Download as rtf, pdf, or txt
Download as rtf, pdf, or txt
You are on page 1of 26

Contents

Ref: Title: Page:

Section One General 4


2.1. General 4
2.1.1. Scope of the Works 4
2.1.2. Basis of Design 5
2.1.3. Site Visit 5
2.1.4. Professional Team 5
2.1.5. Form of Contract 7
2.1.6. Standard Specification 7
2.1.7. Maintenance & Warranty 7
2.1.8. General Requirements 8
2.1.9. Provisional Sums 8
2.1.10 Programme 9

Section Two Description of the Works 10


2.2. Description of the Works 10
2.2.1. Air Conditioning 10
2.2.1.1 General 10
2.2.1.2 Material Specification 13
2.2.1.3 System Pressure and Leak Test. 14
2.2.1.4 Pipework 15
2.2.1.5 Condensate Drains 18
2.2.1.6 Commissioning 18
2.2.1.7 Controls 19
2.2.2. Ventilation 19
2.2.2.1 General 19
2.2.3 Electrical Works 20
2.2.3.1 General 20

Section Three Appendices.


2.3.1 Drawing Schedule 15
2.3.2. Technical Equipment Schedule 17
2.3.3 Tender Breakdown 18

Document Tracking.
Issue: Details: Date: Checked By:

001 Tender Issue 21/09/10 GM

2.1. General
Section One -General
Particular Specification 1 September 2010
.2.1.1. Scope of the Works.

This scope of works, drawings, and specifications relates to the supply, delivery, installation,
setting to work, commissioning, testing and handing over to the client of a complete mechanical
& electrical engineering services installation associated with the replacement air conditioning to
the Restaurant, shop, soft seating area, coffee lounge, also replace the R22 refrigerant system in
the following areas: -

 Room 1023A

 Room 1023

 Room 1027

 Room 2100

 Room 3014

 Room 3015

 Room 3021

 Room 3025

All at Office for National Statistics [ ONS ] at Titchfield.

The mechanical engineering services works will generally be comprised of the following:

1.
Supply & Installation of new air conditioning equipment to provide heating and cooling to the restaurant,
shop and lounge seating areas.
2. Condensate drainage.

3.
Associated electrical modification works from existing electrical supplies.
4.
Installation of air conditioning controls systems linked to the new AG 150 controller
system.
5.
Modification to existing fresh air ventilation system.
6.
De-Gasing (FGas Regs) and Removal and disposal of existing systems.
7.
Testing and Commissioning.

Particular Specification 2 September 2010


8.
Craning of plant to and from roof level etc.
9.
Protection of the occupied space during the works.
10.
Maintenance of systems during 12 months defects liability period.

The mechanical engineering services contractor shall recognise and allow for in their tender the
need for close liaison with MITIE’S Facilities Team.

It is the responsibility of the tenderer to visit the site by appointment prior to submitting his
tender. No claim for variation to the tender sum shall be accepted subsequent to failure to visit site
and omission from the tender.

The mechanical engineering services contractor shall include within his tender for attendance at
all meetings required by the client whether on site or at any other location specified by the client.

The mechanical engineering services contractor shall within his tender make due allowance for
the provision of samples. All samples shall be forwarded to the client's representative for
approval, prior to any orders being placed. This shall include all items of the mechanical
engineering services contractors scope of works and as a minimum all items that will be visible at
the completion of the works, (including but not limited to: condense pumps, grilles, diffusers,
etc.).

The mechanical engineering services contractor should be aware that despite the detailed nature
of the tender drawings, these do not relieve the mechanical engineering services contractor from
the requirements for the provision of fully coordinated working drawings. These should be of
such detail that the requirements of any structural openings can be confirmed and detailed with
the structural engineers prior to the installation of the ductwork, pipework, etc.

The mechanical engineering services contractor should make themselves fully conversant with the
mechanical services drawings. In particular the mechanical engineering services contractor shall
allow for providing full working drawings and in addition any required schematics,
diagrammatic’s etc, together with plant rooms, risers and any particular engineering "pinch
points", that occur.

The mechanical engineering services contractor is required to allow in his tender bid for the
preparation of working drawings and to keep these drawings updated for the complete duration of

Particular Specification 3 September 2010


the contract period, as and when revisions are received by the mechanical engineering services
contractor from the professional team.

These drawings shall then be used to provide the ''As Fitted" documentation and information, which shall be
provided at the completion of the contract, in accordance with the relevant clauses of the Standard Specification MI.

2.1.2. Basis of Design.

The following documentation has been utilised to form the basis of design:

1) Current CIBSE Standards


2) Heating and Ventilating Contractors Association.
3) Statutory Acts.
4) British Standards and British Standards Codes of Practice.
5) Local Authority Building Regulations.
6) Health and Safety at Work Act.
7) The Gas Safety (Installation and Use) Regulations.
8) Water supply Regulations.
9) F Gas Regulations.

