drainage system occurs when:
for ,:Yalues of relatirn imperdousness·· for dif- (1) The entire area tributary to that point
ferent types of urban surfaces, to be used in is contributing to the flow.
conjunction with their rnrious formulas. These 12) The rainfall intensity producing such
estimates coyer conditions applicable to the de- flow is based upon the rate of rainfall which
sign of drainage systems for large areas, us- can be expected to fall in the time required for
ually within urban su:::TOlmdings where the water to flow from the most remote point of the
character of surface is different generally from area to the point being inrnstigated. The
those on airports. "most remote poinC is the point from which
c. From these studies and other information the time of flow is greatest. It may not be at
pertaining to relati,·e impeniousness of dif- the greatest linear distance from the point un-
ferent surfaces, Table I has been compiled der im·estigation.
which is applicable to the conditions found on b. The time at which maximum discharge
airports. The appropriate runoff coefficient occurs is referred to as the time of concentra -
should be selected from Table I for use in the tion. It is composed of two components re-
formula Q = CIA. ferred to as the "inlet time'' and "time of flow''.
d. If the drainage area contributing to a The "inlet time'' is the time required for water
certain inlet is composed of se,·eral surfaces to flmy oYerland from the most remote point
for which different coefficients from this table in the drainage subarea to the inlet. The
must be assigned, the coefficient used in the "time of flow" is the time during which water
formula should be a weighted ayerage in ac- flm,s through the drainage system to any point
Par 4 Chop 3
AC 150/5320-58 Page 11
:.i...t• ~-'--
600 ,----::::::.:= Use Formulo For ++.. .,. ......,. . . . . . . .--+-......,Hf<""T"iH-+-t---+-+-+-<-i,1"--,-+.-.,..-......,,-..,..+++-++.-,-+-+""-i so
Dist onces in Excess:
Of 800 Feet.
----...J .,. __ -~
0
500 --,--------+----++-,---+
,-
w
....
w
z
w 400 - --
u
z
<
,-
v,
0
50
...
V,
w
,-
:i
40 z
~
f
w
~
.::
30
10
Chap 3 Par 6
Page 12 AC 150/5320-SB
inlet. All areas tributary to the particular tern should be sketched upon it, with the out-
structure are not contributing until such time line and identification of each single suharea,
as water is entering the inlet from the most all main and lateral storm pipelines, pipe sizes,
remote part of the individual subarea which it direction of flow, gradients, catch basins, inlets,
sen-es. The time of concentration, therefore, manholes, gutters when required, surface chan-
will be the "inlet time. i• Problems which arise nels, peripheral and outfall ditches, and other
in this regard will ha,·e to be im·estigated and essential drainage features.
resoh-ed individually to determine under what c. The finished grades in conjunction with
conditions of time and flmv the maximum the drainage design are very important. The
volume of water can be expected at the point location of the runways, taxiways, aprons, and
studied. building area is usually fixed by the time the
(2) "Time of flow'' can be determined by drainage design is started ; but the cross sec-
hydraulic computation, i.e., by dividing the tions of the paved areas, their profiles, and all
length of pipe by the rnlocity of flmv. the grades of intermediate areas should be care-
(3) The "inlet time,·· C'Onsidered one of fully studied for their influence on the drain-
the most important factors in determining run- age layout. It is important that all finished
off, will rnry with surface charaderistics of grades be established so that eYery area is
the drainage area. The cun-es or formula in drainable and so that the runoff can be col-
Figure 7 wi11 prm·ide adequate estimates of lected by some drainage facility.
"inlet time'' for the designer. rse the form- d. The primary consideration, therefore, is
ula for distances in excess of 800 feet. 1,11ere the determination of a satisfactory drainage ar-
the particular drainage area consists of sev- rangement at a reasonable cost, im·oh·ing the
eral types of surfaces, the "inlet time·· must location of the shallow channels, inlets, catch
be determined by adding the respectirn times basins, manholes, selection of grades, etc. Trial
established for flmv ornr the length of the computations of several different drainage lay-
seYeral surfaC'es along the path from the most outs should be made in arriYing at the most
remote point to the inlet. practical design. "\Vhen all arrangements for
location of the inlets, shallow drainage swales,
7. COLLECTION AND DISPOSAL OF RUNOFF. and storm pipes have been plotted upon the
a. Before any definite computations C'an be drainage working drawing, a tabulation of
made toward the actual design of the drainage data and computations should be made. Such
system, a topographical map wi11 ham to be a table is further discussed in Chapter 5.
prepared shmving actual ground contours exist- e. Normally, the inlets should be located at
ing on the airport area. The contours pre- least i5 feet from the edge of the pavement at
ferably should be drawn to a 2-foot interrnl. airports with scheduled air carrier operations
This map should be extensive enough to show and 25 feet from the edge of the pavement at
the areas surrounding the airport boundaries airports used exclusively by general aYiation.
with a1l natural watercourses, swales, draws, If inlets are placed close to the pavement edges,
drainage structures, ditches, slopes, ridges and they may be bypassed by the flow of water.
configurations. It should also show all im- Also, no ponding would be possible because the
prornments that might ham a bearing on the impounded water could back up to the edge
runoff and drainage of the immediate area, of the paYement and cause saturation of the
such as railroads, highways, canals, and irriga- subgrade. The grading should be planned so
tion and drainage instaJlations. that the inlets can be placed normally at the
b. An additional detailed plan is necessary edges of the runway safety area or in the area
to show the proposed and ultimate layout of midway between the runways and the parallel
the runways, taxiways, aprons, and building taxiways. The runways and taxiways should
area with the finished contours drawn to a be crowned. Beyond the paved edges, the
I-foot interrnl or less. This plan can be the slopes should be in accordance with design
"drainage working drawing." The entire sys- recommendations. In establishing grades out-
Par 6 Chap 3
n >
=r
Q
n
"ti ,._,~ NOTES.
.., u,
0
, --------
The dimensions ond grades shown here moy be used only .....
..._0<:i" / • ~ oulside of the runway safety oreo,(londing strip) or to~,- ..,..,
u,
// ~ ,
'. t
/- - - -------1\.;r
/ C,' / -__ woy safety oreo. Longitudinal grodes, longitudinol grade
~ changes, vertical curves and distance between changes
?
u,
/ / ~ - - - . . for that part of !he runway safety area belween run- "'
~ woy ends ore the same as the stondords for runways
[!]
~ ~ ~
~~
., - and stopways
: __- Ridges provided for ponding areas within the runway
- · I 5,. Slope - • ~ - - JO'l'. Slope g- 3 '- Slope safety areo sha 11 conform to such stondords. Heodwalls,
:.._ ' ~ - ~ ~~ - culvert pipe ends, and other slructures wilh prolrud1ng
. . . '-....__ ........_ --....___ jJ
=-·,,;..,"'"' '""
vertical faces shall no! be permitted within runway or
:::::t ~~" ~ ~
£'..LAN o..,,. ~ -- , /
}---- ---
E119835' ~
El 20.15' - ~ l o o . El 19835' 1 I r£11985' -·--• · ~
El 19 85'
0~
The percenloge of
!his slope should be
reduced when proclicoble.
----1~1926
-- - ~t,nuou, 1
SAMP~E PROF IL~ I -..c. - ~ ~o.e_e _ _
Pon~(ng
. _ _ _ ·---------------T
_QROSS SECTION -,.,
0
,..;
l.
l
... FIGURE R. Snggested grading for small ponding nrens on contlnnous line of inlets. w
Page 14 AC 150/5320-SB
side of pa rnments, the soil characteristics watercourses as possible can be used for outfall
should be considered so as to aYoid erosion and and rapid remornl of the runoff from the air-
promote infiltration. Less grade is used for port area. This procedure is necessary to pre-
sandy soils than for other soils. A slope of 5 Yent concentration of all the airport runoff in
percent should be used for a IO-foot width ad- one or two outfalls and flooding of property
jacent to pa rnment edges to facilitate runoff. below the airport site. By use of several out-
f. It is desirable to proYide for ponding areas falls when they are arnilable, the cost of the
around inlets as temporary storage for runoff system can be held to a minimum by reducing
from the occasional storm which exceeds the pipe sizes and by shortening the discharge pipe
design storm. If seYeral inlets are in the same runs.
graded area, it is appropriate to design a ridge j. Open peripheral ditches should be used,
between the inlets to prernnt runoff from by- whenerer practicable, to receiYe outfall flow
passing the upper inlet. These ridges and from the drainage system, to collect surface
ponding areas must be designed to aYoid un- flow from the airport site and adjacent areas,
acceptable grades and grade changes within to intercept ground water flow from adjacent
runway and taxi,rny safety areas (see Figure higher terrain, and in many cases to aid in
8). lowering the ground water table. These open
g. Inlets should be placed at all intermediate peripheral ditches should not be constructed
low points created by grading the airport. In where they will cross the rummy safety area
the case of a long run of surface drainage (landing strip) or extended safety area. The
where the fall is all in one direction, the inlets flow across this section should be placed in con-
should be spaced so that the runoff will not duit for at least the width of the safety area.
tranil excessirn distances before reaching a Before a system of peripheral ditches is
structure. Xormally, inlets should be spaced planned for an airport site, the soil should be
so that the flo.y from the most remote point of examined to determine whether the soil will
the drainage area is not more than 400 feet. erode. Open ditches haYe a tendency to erode
h. :\Ianholes, or combination manholes and because of the concentrated flow. Ditches
mlets, should be prm·ided "·here necessan: should not be constructed where the airport
is located on sand unless they are absolutely
0
Par 7 Chap 3
AC 150/5320-58 Poge 15
11 l Several formulas are used by engineers lie gradient of the pipe run. The. hydraulic
to determine the flow characteristics in pipes. gradient should be considered in the design of
Many of them girn practically the same re- storm drains because it is used in the solution
sults, but the Manning formula is the most of velocity and discharge. The hydraulic
widely used and is recommended for use and is gradient at the upper end of the line should
as follows: be established near the elevation of the inlet
Q = A 1.486 R2/3 5112 grate. The ponding volume may pr<>4uce at
n times a higher elevation of the hydraulic gra-
dient at this point.
in which:
(2) Past experience shows that a mean ve-
Q =discharge in cubic feet per second locity of 2.5 feet per second will normally pre-
A= cross-sectional area of flow in square vent the depositing of suspended matter in the
feet pipes: Economy of design and topography
R=hydraulic radius in ft.=area of section will control the velocities. When lower ve-
wetted perimeter locities are used, special care should be taken in
S=slope of pipe im·ert in ft. per foot the construction of the system to assure good
n=coefficient of roughness of pipe alignment, straight grades, smooth well- con-
(2) Charts have been compiled for the so- structed joints, and proper installation of
lution of the Manning formula. They usually structures. The pipelines and slopes should
are used instead of the formula to determi1;e be designed, wherever possible and when topo-
the size of pipe required. Figures 9 to 12 in- graphical conditions permit, so that the ve-
clusive show these charts based on :Manning:s locity of flow will increase progressively or be
formula for discharge of circular pipes flow- maintained uniformly from inlets to outfall.
ing full, with slopes from 0.0001 to 0.1 feet Thus the suspended matter will be carried
per foot, and values of "n'~ = 0.012, 0.013, through the system and out the outfall end.
0.021, 0.023, 0.024, 0.027, and 0.031. The selec- c. The conduits in the drainage system may
tion of the rnlue of "n'~ in Table II is also a be constructed of reinforced concrete, concrete
matter of judgment. The value selected should ,-i.trified clay, corrugated steel, corrugatea" alu-
represent conditions which will prevail during minum alloy, or asbestos-cement pipe. The
the useful life of the line. pipes should be of conventional standard sizes
b. The design engineer should keep in mind and provided with either bell-and-spigot or
that it is important to maintain sufficient ve- tongue-and-grom·e joints in the precast pipes,
locity within the pipes to prHent depositing adequate metal bands for the corrugated metal
of suspended matter washed into the system pipe, and couplings for the asbestos-cement
through the inlets. The velocitv of flow in pipe.
pipes depends on the head or slope and the d. The chemical characteristics of water and
resistance to flow of the wetted portion of the soil which might affect the durability of drain-
pipe interior. The head or slope used in de- age pipes should be investigated. The type
sign always refers to the position of the hy- of pipe least affected by those chemicals should
draulic gradient, which is the line assumed by then be recommended for installation.
the top surface of the flowing water when fr~e e. Bituminous coated, partially or fully
to rise vertically. The wetted portion of the paved corrugated metal pipe should not be in-
pipe interior is used in determining the hy- stalled where fuel spillage, wash-rack wastes,
draulic radius, which is the area of the inside or solvents can be expected to enter the pipe.
of the pipe di,·ided by the wetted perimeter. Such coating or paving is soluble in aircraft
The mean velocity of flow is used in determin- fuel and some aircraft washing liquids. Such
ing the size of drains. liquids are also flammable, thus a fire carried
11 l Some engineers, when designing drain- into the pipe would damage the pipe seYerely.
age systems, do not differentiate between the Design of the drainage system for aircraft
slope of the i1wert of the pipe and the hydrau- fuelling aprons should:
Chap 3 Par 8
Page 16 AC 150/5320-58
(1) PreYent spread of a fuel spill to struc- These objectives may require consideration of
tures, passenger loading fingers, or concourses, one or sernral means. For example, the apron
which could result in the fuel or vapors there- should slope away from buildings. Inlets
from reaching a sourse of ignition or might re- should be located to allow reasonable flexibility
lease dangerous or toxic yapors within the in parking of aircraft without the likelihood
structure itself. of aircraft being positioned over inlets. Sec-
(2) Prevent spread of a fuel spill over
tions of drainage systems should be isolated
large areas of the apron surface and the trans- at interrnls through use of water seal traps or
mission of vapors, which may expose a number
interceptors or separators to prevent transmis-
of aircraft or other equipment on the apron.
sion of flame or vapor through the system.
(3) Provide for the safe disposal of fuel
spillage.
Coeffic. "n"
PIPE
Clay, concrete, and asbestos cement ___________________________________________________ _ 0.012
Corrugated metal
Fully paved----------------------------------------------------------------------- 0.012
25% Paved, 2% x %inch corr_ _____________________________________________________ _ 0.021
3 x 1 or 6 x 1 inch corr_ ________________________________________________ _ 0.023
6 x 2 or 9 x 2~ inch corr ______________________________________________ _ 0.026
Unpaved, 2% x }finch corr------------------------------------------------------ 0.024
3 x 1 or 6 x 1 inch corr_ ___ . ____________________________________________ _ 0.027
6 x 2 or 9 x 2 % inch corr _____________________________________________ _ 0.031
2 x %inch helical corr
12inch diarneter----------------------------------------------------- 0.012
18inch diameter---------------------------------·------------------- 0.015
24inch diameter ____________________________________________________ _ 0.017
30 inch diameter to 48 inch diameter ___________________________________ _ 0. 018 to 0. 021
OPEN CHANNELS
Maximum Permissible
Velocity in Feet/ Second Coeffic. "n"
Paved
Concrete __ ---- ______ ----------- _______________ 20 to 30+--- _____________________ 0. 011 to O. 020
Asphalt_ ______________________________________ 12 to 15+------------------------ 0.013 to 0.017
Rubble or Riprap ______________________________ 20 to 25-------------------------- 0.017 to 0.030
Earth
Bare, sandy silt, weathered ______________________ 2,0______________________________ 0.020
Silt clay or soft shale __ • ____ . _______________ . __ _ 3. 5_ _ __ _ _ _ __ ___ _ __ _ _ _ __ _ _ _ _ __ _ __ _ 0. 020
ClaY------------------------------------------ 6,0------------------------------ 0.020
Softsandstone _________________________________ 8.0______________________________ 0.020
Clean gravelly soiL _____________ ---------- ______ 6. o___ ______ _______ __ __ __ _______ _ O. 025
Natural earth, with vegetation ___________________ 6,0 ______________________________ 0. 030 to 0.150*
Turf
Shallow flow ____________________ . _____________ . 6. O________________________ . _____ O. 06 to 0. 08
Depth of flow over 1 foot ________________________ 6,0 ______________________________ 0,04 to 0.06
*Will vary with straightness of alignment, smoothness of bed and side slopes, and whether channel has light
vegetation or is choked 'll'ith weeds and brush.
Par 8 Chap 3
AC 150/5320-58 Page 17
1000
900
800
700
600
500
400
300
200 2
120 1 .0001
108
I
J .0001
96
90 --1
84~ .0002
-f 0002
D
z
0
<fl 100 b- 0003 0
78_j w
LL
90 72 ._j .0003 --} 0004 <fl
3
80
0 66--j -0004 ---r-
70 0::
' 0006
z <fl
601 .0005
.0006 ,., w
a.
60
w
I
54 .....
(\J
-
0 .0008
0008
0010
-
0
C. I-
50 0 w
w 48~ 0 0010 0 l..
z I' /:--4 w
l!)
0:: 40 42~
' C
"
t C
" . LL
4 '- 0020
I
0
2 39j
36 I 0020 ---t
- a: -z
0::
<fl 30 z ~ 0030 0
33~ 0
0
- 30-i
LL r
-f-
LL 5 >-
<(
0::
0 27....j
'
w
.0030
L
0040
w ~ -
I-
0
~
I 0040 ~ 0
Cl. .0050 ---c- .0060 Cl.
