Professional Documents
Culture Documents
Maintenance Manual For Auxiliaries - PLN-SAKO P-06071 EN PDF
Maintenance Manual For Auxiliaries - PLN-SAKO P-06071 EN PDF
Maintenance Manual For Auxiliaries - PLN-SAKO P-06071 EN PDF
Confidential
Table of Contents
Table of Contents
Genset ...............................................................................................................................2 - 1
Generating set .............................................................................................................................................2 - 2
Generator
Generator maintenance program, ......................................................................................................2 - 3
Level 1 maintenance of ABB Generator, 4000 Hours .........................................................................2 - 5
Level 2 maintenance of ABB Generator, 8000 Hours .........................................................................2 - 9
Level 3 maintenance of ABB Generator, 24000 Hours .....................................................................2 - 11
Level 4 maintenance of ABB Generator, 80000 Hours .....................................................................2 - 13
Table of Contents - i
Table of Contents
Table of Contents - ii
Introduction to the maintenance manual
This section provides information about how to read and apply the information provided
in the plant maintenance manual.
The purpose of the maintenance manual is to provide guidelines for inspection
and maintenance of the auxiliary systems that are within the Wärtsilä scope of
supply.
Note! Maintenance instructions for the Main engine are found in the Engine
Manual.
Note! Even when following the maintenance instructions, normal supervision and
observation of the equipment is required.
Maintenance intervals
As the maintenance intervals often depend on the operating conditions, the stated
intervals are to be considered as guidelines. Take note of these guidelines when
creating your overall maintenance plan for the plant.
The maintenance intervals are given either as running hours for the device or as
calendar-based intervals (weeks, months or years).
The hour-based intervals are to be followed up by an hour counter on the specific
device or running hours of the engine. If none of these are applicable, the best
estimation must be applied.
The calendar-based intervals are counted as total elapsed time. If not otherwise
stated, this interval applies regardless of the running hours of the device.
It is left to the discretion of the maintenance planner to apply the stated interval
correctly.
Maintenance related spare parts and required special tools
Some of the maintenance work described in this manual will require that certain
parts are changed or renewed in connection with the work. These parts, also
called related spare parts, will be listed by their descriptive name on each work
card.
The actual code for that part must then be looked up in the spare part list provided
either by Wärtsilä or the equipment supplier.
When ordering spare parts, always include all the data needed to identify the
component and part installed. The following identification data should be included:
● Brand and model
● Serial number
● Type of application
● Name and description of the spare part
● Spare part code, if available
1-1
Introduction to the maintenance manual
Content
Maintenance routines ..................................................................................................................................1 - 3
Safety aspects for maintenance work .........................................................................................................1 - 4
Locking and tagging out for maintenance or inspection ..............................................................................1 - 6
1-2
Introduction to the maintenance manual
Maintenance routines V1
This section gives information about how to establish sound maintenance routines for the
auxiliary systems.
The auxiliary systems are vital to the function of the plant. Therefore, all
maintenance activities must be carefully done at the correct intervals. All
measures taken and why they are taken must be well recorded.
The maintenance activities are divided into three categories:
● Condition monitoring– by taking the readings of all meters and gauges. If the
readings show a falling or rising trend, the reason has to be found and action
taken.
● Preventive maintenance – Daily inspection and checks of all equipment
visually or by listening to the components with the purpose to detect
abnormalities.
● Preventive maintenance – Scheduled inspections, cleaning and replacement
of components or fluids. Maintenance intervals are found in the maintenance
chart for each of the main components together with instructions.
It is to be expected that the operators possess a good general knowledge of this
type of plant and that they are familiar with both common and local safety
regulations that must be strictly followed.
1-3
Introduction to the maintenance manual
This section describes the general safety aspects to consider when performing
maintenance work on the plant.
General
Only persons with adequate training are allowed to perform maintenance on the
equipment.
● Before starting to operate or perform any maintenance on the components,
read the manuals provided by the component manufacturers.
● Read and obey the safety instructions provided by the equipment
manufacturers and the manufacturers of the liquids handled in the plant.
● Read and obey the safety instructions in the Power Plant manuals.
● Observe the warning signs on the equipment. The signs must not be removed.
Pay attention to the risk of ignition
The equipment may contain combustible liquids.
● Do not light matches or open flames in the vicinity.
● Prevent electrical sparks from occurring.
● Check that the area is free of combustible gases and liquids before using any
power tool.
