Professional Documents
Culture Documents
Gas-Lift-System-N
Gas-Lift-System-N
(MKPP2513)
GAS LIFT SYSTEM – LEARNING OUTCOMES
OBJECTIVE
To increase drawdown on producing formation by injecting gas into lower part of
tubing string & reducing flowing gradient in production string
• SURFACE EQUIPMENT
– Compressor : To compress gas into the tubing/casing @ certain injection pressure
– Choke : To regulate gas injection velocity
– Timer : To regulate time for gas injection
– Pipeline : To flow gas from source/compressor – injection point
– Pressure recorder : To record P vs time (for operational monitoring)
• SUBSURFACE EQUIPMENT
– Gas lift valve
• To get high injection pressure
• Able to regulate gas injection (as orifice)
• To get deep injection point for high lifted fluid
• Able to change injection point
– Standing valve
– Packer
GAS LIFT OPERATION
Pressure Traverse of Gas-Lifted Well
– Compressor
• To compress gas into the tubing/casing @ certain injection pressure
– Choke
• To regulate gas injection velocity
– Timer
• To regulate time for gas injection
– Pipeline
• To flow gas from sources/compressor – injection point
– Pressure recorder
• To record pressure vs time (for operational monitoring)
– Gas lift valve
• To get high injection pressure
• Able to regulate gas injection (as orifice)
• To get deep injection point for high lifted fluid
• Able to change injection point
Gas Rate Effect on Production
Rate
•At maximum:
• average fluid density reduction @ tubing due to slight increase in gas injection rate
being counterbalanced by frictional pressure losses increased due to greater mass of
fluid flowing @ tubing
• Gas flow rate further increases friction term increasing relatively faster than
hydrostatic head reduction term technical optimum gas injection rate
•Maximum economic gas injection rate : gas injection rate @ marginal cost of providing extra
injection gas equal to marginal revenue from extra well production
•Gas lift also can be used for:
• Increase production from natural well flow at lower rate
• Dead well need artificial lift to kickoff before production possible
Effect of gas rate on well production rate
Typical Gas Lift System
Gas from production wells separated, compressed & dehydration unit gas lift manifold
adjusted injection gas flow rate & casing head pressure injected @ individual well.
Gas Lift Well Metering & Control
Gas Lift Application
•Work better in significant GLR
•Two types:
• Continuous flow gas lift
• Intermittent flow gas lift
• Continuous small volume of high pressure gas injected into the tubing/casing in order to
aerate /lighten fluid column until reduction of bottom hole pressure allowed sufficient
differential pressure across a sand face, causing well to produce at desired rate
• Can produced :
– 25 BPD with 1 inch macaroni tubing
– 300 – 4000 BPD with normal tubing string size
– 25,000 BPD with casing flow
• Recommended for:
– High volume & high static BHP
– Offshore application (especially strong water drive)
– Waterflood reservoir with good PI & high GOR
– High PI & high BHP
– Well with sand problem, excessive water from BHP surge or sand bridging @ tubing problem
– Water backpressure well
– Small tubing application
– High viscosity crude if Pwf adequate
CONTINUOUS FLOW GAS LIFT FLOW METHOD
Two methods:
1. Tubing flow
– Gas injected through annulus (casing) & production through tubing
– Characteristics:
– High efficiency
– Low gas volume
– High input/injection pressure
2. Casing flow
• Gas injected through tubing & production through casing
• Characteristics:
– Low efficiency
– High gas volume
– Low input pressure
– High q from deep zone application
– Serious corrosion
CONTINUOUS FLOW GAS LIFT ADVANTAGES
• ADVANTAGES
– Significantly lower producing BHP than continuous flow gas lift
– Ability to handle low volumes fluid with relatively low production BHP
– Wireline or hydraulic operated valve
• DISADVANTAGES
– Limited to low volume well
– Average producing pressure required still relatively high compare with
rod pumping
– Low power efficiency (more gas/bbl than continuous flow gas lift)
– Fluctuation in rate & BHP can be detrimental to well with sand control –
sand may plug tubing or standing valve, gas & fluid handling problems at
surface facilities
– Typically requires frequent adjustments: alter injection rate & time period
routinely to increase production & keep lift gas requirement relatively
low.