2.1.3. Site Visit.

It is a requirement that the contractor visits the site and inspects the vertical and horizontal distribution routes, and
all areas described within the design pack during the tender period. All such visits must be arranged via the Project
Manager
.
2.1.4. Professional Team.

The contractor should be aware of the following members and details of the design team.

The Employer: The Office for National Statistics.


Segensworth Road,
Titchfield,
Fareham.
PO15 5RR.

The Project Manager Mitie Facilities Services Ltd.

Particular Specification 4 September 2010


Room 1000.
The Office for National Statistics.
Segensworth Road,
Titchfield,
Fareham.
PO15 5RR.

Tel: 01329 447840


Contact Emran Mannan

M&E Designer: MITIE Facilities Services Ltd


Room 1.201
Government Buildings
The Office for National Statistics
Cardiff Road,
Newport,
NP10 8XG.

Tel: 01633 456310


Contact: John Davies

2.1.5. Form of Contract.

Details of all contract clauses and conditions, along with other preliminary information of the
main contract are as contained in the separate documents prepared and issued by Project
Manager / Contract Administrator; These documents shall take precedence where conflicts may
occur.

2.1.6. Standard Specification.

Particular Specification 5 September 2010


Issued with this scope of works and drawings, is a standard specification, (Reference Mech 1), for
materials and workmanship which the contractor will be required to comply with in full. This
document forms part of the complete contractual documentation package.

Where any of the preliminary sub-clauses conflict with the quantity surveyors or project
managers’ contractual documentation or standard forms of contract, then the latter will be deemed
to take precedence and be included. Any conflicts shall be notified in writing and issued with the
tender return together with a list of any subcontractor the contractor intends to use on this
contract.

The contractor shall ensure that he is fully conversant with the standard mechanical specification
and its contents and requirements.

Any part of the installation provided by the contractor found not to comply with either this
particular specification or scope of works or the standard mechanical specification will be
rectified by the contractor at no extra cost to the project.

Any variations from either this document or the standard mechanical specification shall be
verified and confirmed in writing by the M&E Services Consultant prior to the commencement of
the variant works.
Please note that where reference is made in any of the contract specifications or drawings to the
consulting engineer or the engineer or the professional team this shall taken to refer to the Project
Manager or Contract Administrator once the contractor has been appointed.

2.1.7. Maintenance & Warranty.

The contractor is required to include in the tender submission a price for the provision of full
maintenance facilities, for all of the engineering services installed by him for a period of 12
months from the date of practical completion. This will then run concurrently with the 12 month
warranty period provided for all new equipment and systems.

During this period, the contractor will be required to bear all charges for the maintenance other
than those associated with normal wear and tear.

The contractor will be required to make service visits in accordance with the requirements and the
recommendations of the manufacturer of each particular piece of equipment installed. A full
maintenance agreement shall include the number of visits and a schedule of equipment to be

Particular Specification 6 September 2010


serviced, as would be contained in a normal maintenance agreement. The successful contractor
shall provide this document, no later than one month after receiving his appointment.

2.1.8. General Requirements.

The contractor shall allow in the submission of his tender for all of the necessary sets or
diversions, to the new services installation, so as to facilitate a complete and coordinated
installation. No claims for additional costs will be accepted for local sets, etc.

The contractor shall identify and allow in his tender submission, for all of the necessary
equipment to be installed to complete the works. All mechanical details and functional details for
all of the component parts used to make up any part of or the complete mechanical installation
shall be provided within the tender submission including literature, such that an advised decision
can be given by the employer / consulting engineer, during the tender analysis. No changes to the
specified manufacturers that will be utilised after the tender analysis will be allowed.

The contractor shall be responsible for the coordination of the new mechanical and electrical
engineering services installation with the existing structure, services, false ceilings, risers, and
voids, etc. as well as each other.

The contractor will be required to take specific design responsibility in respect of this contract.

This responsibility includes, but is not limited to the following:

a) All necessary builders work.

b) All brackets and supports.

c) All detailed working and fabrication drawings including coordination

d) The selection and suitability of all materials and equipment specified by performance.

e) The sizing of the various cable carrying systems.

Where equipment is specified it is the mechanical engineering services contractors’ responsibility


to ensure that the equipment specified meets the performance criteria.

No changes to the specified manufacturers to be used will be entertained.

Particular Specification 7 September 2010


The contractor is to confirm the electrical loading and space requirements of the mechanical
services installation. Any revision that may affect the installation of the proposed services needs
to be identified to the Project Manager at tender stage.

The contractor shall also provide all the information detailed in the standard specification.