Prevent unintended starting during maintenance work
Before starting any maintenance work, make sure that the equipment cannot be
accidentally started.
● Set the safety switch to the OFF position and lock the switch.
● Disconnect the electrical power and tag out the device.
● If needed, isolate the unit by closing and securing inlet and outlet valves and
releasing the pressure.
Prevent electrical shocks
Only trained electricians may perform work on electrical equipment.
● Do not open the electrical cabinet during operation.
● Do not touch electrical wiring and components until the main switch has been
switched off and secured.
● If the equipment contains capacitors, be aware that the capacitors can retain
a charge even after being disconnected from the mains.
Avoid burns and splashes
Before dismantling or opening any process equipment, consider what the system
may contain and take the necessary precautions to avoid burns, exposure to
hazardous substances, spills or splashing.
During operation, the pipes will contain hot liquids, and the surface may be hot.
Allow all elements cool down before performing any maintenance work on them.
Remove all pressure from the system before opening any part of it.
Be aware of the power of pressurized air
The compressed air system contains air under very high pressure.
● Do not open any component, unit or part of the system before ensuring that it
is not pressurized.
● Look out for jets of pressurized air.
● If a part of the system is isolated for maintenance work, the valves must be
locked and properly tagged out in order to prevent accidental opening.
1-4
Introduction to the maintenance manual
1-5
Introduction to the maintenance manual
This is a general procedure for locking out and tagging out equipment to prevent
accidental starting during maintenance work.
Before starting any maintenance work, it is extremely important to make sure that
the equipment can not be accidentally started while it is being serviced.
1 Notify all persons that will be affected that the lockout is about to begin.
2 Verify that the equipment to be serviced is turned off.
3 Locate all energy sources (electrical, pneumatic, steam etc.) that supply the
equipment and turn them off.
4 Secure all energy sources with an appropriate locking device.
5 Place an appropriate warning tag on the energy sources.
Note! If several persons are involved in the maintenance, all persons must attach
their own locking device and tag.
6 Release any stored energy (circuit breakers, pneumatic valves, springs etc.).
7 Operate the controls (switches, valves etc.) to make sure that the equipment will
not operate.
8 Perform the required maintenance work on the equipment.
9 When the maintenance work is finished, the equipment may be taken into service
again:
a ) Check that all tools and loose parts have been removed.
b ) Replace all safety guards.
c ) Ensure that all workers are clear of the equipment.
d ) Remove all tags and locking devices.
Note! Only the person that applied the tag or locking device may remove it.
1-6
Genset
Genset
Content
Generating set .............................................................................................................................................2 - 2
Generator
2-1
Genset
Generating set
Content
Generator
Generator maintenance program, ......................................................................................................2 - 3
This chapter presents a recommended maintenance program for ABB machines.
Level 1 maintenance of ABB Generator, 4000 Hours .........................................................................2 - 5
Level 2 maintenance of ABB Generator, 8000 Hours .........................................................................2 - 9
Level 3 maintenance of ABB Generator, 24000 Hours .....................................................................2 - 11
Level 4 maintenance of ABB Generator, 80000 Hours .....................................................................2 - 13
Generator
2-2
Genset
2-3
Genset
2-4
Genset
General Information
JobID: 014 Type: AMG
Unit: Generating set Manufacturer: ABB
Component: Generator BAG011
Work Information
Type of job: inspection Work time: 8 Hours
Stop time: 8 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
4000 Hours electrician 1 8 component
Required spareparts
Spcode Qty Description
#### 1 Safety package
2-5
Genset
2-6
Genset
2-7
Genset
2-8
Genset
General Information
JobID: 015 Type: AMG
Unit: Generating set Manufacturer: ABB
Component: Generator BAG011
Work Information
Type of job: inspection Work time: 16 Hours
Stop time: 16 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
8000 Hours electrician 1 16 component
Note! Level 1 tasks not included, but must be performed at the same time.
Required spareparts
Spcode Qty Description
#### 1 Maintenance package
Required tools
Code Description
Insulation resistance tester
2-9
Genset
2 - 10
Genset
General Information
JobID: 016 Type: AMG
Unit: Generating set Manufacturer: ABB
Component: Generator BAG011
Work Information
Type of job: inspection Work time: 40 Hours
Stop time: 40 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
24000 Hours electrician 1 40 component
Note! Level 1 and 2 tasks not included, but should performed at the same time.
