Professional Documents
Culture Documents
PRDH20-2-quiz 4 Merged
PRDH20-2-quiz 4 Merged
Aggregate Production
Planning (APP)
Disaggregation
Master Production
Schedule (MPS)
◼ Projected on hand
= Previous period Projected on hand + MPS –
Max(Forecast, Orders)
Product Code
Period 1 2 3 4 5 6 7 8
Forecast 30 30 30 30 40 40 40 40
Customer Orders
33 20 10 4 2
(committed)
Projected On-hand
64
Inventory
MPS
Available-to-promise
(uncommitted)
Product Code
Period 1 2 3 4 5 6 7 8
Forecast 30 30 30 30 40 40 40 40
Customer Orders
33 20 10 4 2
(committed)
Projected On-hand
64 31 1 41 11 41 1 31 61
Inventory
MPS 70 70 70 70
64 – 33
Available-to-promise 70 – 14 70 – 2
– 20 = 70 70
(uncommitted) = 56 = 68
11
◼ Time fence
◼ Demand time fence – Do not consider Forecast
◼ Depends on production plus delivery lead time
◼ Planning time fence – Do not change current MPS
◼ Depends on procurement plus production lead time
◼ Frozen
◼ Slushy or Moderately Firm
◼ Liquid or Flexible
A Dependent Demand
B(4) C(2)
◼ Planned orders
◼ Schedule indicating amount and timing of future orders
◼ Order releases
◼ Authorization for the execution of planned orders
◼ Changes
◼ Revisions of due dates or order quantities
◼ Cancellations of orders if any
◼ Regenerative system
◼ Updates MRP records periodically, usually every week
◼ At this time New MPS/Updated inventory status file
/Up-to-date BOM are fed into the system
◼ Generates complete set of output
◼ Net-change system
◼ Updates MRP/MPS records as changes in MRP/MPS
occur
◼ MRP system is then activated to generate
◼ Only net changes to past MRP run
◼ Entire output is not generated
Dipankar Bose - XLRI
Material Requirements Planning
(MRP) Processing
◼ Known
◼ Bill of Materials (BOM)
◼ MPS for Final Product
◼ For each component/subassembly
◼ Beginning inventory
◼ Safety stock required
◼ Lead time for order
◼ Lot sizing rule
◼ Prepare
◼ MRP
◼ A step is value-added if
◼ The Customer recognizes the value
◼ It changes the Fit, Form, or Function of the product
◼ It is done right at the first time
◼ Types of processes
◼ Value added/ Non-value added/ Necessary, but non-
value added
Dipankar Bose - XLRI
Push Vs. Pull Approach
◼ Push approach
◼ Forecast based
◼ “Move the job on when finished”
◼ Problem → Creates excessive inventory
◼ Pull approach
◼ Coordinated production
◼ Demand pulled through system
◼ Extensive use of visual order triggers
◼ Production/Withdrawal kanban
◼ Problem → Cannot manage high demand uncertainty
◼ Transportation
◼ Moving patients unnecessarily from one hospital unit to
another
◼ Inventories
◼ Inputs to the process that are waiting to be used (e.g.,
stock of aspirin)
◼ Motion/Movement
◼ Staff walking to various places around the work area to
obtain supplies
◼ Waiting
◼ A radiologist waiting for a patient to be brought into
the exam room
Dipankar Bose - XLRI
Muda in Service – A Hospital Example
– Continued
◼ Over-processing
◼ Continuing to care for patients in the hospital when
they could be discharged
◼ Over-production
◼ Performing unnecessary tests to prevent a lawsuit for
malpractice
◼ Defects
◼ Rebilling the insurance company because the first bill
contained an error
◼ Muri/Mura/Muda
◼ Jidoka – Automation with human touch (Autonomation)
◼ Poka-yoke
◼ Andon
◼ Kanban
◼ One piece flow
◼ Level production
◼ Heijunka
◼ SMED (Single Minute Exchange of Dies)