– Generate pressure surge @ surface equipment
Intermittent Gas Lift
GAS LIFT VALVE REQUIREMENTS
• Bellow valve
• Pilot valve
• Continuous flow bellow valve
• Fluid operated valve
• Fluid operated valve with special pilot
• Balanced flexible sleeve valve
• etc
GAS LIFT INSTALLATION
• Open installation
• Semi-closed installation
• Closed installation
• Chamber installation
• Macaroni installation
• Dual installation
• Dual flow choke installation
• Multiple completion installation
• Casing flow installation
• etc
CHAMBER INSTALLATION
•How many unloading valves required & at what depths, these valves be placed ?
Translated into practice by ensuring gas lift valve spacing & pressure setting are such that:
•Operating valve have adequate flow capacity & placed as deep as possible
•Available lift gas pressure able to displace fluid in casing to operating valve depth
•All valves can be opened by appropriate producing pressure gradient, while other valves above it closed
Gas Lift Design Required Data
GAS LIFT DESIGN CONSIDERATION
• Working fluid level = level by which oil column will rise due to working
pressure at tubing bottom if there is an annulus
• Total lift = working submerge + working lift
• Working submerge = vertical distance (ft) between working fluid level and
tubing bottom or equivalent with fluid column height which
produce working pressure at tubing bottom
GAS LIFT VALVE POSITION
Determine by:
• Available gas pressure
• Fluid weight
• Well IPR @ lifting
• Surface backpressure @ wellhead
• Annulus fluid level
• BHP
• Well production characteristics
Annulus Gas Lift Pressure
•Check : gas lift valves can be placed at suitable distances above operating valve to ensure
well can be unloaded using gas lift designed
•Specify optimum :
• Tubing size
• Injection gas supply parameters (P & V)
• Installation depth of operating valve (injection point)
• Minimum wellhead flowing pressure
•First study well performance (IPR, VLP, CP) to confirm for artificial lift
– Capital Cost
• Equipment cost low but compression cost may be high
• Central compression system reduces overall cost per well
– Downhole equipment
• Good valve design & spacing essential.
• Moderate cost for well equipment (valves & mandrels)
• Typically less than 10 valves needed
• Choice : wireline retrievable or conventional valves
– Operating efficiency (hydraulic hp/input hp)
• Fair. Increases for well that require small injection GLR. Low for well
requiring high GLR.
• Typically 20%, but range from 5-30%
– System flexibility
• Excellent. Gas injection rate varied to change rate
• Need correct tubing size
– Miscellaneous problems
• Highly reliable compressor (95% run time required)
• Gas must properly dehydrated to avoid gas freezing
Continuous Flow Gas Lift
Design Considerations
– Operating costs
• Well cost low
• Compression cost varies depending on fuel cost & maintenance
– System Reliability
• Excellent if compression system properly designed & maintained
– Salvage Value
• Fair. Some market value for compressor & mandrel/valve
– System Total
• Requires adequate volume, high pressure, dry, noncorrosive, and clean gas
supply
• Low backpressure beneficial
• Good data needed for valve design & spacing
• API specs & design/operating RPs must be followed