Required spareparts
Spcode Qty Description
#### 1 Maintenance package
Required tools
Code Description
Oscilloscope
Endoscope
2 - 11
Genset
2 - 12
Genset
General Information
JobID: 017 Type: AMG
Unit: Generating set Manufacturer: ABB
Component: Generator BAG011
Work Information
Type of job: inspection Work time: 80 Hours
Stop time: 80 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
80000 Hours electrician 2 80 component
Note! Level 1, 2 and 3 tasks not included, but should performed at the same time.
Required spareparts
Spcode Qty Description
#### 1 Maintenance package
##### 1 Capital spare part package
Required tools
Code Description
Rotor removal equipment
2 - 13
Genset
2 - 14
Fuel gas system
Content
Regulating system .......................................................................................................................................3 - 2
Gas regulating unit
3-1
Fuel gas system
Regulating system
Content
Gas regulating unit
Maintaining gas pressure regulator, 3 Months ....................................................................................3 - 3
The gas pressure regulator is inspected by someone trained in gas pressure regulating facilities
maintenance.
Lubricating the turbine meter, 3 Months .............................................................................................3 - 5
The turbine meter is used for measuring gas flow and requires lubrication.
Maintaining the gas filter, 6 Months ....................................................................................................3 - 7
The gas cellular filter is cleaned and inspected.
unit
regulating
Gas
3-2
Fuel gas system
General Information
JobID: wca0357 Type: 402
Unit: Regulating system Manufacturer: RMG
Component: Gas regulating unit ZAA011
Work Information
Type of job: inspection Work time: 2 Hours
Stop time: 2 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
3 Months O&M Supervisor 2 component
Mechanical, Off-engine 2 component
The gas pressure regulator is inspected by someone trained in gas pressure regulating
facilities maintenance.
Refer to the OEM manual for specific spare parts. All parts marked "EV" are to
be kept in stock for maintenance.
Warning! Before starting any work on the gas regulating equipment, make sure it is
properly isolated, vented and secured from accidental starting.
Required spareparts
Spcode Qty Description
As required O-rings
As required Sealing rings
As required Closing spring
As required Diaphragm
As required Piston, premounted
3-3
Fuel gas system
3-4
Fuel gas system
General Information
JobID: wca0356 Type: TRZ
Unit: Regulating system Manufacturer: RMG
Component: Gas regulating unit ZAA011
Work Information
Type of job: lubrication Work time: 1 Hours
Stop time: 0 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
3 Months Mechanical, Off-engine 1 1 component
The turbine meter is used for measuring gas flow and requires lubrication.
The turbine meter has a lubricator (either an oil nipple, or a pump). The lubrication
interval is 3 months for clean gas and more frequently if dust or condensate-laden
gas is used.
1 Lubricate the meter in accordance to the lubrication instruction plate located on
the turbine meter.
3-5
Fuel gas system
3-6
Fuel gas system
General Information
JobID: wca0358 Type: 906, 907, 906a
Unit: Regulating system Manufacturer: RMG
Component: Gas regulating unit ZAA011
Work Information
Type of job: inspection Work time: 2 Hours
Stop time: 2 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
6 Months Mechanical, Off-engine 2 component
Warning! Before starting any work on the gas regulating equipment, make sure it is
properly isolated, vented and secured from accidental starting.
Required spareparts
Spcode Qty Description
As required Paper filters 1, 2, and 3
As required Filter insert 1, 2, and 3
As required Sealing rings
As required Plastic ring (glued onto filter basket)
As required O-rings
Silicone grease for O-rings
3-7
Fuel gas system
3-8
Lubrication oil system
Content
Lube oil transfer pump unit (Mobile) ............................................................................................................4 - 2
Screw pump
4-1
Lubrication oil system
Content
Screw pump
Inspecting and lubricating the pump, 6 Months ..................................................................................4 - 3
In-service inspection of pump - greasing of bearings and cleaning of strainer.
Overhauling the screw pump, 3 Years ................................................................................................4 - 7
A three year overhaul of the pump, including changing rotor bearings and mechanical seals.
pump
Screw
4-2
Lubrication oil system
General Information
JobID: wca0316 Type: ACE
Unit: Lube oil transfer pump unit QAA901 Manufacturer: IMO
(Mobile)
Component: Screw pump D001
Work Information
Type of job: inspection Work time: 2 Hours
Stop time: 1 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
6 Months Mechanical, Off-engine 1 2 component
Note! When ordering spare parts, please state the complete pump identification
according to its name plate and required spare part set.