2.1.9. Provisional Sums.

Contained in the ‘Tender Analysis’ within the accompany document is a list of Provisional Sums.
No guarantee is given or is implied that the expenditure of such sums will be authorised in whole
or in part. No claim for loss of profit for any provisional sums not expended will be entertained.

2.1.10 Programme.

The current programme proposes that the works are to commence 5 th November 2010 with all the
of the works complete by the end the 24 th December 2010. The contractor is to provide comment
on the programme with estimated completion dates with their tender return.

Section Two - Description of the Works.

2.2. Description of the Works.

2.2.1. Air Conditioning.

2.2.1.1 General.

Particular Specification 8 September 2010


Restaurant, Shop, Soft Seating Area

The existing main air conditioning system in the restaurant (room 1030) is an IMI Marstair
system of duty around 28KW using R22 as a refrigerant. Current legislation makes the use of this
refrigerant redundant and the systems will have to be replaced. The Annex or soft seating area to
the Canteen uses a single split Mitsubishi PUH model unit of 8KW capacity using R417A
refrigerant.

The contractor is to remove the existing air conditioning system in the restaurant, shop and soft
seating area. The units from the shop and soft seating area are to be saved to be re-utilised in the
gym and the dance studio,

The contractor shall supply and install 4 new Mitsubishi PEFY-P63VMA-ER2 ducted fan coils in
the ceiling void in the restaurant as shown on drawing QL392/M/002.

The contractor shall supply and install 1 new Mitsubishi PEFY-P63VMA-ER2 ducted fan coil in
the ceiling void in the shop as shown on drawing QL392/M/002.

The contractor shall supply and install 1 new Mitsubishi 5kW ceiling mounted cassette in the soft
seating area as shown on drawing QL392/M/002.

The contractor shall supply and install 2 new Mitsubishi 5kW ceiling mounted cassettes in the
coffee lounge area as shown on drawing QL392/M/002.

Room 1023A

Strip out existing air conditioning unit and supply and install 1No. new Dimplex 1.5kW electric
panel heater with timer and integral thermostat wired to local 13amp fused spur.

Room 1023

Strip out existing air conditioning unit and supply and install 2No. new Dimplex 1.5kW electric
panel heater with timer and integral thermostat wired to local 13amp fused spur.

Room 1027

Strip out existing air conditioning unit knock down wall between 1027 & 1037, build a new
partition wall with 30 minutes minimum fire protection with 30 minute fire rated beech laminate
door with vision panel with pyrostop glass (not Georgian wire) assembly, ‘Cypher’ code lock and
supply and install 2 number new Mitsubishi Mr Slim PKA-RP35HAL R410A wall mounted air

Particular Specification 9 September 2010


conditioning units as shown on drawing QL392/M/002. Install perimeter electrical dado rail
trunking to perimeter. Allow for extra over price for new ceiling grid, tiles and 6 no. ceiling grid
light units supply and fit.

Room 2100

Strip out existing air conditioning cassettes 10 no. and all associated equipment, blank off
openings in ceiling with MDF panels painted in RAL9010 eggshell white.
Provide alternative price for ‘de gas’ only leaving units and all associated equipment in situ

Room 3014 & 3031

Strip out existing air conditioning cassettes and install ceiling mounted cassettes salvaged from
the Shop as shown on drawing QL392/M/004.

Room 3015

Strip out existing floor standing air conditioning units and install 12 number new Mitsubishi PSA-
RP125 GA floor standing units as shown on drawing QL392/M/004.
Provide alternative price for ‘drop in’ gas only

Room 3021

Remove two number wall mounted existing R22 units and install 2 number new Mitsubishi Mr
Slim PKA-RP35HAL R410A wall mounted air conditioning units as shown on drawing
QL392/M/004.
Provide alternative price for strip out and make good only

Room 3025

Remove existing wall mounted existing R22 units and install 1 number new Mitsubishi Mr Slim
PKA-RP35HAL R410A wall mounted air conditioning units as shown on drawing QL392/M/004.
Provide alternative price for strip out and make good only

Installation

The Restaurant is to remain operational throughout the installation and therefore the contractor
shall have limited access to the site during the normal working day. Work on the roof shall be

Particular Specification 10 September 2010


permitted during the working day however noisy operations that could cause disruption will not
be permitted. All work shall be agreed with PM prior to undertaking. Full area protection is
required in this area to ensure that normal service can resume for all restaurant processes
including early morning food preparation, with all furniture replace as per original layout at the
start of each day.
Restaurant - Existing roof lights
It is anticipated that we shall utilise 7 no. roof lights to provide natural lighting in to the restaurant
area with each light dome receiving a UV filming to reduce the ingress of ultra violet light to the
current standard. Please also price for extra over for the replacement of the domes with ‘Pyramid’
type roof lights from http://www.glazing-vision.co.uk/hingedpyramid.php (contact Chris Gamble
07538 370256), allow for all flat roof works to ensure weather tightness.