20
24 ---<' 0 - 0 ..J
w
*
LL
i:-6
0 I' ....J 0060 ....,:._ 008 0
<fl
....J
<fl . >
21-I 0080 0100
a: 0010 ..J-
w 18 f- 7
I- •
10
w
~
<(
15
0200
'
-{ 0200
8
9
-8 D I 0300
0300
0400 9
-7 121
.0400
6 0600 10
10~ .0500
5 0600 ;;:-0800 II
.0800 1000
4 8j .1000 12
I
13
-3
6J 14
2 5 15
FIGl..RF: 9. ~on10graph for con1puting required size of eircular drain for n 0.012 or 0.013.
Chap 3 Par 8
Page 18
AC 150/5320-58
400 1.5
.000 I
.0001
300 ,
.0002
.0002 2
200
.0003
120 0003
.0004
108 .0005 .0004
.0006 -0005
96
90 .0006
.0008
100 84 0010 .0000
78 0
90 72 v .0010 t\i 3 Z
80
(\J q 0
66 0 0
0
70
60j 0 0020 • w
IJ') 0020 C IJ')
en 60 w •
~
:I: 54 ~ C 0030
a: a:
50 0 48 .0040 .0030
0 z a: 0050
0
~
4W
Cl.
0 0040
42j
z 40
z
~ .0060 0050
w I-
39~
36 .0080
0060
Cl. w
w w 0 w
30 Cl. .0100 .0080
(!)
a: z 33-j
0 .OIOO
..J 5 ~
<( IJ')
..J
<(
:I: a: 27
IJ') z
"l
0 0
20 0200
IJ') 24
0200
6 >-
~ I-
0 0 .0300
21 0
.0300
a:
.0400 7 0..J
18 .0500
w 0600
0400 w
I- .0500 >
"j
10 w .0800 .0600 8
~
9 <( 1000
8 0 9
7 12
6 10
10
5 II
4 8 12
13
3 14
6
15
2
FIGrRE 10. ~omograph for computing required size of circular drain for n 0.021 or 0.024.
Par 8 Chap 3
AC 150/5320-58 Page 19
400
.0001 15
300
.0001
.0002
200 0002
.0003 2
120 .0004 0003
108 0004
.0006
96
90 .0008 0006
100
90
84
78
...
N
.0010 0008 ..,
N
0 .0010 0
80
70
72
66
ci
C .0020
0
C
. 3
61' 60 0
0020 z
54 a:: .0030 a: 0
V> 0
,.,_ 0
,.,_ 0
50 w
,.,_ 48 .0040 .0030 (/)
._, 40 w
.0040 w
(/) 42 ll. .0060 ll.
a:
w 0 0
4 w
z 39 ll.
._,
:i: ...J
"'
.0080 0060
...J
(/)
30 z 36 .0100 I-
w 0080 w
I.? 33 w
a:: ~ 0/00 ,.,_
<l 30
5
._,:i: 20
z 27 .0200
z
-
<l
-
(/)
0
a: 24
0 .0200
>-
I-
.0300
,.,_ 21 6 0
0400 0
0 .0300 ...J
w
a: 18 0400 >
w .0600 7
I-
10 w 0800
9 15 .0600
:I!
<l 1000 .0800 8
8 -
0
7 12 .1000
8 9
5 10
10
4 I I
8
12
3
13
6
14
2
15
FIGl:-RE 11. ::--omograph for computlng required size of circular drain for n 0.023 or 0.027.
Chap 3 Par 8
Page 20 AC 150/5320-58
J
.000 I
1000 2
.00(12
-
.0003
.0004
I
500 .0005
0008 3 0
400 z
0
.0010
.-., u
w
V,
0
300 120 0 a:
108 .0020 "C ...
w
4 ....w
96 .0030 a:
200
.0040 ...
0
...w
84-· z
...u
en
78 ...
w -
z
72
D06il 0
..J
V,
5
...u
>-
-w 66
60
.0080
.0100
0
..J
w
100
<.:> 6 >
a: 54
4l
X .,,w 4&
.,,
u .0200
-
Q
%
u 42
7
-
z
z
.0300
50 -z 36 .0400 8
-er"' 30 .0600 9
0 27 .0800
10
er .1000
...w
w 24
2 2I
-"'
0 18
20
15
I2
I0 10
F1GrRE 12. :Kon1ograph for computing required size of eircular drain for n 0.031.
Par 8 Chap 3
AC 150/5320-58 Page 21
Chap 3 Par 9
...
~
,0 I R ....a"
co
10 ...
• I
•7
f'IVOT
LIN£ s
.00001
•
5
I V
.0000.
.ooooe
.0001
.01
4
Ot .ooot
.()3 .0003
3
.04
..., n .0004
.()I
.oe .OOOI
.I
2 ... .OOOI
..:... .001
C
.2
'i
.3
..: i
c.i
...
...'"'
C
r .oot
•~
:>
........ - t j. >
--:=··············
. ---·· · · - - · "'·
......
.004
.OOI
.OOI
. ,.
04
.03
-· - ----- 3--·
4 u
0
.J
0
...
.J
.01
.II
%
'
•
...>
.02
,. .01
10
.03
to .(M
.3 JO
.OI
~ 40
" ' 1.0 "·
.oa
I• O.f 11, Oft 0.00& ,1 H• ,T. .10
flTUU,Tl.0 a • G,C,4
.2
v • I.tr ,,. ~r• •re.
.10
I ),
~
:r·,· I TI '11..111 .. I
d;
s
1111111~ II
I , I I l 11111 1111111[
· ·
I
11
. ·1 'I
:1'f'ft;jffl
I
:
~0"
3,tlJ
ctm1J <,jl~ ......
"'......
?
"'"'
1
41: I I 11111~ 1 111:
,11 ,h '.oo > r ,~>.
.rv 1L 1 1 11
11I :!00
1
,11' < I I 1 11
1,11!.oc, >
~I
,r,~
..
111 11 II
11 11''1 IO
11
I' 11' •
111 I :,00 ,11'1 •
II ,, 7
t l 11 1,,1t1I~
II~ 1111111
ac 11 111 '
LS
I IIIO
,,11'
CII
::>
i5
,...... 1'' I'
11 1I 4
,......
c(
ac
u
.. ii"'
,,,1111000
,0 ..
c,O·
II
,1
11' ,
I>
::i
I , ,11 tlO 111 ~....~
::> 7 11 1 10 L .. i I o<,;
c(
ac 1111• ~....
0 I 1111 1 IO .. I I
l
11 LS
>-
:i:: 1,1 1111 so
' 11
11 1•'
-o
.4 111
l'I /11_,1''1
111.,
111 I :,0
-.,..
.a
1 ~ 11
1
11
~,,I 111111h1l~1
,111.~ ~
" " - - --- ~ ZJ
21
,
.l
I J
• 5
• •7 I IO
11
_ _ _ _ _ _ _ _ _..
WMJ..Jlu,.,l.1.lullu.lullu.l1.1U.ullwllwll
.l .J .•
1111
1,11 I
• I
41
.•
4 CSJAQ
b ...
I
J)l
e l•
• FIGURE 14. DlmcnslonR of trnpczolclnl chnnnelR with 211.i to 1 Ride Rlope. N
w
l .,,
Q
~
1/J
,0
"N
....
I r1r1pn1
, ,, ,1900
• I;- l l -I I -+ I 1 ,,_,.,
,·---
I 11
• t - - _ j ..
I
i I
,,,,,,,..,.,
,,
JI I
I'
, , 1l)O
,, ,,I
• ,, I ,00
,,,,_
'.
·1- --+--
I
J
I I t
- ' 1I .I
II
,,
....... I I'
1•'' "'°
a:
2 ttltl -~ 1----~~ 1 '
I I
I I
~ I I tOO
~
l
•
I' t--
T -- II ------ ,r.n
"':, II .l 'oo
~"
.
0
a: j·o',~-~y- .\
.,o'¥<_
~
c;~· ".
.I I
~
+-
1----1-
..., l
., ~-------.J
---- ---t
e: - I ,I•''°
' J , ,,
1
100
~
•
b
•
.
j ,1
...J
:,
• =i· 1- ~ -\
,
.
, 1 ,
f 11• fO
1
'•0 """"
•
-- b?W' / -,.'1
I
I I
t
q"-~ .
a: ·' ! ..,..q...
0 I 15 Q(r.;
>- l,,)''I~
I:
'
5 - - +7 < 1. ,I. ',o
·;,4 f-l I
I,. ...,
' 1I1! t
• I I - ,. 11 I '
J
,, ,' 1,/'' ,,
-
- 1·
I' I
,
,,1,,,,, I
, ' ro ,,,
. I 11 Lr:, !I llllll
r J
• !.•1190
I
r
[l/JJl!lJ!IJJ11
.,
11
.4 . 3
AREA , A, SO.FT
"
>
n
-......"'
0
g "'...N
....Q Q
... Frouni.; 15. Dimensions of trnpezoldnl channelR with 8 to 1 Ride slopes. &
Ill
AC 150/5320-58 Page 25
- .
-~~
-'"-+'"--"~>.-+----------==- ..
-
---=
~:k"d<-"'v-......-t-------"""-"':;;.,o
-+:"<"i~!->.----+.------==--==-..
-t',N~"'t---",;cr--------'--=-=;-
- I
l!Wl'"~....w.f-'~~~t>.t-__.._,"""a
E--+--+--""""......,.~.µ..-...._;...,__ a
. -==-__i
!!
-:
. . . "!
Chop 3 Par 9
Page 26
AC 150/5320-58
I
--
-- - - ,,, xv'
'
•
-- ,0
'
--...
,n
-s-..,
-- ...-
<>"',¥,
0
'
-
0
b-,-..-,-h-,r.-r+-T-r...--.rt..,.....,,...-.-..--fn.m-= 2
1.---lt+-\--l,l-'~---;l.----+-+--+-l~--= ~ ...
~--fr-\-l-\-~t--lt-\--\--1l-t'..-t---=
- i
-
---
:..
••
- ·-
&---+-~ -->,.->,~~-->r--t.--\--'.--lt--= i
-
• ·-
"'c-.;
-- o • E
·-
0
,--- N
--
-.
--
-
...
N
- - "' . ..... •
•
...
Chap 3
Par 9
AC 150/5320-58 Page 27
....
lC
.i
lC
z
0
;::.
,,. u
. z
...z
:,
0
0
.;
u
! -i;:
...
0
z
0
"'
:, ;::.
."' "' :,
-'
0
...
0
. ...
C
C
u
i
C
lC II:
u
."' "
0
2
i 0
z
~
.
--
ii
l r,;
,::
t 0
"ii.
§
E
i5
...
,._;
.. 0
...
C
C
"'
f--~-+~~-+~~+-~~--+--+-+-+~f---+~+.~-+~~--''1.--~-+....>.,~~-:
. - . . ... . ~
,., 9
Chap 3
...a ...
a
~
.
ca
.c,
...
""
d
1
PIVOT SIDE
6 t L Ill E SLOPE
5 too~ '
10 I
t I
• l!IO
100
i ..
__J
l I I
s
t . .
:1 ~
~
-...
•
I
I
1.'
I. I
40
....,
X
."'
.. 'SO
..
0
I S· I
.
0
.J
. to
- "'-
I
. .-
J:
4 I
.
0
•'
•
.7
..
X
10 ~
0
II
.J
"'
".u":r
w
0
I I
I
....
] ·t
a ' '
s
%
"'u
II .."'
.4
.
JI
.S
t '
.f
[XAlll'LE
.t
f..-- - . - --- ' . J •.
-·...
-· . t • ,, . r,•1110.1,•Dl
.
I ... ·--t•Jf'- t .... • I I
r I• - I • t •••.
..
.> '::::Ji
,
I ·I
NOTt: THIS
FLOW
CHAIIT
HAVE
TO IE
ll[[N
USED TO
O[T[AIIIN[O
OBTAIN
(FROM FIG.
OTHEII
181
DIMENSIONS arT[II '- AND 4 ,011 IIAlltllUII
,.n
-"'
n,..
a
-......
Q
"'
,:, l•'1Gnnr,: JP. Solntio11 for 1limP11RionR of r,arnholl<'. chnnnPls. ?
... "'
OIi
AC 150/5320-58 Page 29
1.6
0.2
0
0 0.1 0.2 0.3 0.4 0.5
RETAROENCE COEFFICIENT n
BUFFALO 1.6 -- --
BLUE GRAMMA 1.5 1.4 1.3
BLUE GRASS 1.4 1.3 1.2
BERMUDA 1.4 1.3 1.2
LESPEDEZA SERICEA 1.3 1.2 1. 1
EXAMPLE:
Chap 3 Par 9
Page 30 AC 150/5320-SB
Par 9 Chap 3
AC 150/5320-SB Page 31
0 )f
-rFillet weld 1
! ~r Fillet weld O 0
=---.
I '
I 8
i[JDDDDOJ
g-
';.,, c,,
C
:woooorn
I
"'4>u
0
c
4>
0. !OJOEJ[B)O[D i
0
0.
<fl
E
.; lliJD@~orni
3"
A
.-=-- it<'l 1',, 11:
C1>
_,.. iOJOOODDJ[
l_ Ii i IJ:I'1, ~
0
rt')
B B
Ji i: 11
,1
<t
"' !0]0000[]11
3'" ,.. ' 1[]0000[]1
,0 j",3f'Bors J 3 ~ • r 'f
,Ir ~ Web welded-
1"
@ _, I gggg0ii
() 0
PLAN
~~,______C2of_ -- 1•
sr • 3f' • f Irregular T frame.:.
•
1·
_ ...4
f" • 3j II
Bars notched
PLAN
for i" • I" cross bars~
,n _{__
Grode --------;:;I l
-3 Courses of brick
f • 12" t Anchor bolt
19"
18"
,, - 1__
SECTION A-A
SECTION 8-8
Welded Steel Grate CD
Cast Iron Grote ®
I 9f Grate S1ze i• I 12"
, 3 Courses
17 l" lnlel Ooen1ng ~ Anchor bolt - of brick
C
NOTES
©
1 Inlet grating and frame to withstand a.r-
croft wheel loads of largest a,rcraf1
to use the facility
2 _Details, dtmenSIO<ls,ond styles of grntes
and frames do not represent those
© available from any manufacturer.
E. ~, ,- - - , :J .---, i
Select10n of grates and frames wil I
depend on needs for capoci1y,
. ti:;=.'<:::=== . t==,
strength,onchor1ng ,ond single or
multiple grates.
© '6",3f·r a,
Irregular
T frame
SECTION C-C
Cast Iron Inlet Grate @
Examples Of Typical Inlet Grates
Chap 3 Par 10
Page 32 AC 150/5320-58
.---
•
8 !
LI
. a, p'
"" 8
·ij
,. !+
~~~~~~~
A <I
I J
l· • _J •ID
: 0.:.,
<I
z Grate not Grate not
..~~~~~~~
0
~
~
~-
...
~1·
0
• ;+t: Ul
. ""
L 2·-11·
I
PLAN PLAN
21¥;
5'- 3 .,,.
Pave
SECTION 8-8
Three-Grote Inlet Structure
~o~,~~o ; ; II 1
• ~ 2'-6"
L <= 8BBBBB
C
Grale not \I !-= ·.·Jc.
.
l
I
000000 shown g
000000 • . i D
gggggg ~~ ~:J
~:
'l=J!.;;;O~D~O~D~D;,;:D~===;;=~~=( -"':
• •
II:
~. • '·. ' •
; Ii • :
;• • • • : #
..._~ •)
~I
PLAN
Fin. G.L
3'-6" •,:
3 Courses of Brick
a•
·.~·4&:::S?.f~ff;
~·, Reinforcinq bors
12· o.c. for depths 3' to 8';
SECTION C-C Jte"; Bors 12• o.c. for SECTION D-D
Two-Grote Inlet Structure depths 8' to 17'. One -Grote Inlet Structure
!!Q!ll.: Examples of Inlet Design
Oetails dimensions, ond materials for
inlets os well as for ~rates and
frames ore illustrative only.
Par 10 Chap 3
AC 150/5320-SB Page 33
Length 4 D
1 1
I
t---------------4I
I I
L..-------------...J
20·
ELEVATION SECTION
Chop 3 Par 10
Page 34 AC 150/5320-SB
C
:i
0 .<t,I'
i<, -'I
<t!
" '
PLAN
Bolt
1
!~ HC?,r1t 8 Vert
.. ;. ! oc -
i - 12
~
No1e- The Radius Of The
~ j~ , , Rounded E ntronce Should
1
.-. Be From 11! To 1/7 The
L
01ome1er Of The Pipe
~
0
\
;) !
>
.
~
Appro1.
Approx
Wt Cover 325 Lbs
Wt frome 260 Lbs
Tt11c1i.n111 Of Cower 2~
·~
> HALF PLAN SECTION
"'
-'-- '--"--=-----=-~'--.::__..:..C"'-..,.....J
dimensions of M.H. frames ond grotes are illustrative
not intended to represent those of ony monufocturer
TYPE C SECTION C- C
Par 10 Chap 3
Page 35
AC 150/5320-58
-
~~~~~~~m ~~~00~~00 II
---
CD
1
-i ...... 2"
TYPICAL PLAN OF DOUBLE INLET GRATING
WATERWAY OPENING= 5.0 SQ. FT. (DOUBLE GRATING)
ASSUME GRATING IS PLACED SO THAT FLOW WILL OCCUR FROM
ALL SIDES OF INLET. FOR LOW HEADS DISCHARGE WILL CONFORM
WITH GENERAL WEIR EQUATION.
Q= CLH 3/z
WHERE
C= 3.0
L= 13.0 FT.GROSS PERIMETER OF GRATE OPENING (OMITTING
BARS l FOR GRATE ILLUSTRATED
H = HEAD IN FEET
FOR HIGH HEADS DISCHARGE WILL CONFORM WITH ORIFICE FORMULA:
Q=CA~
WHERE
C= 0.6
A=50SQ FT.
