Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Technical

Temporary Works Toolkit | Part 6 thestructuralengineer.org

Temporary Works Toolkit


Part 6: The Temporary Works Toolkit is a series
of articles aimed primarily at assisting the
permanent works designer with temporary

Backpropping of flat works issues. Buildability – sometimes


referred to now as ‘construction method
engineering’ – is not a new concept and one
slabs – design issues always recognised as vital to the realisation
of one’s ideas; it ought to be at the forefront
of an engineer’s mind.
and worked examples www.twforum.org.uk

need to be considered as additional loads.


Eur. Ing. Peter Pallett
In practice, construction working area
BSc, CEng, FICE, FCS
loads were shown by the research on the
Above Ground Temporary Works Consultant, Pallett TemporaryWorks Ltd. ECBP2 to be non-existent! The equipment
was sufficiently sensitive and accurate to
identify in which direction a single person
Introduction This suggests 26kN/m3 for the density of the walked across a slab, but never recorded
Backpropping of concrete slabs during reinforced wet concrete. any changes to the backpropping loads in
construction is a subject often The Concrete Structures Group’s Guide to individual members.
misunderstood in the industry. To address flat slab formwork and falsework (CS140)5 It is recommended that, unless separately
this, last month’s article in the series1 recommends that the concrete density be specified, the construction working area load
covered the theory and detailed methods considered in the wet condition, at 25kN/m3 is not included in backpropping calculations.
recommended for calculating backpropping for normal flat slab construction, for the
loads, based on research carried out for the design of the falsework only; but accepts Example: calculation with two
European Concrete Building Project (ECBP) that the value of density of 24kN/m3 is to be levels of backpropping
and published by the Building Research used for backpropping calculations. Figure 1 shows an example of a
Establishment (BRE)2. backpropping calculation using Method 1
This article continues by discussing some Construction working area load (see Part 4 in this series for a description of
of the design issues and preconceptions The designer of the soffit formwork and the methods available for backpropping
related to backpropping, and gives worked falsework will have considered both the calculations1). The commercial building
examples. working area load of 0.75kN/m2 and the selected has a solid, 250mm thick,
additional transient load on a 3m × 3m area, reinforced concrete, in situ flat slab on
Slab self-weight – concrete density for the falsework design. (See Cl. 17.4.3.1 of columns set on a 7.5m grid.
Unless specified otherwise, the designer of BS 59753.) The additional transient load is The permanent works designer (PWD)
the reinforced concrete flat slab will not included in the backpropping has used an unfactored design load of
generally assume a density of the concrete calculations as it only represents the 10.50kN/m2. This is made up of the slab
of 24kN/m3. This value for density is also operatives placing the in situ concrete. self-weight of 6.0kN/m2, plus service
recommended to be used in backpropping Although the competent designer would imposed load of 2.50kN/m2, plus allowance
calculations. argue that there is always a risk of people for finishes/partitions of 2.0kN/m2.
BS 59753 states a value for concrete walking over any horizontal surface, be it The calculation shows the various total
density of 2500kg/m3, i.e. 24.52kN/m3. floor slab or soffit formwork, they would loads predicted in the floor slabs and the
The higher value agrees with the normally allow for a minimum Service Class 1 loads in the backprops at different stages of
recommendation in BS EN 1991-1-14, which loading of 0.75kN/m2 on every flat surface. construction. It is noted that the backprops
assumes a density of 24kN/m3 plus 1kN/m3 Obviously, the weight of additional are inserted at Fig. 1 stage (c) as reasonably
for ‘reinforced concrete’ and a further construction materials (blocks, bathroom ‘finger-tight’, i.e. with no preload.
1kN/m3 for ‘unhardened concrete’, as it units, etc.) stored on a completed floor in Inspection of Fig. 1 stage (d) clearly shows
needs supporting during its stiffening phase. advance of follow-up trades would always that the supporting slab has a foreseeable