Restaurant lighting
A new lighting system is required to replace the existing, to meet the current standards. Please
allow for –
Grazer LED lighting for each roof light
Ceiling grid lighting to supplement natural lighting
Smart controls including PIR, timer linked to BMS
Restaurant – other systems
Please allow for the installation of –
Broadcast speakers fitted in the ceiling grid – 7 No. (Installed by A IIlingworth – Tel: 01329
823872)
Smoke detectors – replace existing 5000 series with 6000 series (installed by ‘Protec’ – Tel: 084
54565392 Contact Ricky Mark)

Existing ceiling features are to be protected during works and left ‘in situ’

Please allow PC sum for ‘Air curtain’ over restaurant entrance door, as part of the overall air
conditioning system

Working hours
Working Day Monday to Friday 4PM to 5AM
Weekend – Friday 4 PM to Monday 5AM

The contractor shall have full access to the site from Friday 16.00pm until Monday 5.00am which
it is envisaged that the majority of the installation works will be taking place.

Particular Specification 11 September 2010


The contractor is to include for full protection of the workspace to ensure that dust and dirt is not
is not left for the occupants during their occupation of the space. This shall therefore include
plastic sheeting as well as dust sheets together with any cleaning required before occupation of
the client.

The works will involve removal of areas of existing ceiling tiles, it is therefore proposed that
these are removed at the beginning of the works and stored safely, these will then be replaced
once access is no longer required. The lighting and smoke detectors will need to remain fully
functional in the correct locations and therefore these will need replacing prior to any occupation
by the client.

The contractor is to allow for the replacement of 200No matching ceiling tiles (Assume
Armstrong Dune for pricing purposes.) to replace any damaged ones, these shall be used at their
discretion and any tiles that are not used are to be handed to the Project Manager.

Each unit shall have a suitable acoustically lined plenum box fitted to the front with circular
spigots as required. Each spigot shall have its own VCD from which ridged spiral duct shall run to
the diffuser connection. The last 300mm should be run in acoustic flex to allow some flexibly so
that it can be lined up with the ceiling grid.

Return air to the units shall be via perforated face egg crate type grilles within the ceiling, these
shall allow air to return into the ceiling and back to the rear of the fFan coils units.

The supply air and return air grilles are to be powder coated, each grille is to have plenum box or
baffle painted black to prevent light entering the space and so that the ceiling void can not be
viewed from below.

Each unit is to be provided with its own remote temperature sensor in order to provide accurate
room temperature control.

All external condenser’s are to be situated in the areas shown on drawing QL392/M/001 the units
are to be supported on purpose built supports on the original paving slabs.

Each unit is to be fitted with a peristaltic Hi Flow tank type condensate pump as manufactured by
Aspen. The pumps shall be mounted adjacent to the fan coil unit and pump the condensate to the
existing location of the redundant ceiling cassette unit condensate.

Particular Specification 12 September 2010


The air conditioning equipment is to be as manufactured by Mitsubishi Electric and is to be
supplied complete with a five year warranty.

The air conditioning works shall comprise of the following:

i) Supply and fixing of all equipment.


ii) Supply and installation of all refrigeration and condensate pumps & pipework.
iii) All control and communication cabling between the indoor and outdoor units.
iv) Supply and fixing of controllers and associated cabling.
v) All power wiring for both the indoor and outdoor units together with all associated
electrical works.
vi) Testing and Commissioning.
vii) Protection of the work space during the works.

The contractor shall include for positioning all equipment including crane hire associated with
lifting the outdoor units onto and off of the roof. Where there is a possibility of any noise or
vibration from the equipment passing into the structure then suitable attenuation measures shall be
taken to eradicate this. i.e. the installation of anti vibration pads or mounts.

The installation of all internal and external units, refrigerant pipework, interconnecting wiring,
commissioning and testing shall be carried out by an approved Mitsubishi air conditioning
installer.

The fixing of all air conditioning equipment, installation of all refrigerant pipework and full
commissioning shall be performed by a specialist refrigerant installer who has been authorised to
install Mitsubishi Electric equipment (certificate of approval must be submitted prior to
commencement on site).

The installer shall clearly state on his/her tender submission any specialist subcontractors he/she
intends to employ to carry out the work if not in their direct employment.

Full access shall be afforded to site during the installation stage of the project to allow Mitsubishi
to verify that installation methods are fully in accordance with Mitsubishi Electric requirements
and that the equipment warranties will not be invalidated.

All works including labour, materials, plant, tools and equipment will comply with BS EN378.

Furthermore all of the following points should be adhered to:

Particular Specification 13 September 2010


The installer retains the responsibility to advise of any aspects which, based upon experience,
would appear to be inappropriate and or likely to lead to operational problems.