2
g: ACCELERATION OF GRAVITY IN FEET PER SECOND
H• HEAD IN FEET
THEORETICAL DISCHARGE RELATION TO BE MODIFIED BY 1.25
SAFETY FACTOR
COEFFICIENTS BASED ON MODEL TEST OF Sltl.lLAR GRATES WITH
RATIO:
NET WIDTH OF GRATE OPENING TO GROSS WIDTH= 2:3
16 ~ - ~ - ~ - - - . - - . . . . . - - - , - - - - - - , , - - - ,
10 20 30 40
DISCHARGE IN C.FS.
Par 10
Chap 3
Page 36 AC 150/5320-58
Grates and frames for Utility and Basic rectangular design. They are usually made of
Transport airports may be those used by the reinforced concrete, brick, concrete block, pre-
municipality or for highway loadings. Those cast concrete, corrugated metal, or precast pipe
for other airports should be selected to accept sections (Figure 24). The design will depend
aircraft then using or expected to use the air- on the stresses to which they will be subjected.
port in the future. Adequate unobstructed space must be provided
Some manufacturers of grates and frames within the manhole to enable workmen to clean
produce types specifically designed for airport out the line when necessary. Inside barrel di-
loadings such as 100, 150, 200, and 250 p.s.i. mensions equivalent to a diameter of 3-% feet
Hold-down bolts, hooks, or other devices should and a height of 4 feet are usually considered
be provided for the grates to prevent displace- sufficient, but they can be varied to suit par-
ment by traffic. The engineer should specify ticular situations.
the design load to be carried by the grates and h. A gutter is not permissible along a run-
frames and require the vendor to certify that way or a taxiway as it could be hazardous to
the items furnished have that capacity. aircraft operations and would interrupt the
e. The inlet structures may be constructed runoff which should flow unobstructed trans-
of reinforced concrete, brick, concrete block, versely off the pavement and across the safety
precast concrete, or rubble masonry. They area to the field inlets. In wide apron areas,
should be strong enough to withstand the Joads the inlets should be placed in the valley of the
to which they will be subjected. pavement at proper intervals to collect runoff.
f. Catch basins for airport drainage are not i. Inlets in paved areas frequently cause
usually considered necessary particularly when trouble due to differential settlement of the
drainage lines are laid on self-cleaning grades. drainage structure and the adjacent pavement.
Under certain conditions, catch basins are The resulting depressions around the inlets may
needed to prevent solids and debris from wash- result in pavement failure through softening
ing into the system. They should be cleaned of the subgrade. Particular care in compaction
out frequently and im·olrn an additional main- of backfill around inlets will prevent settle-
tenance problem. ment. In rigid parement, the structure is
g. Manholes are more or less standardized normally protected by expansion joints plaeed
as to type and can be round, m·al, square, or around the inlet frame. Also, construction
Par 10 Chap 3
AC 150/5320-58 Page 37
joints are installed at a distance from the to 2.0 for grates in turfed areas to compensate
structure which either matches or is equal to the for grass cuttings. Replacement of drainage
normal spacing for joints. The slab thus lines or structures in or under pavement
formed around the structure should include would be expensive and would disrupt traffic,
steel reinforcement to prevent cracking out- therefore, the drainage system should be de-
ward from each corner of the inlet. signed with a capacity sufficient for the ulti-
j. The number and capacity of grates mate pavement configuration. Terminal apron
selected will be dictated by the quantity of run- drainage design should be coordinated with
off to be handled as well as by the depth of those responsible for the fueling methods and
head at the grate. In low head situations, systems to be employed, as well as with those
capacity (discharge) of the grate(s) will con- responsible for fire and rescue services.
form to the general weir formula, while in In large paved areas, such as aprons, some-
higher head situations the orifice formula is times it is feasible to design several segments
applicable. These formulas and the transition of the system without ridges between adjacent
between them are described in Figure 25. inlets, thus avoiding grade changes and at-
tendant inhibitions to traffic. In these cases,
Medium or high head ponding will be un-
the efficiency of the grate and its placement
acceptable to personnel sen·icing aircraft with
should be considered. For such efficiency, all
baggage, fuel, food, etc. Morem·er, such pond-
rectangular bars should be parallel with the
ing could obscure pavement markings and thus
flow and the openings should cover at least 50
inhibit parking of aircraft at gate positions.
percent of the width of the grate. Multiple
In some cases, flooding of refueling pits would
grates should be placed normal to the direction
occur. Although inlets should be located be-
of the flow.
yond gate positions, controlling elerntions and
apron configuration may result in location of
inlets fairly close to the field side of the air- 11. CULVERTS.
plane. For these reasons, the weir formula A drainage culvert is designed as a structure
and low head is appropriate for use at some (other than a bridge) to com·ey water through
locations. or under a roadway, runway, taxiway, or other
In general, aprons sen·ing instrument or all obstruction. The choice of circular, oval, el-
weather air carrier operations warrant a head liptical, arch, or box cross section and single or
limitation of 0.4 feet. Also, airports where multiple installation will depend on capacity,
continuing operations are regularly conducted headroom, economy and occasionally be dic-
in severe weather conditions would warrant tated by local rules or requirements.
use of a similar limitation. This presumes The development of a new airport site, or
that apron widths and configurations at other the interruption of natural stream channels by
locations will allow runoff to flow directly to airport facilities, or the increase in runoff
turfed areas or that the comparatfrely light caused by airport development may require the
traffic in severe weather conditions could adapt design of culverts or consideration of the
to deeper ponding. It is recommended that capacity of existing culverts. In some cases,
apron areas drain away from buildings, when- the airport storm sewer system will need to
e,·er possible. accept off-site runoff and culverts under roads
The orifice formula portion of Figure 25 is on the airport perimeter could indicate the
applicable to grates in turfed areas, except for volume of runoff to be accommodated.
the unique case where ponding must be Local highway departments or drainage dis-
severely limited, such as small turfed areas be- tricts normally have jurisdiction over design
tween aprons and closeby taxiways. The and construction of culverts and channels. In-
safety factor of 1.25 mentioned in the diag-ram deed, such governmental units may insist on
in Figure 25 is intended for use in paved use of certain design criteria. Accordingly,
areas. That factor should be increased to 1.5 proposed modification or improwment of
Chap 3 Par 10
Page 38 AC 150/5320-58
drainage facilities under roadways or off-site, Field inspection and evaluation of down-
should be reviewed and approved by the re- stream controls or obstructions would indicate
sponsible gm·ernment agency. the potential depth of tailwater and thus in-
The objecti,·e in the design of an economical dicate when outlet control will be applicable.
culrnrt is to provide a waterway opening Usually channels are wide as compared to the
adequate for the passage of floods, and selec- cuh·ert and the depth of water in the channel
tion of a culvert meeting that objecfo·e is is considerably less than critical depth and thus
based on the cu!Yert's hydraulic capacity and inlet control is applicable.
site conditions. It has been demonstrated that the capacity
Many formulas have been developed over of a culvert in inlet control can be increased
the years to estimate runoff/flood discharge by providing a rounded, bernlled, or tapered
and to determine the size of a culvert. The entrance. In other words, the capacity of a
magnitude of the design flood is a function of thin edge projecting metal pipe can be en-
its frequency, therefore, it is important to use hanced by the addition of an attachment or the
the appropriate frequencf building of a rounded, berelled, or tapered
Because of the potential risk to adjacent entrance into a headwall. Similarly, the
property and to automobile traffic, the design capacity of other types of pipe or box culrerts
flood frequency used for cuh-erts under roads can be increased at little cost by incorporating
is for a greater recurrence interrnl than that
a beYel into the headwall.
used for airport storm sewer systems. The
local highway department or drainage district The procedure for selection of the culwrt
may establish the flood frequency to be used: size and t)·pe for most design conditions is
common practice is to design cuh·erts for well covered in several publications. These
minor roads for 10- to 25-year flood frequency publications include charts or nomographs
and for major highways for a recurrence m- allowing- comparison of the capacities of
terrnl of 50 years or more. rnrious types and sizes of culrerts, therefore,
The rate of discharge or flow through a the most economical choice will be apparent.
cuh·ert involves either of two major types of Current issues of sernral, widely used pub-
cuh-ert flow; ( 1) flow with inlet control or lications are listed in the bibliography as ref-
(2) flow with outlet control. Under inlet con- erences 9, 14, 15, 17, 18, 21, and 24.
trol, the cross sectional area of the culrnrt, the
inlet geometry, and the amount of headwater ObYiously, the foregoing is not intended to
or ponding at the entrance are of primary im- be a complete treatment of culrnrt design, but
portance. Outlet control inrnh·es the addi- is included to emphasize some of the funda-
tional consideration of the elerntion of the mentals and to recognize that the airport de-
taihrnter in the outlet channel and the slope, signer may need to consider and include
roughness, and length of the cuh·ert barrel. cuh-erts in the total design.
Par 11 Chap 3
AC 150 / 5320-58 Pag<> 39
OF PAVEMENT COURSES.
* * GRADE MAY VARY WITH AIRPORT
CATEGORY.
to .4
'iiJ G'·, Impervious Material (Topsoil)
0,:/0 •. 0:-:00 11 ~· o .... o . . .
C
*36'
*~I.~:&
.~ ...,.-:r-·'::
,~ 10 P.C:
Cone. ·~r//// / r--._
~:.i>"::f·./ t
/ .r-,...L_ ,,r •
Impervious u ·
material (
Topsoil· )
<I ·o:. . --'"
~ .. o '-'.o.·.<;J,.~:f.tj::~:j';o r,3 to ,4
0
·9· ·." o.·:Vo
· ~ "/. / /'"'-,.___.),:
·o ....... ..· ~ / / ~
. ~.6 ~0 -.. ~.- S~bbose·Q·o·:· 0 ·,:j o-.~
o q ·. ·O ~- :,f9_'.~·-. o-~
~·.v :<::> (Jo t:;;·;.·
"'
AC 150/5320-SB Page 41
drainage is definitely required to remove the could become inoperatiw when water freezes
water from the top of the impen·ious layer. upon contact with the drainpipes. Field de-_
If the laver is not too far below the surface, terminations of frost penetration show that
the subd;ainage pipe trenches should extend the depth of penetration for various soils are
slightly into the impen-ious layer (approxi- fairly consistent for the same location.
mately 6 inches) and be backfilled with a (1) In granular soils, frost enters the
granular material. The granular backfill ma- ground quicker, penetrates deeper at an earlier
terial should be placed around and adjacent to stage, and leaves the ground more rapidly in
the pipe. the spring than in a tighter clay soil. In a
(4) There are cases where an airport will clay soil the frost gradually leaYes in the early
be located on a site in which an imper,·ious spring from both the top and the bottom of
layer of soil is on the surface, with a per,·ious the frozen stratum. It finally tha""s out at a
st~atum below. Surface drainage will always point somewhere near the midsection between
be needed for draining such a site, and the the ground surface and the point of deepest
svstem should be designed to remorn all of the penetration. During this thawini;!-out period,
e~timated runoff. Again, a thorough under- the soil becomes saturated and Yery unstable.
standing of the types and extent of the soil (2) Frost heaving may also occur and
with their respectiYe profiles will be needed be- cause damage to the drainage system. Frost
cause grading operations may open up or heaving is the result of freezing of capillary
pocket the underlying porous stratum. The moisture that cannot be remored by drainage
underlying porous stratum often introduces from certain soils of a silty or silty sand
underground water onto a site, requiring inter- texture. The best way to eliminate frost heave
cepting ditches along the edges of the airport is to remorn the unfayorable soil to a sufficient
or an intercepting drain line to cut off and depth and to replace it with a suitable material
diYert this flow. Surface runoff sometimes not subject to frost heave. In some localities,
maY be directed into the porous layer, if it is low temperatures and snowfalls result in deep
ext~nsi,·e enough, by tapping through the top frost penertation and deep accumulations of
impen·ious layer with proper structures, and sno"" on the parnment shoulder areas and ad-
allowing the surface water to enter the porous jacent thereto. As a consequence. the thaw
layer. period is prolonged and may result in satura-
(5) Drainage engineers frequently find tion of the subgrade and instability of the base
the situation in which there are irregular or subbase.
strata of pen-ious and imperrious materials. Installation of edge subdrains is the usual
The most important thing in this situation is solution, however, it may be found that a
to locate all of the pockets existini;! beneath the
widened subbase will be as effeetiYe and of
surface and to prm·ide sufficient drains to re-
reasonable cost. The examples of widened sub-
mow the water from them. Drainage from
base sections sho""n in Figure 26 are not in-
those pockets can be piped directly from the tended to be standard, as the dimensions and
site or fed into the surface drainal!e system by some of the grades will rnry with the paw-
proper connections. In some cases it may be ment depth and the airport category. This
necessary to remoYe the undesirable material
method of subsurface drainage is not advo-
from th; pockets, especially under and adjacent
cated for airports unless it has been shown to
to the payement, and to backfill "·ith desirable be practical in the general soil and climatolog-
material. ical situation applicable to the site.
b. In seasonal frost areas it is important to
determine the frost penetration, since the
14. LOADS ON CONDUITS.
drainage pipelines should be placed below this
depth whenewr possible. A serious condition a. In the design and construction of drain-
could dewlop if the draina::re lines were laid age system conduits under pa,·ement, the
aboye the frost penertation line. The system maximum anticipated wheel loads should re-
Chap 4 Par 13
Page 42 AC 150/5320-58
TABLE III. l\Iinimum depth of eo,er in feet for pipe under flexible pa,ement (Part 1)
il 0.075 ______ i 1.5 : 2.0 i 2.5 I 2.5 I 3.0 2.5 ', 3.0 1'
I I
0.105 ______ : 11.5 I 1.5 i 1.5 i 2.0 j 0.105 ___________ 1.5 11.5 2.0 2.5 I 3.5 I 4.0 I 1
I
i 0.135 ______ i I ' ! 1.5 1 1.5 2.0 2.5 1 3.0 0.135 ___________ 1
! 2.0 2.5 ! 3.0 3.5; 4.5: I
i o.16s__ ____ ; i 1.5 1.512.0 I 2.0 j 2.5 0.165_, _________ I 12.5 l 3.0 ! 4.0: 5.0 I
I , I
,------------------'------- I
: AIRCRAFT WHEEL LOAD-110,000 lb. dual to 200,000 lb. dual; 1
AIRCRAFT WHEEL LOAD-110,000 lb. d. to 200,000 lb. d; 190,000
'190,000 lb. dt. to 350,000 lb. dt; up to 750,000 lb. ddt & 1,500,000 lb I lb. dt. to 350,000 lb. dt.; up to 750,000 lb. ddt. & 1,500,000 lb.
1
Metal Pipe diameter (in.) · Metal ! Pipe diameter (in.)
1
thickness thickness ,-------------
I (in.) i 12 18 24 36 48 60 J2 84 96 (in.) ! 36 48 60 72 84 96 108 120 ;
!-------,-------...,.------,------1 , I !
I I I, I :
I
1
i I
0.060 ______ : 3.o : 3.o : 3.o .
'0.075 ______ ! 3.0 3.0: 3.0 I 3.5 5.0
I
I
I
'1 I I
I 0.060 ___________ 4.0 4.5 i 5.0 ii 5.0
! 0.075 ___________ 1 3.0 3.5 ' 3.5 14.0
I
4.0 : 1
o.1os__ ____ ! · 2.0 : 2.0 : 2.5 3.5 4.5 • I : 0.105 __________ _( 2.0 2.0 3.0 I 2.5 4.0 ! 4.5 : .
o.m ______ ! 1 I 2.0 3.o j 4.o I 4.5 1 5.5 i 0.135 ___________ 1 2.5 i 3.0 3.5.4.015.0; I
0.165______ 2.5 , 3.5 4.0 : 5.0 ! 5.5
I
0.165 ___________ : I 3.o : 3.5 . 4.5 , 5.5 I
I ASBESTOS CEMENT I
l CLAY AIRCRAFT WHEEL LOAD-up to 30,000 lb. single and up to 40,000 ;
:--~- I
: AIRCRAFT WHEEL LOAD-up to 30,000 lb. single and up to 40,000 I I lb. dual [
• lb. dual Asbestos : Pipe diameter (in.) I
cement- l : - - - - - - - - - - - - - -
I
1
I
!I Pipe type Ii
Pipe diameter (in.) class J 6 10 12 16 18 24 30 36 42 I
I 6 10 12 15 18 21 24 30 36 1500_______ , 2.5 i 2.5 ! 2.5 2.5 i I 1 : i I
i 2.5 i 2.5 I 2.512.512.5 I I
1
2400 ______ _1 2.5 I I I
5000 _______1. 1.5 1.5 j 1.5 1.5 I 1.5 11.5 ,. 1.5 j 1.5 ,
1 1.0 I 1.0 11
I
AIRCRAFT WHEEL LOAD-40,000 lb. dual to 110,000 lb. dual
AIRCRAFT WHEEL LOAD-40,000 lb. dual to 110,000 lb. dual Asbestos Pipe diameter (in.)
1
I
I
I
Pipe diameter (in.)
Pipe type I class , -
cement- 6 -10- -
12 - 16
- -18- -24- -
30 - 36
- -42-
I I 6
10 12 15 18 21 24 30 36
i 1500_______ 5.5 I 5.5 1 5.5 5.5 i 6.0 I .