Required spareparts
Spcode Qty Description
As required Joint kit, for dismantling of the pump, G057
As required Shaft seal, G050
Lubricate the pump and motor ball bearings and check that the pump operates
correctly without excessive leakage, vibrations, or noise.
1 Grease the pump rotor ball bearings, if the pump is provided with external
bearings and grease nipple. The pump should be running during greasing.
Caution! Do not overfill with grease. Overfilling will damage the mechanical seal.
2 Grease the motor bearings, if the motor is provided with grease nipples. The pump
should be running during greasing.
Note! Some motors may have a separate rating plate with information about the
bearings and lubricating intervals. If so, those instructions must be
followed.
4-3
Lubrication oil system
Warning! Do not start maintenance work unless power is switched off and physically
disconnected, the inlet and outlet valves and are shut and accidental
opening is prevented, and the device vented to atmospheric pressure.
Warning! Risk for splashing or spill! Wear protective clothing (including safety
glasses). Do not assume that the system is depressurized even when a
pressure gauge indicates zero.
d) Open and clean the strainer. Place a bucket under the strainer to collect
spills.
Warning! Contents may be hot! Allow time for temperature to normalize before
starting the work.
4-4
Lubrication oil system
4-5
Lubrication oil system
4-6
Lubrication oil system
General Information
JobID: wca0312 Type: ACE
Unit: Lube oil transfer pump unit QAA901 Manufacturer: IMO
(Mobile)
Component: Screw pump D001
Work Information
Type of job: overhaul Work time: 3 Hours
Stop time: 3 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
3 Years Mechanical, On-engine 1 component
A three year overhaul of the pump, including changing rotor bearings and mechanical
seals.
Warning! Before any maintenance work, ensure that the driver is de-energized and
the pump hydraulically isolated.
Note! When ordering spare parts, please state the complete pump identification
according to its name plate and required spare part set.
Required spareparts
Spcode Qty Description
1 Joint kit, for dismantling of the pump, G057
1 Shaft seal, G050
As required Rotor set, G012
As required Valve spring, 615
The overhaul of the pump includes checking the operation, inspecting the rotors
and changing rotor bearings and mechanical seals. The motor may need new
bearings or re-greasing.
1 Check the operation of the pump. Wear parts in the pump may be indicated by
vibration, noise, loss of capacity, reduction in flow/pressure, leakage. See also
instruction for Inspecting and lubricating the pump
4-7
Lubrication oil system
Warning! Risk for splashing or spill! Wear protective clothing (including safety
glasses). Do not assume that the system is depressurized even when a
pressure gauge indicates zero.
3 Dismantle and inspect the pump. Follow the instructions in the dismantling/
reassembly instruction given in the service manual.
a ) Replace the wear parts as necessary.
b ) Change rotor bearings and seals.
c ) Change all O-rings and gaskets.
4 Check the motor bearings and replace/re-grease them if necessary.
5 Put the pump back into operation
a ) Open shut off valves.
b ) Prime the pump.
c ) Do a quick start-stop of the pump to check that it has power and that the
rotation is correct. If the power cables were disconnected they may have
been switched so that the motor is rotating in the wrong direction. If that's
the case, two poles must be switched in order to change the direction. This
must be done by an electrician.
d ) Start the pump and check for leakage. A new mechanical shaft seal may
leak slightly more during the first hours of operation.
Pumps with an external ball bearing including grease nipple, must be re-greased
after one hour of running, while the pump is operating.
4-8
Combined system modules
Content
Pipe module ................................................................................................................................................5 - 2
Prelube pump
Plate heat exchanger
Lube oil filter
Preheater element
5-1
Combined system modules
Pipe module
Content
Prelube pump
Inspecting and lubricating the pump, 6 Months ..................................................................................5 - 3
In-service inspection of pump - greasing of bearings and cleaning of strainer.
Overhauling the pump, 3 Years ..........................................................................................................5 - 7
A planned inspection and overhaul of the pump and motor should be made at regular intervals - not
exceeding 3 years.
Plate heat exchanger
Cleaning the heat exchanger, 1 Years ................................................................................................5 - 9
This is a plate heat exchanger and requires periodic cleaning based on the amount of fouling.
Lube oil filter
Maintaining the oil filter, 1 Months ....................................................................................................5 - 11
This oil filter has four chambers and is equipped with a by-pass valve that opens at 2 bars.