The installer will adhere to the Health & Safety at Work Act and all other relevant attendant
legislation, particularly the management of Health & Safety at Work Regulations 1992,

Personal Protective Equipment at Work Regulation 1992 and the Construction, Design and
Management (CDM) Regulations.

The installer will ensure that all personnel are in possession of the appropriate personal protective
equipment comply with the Personal Protective Equipment Regulations.

The installer will ensure that all personnel are fully competent in the work they are tasked to
perform and any claim to stated qualifications are valid.

The installer will ensure that all personnel are instructed to comply with the prevailing site rules /
directions.

All installer will use calibrated and regularly checked tools. Electrical tools will be calibrated and
checked annually.

Upon completion of the works the Contractor will ensure that all debris is removed and the site is
left clean and tidy to the satisfaction of the contract administrator.

Witnessing of the commissioning of the refrigerant system and final inspection shall be carried
out by both the specialist refrigeration installers and Mitsubishi prior to offering to the contract
administrator.

2.2.1.2 Material Specification.

All refrigeration pipework, interconnecting wiring, condensate pipework, etc. Between the air
conditioning units and outdoor heat pumps shall be installed, and tested in accordance with the
manufacturer's recommendations and the following codes / standards.

i) B.S. 4434 . Requirements for refrigeration safety: Part I General.


ii) Safety code for refrigerating systems utilising chlorofluorocarbons. Part I.
design and construction, published by the Institute of refrigeration.

Particular Specification 14 September 2010


iii) Safety code for refrigerating systems utilising chlorofluorocarbons. Part II -
Commissioning.
iv) Guide to good practice. Unit air conditioning including heat pumps, published
by the Heating and Ventilating Contractors Association.
The latest edition of the I.E.E. Regulations.

Supply and installation of all interconnecting refrigeration pipework should be carried out by a
Mitsubishi Electric Business Solutions Partner or Accredited Installer (certificate of approval
must be submitted prior to installation commencement) in accordance with Section 4, Part 1, of
the ‘Safety Code for Refrigerating Systems Utilising HFC’s’ published by the Institute of
Refrigeration, and to BS EN 378 Specification and Mitsubishi Electric Air Conditioning design
and installation instructions. All pipework must be suitable for R410A/R407C as applicable.

2.2.1.3 System Pressure and Leak Test.

Before the systems are put into service they shall be leak tested and tested for mechanical
strength.
Five Step Strength and Leak Test.

 3.0 bar (N2) Minimum of 3 minutes.

 15.0 bar (N2) Minimum of 3 minutes.

 32.0 bar (N2) Minimum 15 minutes.

 41.5 bar (N2) Strength test for a period of time that is acceptable to show any signs of
deformation to the pipework.

 33.0 bar (N2) After step 4, drop pressure to 33 bar for final leak test for minimum 24
hours.

Pressure testing signage will be clearly visible on site during testing periods.
All completed R410A systems will be, leak tested with dry nitrogen as per the Mitsubishi Electric
Commissioning Log Book method statements as below and BS EN 378. If the system is found to
be leak free. The final pressure readings for both strength and leak testing are to be witnessed and
entered into the Mitsubishi Electric Commissioning Log Book (Method Statement 1).

Three Step Leak Test.

 3.0 bar (N2) Minimum of 3 minutes.

Particular Specification 15 September 2010


 15.0 bar (N2) Minimum of 3 minutes.

 3. 32.0 bar (N2) Minimum 24 hours. Pressure testing signage will be clearly visible on
site during testing periods.

On completion of strength/leak testing an evacuation is to be carried out to 2mm Hg (2 Torr). This


will eliminate the risk of any moisture being present within the pipework installation. It is
recommended that a triple evacuation process be carried as below and as per the method
statement in the relevant Commissioning Logbook (Method Statement 2). This should then be
followed by a pressure rise test.
Six Step Evacuation.

Evacuate the system to 10 Torr from both service valves. System manifold gauges ‘must not’ be
used to measure a vacuum. A Torr gauge must be used at all times.
Break the vacuum with OFN (N2) into ‘suction’ service valve to 1 bar.
Evacuate to 5 Torr from ‘discharge valve’
Repeat step 2
Evacuate to lowest pressure vacuum pump will achieve (2 Torr for 1 hour minimum)
Pressure rise test to be carried for a minimum of 30 minutes

2.2.1.4 Pipework.

Longest possible lengths of copper pipe should be utilised to minimise joints on site. Furthermore
all of the following points should be adhered to.

All copper pipe up to 1 1/8’ (28 mm) outside diameter (O/D) shall be fabricated from refrigerant
quality tube to BS EN 12449:1999. Tube shall be fully annealed up to 7/8’ (22 mm) outside
diameter (O/D) only. Tube shall be delivered to site internally degreased and shall be stored in
clean dry conditions with ends sealed until required for installation.