– Usage/Outlook
• Good, flexible, high rate system for well with high bottomhole pressure
• Used on 10% US lifted wells, mostly offshore
Continuous Flow Gas Lift
NORMAL OPERATING CONSIDERATIONS
• Where;
– Pt = tubing pressure
– Gfa = average flowing pressure gradient above injection point
– L = injection point depth
– Gfb = average flowing pressure gradient below injection point
– D = well depth
– Pwf = well bottomhole flowing pressure
• General steps:
1. Flow type selection @ tubing size & desired q
2. Gas injection depth determination
3. Valve spacing
– Valve selection
– Gas volume required
– Injection pressure required
– Compressor requirements
CONTINUOUS FLOW GAS LIFT DESIGN
RULE OF THUMB
Must considered:
• Continuous gas lift valve requirements
• Separator pressure
• Wellhead flowing pressure
• Top valve position
• Gas injection pressure
• Gas injection volume
• BHT
• Flowing temperature gradient
• Unloading gradient
• Valve spacing
• Tubing size
• Q
• Valve setting
• Installation type
• Well performance especially VLP
CONTINUOUS FLOW GAS LIFT DESIGN
RULE OF THUMB
• Valve setting
– Valve operate based on its characterics
– Ex. Balanced valve drawdown 15 – 25 psi/valve (operational pressure
difference @ surface)
• Tubing size & q
Tubing size (in.) Maximum q (BPD) Minimum q (BPD
1 350 25 – 50
1¼ 600 50 – 75
1 1/2 1000 75 – 125
2 2500 200
2 1/2 3000 250
3 4000 300
3 1/2 5000 -
4 8000 -
Continuous Gas Lift Design
Continuous Flow Gas Lift
CONTINUOUS FLOW GAS LIFT DESIGN –
INJECTION POINT DETERMINATION
6. From Pwf, draw flowing pressure distribution/gradient below injection point (Gfb)
based on:
• calculated pressure distribution
• suitable flowing pressure distribution chart, or
• Assumption of flowing pressure gradient below injection point = static pressure gradient
parallel to Ps @ Gs line
7. Marked surface initial pressure or surface kick-off pressure minus 50 (Pko – 50)
8. Marked surface operating pressure (Pso)
(Pso) = Available pressure - 100
CONTINUOUS FLOW GAS LIFT DESIGN
INJECTION POINT DETERMINATION
• Kick off pressure (Pko) = pressure (measure at gas inlet line @ surface)
required to initiate flow in the gas lift well
Depends on:
1. Valve type
– Balanced valve
• Surface operating pressure – minus ( 15 to 25 psi) / valve downward
– Unbalanced valve
• At surface operating pressure, or
• Reduction of 15 psi/valve downward, or
• Kick off pressure minus 100 psi from conventional operating pressure
•Top valve design: allow fluid in casing/tubing to be unloaded --> deep gas injection can
be achieved
•Upper gas lift ports sized to pass only limited gas volume required for unloading
•Larger port for operating valve
gas injection can be increased to optimum value
• Through which gas will be continually passed
•Dummy valves installed in bracketing envelope where live valves not yet required
•Two types:
• Casing/Injection/Inflow Pressure Operated (IPO) valves
• Tubing Pressure Operated (TPO) valves
•Key factors controlling gas lift pressure required to open:
• Dome pressure
• Tubing pressure
• Bellows & port area ratio
•Valve spread
• = difference between opening & closing pressure
• = Popening – Pclosing
Gas Lift Valve Mechanics
• Opening & Closing forces are equal just before valve open.