Preheater element
Inspecting the electric heater, 1 Years ..............................................................................................5 - 13
Yearly electrical tests and inspection of the gaskets and flange.
pump
Prelube
5-2
Combined system modules
General Information
JobID: wca0308 Type: ACG/UCG
Unit: Pipe module QEA011 Manufacturer: IMO
Component: Prelube pump D001
Work Information
Type of job: inspection Work time: 2 Hours
Stop time: 1 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
6 Months Mechanical, Off-engine 1 2 component
Note! When ordering spare parts, please state the complete pump identification
according to its name plate and required spare part set.
Required spareparts
Spcode Qty Description
As required Joint kit, for dismantling of the pump, G057
As required Shaft seal, G050
Lubricate the pump and motor ball bearings and check that the pump operates
correctly without excessive leakage, vibrations, or noise.
1 Grease the pump rotor ball bearings, if the pump is provided with external
bearings and grease nipple. The pump should be running during greasing.
Caution! Do not overfill with grease. Overfilling will damage the mechanical seal.
2 Grease the motor bearings, if the motor is provided with grease nipples. The pump
should be running during greasing.
Note! Some motors may have a separate rating plate with information about the
bearings and lubricating intervals. If so, those instructions must be
followed.
5-3
Combined system modules
Warning! Do not start maintenance work unless power is switched off and physically
disconnected, the inlet and outlet valves and are shut and accidental
opening is prevented, and the device vented to atmospheric pressure.
Warning! Risk for splashing or spill! Wear protective clothing (including safety
glasses). Do not assume that the system is depressurized even when a
pressure gauge indicates zero.
d) Open and clean the strainer. Place a bucket under the strainer to collect
spills.
Warning! Contents may be hot! Allow time for temperature to normalize before
starting the work.
5-4
Combined system modules
5-5
Combined system modules
5-6
Combined system modules
General Information
JobID: wca0309 Type: ACG/UCG
Unit: Pipe module QEA011 Manufacturer: IMO
Component: Prelube pump D001
Work Information
Type of job: overhaul Work time: 4 Hours
Stop time: 4 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
3 Years Mechanical, Off-engine 1 component
A planned inspection and overhaul of the pump and motor should be made at regular
intervals - not exceeding 3 years.
Warning! Before any maintenance work, ensure that the driver is de-energized and
the pump hydraulically isolated.
Note! When ordering spare parts, please state the complete pump identification
according to its name plate and required spare part set.
Required spareparts
Spcode Qty Description
1 Joint kit, for dismantling of the pump, G057
1 Shaft seal, G050
As required Rotor set, G012
As required Valve spring, 615
The overhaul of the pump includes checking the operation, inspecting the rotors
and changing rotor bearings and mechanical seals. The motor may need new
bearings or re-greasing.
1 Check the operation of the pump. Wear parts in the pump may be indicated by
vibration, noise, loss of capacity, reduction in flow/pressure, leakage. See also
instruction for Inspecting and lubricating the pump
5-7
Combined system modules
Warning! Risk for splashing or spill! Wear protective clothing (including safety
glasses). Do not assume that the system is depressurized even when a
pressure gauge indicates zero.
3 Dismantle and inspect the pump. Follow the instructions in the dismantling/
reassembly instruction given in the service manual.
a ) Replace the wear parts as necessary.
b ) Change rotor bearings and seals.
c ) Change all O-rings and gaskets.
4 Check the motor bearings and replace/re-grease them if necessary.
5 Put the pump back into operation
a ) Open shut off valves.
b ) Prime the pump.
c ) Do a quick start-stop of the pump to check that it has power and that the
rotation is correct. If the power cables were disconnected they may have
been switched so that the motor is rotating in the wrong direction. If that's
the case, two poles must be switched in order to change the direction. This
must be done by an electrician.
d ) Start the pump and check for leakage. A new mechanical shaft seal may
leak slightly more during the first hours of operation.
Pumps with an external ball bearing including grease nipple, must be re-greased
after one hour of running, while the pump is operating.
exchanger
heat
Plate
5-8
Combined system modules
General Information
JobID: wca0333 Type: M
Unit: Pipe module QEA011 Manufacturer: Alfa Laval
Component: Plate heat exchanger B001
Work Information
Type of job: inspection Work time:
Stop time:
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Years Mechanical, Off-engine 1 component
This is a plate heat exchanger and requires periodic cleaning based on the amount of
fouling.
When ordering plates and gaskets, state the serial numbers of the plates and the
type and serial number of the heat exchanger.