All due consideration and allowances shall be taken to keep pipework clean and dry during the
installation works. Ensuring that all pipework unfinished ends are capped off at all times.

The number of joints, bends and sets are to be kept to a minimum. Butt joints will not be
accepted, properly swaged joints must be formed. Bends and sets are to be machine pulled to an
approved radius where possible.

Flared joints must only be used when connecting to the manufacturers equipment.

Particular Specification 16 September 2010


Pipework to properly fixed and supported using a recognised and approved Mitsubishi Electric
Partner Programme support system.

Pipe work shall be suitably identified and labelled with Mitsubishi Electric Partner Programme
labels in order to identify each of the systems.

Brazing shall be carried out in accordance with British Refrigeration Association Specification for
Brazing and BS 14324:2004. Brazing rods shall be cadmium free and conform to BS EN
1044:1999. At all times, when brazing, a small amount of dry nitrogen must be purged through
the pipe to prevent oxidation and scaling internally. Any component susceptible to heat during the
brazing process that may be damaged must be protected. Soft solder shall never be used for
jointing of refrigeration pipework.

All completed R410A systems will be, strength and leak tested with dry nitrogen as per the
Mitsubishi Electric Commissioning Log Book method statements as below and BS EN 378. If the
system is found to be leak free. The final pressure readings for both strength and leak testing are
to be witnessed and entered into the Mitsubishi Electric Commissioning Log Book (Method
Statement 1).

At all times, when brazing, a small amount of dry nitrogen must be purged through the pipe to
prevent oxidation and scaling internally. Any component susceptible to heat during the brazing
process that may be damaged must be protected. Soft solder shall never be used for jointing of
refrigeration pipework. The Contractor shall supply, install, test and commission all
interconnecting refrigeration pipework between the condensing units and the connected indoor
units.

The pipes shall be clipped using an approved pipe clamp, in vertical risers supports such as
"Hydrazorb" or similar, which incorporates a synthetic insulating collar clamped by a plated steel
clamp to a corrosion protection (galvanised or similar) steel or aluminium rail such that the pipe is
positively located at each clamping point. Clamping of pipework over its own insulation shall not
be allowed within vertical risers. The pipework shall be clipped at intervals such that the
pipework cannot sag or distort and at a maximum of 2 meter centres. Supporting of pipework
using tiewraps shall not be acceptable.

Refrigerant pipework shall not be doublebanked or clustered useless space restrictions necessitate
otherwise.

Particular Specification 17 September 2010


Where located external to the building pipework supports shall be carried on heavy duty external
quality galvanised cable tray supported on galvanised steels, or Unistrut type corrosion protection
supports (all cut ends protected with Galvafroid paint). A galvanised sheet steel cover (ridged in
the centre to provide rain runoff) shall be provided, framed as necessary in galvanised angle to
provide rigidity and bolted down over any horizontally mounted external cable tray to provide
mechanical protection and rain runoff.

Pipe supports shall not restrict expansion or contraction of the pipe and restraint shall not be
applied to joints or headers.

All pipework (suction and liquid) shall be insulated with slip on close cell elastometric pipe
insulation (as manufactured by Armaflex or equal and approved), fire rated to Class "0" Building
Regulations 1985, with a wall thickness of not less than 13mm. External pipework insulation shall
be protected with Armaflex paint and shall be covered by a galvanised steel enclosure,
mechanically fixed complete with rain runoff facility. All insulation joints, after pressure and leak
testing, shall be properly glued to Armaflex recommendation so as to provide a complete seal to
prevent any condensation and shall be clearly marked (yellow tape) for ease of identification.

All of the above works shall be carried out before electrical connection is made to the fan coil
units.
The R410a refrigerant charge shall be calculated and weighed to accommodate the actual installed
and measured length of pipework all in accordance to Mitsubishi’s recommendations and
instructions.
Insulation Identification Thermal insulating material used within any building shall, when tested
in accordance with BS 4764:1970, be classified as non-combustible also free from substances
which in the event of a fire would generate appreciable quantities of smoke or toxic fumes.
Insulating materials of Class ‘O’ rating, as defined by the Building Regulations
Thermal insulation will be fitted to all the pipework installations detailed herein. All materials
used will be ‘non-combustible’ Class ‘O’. All insulation materials, adhesives and finishes, will be
suitable in all respects for continuous use without degradation throughout the range of operating
temperatures and within the environment indicated.

The materials and method of installation will comply with all relevant British Standards Codes of
Practice.
The material will consist of flexible CFC free, elastomeric black foam with a closed cell structure.
The outer surface of the foam will be an inherent vapour barrier.

Particular Specification 18 September 2010


In all cases where pipes pass through fire compartment walls, fire resistant and nonflammable
insulation/foam will be packed between the pipe sleeve and the pipe. All insulation will be
supplied at the thickness specified in HVCA standards.

