The document is an inspection report for medium voltage power transformers. It lists checks to be performed including verifying nameplate ratings and terminal markings, ensuring all parts are properly assembled and tight, checking oil levels for leakage, grounding terminations and connections, fuse ratings, bushings for cracks or damages, and ensuring the de-energized tap changer has a padlock. Signatures are required from construction, commissioning, and completion leads to accept the results.
Original Description:
THIS IS A General visual checks for KVA transformers
The document is an inspection report for medium voltage power transformers. It lists checks to be performed including verifying nameplate ratings and terminal markings, ensuring all parts are properly assembled and tight, checking oil levels for leakage, grounding terminations and connections, fuse ratings, bushings for cracks or damages, and ensuring the de-energized tap changer has a padlock. Signatures are required from construction, commissioning, and completion leads to accept the results.
The document is an inspection report for medium voltage power transformers. It lists checks to be performed including verifying nameplate ratings and terminal markings, ensuring all parts are properly assembled and tight, checking oil levels for leakage, grounding terminations and connections, fuse ratings, bushings for cracks or damages, and ensuring the de-energized tap changer has a padlock. Signatures are required from construction, commissioning, and completion leads to accept the results.
General Visual Inspection DESCRIPTION: Medium Voltage (11KV/4.16KV) KVA Power Transformers INSPECTION YES N/A ACCEPTED BY
Verify compliance with all the drawings and manuals.
Verify nameplate ratings and HV, LV terminal markings.
Verify that all parts of the transformer are properly assembled and tight.
Check the HV connections are tight.
Check the cable connections on the LV side and the markings.
Check the oil levels and inspect for leakage.
Check the grounding termination and connections are made sure Check the fuse rating of secondary side.
Check the transformer bushings thoroughly and confirm no signs of
cracks/damages. Check that de-energized tap changer has padlocking provision and padlock in position.. Exceptions/Comments (Do not leave any item blank. Strike through if not required.
Signatures Nestoil Construction Nestoil E/I NETCO Completion lead MPN