Required spareparts
Spcode Qty Description
As required Gaskets
Required tools
Code Description Illustration
Circulation pump for detergent (Cleaning-in-
place)
Clean the heat exchanger at least every year. The cleaning must also be done if
there is a drop in output pressure or temperature.
1 Check the history of the temperature and pressure drop to determine the need for
cleaning.
2 Inspect the heat exchanger for signs of leakage or damage.
3 Shut down and clean the heat exchanger (if needed).
a ) Cool the heat exchanger to below 40 degrees C.
b ) Let the pump recirculate and lower the temperature of the cooling water.
Caution! The temperature drop must not be greater than 10 degrees per minute and
the pressure drop must not be greater than 10 bar per minute.
c) Unless severe fouling is suspected, clean the heat exchanger in place (CIP)
without separating the frame.
d) Refer to the manufacturer's manual for CIP cleaning and for the detergent
requirements.
5-9
Combined system modules
General Information
JobID: wca0334 Type: FFP-32040
Unit: Pipe module QEA011 Manufacturer: Finn-Filter
Component: Lube oil filter B003
Work Information
Type of job: inspection Work time: 4 Hours
Stop time:
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Months Mechanical, Off-engine 4 component
This oil filter has four chambers and is equipped with a by-pass valve that opens at 2 bars.
Note! For a complete list of spare parts, refer to the manufacturer's spare parts
list for this filter.
Required spareparts
Spcode Qty Description
As required O-rings
As required Filter Cartridges
As required Wire mesh element (safety element)
3 Open the air vent screw to release the pressure in the filter tank.
The vent screw is located on the cap.
4 Remove the filter elements.
a ) Remove the nuts for the tank cap and remove the cover.
b ) Remove the nut on the top of the centre rod in the tank.
c ) Disconnect the holder cap and lift it off from the tank.
d ) Lift of the outer filter cartridges and the flange.
e ) Remove the inner wire mesh safety element.
5 Replace the filter cartridges with new ones.
6 Clean the elements with detergent or ultrasonic washing machine.
7 Check the element for damages and replace it with a new element, if necessary.
8 Lift off the bottom plates and springs along the centre rod.
9 Clean the tank, the tank cap, and the bottom plates.
5 - 11
Combined system modules
10 Inspect the O-rings and replace them with new O-rings if necessary.
The O-rings are for the following locations:
● Tank top
● Holder cap
● Bottom plates
● Safety elements
Oil the O-rings and the contact surface before assembly.
11 Assemble the filter in the opposite order.
12 Fill the filter chamber.
a ) Leave the air vent screw slightly open and let incoming flow to fill the housing
while the slow filling port is in the FILL-position.
This slow filling valve is located inside the valve spool. It enables pressure
balancing between housings.
The chamber is full when there is only oil coming out from the top of the
filter.
b ) Close the air vent screw.
c ) Open the valve spool and then close the slow filling valve by turning to the
“CLOSED” position.
13 Check that there is no leakage.
General Information
JobID: wca0342 Type: 1REBT
Unit: Pipe module QEA011 Manufacturer: RICA
Component: Preheater element B004
Work Information
Type of job: test Work time: 5 Hours
Stop time: 5 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Years electrician 5 component
Mechanical, Off-engine 1 component
Warning! The feeding cables must always be disconnected before making any
maintenance or testing is performed on the heater.
Required spareparts
Spcode Qty Description
1REPBT09--- As required Complete heater
1REBZP91--- As required Heating elements
71020700 As required Safety thermostat
71020690 As required Regulation thermostat
70270051 As required Terminal board (16 mm2)
70270011 As required Terminal board (2.5 mm2)
Warning! Before performing any electrical test, ensure that the power has been cut
and that the heater feeding cable has been disconnected from the electrical
panel.
5 - 13
Combined system modules
5 If any of the previous tests failed, open the electrical cable housing and do the
following:
a ) Disconnect the feeding cables coming from the terminal board.
b ) Inspect the cables and connection bonds.
c ) Check especially for cracks in the insulation.
d ) Replace the cables and connections with new parts if they are faulty.
6 If the cables or connections are replaced with new parts, repeat the electrical
conductivity, insulation, and dielectric strength tests.
7 If any of the repeated test failed, do the following:
a ) Open the protection cover and check the integrity of the electrical
connections.
b ) Disconnect the feeding cables coming from the terminal board.
c ) Repeat the electrical continuity test between the disconnected feeding
cables in order to check the integrity.
d ) Mark the faulty heating elements and disconnect them 3 at a time to keep
the load balanced, provided that the power is sufficient for the operation.
e ) If the power is not enough, the entire bundle must be replaced.