The Mitsubishi Electric Business Solutions Partner or Accredited Installer will apply
identification banding in all instances. Labelling will include the wording ‘Refrigerant under
pressure’

2.2.1.5 Condensate Drains.

All condense drains from the indoor units shall be run in either plastic or in copper, in the case of
the latter they will need to be insulated. All condensate drains to run at a 1:80 min fall and
connect to existing. Where it is not practical to obtain the required fall then suitable low noise
condensate pumps of the Aspen peristaltic type shall be used. For tendering purposes the
contractor should allow for a condensate pump on each unit. This is to be approved by the
consultant / contract administrator before ordering to ensure it is low noise.

A condensate line shall be installed to each fan coil unit. This shall be installed (and insulated if
copper) as per the standard specification. Minimum size of condensate pipes to be 22mm copper
or 20mm plastic, insulated and pumped or by gravity from each fan coil/cassette,
Pipework will be adequately supported in such a manner as to permit free movement due to
expansion and contraction. Pipework should be graded to fall throughout, run to waste and should
also be fitted with cleanable traps. On completion, a leak and function test must be carried out.
Gravity drains will be installed whenever possible.

The mechanical engineering services contractor shall include for all sets, joints, bends and
diversions necessary to install the pipework in the ceiling void. No claims for additional costs in
this respect will be considered.

2.2.1.6 Commissioning.

The Subcontractor shall fully commission all equipment and refrigeration systems to provide the
design and performance standards stated in this specification.

The subcontractor shall demonstrate that the systems fully meet the requirements of this
specification to the reasonable satisfaction of the Engineer before the agreed date of handover of
the installation. The final commissioning of the systems however shall be carried out by
Mitsubishi, however full attendance shall be required by the contractor.

Particular Specification 19 September 2010


2.2.1.7 Controls.

The contractor is to provide a central controller which incorporate 7 day control per system
together with individual controllers for each fan coil on the system. The central controller is to be
situated in the lockable riser as shown on the drawing, a Modbus interface is also to be included
for connection in the future when the current BMS is replaced.

The VRF Installer shall be responsible for the interconnection control wiring and containment
between the indoor and outdoor units and the control wiring centralised controllers and all other
relevant components.
All control wiring shall be carried out in 2 core 0.5mm 1.5mm PVC non screened CY flexible
control cabling to BS6141 and BS6500 (to comply with CE Regulations 1995) colour coded and
separately marked at 3 metre intervals for ease of identification and maintenance.

Where required control wiring containment shall be steel conduit or cable trunking. All
containment located externally shall be galvanised.

Where the mechanical engineering services contractor requires additional holes through the steel
beams or any other structural element including any holes through the floor slab the mechanical
engineering services contractor must detail the requirements on builderswork drawings and
submit them for approval by the structural engineer before proceeding.

2.2.2. Ventilation.

2.2.2.1. General.

The mechanical contractor is to allow for all necessary fire stopping / fire dampers etc. where
ductwork passes through fire compartments. The contractor to ensure this is all ventilation items
are coordinated into the building structure.

Ductwork, grilles and diffusers unless specified otherwise all sheet metal ductwork will be
manufactured and installed in accordance with HVCA specification DW/144. Ductwork systems
will be designed to give a maximum air velocity of 6.0 m/s on main ducts and 2.5m/s on branch
ducts. The ductwork system design is to take into account the equipment’s characteristics in terms
of static pressure generation and acoustic properties.

Particular Specification 20 September 2010


The mechanical engineering services contractor shall include for all sets, joints, bends and
diversions necessary to install the ductwork in the ceiling void. No claims for additional costs in
this respect will be considered.

2.2.3. Electrical Works.

2.2.3.1. General.

The electrical requirements in respect of the mechanical services are to be provided by the
contractor by means of local isolators etc. adjacent to the mechanical items of plant. The
contractor shall allow for all extending all existing supplies interconnecting electrical supplies
from these isolators to the mechanical equipment. Although the contractor is not responsible for
the existing electrical supplies it shall be tested prior to connecting equipment to ensure that the
feeds are correct and that no damage occurs.

The contractor shall include for the installation (unless otherwise specified). including connecting
all items of mechanical equipment. The Contractor shall provide and install all wiring, cables,
conduit, trunking, cable trays, termination points, local means of isolation, control wiring etc., to
mechanical plant items to ensure that all items of equipment and controls fully function in
accordance with manufacturers’ recommendations and the current IEE Wiring Regulations,
CIBSE Codes of Practice, British Standards and UK Building Regulations.

All electrical cables used for power distribution will comply with 17th Edition IEE Regulations.
All cables used for data/control must be greater than 1.25 mm 2core screened. Appropriate glands
will be fitted to each item of equipment in accordance with environmental conditions.