◼ Milk run logistics
◼ Kaizen
◼ TPM is a
◼ Lean tool
◼ To optimize the effectiveness of manufacturing
equipment and tooling
◼ Starts with 5S
◼ Builds a comprehensive Downtime Database by
◼ Cause/ Frequency/ Duration
◼ Predicts and prevents downtime by PM system
◼ Expands role of Operator
◼ First point of early warning and prevention
◼ Total Employee Involvement (TEI)
Dipankar Bose - XLRI
5S
◼ Seiri → Sort
◼ Seiton → Set in order
◼ Seiso → Shine
◼ Seiketsu → Standardize
◼ Shitsuke → Self-discipline
◼ Initial Control
◼ 5S
◼ Pillars
◼ Autonomous Maintenance – Jishu Hozen
◼ Planned Maintenance
◼ Quality Maintenance – Hinshitsu Hozen
◼ Focused Improvement – Kobetsu Kaizen
◼ Early Equipment Management
◼ Education & Training
◼ Safety, Hygiene & Environment
◼ Office TPM
Dipankar Bose - XLRI
Production Management – PRDH20-2
Session 15 → TPM (Continued) + Overall
Equipment Effectiveness (OEE)
TPM – Five Phases for Actions against
Breakdown
Wrong Output
SOP is correct Dipankar Bose - XLRI
How People Connect
◼ Balking/Reneging/Jockeying
◼ Population source
◼ Finite/ Infinite
◼ Line or QUEUE/ SYSTEM
◼ Number of servers
◼ Single/Multiple
◼ Parallel/Series
◼ Arrival & Service pattern assumptions
◼ Rate → Poisson; Inter-arrival time → Exponential
◼ When waiting occurs?
◼ Problem if assumptions are not valid
◼ Service policy
◼ FCFS/Priority rules (Not covered)
Dipankar Bose - XLRI
Models for Waiting Line
◼ Infinite population
◼ Single Channel
◼ Service Rate – Poisson → M/M/1
◼ Service Rate – Constant → M/D/1
◼ Multiple Channel
◼ Service Rate – Poisson → M/M/S
◼ Finite population
◼ More Notations
◼ Number of servers = S (in Textbook M)
◼ Average Service rate considering all servers = S
◼ Average Server utilization = = /(S)
◼ How to increase average server utilization?
◼ Average number of customers being served (at any
time, considering all servers) = r = /
◼ Relation between QUEUE and SYSTEM
◼ Average number waiting in SYSTEM = Average number
waiting in QUEUE + Average number being served
◼ Average time waiting in system = Average time waiting
in QUEUE + Average time for service
Dipankar Bose - XLRI
M/M/1 System
𝜆2
◼ Average number of customers in QUEUE = 𝐿𝑞 =
𝟐𝜇(𝜇−𝜆)
◼ =
𝑆
(1 – desired fraction)
◼ K=
Lq (1 – )
LN(K)
◼ LMAX =
LN()
◼ Notations
◼ Average Working time = U (Exponential)
◼ Average Servicing time = T (Exponential)
◼ Service Factor = X = T/(T + U)
◼ Total number of customers (Population) = N
◼ Number of Servers = S
◼ Infinite population
◼ Total cost = Ls × Cost of waiting per customer + S ×
Cost of each server
◼ Finite population
◼ Total cost = N − J × Cost of waiting per customer +
S × Cost of each server
◼ T/X = T + U
◼ Total Cycle Time= T + U + T(1 – F)/XF = [1/F]T/X = T/XF
◼ Pure strategies
◼ Changing inventory level
◼ Introducing overtime
◼ Changing workforce level (Hiring and Laying off)
◼ Subcontracting
◼ Influencing demand
◼ Mixed strategies
◼ Resources
◼ Workforce/Facilities
◼ Demand forecast
◼ Policies
◼ Overtime/ Inventory levels/ Back orders/
Subcontracting
◼ Costs
◼ Inventory carrying/Back orders/Inventory changes
◼ Hiring/firing/Overtime
◼ Subcontracting
◼ Subcontracting cost
◼ Use the data given in Excel file and use the data to get
values in
◼ Exhibit 1
◼ Why production at each month = 8400?
◼ Exhibit 2
◼ Why employee in each month = 199?
◼ Exhibit 3