!Std. strength; , ; l ! 1 ! \ I 2400 _______ , 6.o , 6.o 6.o 6.o 6.o
: clay _____ 4.0 , 5.5 6.0 , 6.0 ! 6.0 I 6.0 6.0 ; 6.0 6.0 I 3300 _______ : 3.5 3.5 3.5 3.5 1 3.5 3.5
3.5 3.5 I 3.5 :
1
I Extra
1
!-i--:--!--:--,----·---- 4000 _______1
1 3.5 3.5 3.5 , 3.5 :
5000 _______ ! I 3.5 3.5 3.5 3.5 3.5 3.51' 3.51' 3.5 :
i stren gt h cla y' 2.0 i 3.5 : 3.5 ! 3.5 : 3.5 I 3.5 3.5 3.5 5 6000_______ : 2.5 2.5 ,
I 7000 _______ . , 2.5 i 2.5 :
Par 14 Chap 4
I
AC 150/5320-SB Page 43
'l'.\BLE III.-:\Iinimnm depth of cover in feet for pipe under flexible pavement (Part 2)
CORRUGATED STEEL 2 2/3" x 1/2" CORRUGATIONS CORRUGATED STEEL 3" x 1" CORRUGATIONS
AIRCRAFT WHEEL LOAD-Up to 30,000 lb. single and up to AIRCRAFT WHEEL LOAD-Up to 30,000 lb. single a,1d up to 40,000
' ________ 4_0._oo~O~lb_.~d-ua_1_ _ _ _ _ __ lb. dual
Metal Pipe diameter (in.) Metal Pipe diameter (in.)
1
thickness I thickness
(in.) 12 18 24 36 48 60 72 84 96 (in.) 36 48 60 72 84 96 108 120
I : . :
I
I I I I I I
I
I
AIRCRAFT WHEEL LOAD-40,000 lb. dual to 110,000 lb. dual AIRCRAFT WHEEL LOAD-40,000 lb. dual to 110,000 lb. dual
Metal Pipe dian,eter (in.) Metal I Pipe diameter (in.)
thickness thickness
(in.) 12 18 24 36 48 60 72 84 96 (in.) 36 48 60 72 84 96 108 120
i ,---~.------------ I
1 : !i '
t 0.052.. .... : 1.5 • 2.0 , 2.0 : 2.5 o .052. _...... _.. 2.5 3.0 3.0 3.0
i 0.064 ...... 1 1.5 : 1.5 2.0 i 2.5: 2.5
I
0.109...... I
I
0.168...... ,
!
2.0 , 1.5 2.0 2.0 ' 2.0 ' 2.51
I
I 0.168 ........... u
1
1.5 1.5 i
11.5 2.0 2.0 ! 2.0 I 2.5 1
I I I
, I ' j
AIRCRAFT WHEEL LOAD-110,000 lb. dual to 200,000 lb. dual; AIRCRAFT WHEEL LOAD-110,000 lb. dual to 200,000 lb. dual;
190,000 lb. dt. to 350,000 lb. dt.; up to 750,000 lb. ddt. i 190,000 lb. dt. to 350,000 1b. dt; up to 750,000 lb. ddt.
Metal Pipe diameter (in.) I Metal Pipe diameter (in.)
I 36
J 1
thickness 1
(in.) ; 12 18 24 36 48 60 72 84 96
thickness
(in.) 48 60 72 84 96 108 120 I
I
0.052.. .... 2.0 2.5. 3.0 3.0
1
0.052 ....... ~~ 3.o 13.5 !1· 3.5 j I I I ! j'
0.064 ...... i 2,0 2.5 2,5 i 3,0 I 3,0
I
1 0.064 ........... 2.5 '13.0 3.5 I 3.513.5 l ! I .
0.079 ...... i 2.0: 2.0 i 2.5 • 2.5, 2.5 3.0 i : 0.079 ........... 2.0 2.5 3.0 , 3.0 , 3.5 3.5 : I i
0.109 ...... ' ; 2.0 '2.5; 2.5 · 2.5. 3.0 , 0.109-. ......... 2.0 I 2.0 . 2.5 , 2.5 : :r.o
1
, 3.5 . 3.5 i 3.5 ,
0.138...... 2.0 1 2.0 2.5 3.0 3.0 0.138 ........... 2.0 : 2.0 ! 2.0 112.5 ', 3.0 : 3.0 : 3.5 i 3.5 !
0.168...... I 2.0 2.0 2.5 1 3.0 3.0 I 3.0
II 0.168 ........... 1 2.0 12.0 i 2.0 2.0 I 2.5 : 2.5 i 3.0 I 3.0 I
I I ! ! I
AIRCRAFT WHEEL LOAD-Up to 1,500,000 lb. 1 AIRCRAFT WHEEL LOAD-Up to 1,500,000 lb. II
I_ 1 ! • 1 I ! 1 I I ! J ! I
STRUCTURAL PLATE PIPE-9" 121 /2" CORR. FOR ALUMINUM; 6" x 2" CORRUGATIONS FOR STEEL
l
AIRCRAFT WHEEL LOAD-Up to : AIRCRAFT WHEEL LOAD-40,000 Al RCRAFT WHEEL LOAD-110 k.d. AIRCRAFT WHEEL LOAD-Up to
30,000 lb. s. or 40,000 lb. d. lb. d. to 110,000 lb. d. to 200k.d.; 190 k d.t. to 350 k. d.t.; 1,500,000 lb.
: to 750 k. d.d.t.
, Pipe dia. +8 but not ,ess than 1.0' I Pipe dia+6 but not less than 1.5' Pipe dia. +5 but not less than 2.0' Pipe dia+4 but not less than 2.5' j
I
Chap 4 Par 14
Page 44 AC 150/S320-5B
TABLE III.-1\Iinimum depth of cover in feet for pipe under flexible pa,ement (Part 3)
NONREINFORCED CONCRETE
AIRCRAFT WHEEL LOAD-Up to 30,000 lb. single and up to 40,000 AIRCRAFT WHEEL LOAD-40,000 lb. dual to 110,000 lb. dual
ib. dual
Pipe diameter (in.) Pipe diameter (in.)
Pipe type Pipe type
4 6 8 10 12 15 18 21 24 4 6 8 10 12 15 18 21 24
Std.
~,~
Std.
I 2.0
strength
Extra
strength
2.0
1----
I 1.0 . 1.0
2.0
1.5
2.0
1.5
2.5
1.5
2.5 2.512.5
1.5 - : 1 - : 1.5
2.5 strength
Extra
strength
3.5
3.0
5.5
3.5
6.0
3.5
6.0
3.5
6.0
3.5
6.0
3.5
REINFORCED CONCRETE
AIRCRAFT WHEEL LOAD-Up to 30,000 lb. single and up to 40,000 lb. dual
Reinf. concrete Pipe diameter (in.)
0 01" crack
D·load I 12 15 18 21 24 27 30 33 36 42 48 54 60 72 84 96 108 120 132 144 I
800 •••••••••.••• 1 I I i 2.0 I 2.0 I2.0 I
2 .0 1.5 i; 1.5 1.5 1.0 11.0
I 1.0 11.0 I I 1.0 . 1.0 I 1.0 11.0 1.0 1.0
1000 •.•...••.••. , 2.0 I 2.0 2.0 2.0 , 1.0 1.0 1.0 1.0 1.0 1.0 1.0
1350 •.•..•.•.... 1 1.511.5 1
1.5 1.5 1.5 [ l.5 I 1.5 1.5 1.5 ! 1.0 1.0 1.0 i 1.0 I 1.0
I 1.0 1.0 1.0 1.0 1.0 1.0
2000 •.•..••••••. ! 1.0 1.0
3000 ••...•••••. .1 1.0 1.0
i
I
1.0
1.0
1.0 I 1.0 11.0 11.0 1.0 1.0 11.0 11.0 1.0 11.0 11.0
1.0 11.0 1.0 1.0 . 1.0 1 1.0 I 1.0 1.0 1 1.0 , 1.0 1.0
1.0 1.0 1.0 I 1.0
1.0 1.0 1.0 I 1.0
1.0
1.0
1.0
1.0
AIRCRAFT WHEEL LOAD-40,000 lb. dual to 110,000 lb. dual
I Rein!.
I
concrete
0.01" crack i
Pipe diameter (in.)
D·load i 12 15 18 21 24 27 30 33 36 42 48 54 60 72 84 96 108 120 132 144
800 .•.•••.••.••. 1 i I I I
I I I I I I l
6.5 I 5.5 4.5 13.5 i 2.0 11.5 1.5 1.0
I
1000•........... 1 5.5 I 5.5 5.5 I 5.5 5.5 I 5.0 ' 5.0 15.0 4.5 • 4.5 I 4.0 . 4.0 ' 3.5 I 3.0 ' 2.0 1.511.0 1.0 1.0 1.0
I I
i
1350 •..•.•....•. : 4.0 i 4.0 i 4.0; 4.0 3.5 3.5 I 3.5 I 3.5 · 3.0 3.0 1 2.5 I 2.0 2.0 ! l.5 11.0: 1.0 1.011.0 1.0 1.0
I
2000 •...••.•••.. : 3.o \ 3.o 2.5 2.5 1 2.512.0 12.0 i 2.0 \ 1.5 ! 1.511.5 1 1.0 1.0 1.0 1 1.0 11.0 1.0 1 1.0 1.0 1.0
3000 ••••.....•.. , 2.Q 2.Q 1 }.5 i l.5 1.5 l.5 I l.Q I }.Q: l.Q 1.0 11.0 11.0 I l.Q 11.0 I l.Q 1.0 l.Q 1.0 1.0
I I
1 1.5
AIRCRAFT WHEEL LOAD-110,000 lb. dual to 200,000 lb. dual; 190,000 lb. dual tandem to 350,000 lb. dual tandem; up to 750,000 lb. d.d.t.
Remf. concrete Pipe diameter (in.)
0.01" crack ,-----------------------------------
D·load j 12 15 18 21 24 27 30 33 36 42 48 54 60 72 84 96 108 120 132 144
1.0I7.0 7.0 6.5 6.5: 6.5 6.0 6.0 6.0 I 6.0 6.0, 6.0 6.0 5.5 , 5.5 1 5.0 1 4.5 4.0
1
I 2000 •.••...•.•... 4.0 ! 4.0 14.0 4.0 1I 4.0
3000 •••...•••••. j 3.0 i 3.0 . 2.5 I 2.5 , 2.0
I
4.0 ! 3.5 ! 3.5 3.5 1' 3.5 I 3.0 12.5 2.0 2.0 ' 2.5 I 2.5 1 2.0 : 2.0
1
2.0 1 2.0 , 2.0 2.0 , 1.5 , 1.5 1.0 1.0 1 1.0 i 1.5 , 1.5 11.0 1 1.0
I 1
1
2.0 ! 1.5
1.0 : 1.0
AIRCRAFT WHEEL LOAD-Up to 1,500,000 lb.
1
1
Rein!. concrete ' Pipe diameter (in.)
0.01" crack
D·load 12
I 15 18 21 24 27 30 33 36 42 48 54 60 72 84 96 108 120 132 144
2000 •.••.••••••• [ 7.0
3000 ••••••••••.. / 4.0
I 74.o.0 II 74.0.0 '1 4.0
7.0 ·17 .0
4.0
·1 6.5 : 6.5 ·16.516.0 16.0 '16.0 '16.0 16.0 l 6.0 16.0 '16.0 16.0 16.0 i 6.0 16.0
4.0 i 3.5 3.5 3.5 3.5 3.0 3.0 3.0 I 3.0 3.0 3.0 3.0 3.o I 3.0 3.0
1. Cover depths are measured from top of flexible pavement, however, provide at least 1 foot between bottom of pavement structure and top
of pipe.
2. The types of pipe shown are available in intermediate sizes, such as 6", 8", 15", 27", 33", etc.
3. For pipe installation in turfed areas use cover depths shown for 30,000 pound single; 40,000 pound dual.
4. Cover depths shown do not provide for freezing conditions. Usually the pipe invert should be below maximum frost penetration.
5. Blanks in tables indicate that pipe will not meet strength requirements.
6. Minimum cover depths shown for flexible pipe are based on use of excellent backfill.
7. Minimum cover depths shown for rigid pipe are based on use of class B bedding. . .
8. Minimum cover requirements for concrete arch or elliptical pipe may be taken from tables for reinforced concrete circular pipe, prov1dmg
the outside horizontal span of the arch or elliptical pipe is matched to outside diameter of the circular pipe (assumes that classes of the pipes are
the same).
9. Pipe cover requirements for "up to 1,500,000 pounds" are theoretical as gear configuration is not known.
RIGID PAVEMENT
For all types and sizes of pipe use 1.5 foot as minimum cover under rigid pavement (measure from bottom of slab, prov.iding pipe is kept
below subbase course). Rigid pipe for loads categorized as "up to 1,500,000 lb." must, however, be enher class IV or class V reinforced concrete.
Par 14 Chop 4
AC 150/5320-56 Page 45
rDensety Compocted
Backftl I
fine G,ooulof
_of:ie,_ Fill Moter1ol
IClassA) I Closs D)
CONCRETE CRADLE IMPERMISSIBLE
BEDDING BEDDING
- Ot:M,e\y Compoc1td
Backfil I
Compacted Granular - ,. ' - Lightly Compacted Backftll
Moter101
~';,Be
• -Compocte6 Granular Moteriol Or
1 Closs B ) I Class Ci Densely Compacted Bockf,11
Fl RS T CL AS_S BE DOING ORDINARY BE()_DING
Trench Conduit Bedding
- t.ot1o1rol Ground Surfoct ,---- '"'op Ot EmbC',kmo:.n! , - Top Of Emboritr.ment - Top Of Embank rT'er•
:-,.,,.,,::{~~ .t-\ M . .A:::3. 1 ~0(;::.S z,"< *'' ~&~~',/-.?··'~
I
/~'<! Tfu'<. (-.._<0( {SJ'.-*,\. -·~'<?)'WT!)\\
Sutfoc.e- 1-
Chap 4 Par 14
Page 46 AC 150/532C-58
ceirn consideration. The pipe grades should installed, are abo,·e or below the existing
be established to proYide the necessary depth ground surface.
of cornr, that is, the distance between the !op
(1) Trench conduits are those which are
of the pipe and the paYement. A safe design
installed in relati ,·ely narrow trenches dug in
requires consideration of the probable maxi-
passiYe or undisturbed soil and then coYered
mum wheel load, the inherent strength of the
with earth backfill which extends to the orig-
pipe, the details of construction conditions, the
inal ground surface or for some distance abm·e
type and bearing strength of the paYement,
the pipe. When the conduit is placed in a
and a factor of safety. The design of airport
trench not wider than two times its outside
paYements is predi~ated on gross aircraft
width and coYered with earth, the backfill will
weights as applied to the type of landing gear
tend to settle downward. This downward
geometry, i.e., single, dual, and dual-tandem
mm·ement of the backfill in the trench abm·e
wheels. The recommended minimum depths
the conduit is retarded by frictional forces
of coyer giYen in Tabl~ III should be used.
along the sides of the trench which act upward
X ote that cm·er under flexible pa wment rnries
and help support the backfill and thus reduce
with the aircraft wheel load and type of pipe,
the dead load.
whereas cornr under rigid parnment does not
im·ohe such yariables (see rigid paYement re- (2) Computation of actual loads on pipe
termination of either the maximum allowable iations. The closer the engineer can come to
fill height or of pipe types suitabe for depths producing a trench type of installation, the
beyond the influence of lirn, loads. The con- more fayorable are the loading conditions.
tr~l and method of placing pipe under high There are two methods of construction that
embankments affect the magnitude of the re- would tend to reduce some of the load factors
snltant load. ".,.hen the pipe is installed in a normally found in projection conduits. These
trench of specified width, the resultant load on are the negatire projecting conduits and the
the conduit is less se,·ere or critical. ,Yhen the imperfect or induced trench, (see Figure 27(c)
installation does not im·ohe a trench or where and ( d) ).
the trench width is not controlled-that is, rnry (a) The negatfre projecting conduits
wide in proportion to width of pipe-the mag- are those installed in shallow trenches of such
depth that the top of the conduit is below the
nitude of the load becomes more critical. Be-
natural ground surface. They are then coYer~d
cause of the influence of the abo,·e installation
with an embankment which extends some dis-
conditions, underground conduits of the rigid tance abm·e the ground elerntion.
type are classified into two major groups:
(b) The imperfect trench (induced
trench conduits (Figure 27 (a)) and embank- trench) is the method of construction in which
ment conduits (Figure 27(b), (c), and (d) ). a cushion of compressible material is placed
Embankment conduits are further snbddiYided in a purposely constructed trench directly
into positiYe and negati ,·e projecting sub- aborn the pipe in th{' interior of the embank-
o-rou})S ' de1)endino-
~ ~
on whether the conduits, as ment.