The whole installation will be in full accordance with the IEE Wiring Regulations in every respect
with particular attention to clipping, earthing of equipment, glanding off, final connections and
isolating. Earth bonds on refrigeration, cold water and drainage pipework to be applied,
throughout. Equipotential bonding between exposed conductive parts and extraneous conductive
parts at the same potential, to be applied throughout.

On completion the installation should be tested in accordance with the requirements of inspection
and testing section of the IEE Wiring Regulations. Inspection shall include physical check that all
equipment has been securely fixed and that all electrical connections are mechanically sound.

Where necessary to prevent damage to components of equipment, the equipment shall be


disconnected for the duration of the relevant tests. Heat resisting cable should be used in all

Particular Specification 21 September 2010


locations where wiring is subjected to ambient temperatures in excess of 400C (1040F). A suitable
means of isolating the electricity supply shall be fitted adjacent to and within reach and sight of
the equipment with over current protections.

When running interconnecting control wiring it is essential to avoid the risk of electronic control
signals being corrupted. Care should therefore be taken to avoid running control cables too close
to power cables.

Particular Specification 22 September 2010


Section 3 Appendix 1. 3.1. Drawing Schedule.

Drawing No. Title: Rev. Scale:

QL392/M/001 Site Plan. T N.T.S


QL392/M/002 Restaurant Layout. T 1:100
QL392/M/003 Room 2100. T 1:100
QL392/M/004 Rooms 3014, 3015, 3021 & 3025. T 1:100

Particular Specification 23 September 2010


Section 3 Appendix 2.

3.2. Technical Equipment Schedules.

Particular Specification 24 September 2010


Section 3 Appendix 3. 3.3. Tender Breakdown.

QL 392 Replacement Air Conditioning.

Item. Description of works. Value £.


Mechanical Services.

1. Strip out and removal of existing air conditioning systems. £

Supply and installation of new Mitsubishi fan coils to Restaurant, shop, soft seating area and coffee
2. £
lounge as shown on drawing QL392/M/002 & as per description of works.

Room 1023, 1023A Strip out existing air conditioning units, supply and install 2
number new Dimplex 1.5kW electric panel heater with timer and integral
3. £
thermostat wired to local 13amp fused spur.

Room 1027, Strip out existing air conditioning unit knock down wall between
1027 & 1037 and supply and install 2 number new Mitsubishi Mr Slim PKA-
4. RP35HAL R410A wall mounted air conditioning units & as per description of £
works.

Room 2100, Strip out existing air conditioning cassettes and all associated
equipment, blank off openings in ceiling with MDF panels painted in RAL9010
5. £
eggshell white.

Room 3014 & 3031, Strip out existing air conditioning cassettes and install
6. ceiling mounted cassettes salvaged from the Shop. £

Room 3015, Strip out existing floor standing air conditioning units and install 12
7. number new Mitsubishi PSA-RP125 GA floor standing units. £

Room 3021, Remove two number wall mounted existing R22 units and install 2
8. number new Mitsubishi Mr Slim PKA-RP35HAL R410A wall mounted air £
conditioning units as shown on drawing QL392/M/004.

Room 3025, Remove existing wall mounted existing R22 units and install 1
number new Mitsubishi Mr Slim PKA-RP35HAL R410A wall mounted air
9. £
conditioning units as shown on drawing QL392/M/004.

10. Installation of air conditioning controls system. £

11. Connection to existing condensate drainage including pumps. £

12. Protection and cleaning of office environment throughout the works. £

13. Testing and Commissioning. £

Particular Specification 25 September 2010


14. Associated electrical works. £

15. Craning of plant on and off of roof level. £

16. O&M manuals & Record Drawings. £

17. Any item considered necessary but not mentioned above. £

18. Modifications to smoke detectors and recommissioning of fire alarm system by Protec. £ 5,000.00
£ 1,500.00

£ 21,600.00
19. Replace ceiling grid & Tiles in Restaurant area only.

£ 11000.00
Replace & up grade lighting in Restaurant area only
20.

£ 5000.00
LED Lighting to Apertures
21.

£ 6500.00
Provisional sums:• Build Upstands to Apertures
22.

£ 3000.00
23. Provisional sum for entrance door air curtain

£
24. Extra over for 7 no. Pyramid roof lights to current regulations standard

£
25 Alternative price for ‘drop in’ gas only to room 3015 system

£
26 Alternative price for system ‘de gas’ only to room 2100

£
27 Alternative price to strip out and make good system in room 3021

£
28 Alternative price to strip out and make good system in room 3025

£
29 Extra over for open able hinged pyramid roof light 7 no.

£
30 Alternative price for introducing air ventilation system in to shop area

£
31 Maintenance of the systems during the 12 month defects period.

32 Total: Fixed Sum £

Particular Specification 26 September 2010

You might also like