or
1 - - - - -
6. From table (step 5), and catalog @ valve manufacture, based on required
valve capability, selection valve to used
Well Unloading
Unloading Process (Initial) Dead Well
•Fluid level in casing & tubing just below surface & balances Pres. no flow dead well
•No gas injected
•All gas lift valves open due to fluid hydrostatic head
•Unloading process lowered fluid level in casing annulus to top gas lift valve
•Gas injection into tubing commenced evacuates liquid in tubing above top gas lift valve into
separator @ multiphase flow conditions
•Reduces fluid density above top valve further casing fluid unloaded through valve no. 2,3 & 4
since P @ tubing < Pcasing
•Well start to produce if pressure reduction sufficient to give drawdown @ perforation for q
Gas Lifted Well Unloading; Stage 3
•Top valve closed due to reduced pressure (casing pressure for casing pressure operated valves or
tubing pressure for fluid operated & proportional response valves) after gas lift established through
valve 2
•All gas injected through valve 2
•Unloading well continues with valve 2,3 & 4 open & casing liquid flowing into tubing via valve 3 &
4
Gas Lifted Well Unloading; Stage 5
•Reduction in casing or tubing pressure valve 3 starts to flow gas & valve 2 closing
•All gas injected through valve 3
•Process continued
Producing Gas Lifted Well Pressure Traverse
•Process continued with pressure reduction valve 4 exposed & closing of valve 3
•All gas injected through valve 4
Typical Casing & Tubing Pressure Measurement @ Gas Lifted
Well Unloading
•Development of tubing head & casing head pressure with time @ unloading process stage 1-7
•Sequential reduction in casing head pressure as gas successively injected through lower gas lift
valves
Safety Factors
• Can be used when BHP & PI unknown & gas column weight neglected
• First valve depth:
– Dv1 = {(Pko – 50) – Pwh} / Gs
– If well unloaded to atms. Pwh = 0
– If static fluid level < Dv1 top valve depth = static fluid level (conventional spacing)
– For balanced valve reduce 25 psi/valve downward
– For unbalanced valve:
• Spacing @ surface operating pressure constant, or
• Reduction of 10 psi/valve downward
• Availability:
– Stage : 1, 2 or 3
– Drive : direct-drive or belt-driven
– Fuel consumption: 10 scf/hr/bhp
• Selection calculation:
– Size determination
– Stage
COMPRESSOR SIZING – ONE STAGE
7. Cylinder Selection
– From manufacture shell & cylinder data for selected shell in step 5 select
cylinder with displacement > required displacement @ step 6
• Compare allowable maximum pressure and maximum pressure difference
@ selected cylinder with operating pressure (step 1) and operating
pressure difference
– Operating pressure difference = discharge pressure – suction pressure
• Both pressures must be < allowable maximum pressure
9. Cylinder Selection
– Based on selected shell size (step 7), refer to cylinder & shell data select
cylinder @ stage with displacement > calculated displacement (step 8)
– Compare maximum allowable pressure & maximum pressure difference @
selected cylinder with operating pressure & operating pressure difference (step
1)
– Stage one operating pressure difference = inter-stage pressure (step 4) – suction
pressure
– Stage two operating pressure difference = discharge pressure – inter-stage
pressure
10. Accurate Volumetric Efficiency @ Cylinder Determination
– Veff. = m – (ICC)(ICR1/N – 1)
– Where; m = cylinder V eff. Constant (manufacturer)
ICC = cylinder constant (%) - manufacturer
COMPRESSOR SIZING – TWO STAGES
•Gas quality
•Solids
•Reservoir performance change
•Gas supply
•Well startup (unloading)
•Well stability
•Dual gas lift
Gas Quality
•To prevent fluid damage to lower gas lift valves as liquid in annulus unloaded when starting
up by avoiding excessive fluid flow rates
•API start-up procedures:
• Provision to monitor tubing & casing pressure and production rate @ unloading
process
• Tubing head pressure must be blown down to separator flowline prior to starting
unloading process. Chock should be fully opened @ kick-off process
• Unloading process commenced under casing head pressure control. Casing gas
injection rate adjusted pressure increases at rate of 10 psi/min until system
pressure reached. Need to monitor liquid level in annulus (by echometer)
• Maximum lift gas injection rate < 50% planned design rate
• Drop in casing head pressure when gas injected into upper valve & subsequent
lower valve gas injection rate change
• Need to established steady state flow regime
•Good practice to check that well unloading process can still proceed with valve pressure
settings based on cooler temperature profile than that predicted for equilibrium producing
conditions reduced T profile is safer
Well Stability
•To prevent interfering each other install valves with significantly different operating
characteristics in different string (eg. IPO & TPO). Gas allocation controlled by installed
choke in operating valves
Inefficient Gas Lift Operation