Par 14 Chap 4
AC 150/5320-58 Page 47
These two installations act to reline Experimental data indicate that the four
the load on the conduit. ~Iany designers haw classes of bedding, in the order listed above,
adopted them for placing conduits under high ha,·e load factors of approximately 2.8, 1.9,
embankment with remarkable success. 1.5, and 1.1. The load factor is the ratio of the
c. The supporting strength of a rigid con- supporting strength of rigid pipe in the field
duit depends mainly on the width and quality to the strength in the three-edge bearing test
of the contact between the pipe and the bed- (D-load).
ding, as this affects the distribution of the d. The term "D-load" is used to express
wrtical reaction. Subsidence of conduits is a the allowable load on reinforced concrete pipe
reflection of the load bearing capacity of the in pounds per linear foot per foot of internal
in-place soil and distribution of the load-such diameter. Thus, field loads expressed in pounds
capacity' should be determined by soil tests. per linear foot may be converted to D-load by
Four classes of bedding are used for installing dh·iding by the nominal pipe diameter in feet.
rigid conduits. They are listed in the order of The advantage of the D-load designation is
their relafo·e load distribution capability (see that all sizes of different types and classes of
Figure 2i). pipe of a girnn D-load in similar bedding and
(1 l Ola.ss A: This method consists of plac- installation conditions generally will support
ing the lower part of the conduit in a cradle the same earth load.
of concrete haYing a minimum thickness under e. Conduits installed at a depth somewhat
the pipe of one-fourth the nominal internal greater than the minimum cover depths of
diameter and extending up the sides of the pipe Table III are subjected only to dead loads.
to a height equal to at least one-fourth the The dead loads may be greater or less than the
outside diameter. The minimum compressiYe actual weight of the column of material abow
strength of such concrete shall be 200 p.s.i. the conduit, however, the weight of the ma-
(21 Gla.ss B: This method prO\·ides that terial is a primary factor in the maximum al-
the conduit be set on fine granular material lowable depth of backfill. The associations
in an earth foundation carefully shaped to fit representing producers of different types of
the lower part of the pipe exterior for a width pipe have prepared tables of allowable depths
of at least 60 percent of the outside diameter of backfill for the various sizes, strengths, and
of the pipe. AlternatiYely, the pipe may be shapes of pipe. These tables also take into ac-
bedded in compacted granular material which count such factors as the unit weight of back-
extends up to the midpoint of the pipe diam- fill material, width of trench, class of bedding,
eter. The remainder of the pipe is entirely whether in trench or embankment and for flex-
surrounded by thoroughly compacted granular ible pipe-the stiffness of the pipe wall. The
materials. tables are applicable to airport drainage de-
13) Glass C: This method requires that the sign.
earth foundation be shaped to fit the lower
part of the pipe exterior "·ith reasonable close- 15. LOADS ON STRUCTURES.
ness for at least 50 percent of the outside di- a. At some airports it is necessary to install
ameter of the pipe. Alternatirnly, the pipe box cuh-erts in lieu of conduits, in order to
may be bedded in compacted granular ma- provide great drainage capacity. Although not
terial or densely compacted backfill. The re- related to drainage, utility tunnels are often
mainder of the pipe should be surrounded by similar in design to box culverts. These struc-
compacted granular or fine-grained material. tures, as well as inlet grates and taxiway
(4) Cla8s D: This method requires little bridges, are subject to direct aircraft loadings
or no care either in shaping the foundation sur- at some airports. Large aircraft such as the
face to fit the lower part of the pipe exterior B-74i, DC-IO, L-1011, etc., will impose loads
or in filling and compacting all spaces under substantially in excess of 350,000 pounds, i.e.,
and around the pipe. This method is not up to 860,000 pounds. It is said that increas-
recommended. ingly heavy aircraft will be deYeloped so that
Chap 4 Par 14
Page 48 AC 150/5320-58
a 1.5-million pound aircraft appears feasible b. ·when cut-and-fill slopes are constructed
and reasonably certain to materialize. to obtain the most economical section, some
Ob,riously, point loading on some structures prorision for their protection should be made.
will be greatly increased oYer that used for de- In airport construction, these slopes are usually
sign assumptions in the recent past. Accord- made as flat as possible and vary from a 2 :1
ingly, it is recommended that structures, which slope to one as flat as 10 :1. Cut slopes more
may need to accept loads such as mentioned than 8 to 10 feet deep, with higher ground
here, be designed to withstand the following above them, should be provided with a cutoff
loadings: surface ditch constructed several feet back
(1) For spans of 2 feet or less in the least from the top of the bank and running parallel
direction, a uniform live load of 250 p.s.i. to the top-of-cut line to intercept the surface
(2) For spans between 2 feet and 10 feet
water fl.owing down from the higher ground.
in the least direction, a uniform liYe load rnry- To protect the cut slopes, it may be necessary
ing between 50 p.s.i. and 250 p.s.i., in direct to riprap, sod, sprig, or seed with rapid-grow-
proportion to the span length. ing grass or regetation. It is good practice
also to construct a ditch at the base of the bank
(3) For spans of 10 feet or greater in the
to intercept. the flow of runoff. Figure 28
least direction, the design should be based on
illustrates seyeral recommended types of in-
the most critical loading condition which may
terceptor ditches.
be applied by gear configurations as illustrated
in Appendix 2 to AC 150/5320-6A, Airport c. All fill-slopes that are more than 5 feet
Pa,·ing. high should be protected against surface water
erosion by building berms and gutters along
b. The following elements of Appendix 2
the top of the slope to intercept the surface
to AC 150/5320-6A are also applicable to
water and to prevent it from spilling down the
drainage:
slope. The surface water, thus intercepted,
(1) As always, footing design will rnry
may be disposed of by properly constructed
with depth and soil type. For shallow struc- concrete spillways, vertical drop inlets, or
tures or those subject to direct hea,·y aircraft other suitable means of conducting the water
loads, such as inlets and box culrnrts, concen- down the slope to proper outfall ditches. Ser-
trated load design may require hea,·ier and eral recommended types of embankment pro-
more widely spread footings than heretofore tection structures are shown in Figure 29.
prO\·ided. " 7hen a berm is placed along the top edge of
(2) Locked wheel braking loads must be the embankment, some method of protection is
anticipated for structures subject to direct necesary, for example, by shooting the berm
wheel loads. with a light asphaltic material, sodding the
(3) Because soil is relatinly insensitfre to berm, or prm-i.ding paved gutters. The method
increased loadings, a soil cm·er is recommended which most nearly satisfies local conditions
ornr structures where clearances permit. should be used.
d. One oversight in the construction of the
16. EROSION CONTROL. spillways has been the failure to provide an
a. An important item in airport drainage is adequate cutoff wall beneath the apron at the
to proYide for adequate protection of cut-and- entrance to the spillway. This cutoff is most
fill slopes. Unless the slopes are correctly de- important to prernnt water from seeping under
signed for the type of material contained in and along the spillway, and causing faiure
them, erosion will start during the first storm. from lack of support. It is desirable to con-
The usual engineering practice is to establish struct either a series of baffies or a stilling basin
a certain percentage of slope for the type of at the base of the spillway to reduce the ve-
material encountered as shown on the soil pro· locity of the flowing water. The elevation at
file and to maintain that slope throughout the the outlet should be the same as that of the
particular section. ditch into which it empties. ·where open-
Par 15 Chap 4
AC 150/5320-58 Page 49
trough type spillways are constructed, their The required dimensions of the apron of the
cross-sectional area should be larger than that structure and/or riprap are predictable. For
required for the design storm, and prodsion example, hydraulic laboratory investigation
should be made in the design for ample free- and field observations show that gully scour
board. may be expected in a cohesionless soil if the
e. The channel below culrnrt outlets or spill- Froude number of flow in the channel below a
ways should be protected against erosion. culvert outlet ( without a structure or riprap) is
Usually headwall or stilling basin structures 0.35 or greater. The Froude number (Fo)
are provided as illustrated in Figure 29-to- equals average velocity of flow at the culvert,
gether with stone riprap in the channel. If f.p.s. (Vo) divided by the square root or ac-
a headwall, stilling basin, or riprap is not pro- celeration due to gravity, ft./sec. 2 (g) multi-
vided-then erosion may be expected in most
plied by the culvert diameter, ft. (Do) or
soil conditions and with other than minimum
Fo = Voyg Do. Then the length of area to be
Yelocities. The erosion will occur as gully
scour or as a scour hole. Gully scour may protected, if maximum tailwater applies, equals
erode the bottom and sides of the channel so Do ( 8 + 55 Log Fo). The beginning width of
se,·erely as to undermine the cuh·ert, destroy such area equals 3 Do and the area increases in
or clog the channel, and cause loss of embank- width with a flare of 1 on 5. These and other
ment. A scour hole can undermine the storm relationships are explained in reference 33 of
drain causing loss of some of the pipe sections. the bibliography and texts on drainage.
Chap 4 Par 16
? :.
UI
0,
Interceptor In Soils Thot Erode Rapidly "\,Edge of Runway or ....0
This Slope Should Be Toxiway Safety Area
Flottened And Protected.
1
,o .. . ~
Subject To Soil Condition And Bockslope Various
Means Of Stobilizotion Moy Be Found Acceptable
Such As Bituminous Fogs, Jute Mesh, Strow, Sod, Ete. n·,\C:l,,e<
"' ~,o
~2~ o<
SURFACE 8 INTERCEPTOR DITCHES
Sod Lining
Types of Unings
Sod Riprop
Glay Concrete
Sodded Ditch Lumber Asphalt
Ripropped Ditch
-/ -- 7....
Couse Scouring.
~Ope
l/;
~i_'..J
SURFACE 8 INTERCEPTOR DITCHES
,..
n
Types Of Surface And Interceptor Ditches ....
n-:r
0
....
._
0
u,
"O
FIGURF. 2R 'l'yp0,; of ,;11rfae0 an<I int0recptor ditches.
?
....m
"'
AC 150/532.0-58 Page 51
\ \ e·
• .----~~-r-\-r,
A . ··~"-
A PRON
-.. --r~'*---
.... ------- ---
'' 0
ALTERNATE
STILLING BASINS
R,pro~
.
I
>
\Mttol, VCtoy,Atb Cement.O,
\C°"'rttt P1pt
O,om Vor,oblt ---,
...I____
SECTION 0-0
I
0
APRON :1·
~---
I
;:. Jo~·
L=z:...~ ~..,,.,.,_~--=~~==-----~
: ~---;_~-----~-~---~-=--=-= =-=-.=-
)--- · ; :
I
r:::: PLAN
VERTICAL DROP INLET
Chap 4 Par 16
I
• Page 52 AC 150/5320-58
Chap 5 Par 17
Page 54 AC 150/5320-58
ful study of the topographic map will disclose direction), additional inlets should be placed
the characteristics of the area terrain and the at regular interrnls down this swale. Under
general pattern of drainage design i1n-oh·ed. such conditions, the ridge shown in Figure 8
will protect the area around the inlet, prevent
18. DRAINAGE LAYOUT.
by-passing, and facilitate the entry of the water
a. ·with the general configuration of the ter- into the structure. If the ridge area is within
rain well in mind, actual layout of the drain- the runway safety area, the grades and grade
age system can now be undertaken. This can changes will need to conform to the limitations
best be done on the drainage working draw- established for runway safety areas in other
ing (Figure 30), upon which have been placed ad,·isory circulars. It is also essential for all
the runway layout and the tentatirn finished ponding area edges to be kept at least 75 feet
grading by contours drawn to a I-foot interrnl. from the edges of the pavement. This pre-
The finished contours re,·eal that a crown sec- vents saturation of the base or subbase and of
tion has been used which is the standard the ground adjacent to the pavement during
cross section for the runways, taxiways, and periods of ponding.
safety areas. This cro,Yned section slopes each d. After the field storm drain system has
"·ay from the centerline of the runway on a been tentatively laid out and before the actual
transrnrse grade to the edge of the pavement, computations have been started, the areas con-
except where it becomes necesary to warp the tiguous to the graded portion of the airport
grade to provide a smooth transition at the which may contribute surface flow upon it
intersection of pavements. As noted on the should again be studied. A system of open
typical cross section of Figure 31, the inter- channels, intercepting ditches, or storm drains
mediate areas of the runway safety area, each should be designed where necessary to intercept
side of the runway pavement will be on a this storm flow and conduct it away from the
trans,·erse grade away from the paYement. airport to conrnnient outfalls. Several types
This grade may be rnried slightly to properly of interceptor ditches are shown in Figure 28.
desip1 for drainage to inlets. A study of the soil profiles will assist in lo-
b. Sm-eral trial drainage layouts will be nec- cating porous strata which may be conducting
essary before the most economical system can subsurface water into the airport. If this con-
be selected. The first consideration will be the dition exists, the subsurface water should be
tentatiYe layout serving all of the depressed intercepted and diYerted.
areas in which owrland flow will accumulate. e. All inlets, structures, and pipelines should
The inlet structures will be located, during the be identified by numbers or letters for ready
initial step, at the lm,est points within the reference and for use in the computation sheets.
field areas. The pipelines will be shown next. It is customary to start numbering at the out-
Each of the inlet structures will be connected let end of the pipeline and to progress up-
to the field pipelines, which in turn will be grade. The areas contributing to each inlet
connected to the major outfalls. should be outlined and the acreage deter-
c. Before proceeding further, recheck the mined, differentation being made between the
finished contours to ascertain whether the sur- types of surfacing such as paYement, turf,
face flow is a"·ay from the pa,·ed areas, that earth, and so on. Profiles of the existing
the flow is not directed across them, that no ground and final grades along the proposed
field structures fall within the paved areas drainlines should be obsened and perhaps
( except in aprons), that possible ponding areas plotted; these data will be needed in deter-
are not adjacent to pavement edges, and that mining the grades of the pipeline (see Figure
there are no excessi,·ely long distances for sur- 32).
face water to flow into the inlets. If there f. Unless the pipe size changes, the flow line
is a long gradual sloping swale between a run- through the inlets should be uniform. Occa-
way and its parallel taxiway (in which the sionally, drop inlets are installed to alleviate
longitudinal grade, for instance, is all in one steep gradients on the pipeline.
Par 17 Chap 5
I
.....- - - - - - - - - - I
i
/
I
...
!: i
'
.f
...
j C
I a.
<t
:::.
....
0
a:
0
C
(.) .;
:ca. 0
<t
10
a:
I
Cl
~ l
0
0
I
I
•
oA
12 ~
I ;::
I
I
Chap 5 Par 18
... ...
!! .
c&
. ~ - - - ---- t - - - - - - 2 , 0 ·~___!_()~
z----L6~'._- t
· 1t, -------- - - - ----· 250'.._ _____ --·- ---1,-- ______ ----·-----
6
u,
°'
I
-•"'
--t !,!_qp_t_ .c:~~ 1 'I.
_l__5_'-_ . , '":-.
--~-
/ --;~-.-~ ----·
/_o
-Bou
' / ·1
Runway PovlnQ Surface
c'f"~:-~c.::-:---=',~Tc=-·-='::-::::_-::, .:, ~-
---- ----
Lsuborode , / Subbose
__! 5-'----t----------~-.~
lo•- 11.5\
lnttr"'tdlolt
Area Mor
,slope 1.5'-
Ditch
Subsurloee Drains
Storm Oroln System With
~ ·'' .l\\•
\
1 /Lomphole
D,tch ~ ___________________
r
...g
500' Mo•
- -·- -i
- E- ,.._--..-== =
_ 0_!01~7
Run~oy___ P~_vl_,!'O_ ~urfo~_,__ __
=-e=
A_ !_ _ _ _ _ _
- -
/7 -
;,, Oro1n ~
,._ ''
Manhole
~lif ,-: ~-c'-~.
/ :
With Grate'(~~ To
1
I:•~•~-·-=._·:_
Out foll Ditch
_Varl~blt
P:: -(~:P~:o~
_ _ -t---""•rloblL2.00'.='0.o:_
0
E·~:~;l:-N~~-)
----+- . ______
tl~ ~ "~= ,-~-~
Y11tJab11 ~
0
~- - r::~== - ~-c ~-;cO-c-=- c :, . -:-C:-'c-c• ·
- 250'
------· ----~
-1)(1'
Runway Paving Surface --
Slope 15 \ !>,
l..---=--$~
-_ -. -- -_ -- -= ==::-::. ::.:. C: :::,-_-___ -::..-_--=- =-=:, _-:cQ--.:::. :::._ -_ -----:. = = = =--:. --';-j=- =- ====-=~ I=.:. :.CJ:..-_ ---:,-_ -:..:.
_ . - - - - lnl1t1 - - - - - Monhole With Grote~
==--a~ =- -- -= == =--::.--:. -_:: _-_ u;,=.
I Vorloblt l Vorlobil 200' -400' j, Vorlobl• .~ ;I
.--- Ta_1j~oy
~B
PLAN ( Typical Example No. 2) ~To Outfall Ditch )lo
n
Oimenelone and Slopes Sh""n Above
-
u,
111u1trote A Major Alrpa,1 and Are 0
Runway Safety Area And Runway Drainage Nol Applicable To Al I Airport,.
u,
n c.,
:r ~
...
D
Frnur.E 31. Runway safety area an<l runway drainngf'.
?
u,
u, co
n >
.,,:r
D
n
"'
-...
"'0
"'
~
?
"'
I"
.. ,o H[.&OWALL
-0..
,~. ,.... ,.,,,!
. ,,>- e!tt' ae• tt1Pf,_ 16•9'
... ~· IIJ• Pl,E
-(
O•OO
2,.41
". 4,
t . ,,,t..
~_o.
~'
' .,~~
NOTES•
!>, ,.. 3
O' lnl•t 9rotu pkleed 0.1 fHt below flni1hed 9rod1
"· 1+ :,o
011tonct1 shown for plpt a,, to cent,n of int,11
#1t SH o,ow1n91 of Inlets ond headwall for cl1toil1
50t97
PLAN
-oE.:1=1=:c
c~lc =:c*1'=,,I.= s:r.l=t=-.t=-:t=c:p=
~=1:C'*=t:=~·1-··ct= le--=
~gg-,~
~=t-::: icc=f=
·1·= =.r=l~
-~
,=~{tg
-I"=•-. TF~§
~~.·=
,=t-=· t-4,-~~,
~~
-"E ·- F~
!!•M EE' ~- =, I==
i:l ,....-0:·-~or:~- ·~~
l; ..... ·I==
slf.11 -•il 1=-f=
tY I ..... If
"f:r.1"'7~1
1Wttrmt ••
- ITI
.,,, ILl'f tLt•T
~ ~ -1,19;··,;. .