30 January 2017 | TheStructuralEngineer

TSE61_30-32 Temp Works Toolkit_v1.indd 30 15/12/2016 10:18


Technical
thestructuralengineer.org Part 6 | Temporary Works Toolkit

load applied that is at least 12% greater than agreed amount (Pp), then this has the effect compared to the predicted value from
that anticipated by the PWD in the original of reducing the imposed load on the Method 1 of 10.55kN/m2.
slab design. Not only does it mean that the supporting slab, and increasing the load on As an engineer, it is my opinion that this
new slab can only be cast when the the lowest slab; but it depends on the close correlation between theoretical and
supporting slab has reached full maturity, but magnitude of preloading. practical loads fully justifies the use of these
the PWD would need to approve the Figure 2 stages (a), (b) and (c) show the methods of backpropping calculations for
construction methodology. effect on the total applied load for the same the building industry.
The philosophy of loading a slab to above example given in Fig. 1, but applying a
its design service load is extensively preload representing only 0.50kN/m2 to the Preloading of backprops
discussed in Annex E of CS1405. backprops. As previously recommended, no How, then, could a site effectively, and safely,
This explains the opening quote in Part 4 construction working area load is applied on preload backprops to its advantage?
of this series by the respected engineer: ‘It’s the slabs. Provided similar props are used, the
not a question of whether they crack, but by Comparing results from Fig. 1 stage (d) to change in length will be directly proportional
how much they crack!’ Fig. 2 stage (c) shows that installing to the load; thus, for a given storey height
If this is such a fundamental issue in backprops with preload has a significant and particular type of proprietary prop,
multistorey construction, why have we not effect. In this example, it reduces the turning the adjusting collar a set amount
seen many collapses or serious incidents? supporting slab foreseeable load applied would initiate a crude measuring device for
There are three possible answers: from 12% greater than anticipated to less preload.
1) Designers have simply ignored it, favouring than 1% greater than anticipated. In practice, it was found difficult to control
rigid prop assumptions with lower values. Nonetheless, the temporary works designer the preload at the ECBP, even with load cells
2) Concrete at an early age is autogenous (TWD) would still need to refer this ‘overload’ installed, because of the tendency to
and has some self-healing processes that to the PWD for consideration. transfer load between adjacent props as one
may have partially hidden any overloading. Once again, this demonstrates that the is tightened up, due no doubt to the thin slab
3) The operatives have installed the new slab can only be cast when the and the flexible nature of the slab.
backprops ‘a bit tight’. supporting slab has achieved at least its full Calculation of the prop extension required
characteristic design strength; it also to achieve a particular preload is
The third answer is probably the likeliest. If assumes that no additional construction complicated by the stiffness of the slabs,
fitted loose, the individual backprops would loads are applied to the floors, e.g. from which will move up and down with load, thus
fall over, so the operative puts some storage of materials. changing the elongation, etc.
pre-tension into the backprops. The examples given in this article have The prop stiffness (kN/mm), translated by
The following calculation shows the effect used the in situ reinforced concrete slab the temporary works coordinator (TWC) into
of preloading backprops using the same design involved in the research at the ECBP2. load per turn, and hence the number of
example. The results from the precise monitoring at complete turns on the adjusting screw to
the ECBP on the fourth-floor construction give this extension, may be impossible to
Example: calculation with two levels of are shown in Fig. 2 stage (d). Note in predict and calculate. Other methods, such
backpropping installed with preload particular the load in the supporting floor as load indicating washers, may be possible,
If all of the backprops are preloaded by an slab, which was measured at 10.57kN/m2, but no one method seems to be simple

S Figure 1 Example with two levels of backpropping (250mm solid flat slab)

6.25
0.75
(say)

Supporting 0.50
Notes
slab
1) Unfactored design load
for slab is 6.00 (self-
weight) + 4.50 (imposed) 6.75 7.25 7.25 11.80
= 10.50kN/m2
2) Full construction load on
supporting slab in case 0.00 2.45
(d) using Method 1 gives
(65% × 7.00) + 7.25 =
11.80kN/m2 6.75 6.75 6.75 8.36
3) If the falsework designer
had selected a concrete
density of 25kN/m3 with 0.00 0.84
full operations load, this
would now give 65%
× (6.25 + 1.50) + 7.25 = 6.75 6.75 6.75 7.59
12.29kN/m2
4) The TWD would need (a) Cast (b) Erect (c) Insert (d) Cast new
to discuss with the PWD supporting falsework backpropping slab
how to deal with the slab, strike
and allow to
loading during construc- deflect
tion that exceeded the
design service load by at
least 12% for the slab
All loads stated in kN/m2

TheStructuralEngineer | January 2017 31

TSE61_30-32 Temp Works Toolkit_v1.indd 31 15/12/2016 10:18


Technical
Temporary Works Toolkit | Part 6 thestructuralengineer.org

concrete slabs can be applied without


S Figure 2 Example with two levels of preloaded backpropping
(250mm solid flat slab)
change?