8 Reassemble all disconnected items.
9 Visually inspect the gaskets.
10 Refer to the OEM manual and follow the instructions for startup.
5 - 14
Compressed air system
Content
Working on the compressed air system ......................................................................................................6 - 2
Instrument and working air unit ...................................................................................................................6 - 3
Compressor
Dryer
Starting air unit ..........................................................................................................................................6 - 16
Starting air compressor
Starting air vessel ......................................................................................................................................6 - 23
Inspecting the start air vessel (4 year)
Inspecting the start air vessel (8 year)
6-1
Compressed air system
Warning! Never use compressed air to blow clean your working clothes or any part
of your body. To do so is to risk your life! Air may enter your bloodstream.
Warning! Before starting to work on, or opening up, any part of the compressed air
system, make sure that it is not pressurized.
Attention Use proper blow guns and eye protection when using compressed air for
! cleaning purposes.
6-2
Compressed air system
Content
Compressor
Inspecting the air compressor (1500 h), 1500 Hours ..........................................................................6 - 5
Inspect the air compressor and change oil and oil filter.
Inspecting the air compressor (annual), 1 Years ................................................................................6 - 7
Inspect and maintain the air compressor and check safety valves.
Inspecting the air compressor (3000 h), 3000 Hours ..........................................................................6 - 9
Inspect the air compressor and change oil separator element.
Dryer
Cleaning the instrument air dryer, 1 Months .....................................................................................6 - 11
The ambient air filter is cleaned monthly.
Inspecting the instrument air dryer, 3 Months ...................................................................................6 - 13
The inlet strainer is cleaned every three months.
Maintaining the instrument air dryer, 1 Years ...................................................................................6 - 15
Annual maintenance includes checking the set points and replacing filter cartridges.
Compressor
6-3
Compressed air system
6-4
Compressed air system
General Information
JobID: 209 Type: WD
Unit: Instrument and working air unit TCA901 Manufacturer: Tamrotor
Component: Compressor D01
Work Information
Type of job: Overhaul Work time: 2 Hours
Stop time: 4 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1500 Hours Mechanical, On-engine 1 2 component
Inspect the air compressor and change oil and oil filter.
Warning! Do not remove the filter plug when the oil separator is under pressure.
Required spareparts
Spcode Qty Description
TAM-855 886 19 1 Oil Filter
TAM-897 866 29 1 Air Filter
Change the oil, oil filter and replace the air filter.
1 Stop the compressor operation.
a ) Stop the compressor and wait until the oil separator exhaust is complete
(approximately 2 minutes).
b ) Switch off the compressor with the main switch and make sure the
compressor can not be started unintentionally.
c ) Close the shut-off valve between compressor and the compressed air
system.
d ) Close the drain valve.
e ) Release the pressure from the cooler:
1 Open the valve carefully until no pressure remains.
2 Open the safety valve cap for 4-5 turns.
2 Change the oil.
a ) Run the compressor until the oil temperature is + 40…50 C before changing
oil.
b ) Change the oil life setting in the electronic control unit, if necessary
(recommended setting: 1500 h).
6-5
Compressed air system
Caution! Make sure no impurities or dirt get in through the open valve, as they could
cause damage to the air end.
Note! For a more effective cleaning, brush the underside of the cooler, but do
NOT use a metal wire brush.
6-6
Compressed air system
General Information
JobID: 210 Type: WD
Unit: Instrument and working air unit TCA901 Manufacturer: Tamrotor
Component: Compressor D01
Work Information
Type of job: inspection Work time: 16 Hours
Stop time: 16 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Years Mechanical, On-engine 1 16 component
Inspect and maintain the air compressor and check safety valves.
Warning! Do not remove the filter plug when the oil separator is under pressure.
Required spareparts
Spcode Qty Description
TAM-855 886 19 1 Oil Filter
TAM-897 866 29 1 Air Filter
TAM-033 890 10 1 Intake valves seal kits
TAM-033 892 70 1 Output valves seal kits
The annual maintenance of the unit includes oil changes, testing of safety
functions and checking the general condition of the unit.