~ ' _...tJ '~i.~E=
I~
cc.,_
ald:,o~ S•~ . ·o~-• ....'E - ,so·.,"'·P1P£ s-000017··
Y~ ~
MIV~_._',_t~~ ···••· tft ··---f - +---+--·-·-+- ~,t- n•!f ~•o· ll'tl 1•00001 ,!I
g. Ditches form an integral part of the (6) Determine the time of concentration
drainage system. The size of the ditches and for the inlet in accordance with the principles
their functions are quite variable. Some outlined under "Time of Concentration,': para-
ditches serrn to carry the outfall away from graph 6.
the pipe system and drainable areas into the (7) From the plotted rainfall curve for
natural drainage channels or into existing wa- the design storm, find the rainfall intensity "I"
tercourses. Sometimes it becomes necessary for the corresponding time of concentration.
to construct extensiye peripheral ditches. (8) Record the acreage of the subarea
Their purpose is to receiYe outfall flow from which is contributing to the inlet.
the drainage system, to collect surface flow
(9) Compute the quantity of runoff by
from the airport site or adjacent areas, and to
the formula Q = CIA. This is the amount of
intercept possible ground water flow from
water which must be accommodated by the
higher adjacent terrain. Open ditches are
drain pipe from this inlet.
liable to erode if their gradients are steep and
(10) Select slope and determine the pipe
if the Yolume of flow is large. "\Yhen neces-
sary, the ditches may be turfed, sodded, stab- size which will carry the runoff. Charts as
ilized, or lined to control erosion. shown in Figures 9 through 12 may be used.
(i) As the design progresses along the line,
h. "\Yith the plans and data referred to in
the preceding text, it is possible to design the the runoff naturally accumulates. Each suc-
drainage system. A step-by-step drainage pro- ceeding pipe run carries the water from the
cedure is as follows: upper reaches of the system in addition to the
water introduced through its immediate in-
(1) Identify the structures and estabish
let structure. This accumulation, however, is
the lengths of pipe segments between struc-
not necessarily a straight arithmetic summation
tures. Scaled dimensions are of sufficient ac-
of flows from preceding inlets. Flow from in-
curacy at this stage.
fluent lines may have to be adjusted to repre-
(2) Select Yalues for coefficients of run-
sent the amount of water which they are con-
off "C' for the se,·eral types of surfaces over tributing at the time of concentration for the
which water will flow. Table I may be used point being investigated.
as a guide in arri,·ing at acceptable rnlues for
this factor. 19. SURFACE DRAINAGE.
(3) Compute a weighted rnlue of "C", if
a. A portion of the actual design of the
required, as explained under "Runoff Coeffi- system can now be considered in accordance
cient;' paragraph 5. with criteria and data gh·en previously. For
(41 Determine the distance from the inlet example, the area between the apron and taxi-
to the most "time-remote"' point in the tribu- ways of the airport layout has been selected
tary subarea. If in flowing from such point, for detail analysis in making the necessary
water traYerses different types of surfaces, the calculations and determinations (see Figure
lengths of flow oYer each type of surface should 33).
be determined. b. The rainfall data for the location under
(51 Using the distances determined accord- study has been obtained from graphs found
ing to step ( 4), the time of flow to the inlet in the U.S. "\Veather Bureau Technical Paper
from the most "time-remote" point can be Ko. 40. These data haYe been plotted and
established. The time so determined is the curves drawn (Figure 6) to indicate the in-
"inlet time.'' It may be obtained by the use tensity of rainfall. The cun·e of the intensity-
of the currns in Figure 7. If the distance ex- duration for a 5-year frequency will be used
ceeds the limits of the currns, use the formula in the computations. From this cun·e, the in-
in Figure 7. Keep in mind that the total length tensity for the corresponding time of concen-
of ornrland flow may consist of sereral sub- tration for each inlet can be readily deter-
lengths, each of different surface or slope. mined and used in the S)'Stem design.
Par 18 Chap s
AC 150/5320-SB
c. After the drainage layout has been de- (8) Column 8 gh-es the rainfall intensity
cided and sketched on drainage working dra"·- based on the time of concentration and the de-
ings, the extent of the subarea contributing to sign storm frequency ( from Figure 6).
each intake structure is measured and tabulated. (9) Column 9 giYes the acreage of the sub-
The recording of the sizes of the subareas is area immediately tributary to the inlet being
shown in Table IV. Inspection of the areas inrestigated. (See Table IV.)
will show that surface water ' ""ill flow partly (10) Column 10 shows the amount of nm-
oYer paYements and partly m·er turfed areas. off from each tributary area as determined by
A runoff factor of 0.90 has been assumed for the Rational Method formula Q = CIA.
the paYed areas and 0.30 for the turfed areas.
111 l Column 11 gires the accumulated run-
A weighted yalue of the factor "(''' or runoff
off which must be accommodated. In the ex-
coefficient was calculated as explained in Chap-
ample problem the maximum accumulated
ter 2 and is shown in Table IV. In working
runoff to be discharged from inlet 11 consists
up the data shown in Table V, a bell-and-
of the runoff from the subarea tributary to in-
spigot type of pipe was used and a rnlue of
let 12, plus the amount of runoff from the sub-
n = 0.015 was assumed.
area tributary to inlet 11. The total accumu-
d. For conYenience in the computations and lated runoff at inlet 11 is shown in the table.
recording the results, a form such as that of
1121 Column 12 gh-es the wlocity of flow
Table V is suitable. Explanation of the Yar-
through the pipe, determined by diYiding the
ious columns of this form is as follows:
pipe capacity by the area of the pipe. To be
(1 l Column I identifies the inlet being in-
self-cleaning, drains should be designed to
wstigated. All structures should be numbered, haYe a flow Yelocity of not less than 2.5 f.p.s.
preferably starting with the first structure
1131 Colunm 13 giYes the size of the pipe
from the outfall and progressing along the
required to accommodate the flow.
line to the uppermost end.
1141 Column 14 shows the slope of the
121 Column 2 identifies the particular seg-
pipe. Selection of the slope usually will be
ment of the drainage system beinf! designed. goyerned by such factors as topography,
(31 Column 3 shows the length of that amount of coYer, depth of excaYation, desired
segment of the line. discharge Yelocity and capacity, and elerntion
141 Column 4 giYes the ··inlet time .. or time of discharge basin or channel.
required for water to flow oYerland from the 1151 Column 15 shows the capacity of the
most time-remote point of the tributary sub- pipe in cubic feet per second on the slope in-
area to the inlet being considered. dicated. ObYiously, the capacity must exceed
151 Column 5 gi,·es the "flow time·' the accumulated runoff if the system is to op-
through the particular pipe segment. This is erate properly ( use Figures 9 through 12).
obtained by diYiding the pipe length by the 1161 Column 16 gi,·es the invert elerntion
rnlocity of the drain. See column 12 for Ye- of the structure identified in Column 1.
locity. 1171 Column 17 is arnilable for any re-
161 Column 6 shows the time of concen- marks pertinent to the design.
tration. For inlets 12 and 13 in the example, e. It is obvious that many combinations of
time of concentration equals the "inlet time." pipe sizes and slopes can be selected which will
Maximum flow does not occur at inlet 11 until prm·ide the required pipe capacity. It is good
all areas tributary to it are contributing to that practice to select the smallest size pipe, con-
inlet. All areas are contributing to inlet 11 in sistent with such considerations as economy of
55.4 minutes (see note in Table V). excarntion and flow Yelocity, that will accom-
171 Column 7 shows the coefficient of run- modate the desired discharge. rsually 12-inch
off for the subarea contributing to the inlet. A pipe is the minimum size used to carry sur-
method of determining the runoff factor is face runoff. It is the general practice to in-
illustrated in Table IV. crease pipe size as the Yolume of water to be
Chap S Par 19
Page 60 AC 150/5320-58
••2 - + - - - - - - - - - - - > .
APRON
''
')
';--------··· I
4T =----=--
'I
----------- I
I
I
L
I
I
I
I
I
I
I
I
....,,.
)(
,,.-<
:e
GRAPHIC SCALE
LEGEND
a Inlet
Ditch
Storm Droin
Limits of Contributing Dro,noge Areo
Par 19 Chap 5
AC 150/5320-56 Pc,g~ 61
lnlel Tributary Area To In let, ( in ocrts) Dist once Re mote Point To lnlef ( in ff I Time !'or Overland flow ( in mins.J
No Pavement Turf 80th Sub Totol 11 Pavement Turf Toto\ Pavement Turi Tola\
To Inlet@ To Inlet(@)
To Inlet @ To Inlet@
9.24
14.72
X 0.30 • O.t 9
C • 0.53
~.
21.50
21.50
0.30• 0.27
C • 0.35
®
~.
To Inlet
0.90 • 0.08
16.05
14.59 X 0.30• 0.27
16.05 C • 0.35
Subtotals ore shown to ii tustrate that the area contributing lo dowt'lstreom it'llets is a summation of
trit>utory areas obove them plus the atea COt'llributing lo the inlet itself This prevails where lime
of concentration for the in1e1 in question is also o \Ummotion - see paragraph 6b ( I ) .
tn runoff colculolions the' occumutotion is ac111olly mode by addition of the runoff from
lhe line se11ments ( os shown by Tobie v ).
Chap S Pot 19
"D
!! 'fAm,p; V. Drainage RyRtem rteRip;n <latn -:
- "'.
,0
...
0-
'c
C
0 :o.. "ti Q)
Q)
a.
- _~....
Q)
Cl> Q)
,.,_ 0 ~:,
a.
a:
--~
Cl>
-
E C
....Cl>
c,,
Cl>
(/)
Cl>
0
.c
'& E
..
C c,,
C
Q)
E
i=
....
Q)
E
i=
3
0
Cl>
E
C
Cl>
u
:: ~Q
o:::Cl>
C
Q)
-o~'"'
- "'
C C
.... <l
o.
]o 0
C
E::
::, 0
0 C
>,
.... 0
·uoO
!:'
~
a.
0
Q)
0
Q)
a.
~
0
>,
u a.
a.O.
·-
CJ
-...
Q)
·.;:
C
0
0
>
Remarks
C 0 C -0 Cl>
.... ·- Q) ::, u :, 0 > Q)
Cl> :, 0 o-
..... ~~ >ii -0
Q) ·- 0
C
:..J ...J (/) C
LL (.) a:: t) 0:: C a:: <l a:: (/) (/) (.) 0
C
-
-
lJJ
I 2 I 12-11 51 o 11 52 3.4 52 0.49 I 1.98 I 14.69114.25 I 1425 1 20 30 I .0016 I 14. 25 153096 ( n • 0.015)
10 10- 9 550 II 39 3.3 I 604 0. 35 I I 78 I I . ~ 7.46 36 53 28 54 .0007 I 45 O_J 5274? t__~ee note below
9 9-0UT/ I I 45 I/ 42 4.2 65.9 o.35 I 1.10 16.05 9.55 59.32 3.3 60 .0008 I 65~--! 526.:?!+-------~----
OUT 525.65
f - - - - - - - ~ - - - - ' - - - . - J ' - - - - L - _______..J______......il... _ _ _ _ _ . J . - . _ ___ . ------- ------
NOTE: Time of concentration for Inlet #11 is 55.4 minutes (52-t- 3.4 = 55.4) which is the most time remote point
for this inlet. Likewise time of concentrotion for 1n let #IO is 60 .4 minutes ( 52 + 3.4 + 5.0 = 60.4 )
>
n
u:
n
:T
0
-......
0
"'
"ll ?
"' "'.,.
AC 150/5320.:.58 Page 63
accommodated mcreases. The ,·elocity in the c. A study of the cumulative rainfall for
entire system should be maintained or increased 5-year and 10-year frequency will be used as
progressively along a line to pre,·ent settle- the rate of supply. The rainfall usually di-
ment of suspended solids. Care should be minishes gradually in intensity after a couple
taken to avoid flow retardance or the creation of hours. Shown in the table is the tabulation
of turbulence in the system as this also will of the hourly intensity in inches for various in-
cause settlement of suspended solids. ten·als for both the 5-year and 10-year fre-
f. A form similar to that described may be quency. Also shown are all the necessary data
used in the design of any of the several sec- for the cumulative runoff for the two fre-
tions of the system. The desriability of using quencies, and the discharge for a 30-inch diam-
ponding areas should be studied and the sys- eter pipe. These data have been plotted in
tem should be checked for its capability to Figure 35. Also plotted are the discharge
take care of storms heavier than the design capacities for 21-inch, 24-inch, and 33-inch
storm. pipes.
d. Computations indicate that if the inlet is
20. PONDING. constructed to an eleYation slightly below con-
tour 534, there will be a ponding storage ca-
a. The rate of outflow from a drainage area pacity between it and contour 536 of 243,300
is limited by the capacity of the drainage fa- cubic feet. From Figure 35, it can be seen that
cility serving the area, usually a drainpipe. the 33-inch pipe will empty the area in 39 min-
,vhene,·er the rate of runoff at a structure such utes after the start for the cumulatiYe runoff
as an inlet exceeds the drain capacity, a tem- from the 5-year frequency storm and will
porary storage or ponding occurs. As soon as empty the area in 51 minutes after the start
the rate of inflow into a ponding basin be- for the cumulatirn runoff from the 10-year
comes less than the drain capacity, the accumu- frequency storm. The 21-inch pipe would pro-
lated storage will be drawn off at a rate equal ,·ide sufficient discharge to keep the maximum
to the difference between the capacity and the
ponding down to 82,985 cubic feet after 60
rate of inflow. The rate of outflow from a
minutes after the start of the runoff for the
ponding basin is affected somewhat by the ele-
vation of the water at the drain inlet, and it 10-year frequency storm: howe,·er, this pipe
will increase as the head on the inlet increases. would not empty the ponding area for an addi-
Because of the flat slopes on an airport, the tional 3 hours or more.
surface areas of the storage basins surround- e. One objecfo·e should be to limit the pond-
ing the inlets are usually rnry large in com- ing to less than 243,300 cubic feet, and it will
parison with water depths at the inlets. Al- be noted that even the 21-inch pipe would ac-
though the hydraulic gradient at the inlet is complish that. Another objectiYe should be
raised slightly because of ponding, any in- to dispose of the ponded Yolume in a reason-
crease in drain capacity should be considered able time so as not to have ponds in the run-
a small factor of safety and not taken into
way safety area for long periods. Also, a pro-
account.
longed storage of water may make the area un-
b. Figures 34 and 35 and Table VI have stable for some time after the storm and may
been prepared to illustrate the proposition of kill the grass. For example, note that the
ponding. For example, the area to be drained
21-inch pipe would not empty the pond from
is part of that shown in Figure 33 except that
for simplification, the contours have been a 5-year storm for more than 3 hours. The
changed to create one large ponding area with 30-inch pipe would, howe,·er, empty the pond
only one drain to handle all the runoff. The in less than an hour. Under these circum-
size of the drain can be varied to compute the stances, the 30-inch pipe would be a more ac-
different time periods needed to discharge the ceptable selection, howernr, the 21-inch pipe
volnm<> of ponding accumulated. might result in the hazards mentioned above.
Chap 5 Par 19
I
Page 64 AC 150/5320-SB
_/I
~ - - - - - - - - - TAXIWAY - --541 - - - - - - - - · - ---t-- - -
·,, 540 '
5 39
GRAPHIC SCALE
LEGEND
.,...
0
D Inlet
)- Headwall
Storm Drain
Drainage Area \ \
\ \
r Pandi"Q Area
Par 20 Chap 5
AC 150/5320-58 Page 65
120 17.53 x 1.05 X 7200 • 132 527 17.53 X 1.23 x 7200 • 155246
Chop 5 Par 20
,D ,D
~ ~
~ $
0 ~
~
:::f' lI r I
160 I
,o
. f 1
I
I·
60
I
- Jt
vt 71 r 1
I - /1 I I I ,._,,..i.,~
J L++'t
I 7""1" ...j 160
_.._ --- -____ 1______ .
I
~ -----t---
8120
0
j
0
§
100
80
T l-
l-
~
. I \~\
I / ............I. -/.. I
-A-l
I I+----- ---
+-·. t
I
l-~
t 1...,........1 --t---t-
I ··i-··- \-
-t-
--··\·· --\--·
~t120
j 80
IOO
20 I fl---A>1 J.,, ~ -- l l I I I i I l I 1 j l i j l 20
O 0
0 5 10 15 20 30 60 90 120 150 180
Time ( in Minutes)
I ,..
n
I ~
9
D
,
Cumulative runoff for ponding in Figure No 34
21. SUBSURFACE DRAINAGE. flowing water is found in only a small area, the
a. Subsurface drainage to be considered on drain line may be carried to an appropriate
airports consists, in general, of prO\·iding in- outfall. If that solution is not found to be
tercepting drains to divert subterranean flows, practical, the line may be connected to the
draining wet masses or areas, controlling mois- sealed surface system by a connection similar
ture in the base or subbase of pa rnment or any to that shown in Figure 37. Care must be taken
combination of these. Draining large field to prevent the water in the sealed system,
areas by subsurface drainage is not usually when flowing full, from backing up into the
necessary on airports, since it can be done more subdrainage line and saturating the area con-
efficiently by grading properl~· and installing tig,.1ous to the subdrain.
surface drainage. Subdrains shoud be designed d. Certain types of soils are self-draining,
to function as subsurface drains only and some can be drained by artificial means, and
should not operate to remove surface drainage. others are not drainable.
b. The presence of a high-"\\'ater table on an 11) Soils such as grarnlly sand, silty sand,
airport site calls for a thorough soil suney and some types of clay sands are often self-
and a determination of the cause of such under- draining.
ground "ater. The details of a comprehensiYe (2) Soils like sandy clay, clay silts, and
soil suney are co,·ered in Chapter 2 of AC certain sandy silts are drainable, and subsur-
150/5320-6A. The water table may be exten- face drains wil be effectire. The percentage
sive or be located in one or more isolated por- of sand in these soils determines their ability
tions of the site. The soil horizons and types to be drained.
of soil will definitely reveal "hether it is:
(3) Soils composed of silt or clay without
(1 l pocketed in pervious soils over un- a sand content such as silty clay, silt, and clay
pen·ious stratum, are difficult or impossible to drain.