6.25
The Temporary Works Forum (TWf)
0.75 formed a working party to discuss
(say)
0.50 0.50
backpropping and future research needed. If
6.82
you are interested in participating, please
contact secretary@twforum.org.uk.
6.50 6.00 10.55 10.57

0.50 2.95 2.25


REFERENCES
6.00 6.00 7.61 7.35
E1) Pallett P.F. (2016) ‘Temporary Works
Toolkit. Part 4: An introduction to
0.50 1.34 0.90
backpropping of flat slabs’, The Structural
6.00 6.50 7.34 6.90 Engineer, 94 (12), pp. 36–41

(a) Erect (b) Insert and preload (c) Cast new (d) Loads measured
falsework, backpropping slab at ECBP (4th floor) E2) Beeby A.W. (2000) BR 394: A
allow slab to, say, 0.50 (preload 0.30kN/m2) radical redesign of the in situ concrete
to deflect
frame process, Task 4: Early striking of
formwork and forces in backprops, London:
All loads stated in kN/m2 University of Leeds and Building Research
Notes Establishment Ltd
1) Unfactored design load for slab is 6.00 (self-weight) + 4.50 (imposed) = 10.50kN/m2
2) No construction operations loading is included in the backpropping calculations E3) British Standards Institution (2011)
3) Full construction load on supporting slab in case (c) using Method 1 gives BS 5975:2008+A1:2011 Code of practice
(65% × 7.00) + 6.50 – 0.50 = 10.55kN/m2
for temporary works procedures and the
4) The TWD would need to discuss with the PWD how to deal with the loading during
construction that slightly exceeded the design service load for the slab permissible stress design of falsework,
5) The loads in floors and backprops at stage (d) were recorded by BRE on the ECBP at the fourth floor London: BSI

E4) British Standards Institution (2002)


BS EN 1991-1-1:2002 Eurocode 1. Actions
on structures. General actions. Densities,
enough to operate regularly, allowing for requirements between the client wanting a self-weight, imposed loads for buildings,
modern, quite flexible floor slabs. Operators certain shape to the deflected floor, the actual London: BSI
still need to install backprops as individual specification used and the construction
items, and complex academic systems of methodology to achieve fast construction. E5) Concrete Structures Group (2003)
CS140: Guide to flat slab formwork and
preloading will rarely be justified. Although none of the fast-track approaches at
falsework, Crowthorne: Concrete Society
There is a precedent for accepting the ECBP ever infringed the PWD’s overall (Guide includes backpropping Excel
operator-based preloading in the deflection criteria, the subject needs spreadsheet on CD-ROM)
construction industry – the torque on addressing. A useful article by Alasdair Beal
scaffold fittings is practically solved by discusses further the implications of ‘Floor E6) Beal A.N. (2011) ‘Floor slabs, lasers and
limiting the length of the scaffold spanner slabs, lasers and levels’6. levels’. Concrete, 45 (9), pp. 15–17 [Online]
and by the physical capability of the ‘average Available at: www.anbeal.co.uk/V45109P15.
pdf (Accessed: December 2016)
scaffolder’ tightening up the fitting! This Post-tensioned flat slabs
simple approach of operator-based loading The research discussed in this article relates
E7) Concrete Society (2012) CS030:
was used at the ECBP, with backprops to in situ reinforced concrete slabs, but what Formwork – a guide to good practice (3rd
inserted ‘operator tight’. Inspection of the happens if the cast slabs are post-tensioned? ed.), Camberley: Concrete Society
actual preload achieved at the ECBP of 0.90 This question was a recommendation for
and 2.25kN/m2 (Fig. 2 stage (d)) research in Section 8 of the Concrete
demonstrates that the assumption of a Society’s Formwork – a guide to good practice7
FURTHER READING
conservative preload of 0.50kN/m2 is and it is now becoming more relevant as the
practically achievable. use of post-tensioned slabs increases. EAlexander S. (2004) ‘Propping and loading of
This confirms the author’s opinion that Issues that the PWD needs to address in-situ floors’, Concrete, 38 (1), pp. 33–35
sites have traditionally been putting in during post-tensioned construction include:
backprops with preload and explains why  How does the PWD know the load in each EIsgren C., Vollum R. and Webster R. (2004)
problems have not materialised in flat slab at each stage of construction? ‘Reducing slab deflections in fast-track
multistorey buildings.  If partial prestressing at an early age construction with the formwork strip model’,
Concrete, 38 (1), pp. 15–16
for striking formwork is permitted, what
Deflection of flat slabs at early age happens to the loads in lower floors
Fast-track construction, and requirements for fitted with backprops? Is the relief of
slabs to be struck safely at an early age and stress proportional to the stiffness, or is HAVE YOUR SAY
to take up instantaneous deflections, all it a negative version of the Method 1 load
To comment on this article:
require considerations by the TWD and PWD. transfer?
Eemail Verulam at tse@istructe.org
The subject needs close cooperation between  Does a post-tensioned supporting floor act Etweet @IStructE #TheStructuralEngineer
designers. There may be conflicting in such a way that the theory for reinforced

32 January 2017 | TheStructuralEngineer

TSE61_30-32 Temp Works Toolkit_v1.indd 32 15/12/2016 10:18

You might also like