Professional Documents
Culture Documents
Temporary Works Toolkit: Backpropping of at Slabs - Design Issues and Worked Examples
Temporary Works Toolkit: Backpropping of at Slabs - Design Issues and Worked Examples
load applied that is at least 12% greater than agreed amount (Pp), then this has the effect compared to the predicted value from
that anticipated by the PWD in the original of reducing the imposed load on the Method 1 of 10.55kN/m2.
slab design. Not only does it mean that the supporting slab, and increasing the load on As an engineer, it is my opinion that this
new slab can only be cast when the the lowest slab; but it depends on the close correlation between theoretical and
supporting slab has reached full maturity, but magnitude of preloading. practical loads fully justifies the use of these
the PWD would need to approve the Figure 2 stages (a), (b) and (c) show the methods of backpropping calculations for
construction methodology. effect on the total applied load for the same the building industry.
The philosophy of loading a slab to above example given in Fig. 1, but applying a
its design service load is extensively preload representing only 0.50kN/m2 to the Preloading of backprops
discussed in Annex E of CS1405. backprops. As previously recommended, no How, then, could a site effectively, and safely,
This explains the opening quote in Part 4 construction working area load is applied on preload backprops to its advantage?
of this series by the respected engineer: ‘It’s the slabs. Provided similar props are used, the
not a question of whether they crack, but by Comparing results from Fig. 1 stage (d) to change in length will be directly proportional
how much they crack!’ Fig. 2 stage (c) shows that installing to the load; thus, for a given storey height
If this is such a fundamental issue in backprops with preload has a significant and particular type of proprietary prop,
multistorey construction, why have we not effect. In this example, it reduces the turning the adjusting collar a set amount
seen many collapses or serious incidents? supporting slab foreseeable load applied would initiate a crude measuring device for
There are three possible answers: from 12% greater than anticipated to less preload.
1) Designers have simply ignored it, favouring than 1% greater than anticipated. In practice, it was found difficult to control
rigid prop assumptions with lower values. Nonetheless, the temporary works designer the preload at the ECBP, even with load cells
2) Concrete at an early age is autogenous (TWD) would still need to refer this ‘overload’ installed, because of the tendency to
and has some self-healing processes that to the PWD for consideration. transfer load between adjacent props as one
may have partially hidden any overloading. Once again, this demonstrates that the is tightened up, due no doubt to the thin slab
3) The operatives have installed the new slab can only be cast when the and the flexible nature of the slab.
backprops ‘a bit tight’. supporting slab has achieved at least its full Calculation of the prop extension required
characteristic design strength; it also to achieve a particular preload is
The third answer is probably the likeliest. If assumes that no additional construction complicated by the stiffness of the slabs,
fitted loose, the individual backprops would loads are applied to the floors, e.g. from which will move up and down with load, thus
fall over, so the operative puts some storage of materials. changing the elongation, etc.
pre-tension into the backprops. The examples given in this article have The prop stiffness (kN/mm), translated by
The following calculation shows the effect used the in situ reinforced concrete slab the temporary works coordinator (TWC) into
of preloading backprops using the same design involved in the research at the ECBP2. load per turn, and hence the number of
example. The results from the precise monitoring at complete turns on the adjusting screw to
the ECBP on the fourth-floor construction give this extension, may be impossible to
Example: calculation with two levels of are shown in Fig. 2 stage (d). Note in predict and calculate. Other methods, such
backpropping installed with preload particular the load in the supporting floor as load indicating washers, may be possible,
If all of the backprops are preloaded by an slab, which was measured at 10.57kN/m2, but no one method seems to be simple
S Figure 1 Example with two levels of backpropping (250mm solid flat slab)
6.25
0.75
(say)
Supporting 0.50
Notes
slab
1) Unfactored design load
for slab is 6.00 (self-
weight) + 4.50 (imposed) 6.75 7.25 7.25 11.80
= 10.50kN/m2
2) Full construction load on
supporting slab in case 0.00 2.45
(d) using Method 1 gives
(65% × 7.00) + 7.25 =
11.80kN/m2 6.75 6.75 6.75 8.36
3) If the falsework designer
had selected a concrete
density of 25kN/m3 with 0.00 0.84
full operations load, this
would now give 65%
× (6.25 + 1.50) + 7.25 = 6.75 6.75 6.75 7.59
12.29kN/m2
4) The TWD would need (a) Cast (b) Erect (c) Insert (d) Cast new
to discuss with the PWD supporting falsework backpropping slab
how to deal with the slab, strike
and allow to
loading during construc- deflect
tion that exceeded the
design service load by at
least 12% for the slab
All loads stated in kN/m2
6.25
The Temporary Works Forum (TWf)
0.75 formed a working party to discuss
(say)
0.50 0.50
backpropping and future research needed. If
6.82
you are interested in participating, please
contact secretary@twforum.org.uk.
6.50 6.00 10.55 10.57
(a) Erect (b) Insert and preload (c) Cast new (d) Loads measured
falsework, backpropping slab at ECBP (4th floor) E2) Beeby A.W. (2000) BR 394: A
allow slab to, say, 0.50 (preload 0.30kN/m2) radical redesign of the in situ concrete
to deflect
frame process, Task 4: Early striking of
formwork and forces in backprops, London:
All loads stated in kN/m2 University of Leeds and Building Research
Notes Establishment Ltd
1) Unfactored design load for slab is 6.00 (self-weight) + 4.50 (imposed) = 10.50kN/m2
2) No construction operations loading is included in the backpropping calculations E3) British Standards Institution (2011)
3) Full construction load on supporting slab in case (c) using Method 1 gives BS 5975:2008+A1:2011 Code of practice
(65% × 7.00) + 6.50 – 0.50 = 10.55kN/m2
for temporary works procedures and the
4) The TWD would need to discuss with the PWD how to deal with the loading during
construction that slightly exceeded the design service load for the slab permissible stress design of falsework,
5) The loads in floors and backprops at stage (d) were recorded by BRE on the ECBP at the fourth floor London: BSI