This document outlines the reporting requirements for structural concrete work. It includes a table listing 9 reports that are required, including the title of each report, when they must be submitted, and how frequently. The reports include items like sources of materials, mix designs, testing laboratories, batching plant equipment, hot weather procedures, certificates for cement and admixtures, and results of plant trial mixes. Most reports are required 31 days before concrete delivery and one time, but some require resubmitting if changes occur.
This document outlines the reporting requirements for structural concrete work. It includes a table listing 9 reports that are required, including the title of each report, when they must be submitted, and how frequently. The reports include items like sources of materials, mix designs, testing laboratories, batching plant equipment, hot weather procedures, certificates for cement and admixtures, and results of plant trial mixes. Most reports are required 31 days before concrete delivery and one time, but some require resubmitting if changes occur.
This document outlines the reporting requirements for structural concrete work. It includes a table listing 9 reports that are required, including the title of each report, when they must be submitted, and how frequently. The reports include items like sources of materials, mix designs, testing laboratories, batching plant equipment, hot weather procedures, certificates for cement and admixtures, and results of plant trial mixes. Most reports are required 31 days before concrete delivery and one time, but some require resubmitting if changes occur.
1. Sources of material a) 31 days prior to delivery a) One time of concrete b) Un-apparent change b) as required 2. Supplier Quality Inspection a) 31 days prior to delivery a) One time Plan of concrete 3. Mix design for all classes of a) 31 days prior to delivery a) One time concrete of concrete b) When mix is re-designed b) As required for any purpose
4. Name, location, equipment a) 31 days prior to delivery of a) One time
& personnel of test concrete laboratory to be used by b) If changed b) As required supplier (including own laboratory) 5. Programs, methods and a) 31 days prior to delivery of a) One time details of batching plant concrete equipment
6. Proposed methods of a) 31 days prior to delivery of a) One time
complying with hot weather concrete mixing and delivery
7. Certificates for cement and a) 31 days prior to delivery of a) One time
mineral admixtures from concrete manufacturers and/or b) For each new delivery b) As required suppliers from manufacturer
8. Certificate for admixture a) 31 days prior to delivery of a) One time
from manufacturer concrete b) If any change occurs b) As required 9. Report of plant trial mixes a) 31 days prior to delivery of a) One time with 7-day and 28-day test concrete results for all classes of b) If any change b) As required concrete required for the work