(2) In low areas of an undulated 1m-
(4) Although the abO\·e general soil class-
pen·ious stratum, ifications are helpful in deciding where sub-
(3) confined within a porous waterbearing surface drainage will be practical, the penious-
stratum, or ness of a given soil, base, or subbase course is
(4) "·ithin a high flood plane of a stream measured by the coefficient of permeability.
or "atershed. There are seYeral methods of determining the
In many locations the water table fluctuates coefficient-both in the laboratory and in the
with the seasonal rainfall. This should be field. The coefficient of permeability is ex-
checked when making the soi] surwy. Condi- pressed as centimeters per sec. (1 cm./sec. =
tions 1 and 2 can generally be best relieved by 1.97 ft./min.) repr~senting rate of flow. The
the use of subsurface drains placed within the range of coefficients is Yery large so they are
actual areas having the high-water table. Con- usually expressed as values with exponents
ditions 3 and 4 are usually remedied by cor- ranging from the most permeable at 102 to
rectly placing intercepting surface ditches to rery impermeable at 10·9 • The value 10·4 is a
cut across the porous water-bearing stratum,
useful reference point as a soil with such a
or to install intercepting drain lines, occa-
coefficient. is just able to drain a very heavy
sionally supplementing either with subsurface
drains within the area affected. Figure 36 rainfall. The coefficient of permeability of un-
illustrates types of subsurface installation that treated base and subbase courses depends prin-
hare prornd satisfactory. cipally upon the percentage by weight of the
c. Even though a very thorough soils sur- fraction passing the 200-mesh sieve. For ex-
rey of the site has been made, the presence of ample, on that basis material meeting FAA
free-flowing ,Yater should be noted during con- construction Specifications P-154, P-208, or
struction. "'hen encountered~ action should P-209 would haw, coefficients ranging from
be taken to collect and dispose of it. If free- 10- 1 to 10·4.
Chap 5 Par 21
Page 68 AC 150/5320-58
A Corps of Engineers study shows, how- amount of precipitation of seepage, and other
ever, that the drainage characteristics of base factors all affect the flow and, therefore, the
course materials may also depend on the den- size of the pipe needed.
sity of the material. Increases in density (1) The rate of infiltration for subdrainage
(compaction) cause large decreases in permea- that is commonly used is 0.25 to 0.50 of an inch
bility and moderate decreases in effective po- in 24 hours. A rate of 0.25 inch per acre in 24
rosity. Moreover, the drainability of a highly hours is equal to 0.0105 cubic feet per second
compacted material can approach zero when it for each acre.
contains as little as 5 percent fin.es (passing the (2) 'When the rate of infiltration is known
200-mesh sieve). the proper size of pipe may be determined
The investigation of need for subsurface from Figures 9 through 12.
drainage to protect the pavement subgrade h. Generally, a single line of subsurface
should therefore include a determination of drains along the pavement edges is sufficient
permeability of subgrade soils and parnment for the width of most runway and taxiway
courses. Similarly, the practicality of inter- bases. It may be necessary on bases wider
cepting drains could be indicated by the co- than 75 feet from crown to edge-such as on
efficient of permeability of the soil in the area aprons-to install intermediate lines of drains.
selected for installation of the drain pipe. Item 7 of the bibliography is a source of de-
Pavement courses that have been adequately sign procedure and criteria for determining the
stabilized with cement or bitumen are im- spacing of such intermediate drains.
permeable, therefore, a pavement edge drain i. The types of pipe used for subdrains are:
system would be unnecessary. A high water plain or perforated vitrified clay or concrete
table or other circumstances resulting in wet pipe, perforated corrugated aluminum alloy
subgrade soils may, in these cases, best be han- pipe, perforated corrugated steel pipe, cradle
dled by interceptor drains. inrnrt vitrified clay pipe, perforated asbestos-
e. It is important, during grading opera- cement pipe, perforated bituminous-fiber pipe,
tions, to place the best drainable type of soils and porous concrete pipe.
arnilable adjacent to or beneath the paYed j. A type of subdrainage installation con-
areas. This will form the strongest soil struc- sidered important in many localities for the
ture where it is most beneficial and, at the protection of the base and subbase of the run-
same time, will provide drainage away from the ways and taxiways is the intercepting drain.
base and subbase. The poorer undrainable This drain should be placed across and at the
types of soils should be moved to non-traffic lowest portion of the seepage stratum in order
areas. to cut off and divert the entire flow. The
f. Figure 36 illustrates several different drain should seldom, if e,·er, be placed under
types of subdrainage systems often used on the pa,·ement proper.
airports. These are only examples. The par- k. The control of moisture under pavement
ticular type to install will depend upon the is the principal reason for subsurface drain-
actual conditions at each airport site. A re- age along the pavement edges. Free water
view of the soil sun·ey data during construc- may collect below the pavement under several
tion is the only safe way to determine the different conditions. The water table may rise
proper type of subdrainage system. into the base or subbase during an exceptionally
g. The design of a subsurface drainage wet season, or it may be high enough to supply
system is somewhat similar to that of a surface capillary water to the top of the subgrade.
drainage system. The flow from a subsurface Frost layers contribute free water when they
system is considerably less than for other types, thaw out and this water should be carried
and the grades are usually flatter. The grades away by proper drains. This can be done by
should not be less than 0.15 foot in 100 feet. connecting the pen·ious base and subbase or
The type of surface, the soil, the infiltration, the pa,·ement with the backfill material in the
the spacing and depth of the drains, the subdrain system. The subsurface drains should
Par 21 Chap 5
AC 150/5320-SB Page 69
be installed in accordance with "C" in Figure Cl I A fine material will not wash through
37. As shown on the drawing, these drains a filter material if the 15-percent size of the
need not be large; and, under normal con- filter material is less than 5 times as large as
ditions, a pipe 6 or 8 inches in diameter will the 85-percent size of the fine material and the
suffice. fine material is well graded. If the fine ma-
It is necessary to have access to subdrains terial (natural foundation soil) is uniformly
for observation and flushing. Inspection/ graded, then the 15-percent size of the filter
flushing holes are usually spaced no more than (backfill) material should be less than 4 times
500' apart. They are constructed of the same as large as the 85-percent size of the fine ma-
type and size pipe as the subdrain with a grate terial.
or cover at the surface. (21 The ratio of the permeability of the
I. In some localities, low temperatures and filter material is also important to allow free
snowfalls result in deep frost penetrations and water to reach the pipe. Appropriate permea-
deep accumulations of snow on the pavement bility will be assured by conformance with
shoulder area and adjacent thereto. As a con- the following equations:
sequence, the thaw period is prolonged and 15% size filter material
may result in saturation and thus, instabilitv ,o
15 01. si· ze f oun d a t'10n SOI.1 = 5.0 or greater and
of the subgrade. ·
15% size filter material
Although installation of subsurface drains
,o
15 e1. size
• f oun d a t·10n SOI.1 = not more than 25.0.
at the parement edges is the preferred solu-
tion, it has been found that, in some areas, a (31 In addition to meeting the above size
widened base or subbase works as well and is specification, the grain size curres for filter
reasonable in cost (see paragraph 13b(3) ). and fine material should be approximately
parallel in order to minimize washing of the
m. "When pervious bases and subbases are
fine material into the filter material.
used with impenious subgrades, the low area
in the longitudinal profile of the pavement can (41 Filter materials should be packed den-
be a troublesome water collection basin. Nor- sely, to reduce the possibility that moYement
mally, subdrainage pipes should be installed of the fines might cause any change in the
at the paYement edges to prm·ide an outlet for gradation.
that water. In some cases, however, french (51 A filter material is no more likely to
drains (trench sections filled with perdous ma- fail when flow is upward than when flow is in
terial) leading from the base and/or subbase some other direction, unless the seepage pres-
outward. into the shoulder area will proride sure becomes sufficient to cause flotation or a
some relief. "quick" condition of the filter.
n. The construction specifications should re- (61 A well-graded filter material is less
quire backfilling the subsurface trenches with susceptible to running through the drain pipe
well compacted granular material to act as a openings than a uniform material of the same
filter. To prevent the possibility of large quan- average size. However, even a filter material
tities of surface water entering these drains, haYing a wide range of gradation cannot be
the pen·ious backfill material surrounding the used successfully over a drain pipe having a
drains should not extend to the top of the large opening, since enough fine particles to
trench. cause serious clogging will move out of the
well-graded filter into the pipe.
o. The filter material requirement should be
carefully considered because the quantity of (71 Large openings in the drain pipe tend
water to be handled by these subdrains is to increase the rate of infiltration, but also
relatively small and it is possible that the sur- increase the tendency for filter material to
rounding natural soil may filter into interstices collect in and clog the pipe.
of the filter material. The following should be (81 ·where it is feasible to design and use
considered in filter and underdrain design : two gradations of backfill consisting of a sep-
Chap 5 Par 21
Page 70 AC 150/5320-SB
arate layers with coarse aggregate near the backfill material will be ,ery difficult to pro-
openings of the pipe, pipes with larger open- duce commercially as many different soil grada-
ings would probably operate satisfactorily. tions may be encountered. Figure 39 illus-
p. Figure 38 is a graph of the gradation of trates several soil gradation c11rres and also in-
a sample soil that is uniformly graded, and dicates the theoretical curve (No. 5) with
another that is well graded. It also shows the a piping ratio of 5 for the backfill material
uniform filter material required for backfill to for soil type No. 4. Also plotted on the graph
prevent infiltration of the uniform soil into the are the specification limits for commercial size
filter material. Also shown is the well-graded concrete sand and concrete coarse aggregate.
filter material required for backfill that will (41 A backfill material is safe to use if
prerent infiltration. This graph is an example the gradation curve for that material indicates
to illustrate the factors discussed. that the particle sizes are less than the plotted
(1) To use the graph, follow along the theoretical gradation curYe with a piping ratio
cun·e drawn for the well-graded soil to a of 5 for any particular soil. Figure 39 in-.
point where 85-percent size passes the 0.25 dicates that the specification limits of com-
millimeters. Then follow along the curre mercial size concrete sand meet this require-
drawn for a well-graded backfill to ,,here 15- ment for the well-graded soil :Ko. 4. How-
percent size passes a certain sieYe. It will be eYer, the permeability ratio requirement of 15
noted that it is the 1.25 millimeter size or 5 percent size yersus 15 percent size being greater
times the 0.2.i millimeters. This also holds than 5.0 would require that currn Ko. 8 be
true for uniform material cunes if the 85-per- used. Accordingly, the concrete sand should
cent size of the uniform soil is multiplied by 4 be checked against cun·e No. 8. A pre-
to check with the 15-percent size of the uniform liminary im·estigation should be made in the
backfill material. Thus these curYes illustrate locality of the site to determine the type and
the piping ratio requirements. Similarly, they gradation of concrete sand arnilable. If the
illustrate the permeability ratio requirements. sand falls within the limits shown, it should
(2) To use a graph of this type, the nat- be used for backfill material.
ural soil should be screened for a mechanical (51 Certain installations will require the
analysis and the gradation cune plotted. Then specifying of two separate sizes of backfill
establish the 15-percent size of the backfill ma- materials. The example shown in Figure 39
terial just less than 5 times the 85-percent size contemplates the use of the commercial size
of the natural soil, and construct a cun·e for concrete sand for the backfill mnterial adjacent
the backfill material parallel to the original to the well-graded soil :Ko. 4 to prerent infiltra-
soil cune. This ,,ill be the curre of the grada- tion. Assuming that the openinf!s in the drain-
tion of the backfill material desired. pipe would allow the finer backfill material to
(3) It will be noted from a study of Fig- enter the pipe if placed directly against it, a
ure 38 that there will be a separate and distinct larger size material which will not enter the
gradation curre for each type of soil analyzed. pipe nor allow displacement of the finer back-
Consequently, there will be a separate grada- fill material should be placed adjacent to the
tion cune for the backfill material to use with pipe.
each soil type. The limiting piping ratio for a (61 Using the same procedure as was used
uniform soil is 4, and for a well-graded soil is to establish cune No. 5, the safe gradation is
5, and a backfill material with a parallel grada- determined for the coarse backfill material
tion currn not exceeding the piping ratio will (larger size material) by using Figure 39
pro,e satisfactory in preYenting infiltration. again. A theoretical gradation cune (No. 7)
If the specifications are written so that the with a piping ratio of 5 is constructed for the
gradation for the backfill material follows the finer backfill material by using the finer side of
exact curre drawn parallel to the soil gradation the gradation band for the concrete sand as the
c11r,e with its required piping ratio for each reference currn (Ko. 6) for this new gradation
type of soil, it will be seen that the graded curve, since the percentage of the smallest
Chap S Par 21
AC 150/5320-SB Page 71
/7
Drain
Impervious "1ateriol
Shoulder-,
Perforated or open
joint subdrains in
pockeled area.
Sealed
~~ K •
· ;_;:. Pervious Loyer ~
Pocket
Perforated or
Open Joints
Material No. 6.
No. 5.
====rz,rz,==~nwoy Surface
Interceptor
No. 7.
Types of subsurface drainage.
Chap S Par 21
Page 72
AC JS0/5320-SI
1opsoil
lopsoil
Impervious
- '
Moteriol
,_
~,,:;ii#f(.f:175
,1,.-u1
""'
(
Semi-Porous
.."'. ·:· ._ :. \-:_..·.,-:.; :•. ~:- :·. •:·~- Strata
•. Select Moteriol •. -'. .
,: with piping ratiq;
,·,
.
.
.. . ..
.
. . . ..
. •..,c:,...'O•r···
, . ..
. .
•. 0 ' . .
.
--;---:,-:-~~:: .....s !hon 5 . ·· ·
.. ·. _: o·.. ·'.·c·,
·o ·
~ ~~~-. ·. ~·· ''· ··.-:·~-·-·. ··c _' ·: ·. <>~c:.- .: · ... :
'· 0. '.:· .... ·-.. ~·-· ;__ :.. -... _. o·: ..• ::- . -o· o: ·.
· . · · · · •. ·. · · · .- · · · .- . · · ·o -· o " . · •
·. ·,-o· · ·0 •.. : .'!'. :-:.~: ·. .-.--\;~ --~·:
. . .
Down ..•.
''/:4'
INTERCEPTOR WITH "s"
OPEN JOINT PIPE INTERCEPTOR WITH
PERFORATED PIPE
10'
Surface
Min. 2' Min Impervious Backfill
Material-?
/ ,// , ~ ,~<;>
/ / :/,, Bose/Material/'./ /'/// ·
·~ .
••///'///'
.
/
'
.,,
/ ./ /
//./
/ ... ,-' :··
.
..
...
·-·~--- ·;·
.. .
.· ! :
. ..
~
-,
-
. . •
.
.
. . ..
' . .; .. •
. . '
.
~..
.
·..
I
..
I
.
.
.
.•_
,·
.
.
~
.
..
.
'
•
.
".
o
.
; ..
•
.
.
•
.
.
I
'
'
'~. . .
Approx 4:1
.. ·: . . ......
Slope i. '. ·. ·,. •.; ' •
......
. . . .. .. .. . ............
""'. •-
.
Select Moterial
with piping ratio . . . .. . . . . .•
. .
. .. .
... •
..
.
. METAL PIPE
-
;
...·~.........
.
..• _•• , .. ~.c. .......... ,.
...............
less than 5 • _4_.-.. ; ......... 1,-,.•... .•.:
b •f ., ,
placing aC" I
_:.....--~··:·~!:· .··J> ~,, -· ••
.'~:•:I~o·:·~:,
. ....1: .....
,· ....,
·;~.
,. ......
! . Subdroin
·._... '. ·:··. . -~--. 'j
Bedding --.JI..:... . .• . . • . •.· _1
..... ~. . ;. . . . . _ __,__ .
Sealed Line
"c''
SUBSURFACE DRAINAGE
CLAY, ASB CEMENT, CONCRETE OR
BIT FIBER PIPER
LEGEND 5KETCt£S OF SUBDRAlN CONNECTION
TO MAIN DRAIN LINE
: .:.:; Lorge Grodotions ( Filter Material) "o"
[,:·:·:~:;J Smoll Gradations ( Filter Material)
~ Impervious Material
Par 21 Chap S
n':r )I,
n
.,,
-+-
Q
"' I
Openings in. Inches Numbers ( A. S.T. M. Standard Sieve Numbers) "'0
.....
r 1f
1· f f f'f f I L_ ~ ~-'L .. 1~- 2p 3p ~o 5p rp l<j>O 110 290
"'w
!"'
100
1111
90
85
80 r-r--------+---.Jl-----+---1---1i-+----4~ ~ ~
0 0
::U C
I- ~ 1 ~
::i:: 70
~
GI ~.-i----+-----+-----l
w ,.. 0
~ z
3:
60 --+----1----1~-,'-----+--_JW-l.,.,--t----if------+---__j
>- r Q
ID
r
~
Z 50
iii
IJ) ~m
<l ::u
Q.
