By Nidal Alsayyed
In order to control the cost and lead time of the incoming repair & service orders from customers, we need
to analyze, verify, validates, and develops an simulation (i.e. ARENA) model to reach an optimized solution
for the handling, and assignment of repair tasks to the Service Repair Technician (SRC) and Service Support
Engineers(SSE).
2
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Objective
With the introduction of Multi piece flow which is described as an ideal state of efficient operations, where
batch sizes and RMA requests are directed to the right manpower in more efficient manner. It is the aim of
the project to improve, quality of Repair, processing times and as a result more efficient changeover times.
RMA Process: A return merchandise authorization (RMA), return authorization (RA) or return goods
authorization (RGA) is a part of the process of returning a product to receive a refund, replacement, or repair
during or outside the product’s warranty period.
RMA RMA
YTD 2019
Tickets Repairs RMA 0 42 47 0 50
Inspection 0 0
Waiting Quote/PO 42 1252 0 20 40 60 80 100 120 140 160
Inspection Waiting Quote/PO Open RMA Arrival Waiting Parts In Repair Factory Repair
Open RMA Arrival 47 1
Waiting Parts 0 0
In Repair 50 1336 0
Factory Repair 1 0 RMA 0 1252 1 1336
Complete 933 28769
Cancelled 66 16 Inspection
0 Waiting500
Quote/PO Open
1000RMA Arrival1500
Waiting Parts2000In Repair Factory Repair 3000
2500
4
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
RMA flow chart.
RMA Receive
No Send quote Yes Quote Sent to Finance Send Invoice and Print Work Order &
Warranty to client to Invoice can be Payment Payment
Place in Que for
approve Generated Method to Client Received
Repair
Yes No
Return material back
to the customer
CoffeeRepair
Mug & QC
RMA 10 Days RMA Incoming 12 Days Print Work Order & 14 Days
Place in Que for Repair, QC & Package
Requestor Inspection
Repair
Helper 2 - - - - - √ - -
Helper 3 - - - - - - √ -
6
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
RMA Ticket Volume
Type Prior Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Bench mark 0 2800 2800 3000 3000 2800 2800 3000 3000 3000 3000 3000 3000 35200
New 0 3313 3127 3917 1741 3246 2807 2167 2445 1998 2750 2750 2750 33011
Open 5935 7280 6843 5726 4089 5148 5737 2550 2631 2826 2567 2317 2067 2826
Closed 0 1968 3564 5034 3378 2187 2218 5354 2364 1803 3000 3000 3000 36870
8000
12000
7000
Closed
10000
RMA Ticket Volume
2000 2000
1000
0
Feb
Apr
Aug
Sep
Dec
Oct
Nov
Jan
May
Jun
Mar
Jul
Prior
0
Prior Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
7
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Input data.
Repair Parts Top Module failures
Total Annual Repaired Top Module failures %
Sl.No. Part Percentage
Quantity Pixel Failure
1 Connector 2 0.0% Damaged pixel
2 Controller 26 0.1% Bad Pixel 60% of Module Failures
3 Data Cable 194 0.5% Dead pixel
4 Hub card 60 0.2% LED Broken/Bad LED
5 Mechanics 307 0.8%
6 Module 35812 97.1% This table shows the top module failures
7 Power box 205 0.6%
8 Power cable 4 0.0%
9 Processor 62 0.2% Total Annual Repaired Quantity
10 PSU 19 0.1% Connector
Controller
11 Receiving card 86 0.2% Data Cable
12 Sender Card 14 0.0% Hub card
8
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Repair Technician Time Log Analysis :Existing
• Considering average of 6.5 persons working at 8 hours a day for 26 day a month.
• Repair person engagement = (11075.5/ (6.5x8x26)) = 8 hours a days
• Repairs persons are 100% engaged in there work with out put of 3.3 pieces per hour 9
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Present Layout.
• In present condition two repairs rooms are available to carryout the repair activities.
10
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Proposed Layout: Introduction of parallel U-shaped assembly line system in repairs
• In present condition two repairs rooms are available to carryout the repair activities.
11
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Proposed Layout: Introduction of parallel U-shaped assembly line system in repairs
12
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Parallel U-shaped assembly line system
Flexibility is one of the most crucial criteria of modern manufacturing systems to satisfy customized demands in
a cost-effective manner. U-shaped lines (or U-lines shortly) do not only provide the flexibility and efficiency of a
proper line design but also increase functionality of workers on the line.
Two U-shaped lines are located in parallel to each other to establish an assembly environment where operators
are multi-skilled and located between two adjacent lines, being able to handle tasks on both of the lines.
Advantages.
Flexibility
Increase functionality of workers
Multi skilled workers are used effectively
Workers can handle multiple tasks
Compact
Increased communication
Facilitate teamwork
Minimize material handling 13
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Parallel U-shaped assembly line system in repairs
Multi line
station LINE I (Front)
W1,1 W1,2
LINE I{ (Front)
W2,2
W2,3,1
Crossover
station W3,2
LINE II (Back)
W4,1 W4,2
Multi line
station LINE I (Back)
14
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Arena simulation concept model
15
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
TAT of RMA process flow: Existing
RMA 10 Days RMA Incoming 12 Days Print Work Order & 14 Days
Requestor Inspection Place in Que for Repair, QC & Package Exiting TAT time
Repair =36 days
16
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Packaging improvement
The packages designed should withstand the following test conditions in
order to avoid the damages
• Handling drop
• Shipping drop
• Random (Transportation) Vibration
• Mechanical Vibration & Shock
1. Mechanical damage (strain, shearing)
Examples: Capacitor leads break over time, bolts break under load
• Considering average of 6.5 persons working at 8 hours a day for 26 day a month.
• With the same existing repair persons additional 7000 pieces can be repaired in same time line.
• Repairs persons are 100% engaged in there work with out put of 3.96 pieces per hour 18
ABSEN MULTI PIECE FLOW FOR SERVICING & REPAIRING
Cost of Employee in repairs 45000
40000
Average repairs Qty/Month Qty/Year 35000
30000 In ABSEN - USA
In ABSEN - USA 2933 35200 25000
20000 With proposed
With proposed simulation 3521 42257 15000
simulation
10000
•
32
CTC to company per month = 221500 / 12 = 18458 $ 31
Avg. Floor Time Days
30
29
• With the decrease in lead time by 16.7 % . The same numbers of 28
27
repairs will be out in 10 months. As per US ABSEN From simulation
results
PACKAGES
Months Damage % in packaging Pieces damages Existing Proposed
12 ( one Year) 2 737.4 Pieces 40.56 K USD 12.17 KUSD
With better packaging Damages can be reduced to 70%
20
Benefits 15
USD
10
Benefits
5
Sl. No. Parameters Benefits
Throughput time reduction 0
As per US ABSEN From simulation results
1 Improved from 14 to 11 days
in repair
Improved from 3.3 pieces per hour to
2 Repair quantity / hour
4 pieces per hour
3 Manpower productivity 16.7 % increase in productivity
A total of 268 KUSD saving which is
Savings on investment cost to
4 equal to repair additional 7000
repair more modules
modules with the existing resource
21