I- 40
,.....
iE
z
w
(.)
5 30 \\ m
,-::u
-
r I
\
Q.
K:\
I 1~
'
''
'
20
~
15 ¥1
10 ~ ''
' K
I"'
I i
' ''
!I I :
0
50 10 5 2
''
1.2.~·' -~
.5 .25
.15:' .12:,'
.10
.JI~.05 .02
]
.01
GRAIN SIZE IN MILLIMETERS
COARSE AGGREGATE MEDIUM
COARSE SANO FINE SANO SILT
A
_,
'N : CD: V
i_ ,........ ff ..,,
' <D
. ' a, lncht~
·_..._N ,.-,,
-t
·_..:! 'ff"
Numb•••
<D ., 0 <f
"'I -I
/J.. S T. M. ST/J.NO/J.RO SIEVES
., 0
CV
"'
N
0
"'
0
<f '°0 0
(D
0
,.._
O
a,
0
0
OOOo,o,.._NO
NV,.._
00011')0
(\J NN ff') V
PIPING RATIO•
15% SIZE FllTER MATERIAk
85% SIZE FOUNDATION SOil
: ( 5
I
tQQ ... ,J
1
I
l 1
n
I
'
-..
I I
l' "..._ ,-,-
I I
._,_I ,:..::_, ~ el ~ ·, I~ --~ :::.~~ -i- - '__ , 'r I I I ~ I 'I I
,,,,,:- ···:', · ·-._ l-'
1'
;v,.,,,
,• /
,,,
/ :
t, l j_' , . , , : . .
:. "'-~;"
,,;,,. ,, i \
I
i I
\
I
"
·..
l' ,,''\
'
'·,
'·
I :I I'· I
·, '
i
' ' ' ' ''' .
85 i II
~- ·: • : • . , , i · 'y CLAYEY
f :
/\ I 1
'
1
1
1 / ' 1 ·~r.·.. _'.. ,-,_~ .· -
,_~_..___,__,._.._
; , '
.&-.'--+-+-·+---·
! ·. ; '. •,(I) SILT SOIL
'- +- "T T
1 11
0
I '\ \ \ ~
II
:
'. _. ·,,,,
·.
··-·----·-
. ;,
·••
·.
1,1'
,"\
I SPECIFICATION
LIMITS Of COMMER.\
\'.
N·
i
I. ' "
i
t •--~-
' ' '
ro ,, .
·,
·\ SA NO s
· rrx1 HI
,,.:_t11!t \
I
'
I
1 , , , , , , , 111 , , , , •
l ', /:,.<,:r;.,',::,
j
1
\1---FINE I ', ,.
I' I I I I I I I r1T1 ' I i ' '
~
"'60' .
3'
i I\ SPECtflCA
.
p /p~~
•
.... ...
',
·.
\
p
•./--
' \
~~~-.-~·/:~::
•
/.,:,:
( 4',
.. ·. /
.
,.
I
, ·.·,
)
.r
:/,.,//,,.·_:~:_
• .
. .
, •
1
1
1 1
' I 3
\.
SANO
,,
'· II
1'
1,
1'.
1'
1'
+- --t------+- ··-·-·- -1--· ·+-
>-
ID -1···· -
!\ -·· ·
TION LIMIT
or COMM· . .
.
·. •
I ·· / --
'(''• ''''.'''.
t ,. / f/t-- ')
. _ _
,.
·\--·
f-
.
i
!
I -~-
I "'
·f'.. ··- +--·-- -··
c, ' Cr) ERCIAL SIZI ·. I 'x,.- _L; 1 '\. ·.. I •
;
~
O CONCRETE
___.--\. COARSE
. .
.
'
I
· · · ·· ·
'\ -,., ' ;_/ "'
\
I
f'-. I
1
III II I I I I I
fTTI [I I I I I
1t THEORET\, AGGREGATE
ICAL GRA.:- i7-/.,._ ~~7::~ - ..- - __ .__ ·- · ·-:-· -1- ..
·. I
·--.....---1\~-~.'/.·% -· . . . / .•
"'(°1./I>''.:\
' "', '6'
• '.; ;\.
r ···- ·- -- - - - - ____l
I\ ,--..
. - · ·-- --- - - - ~
. ..++--
>-
~
10ATION Of"?;,/,··:,.·;
40COIIRSE · _; ·' ' ,
·.J·.I .. ,·
'; . ,, '. , .
It \ ·.
1'
I'-, 111111 I I I I
u
a::
,._,
BACKFILL \-~,- ,;· /
TT
MA.WIH '· ////
/,,_,,/
'5' 1
.
\::!,/·,
.
'\·" . . ;
.,,. V,cr./.·/
,_---,,-.·u-/.·/·,-.·.
.· ,/· / , , 'r\ I
l
\\
•
" •,
I I I,, I I I I I
AA 1 t-'{?~,;t .
/_;;,J L
-
- '-~ --- - ·.
•. ·.
N-; , •
l''(;;!/V/t/';
'<-v;
,ii~ 0; ~:: ,;
<i/ v, v, ..;.,/ '//.
·,.' ••··,.\
,,.:r,,/- ~-/ .·,' .,
---!.----"~ -- 1
\
·-
I' I'
. ·
·.. · SANDY· LOA~ SOIL
@(LITTLE OR NO PIPING
.·.,>-... -,
h j t 1 111
'
. -- -t ·• - · --a-.-- - ··· · '1/,,// ,.-,./.,;/,.',,
, ,. : ,,~ , . · - - r---..- .,__
··· - - ___ ,___ --tl-ttt ! I l+-t
• I ' ; ; , . · , .• /,. J, ...
' ·· .... I ·; ·'<°' '.; ,..:;.. ;,,," 1' --··· I I II I I I I
\.f .. ( I'\.'. ... .1./ , ' I,,.., 'K""--WELL GRADED rrr I I I I rt I
. ·1· • I'< :...r,L,,,-;_..-,.,
·,'.- , / ·.,-,., · '~< - @---- I ~ 1',- -- - ~ SOIL
•,.I~- t t - --+---- I I I I I l--+-.J-
:' ····..
··. . /_
/ .._,a
-- --,...~-.:...J . , --1---- 1 1111111 I
- I J°J)JI I I ,-- !JI!! l Il . __ j..::;._-t: - - ::j+j:± H•
II
I.J.L.l..J.+.
I ,I
,
_ _ _ _ ) N q en a, t0 10 ~ N om co,.... U) I() ., N - 0\ co
<:I" P"') N - ' -
f,.... l'f')
-0000 C) C) "'0 q ooo 0
oq o
Cl) ,._
0
0
OPENINGS IN MILLIMETERS
COIIRSE AGGREGIITE _____ _! COIIRSE : A N O l M~~~~M_J FINE SIINO l SILT IINO CLAY )Jo
t')
-...
9g
-...
0
c.,
t.)
' - •
r•
AC 150/5320-58 Poge 75
3"
~
16 Coble - or rope
~- Hole-
32
r (•i" • r, 18" Make two or more
L ,
'"
a:,
r. ,s·. 16'-o"
Fla! rolled steel
:: '
we,gh! of Templa!e
approx 188 lbs.
II
_j
Ll ___ 14" ______ _
~---- _16'._
,s·
ISOMETRIC VIEW OF
PIPE AND TEMPLATE IN TRENCH
-Ground line
[] PLACE Is!
(Gronulor Bedd:ng) - '~
D PLACE 2nd
( F,ne B0ckf11I)
D PLACE 3rd
(Coarse Bockfdl)
D PLACE 4th
(Fine Bockfilt)
D PLACE LAST
( Impervious BockftU)
·,•
I
Sizes in Inches
I
: o,ameter : 10 8 : 6
I, Width
Trench
of
I 24: 22 i 20:
I
Chap 5 Par 21
Page 76 AC 150/5320-SB
size will indicate the material most difficult to efficient airport drainage system should be well
control. This new curve No. 7 indicates that designed and should be constructed in accord-
the courser side of the gradation band of the ance with the requirements of AC 150/5370-
commercial size concrete coarse aggregate will lA, Standard Specifications for Construction
satisfactorily prevent infiltration of the .fine of Airports. Quality construction which is.at-
backfill material and will not enter the pipe. tained by consistently using proper and ac-
With openings in pipe rarely exceeding 14 cepted construction methods and practices
inch and with the arbitrary piping ratio of 5, along with adequate inspection ensures a drain-
a factor of safety is provided for use in actual age system that functions properly. Poor con-
field conditions. struction leads to progressive deterioration
q. During the past few years, industry has and endless maintenance and reconstruction
developed woven plastic filter cloths which problems.
have been found to be satisfactory for protec-
tion against beach erosion, for protection 23. POLLUTION CONTROL.
against steep slope erosion and as a filter in Construction of drainage systems and grad-
subsurface drain installations. ing as a contributory part of good drainage
In the latter connection, note that para- systems are to be accomplished in a way to
graph o above refers to the possibility of e,·en control pollution. Sodding or some other form
well-graded granular filter materials moving of stabilization of graded slopes and ditches
into pipe openings or perforations. It is recog- should be done to minimize erosion and pre-
nized too, that gradations of granular material, vent pollution of streams and rivers.
meeting the piping ratio and other require- Although this advisory circular is aimed at
ments of paragraph n above, may not be eco- storm water drainage and subsurface drainage
nomically available. In these cases, a single and not at sanitary sewer systems, it should be
wrap of woven filter cloth around the pipe may recognized that civil airports often support
be used in lieu of the coarser backfill illustrated populations which are sufficiently large to con-
in Figure 40. Filter cloths have openings tribute to the pollution of water resources if
with a size generally like the No. 40 sieve. The raw sewage is discharged from the airport.
cloth may be wrapped around open joints of structures such as the terminal building. In-
unperforated pipe or around the entire length stallation of sewage treatment plants, or di-
of perforated pipe. Prefabricated filter cloth version to such plants, should be required and
sleeves may also be used to encase the pipe. should conform with local, county, or State
,vhen the gradation of granular filter material sanitary codes. In either case, the sanitary
is such that it satisfies requirements pertaining sewer system should be separate from the
to material adjacent to joint openings or pipe storm sewer system.
perforations, but is too coarse to satisfy the
filter criteria pertaining to the protected soil, 24. MAINTENANCE OF THE SYSTEM.
a single layer of filter cloth may be used adja- a. Maintenance is essential to preserrn and
cent to the protected soil in lieu of a second prolong the service and utility of all drainage
filter material. This use, however, is restricted facilities. All structures and visibe units of
to situations where the protected soil is sand. the system should be inspected frequently, and
the malfunctionings should be immediately cor-
22. CONSTRUCTION. rected. Several items that will need constant
The usual construction work associated with checking are: the inlet grates for clogging by
a drainage system includes such items as exca- grass cuttings, sticks, ice, and debris ; the
vation, trenching and shoring; preparation of catch basins and pipelines for stoppage by
bedding, laying, aligning and jointing of pipe; sediment, and waste; settlement around pipes
( Figure 41, Methods of laying drainage pipe) and structures from infiltration; stoppage in
backfilling and compacting; installing struc- outfall ditches; erosion around structures in
tures; and cleaning up. A successful and watercourses or embankments; high shoulders
Par 21 Chap 5
AC t 50 / 5 320-5!
.---.-Strinoers
.' I'
~
'>-C,ro,s btoces
'•
. -•
•
•, •
,
• • Select
' • bedd1no
-- --
U'Se strinqer Plank.in~.--..__ . -
for large size ' ''-"""
pipe
SECTION ELEVATION
EXAMf>LE OF PIPE SEOOING tN UNSTABLE GROUNO
Noil sel even foot
cut to invert - ~
A taut chQlkli~
2'112• or
2'11. 4" stall.es --f\·
....,
I / l J
I '
'w'
~
.•'
{ !
''
4• to 6" rode rod z•• z·. st,aiqnt,
bond marked and oraduated
Tonque end (Hold grode rod ver1itol
downstream ~
Overfilling for Set invert to required
sealed joints line and grade.)
Upstream end
Dir. of Fl- vert orode tal shoe at right
onotes to grade rod
hole
.,.:.;....:...~- r
~~~~w
e.ddif\9 i1ench bo,\om
8ANOING OF
TONGUE ANO GROOVE JOINTS LONGITUDINAL SEC1'1QN - B
Por 22
Cbop 5
Page 78 AC 150/5320-SB
Par 24 Chap 5
~c 150/5320-58 Page 79
BIBLIOGRAPHY
1. FAA "Standard Specifications for Con- 14. Bureau of Public Roads "Hydraulic Charts
struction of Airports," Advisory Circular for the Selection of Highway Culverts,"
150/5370-lA, l\fay 1968. Hydraulic Engineering Circular No. 5, De-
2. FAA "Airport Drainage," Advisory Cir- cember 1965.
cular 150/5320-5A, 1965. 15. Bureau of Public Roads "Capacity Charts
3. FAA "Airport Design Standards-Site Re- for the Hydraulic Design of Highway Cul-
quirements for Terminal NaYigational Fa- verts," Hydraulic Engineering Circular
cilities," Advisory Circular 150/5300-2A. No. 10, March 1965.
4. FAA "Utility Airports/' Advisory Circular 16. Public Roads Administration "Drainage of
150/530C4A. Highway Pavements," Hydaulic Engineer-
5. FAA "Airport Design Standards-Air Car- ing Circular No. 12, March 1969.
rier Airports-Surface Gradient and Line 17. American Concrete Pipe Association
of Sightt Advisory Circular 150/5325-2B. "Design Data, Loads and Supporting
6. Department of the Army "Drainage and Strengths, Hydraulics of Sewers, Hydrau-
Erosion Control Surface Drainage Fa- lics of Culverts, Installation, and Miscella-
cilities for Airfields and Heliportst Tech- neous," 1968-1969.
nical l\Ianual Tl\I 5-820-1, August 1965. 18. American Concrete Pipe Association "Con-
7. Department of the Army "Subsurface crete Pipe Design Manual," 1970.
Drainage Facilities for Airfields," Tech- 19. American Concrete Pipe Association "Con-
nical l\Ianual Tl\f 5-820-2, August 1965. crete Pipe Field l\Ianual," 1968.
8. Department of the Army "Drainage and 20. American Concrete Pipe Association "Con-
Erosion-Control Structures for Airfields crete Pipe Handbook," 1967.
and Heliports," Technical l\Ianual Tl\I
5-820-3, July 1965. 21. American Concrete Pipe Association "Hy-
draulics of Culverts," 1964.
9. Department of the Army "Drainage for
Areas Other than Airfields," Technical 22. Portland Cement Association "Handbook
Manual TM 5-82(4, July 1965. of Concrete Culvert Pipe Hydraulics,"
1964.
10. Department of the Army "Conduits, Cul-
verts and Pipes," Engineer l\Ianual EM 23. Portland Cement Association "Airport
1110-2-2902, l\farch 1969. Drainage," 1966.
11. Department of the Army "Guide Specifica- 24. American Iron and Steel Institute "Hand-
tion for l\Iilitary Construction Storm- book of Steel Drainage and Highway Con-
Drainage Systemt CE-805.01, August struction Products/' 1967.
1968. 25. National Corrugated Steel Pipe Association
12. Department of the Army "Guide Specifica- "Installation Manual for Corrugated Steel
tion for l\Iilitary Construction Subdrainage Structures," 1965.
System/' CE-805.02, August 1969. 26. The Asphalt Institute "Drainage of As-
13. Soil Conserrntion Sen-ice "Handbook of phalt Pavement Structures," May 1966.
Channel Design for Soil and ,vater Con- 27. ,vater Pollution Control Federation "De-
sen·a tion. '' sign and Construction of Sanitary and
Paget 80 AC 150/ 5320-58
Storm Sewers" '\VPCF Manual of Prac- 30. American Society for Testing and Ma-
tices No. 9 (ASCE Manuals and Reports terials, Standard specifications for the var-
on Engineering Practice No. 37), 1969. ious types of pipe.
28. American Public '\Vorks Association "Ur- 31. American Association of State Highway
ban Drainage Practices, Procedures, and Officials, Standard specifications for the
Needs," December 1966. various types of pipe.
29. Weather Bureau "Rainfall Frequency Atlas 32. M. G. Spangler "SQil Engineering," 1960,
of the United States for Durations from 2nd Edition, Chapters 24 and 25.
30 Minutes to 24 Hours and Return Periods 33. Erosion and Riprap Requirements at Cul-
from 1 to 100 years," Technical Paper No. vert and Storm-Drain Outlets, Research
40, May 1961. Report H-70-2, January 1970, U.S. Army
,veather Bureau "Generalized Estimates of Engineer Waterways Experiment Station,
Probable Maximum Precipitation and Vicksburg, Mississippi.
Rainfall-Frequency Data for Puerto Rico 34. Drainage Characteristics of Base Course
and the Virgin Islands," Technical Paper Materials Laboratory Investigation, Tech-
No. 42, 1961. nical Report No. 3-786, July 1967, U.S.
,veather Bureau "Rainfall-Frequency At- Army Engineer ,vaterways Experiment
las of the Hawaiin Islandst Technical Station, Vicksburg, Mississippi.
Paper No. 43, 1962. 35. Bureau of Public Roads "Corrugated Metal
'\Veather Bureau "Probable Maximum Pre- Pipe, Structural Design Criteria and Rec-
cipitation and Rainfall-Frequency Data ommended Installation Practice," Revised
· for Alaska", Technical Paper No. 47, 1963. 1970.