1 Stop the compressor operation.
a ) Stop the compressor and wait until the oil separator exhaust is complete
(approximately 2 minutes).
b ) Switch off the compressor with the main switch and make sure the
compressor can not be started unintentionally.
c ) Close the shut-off valve between compressor and the compressed air
system.
d ) Close the drain valve.
e ) Release the pressure from the cooler:
1 Open the valve carefully until no pressure remains.
2 Open the safety valve cap for 4-5 turns.
6-7
Compressed air system
6-8
Compressed air system
General Information
JobID: 208 Type: WD
Unit: Instrument and working air unit TCA901 Manufacturer: Tamrotor
Component: Compressor D01
Work Information
Type of job: inspection Work time: 4 Hours
Stop time: 4 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
3000 Hours Mechanical, On-engine 1 4 component
Warning! Do not remove the filter plug when the oil separator is under pressure.
Required spareparts
Spcode Qty Description
TAM-035 822 28 1 Oil Separator Element
6-9
Compressed air system
Note! When assembling the valve leave the nut about 2 mm off the valve cover.
General Information
JobID: 267 Type: HIT
Unit: Instrument and working air unit TCA901 Manufacturer: Hankison
Component: Dryer D02
Work Information
Type of job: Wash/Clean Work time: 1 Hours
Stop time: 1 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Months Mechanical, Off-engine 1 1 component
6 - 11
Compressed air system
6 - 12
Compressed air system
General Information
JobID: wca0268 Type: HIT
Unit: Instrument and working air unit TCA901 Manufacturer: Hankison
Component: Dryer D02
Work Information
Type of job: Overhaul Work time: 1 Hours
Stop time: 1 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
3 Months Mechanical, Off-engine 1 1 component
Warning! The compressed-air system of the refrigerated compressed air dryer must
be depressurised.
6 - 13
Compressed air system
6 - 14
Compressed air system
General Information
JobID: wca0269 Type: HIT
Unit: Instrument and working air unit TCA901 Manufacturer: Hankison
Component: Dryer D02
Work Information
Type of job: Overhaul Work time: 2 Hours
Stop time: 2 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Years Mechanical, Off-engine 1 2 component
Annual maintenance includes checking the set points and replacing filter cartridges.
Required spareparts
1 Maintenance kit
6 - 15
Compressed air system
Content
Starting air compressor
Inspecting the start air compressor, 1000 Hours ..............................................................................6 - 17
This is a 1000 hour inspection - including valve overhaul and oil change.
Overhauling the start air compressor, 5000 Hours ...........................................................................6 - 19
This is a 5000 hour general overhaul of the air compressor.
Overhauling the start air compressor, 10000 Hours .........................................................................6 - 21
This is a 10,000 hour overhaul replacing the 5000 hour and 1000 hour service
compressor
air
Starting
6 - 16
Compressed air system
General Information
JobID: 229 Type: HL2/120
Unit: Starting air unit TSA901 Manufacturer: Sperre
Component: Starting air compressor D001, D002
Work Information
Type of job: inspection Work time: 4 Hours
Stop time: 4 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1000 Hours Mechanical, On-engine 1 4 component
2 Years
This is a 1000 hour inspection - including valve overhaul and oil change.
Note! Make sure that overhaul kit no. 3038MK2 and 3035MK2 are in stock before
starting overhaul of compressor according to 1000 hour service. Follow the
installation instructions included in the kit.
Required spareparts
Spcode Qty Description
SPE-3038MK2 1 Overhaul kit (valve springs, plates and
gaskets)
SPE-3035MK2 1 Overhaul kit (valve springs, plates and
gaskets)
Caution! The safety valves are sealed and the setting should not be adjusted.
6 - 17
Compressed air system
6 - 18
Compressed air system
General Information
JobID: 212 Type: HL2/120
Unit: Starting air unit TSA901 Manufacturer: Sperre
Component: Starting air compressor D001, D002
Work Information
Type of job: overhaul Work time: 8 Hours
Stop time: 8 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
5000 Hours Mechanical, On-engine 1 8 component
Note! Make sure that overhaul kit no. 7937 is in stock before starting the overhaul
of compressor according to 5.000 hour service. Follow installation
instructions included in the kit.
Required spareparts
Spcode Qty Description
SPE-7937 1 Overhaul kit - 5000 hour maintenance
SPE-3035MK2 1 Overhaul kit (valve springs, plates and
gaskets)
SPE-3038MK2 1 Overhaul kit (valve springs, plates and
gaskets)
6 - 19
Compressed air system
Caution! The air pressure should not exceed the maximum working pressure + 10%.
Note! The safety valves are sealed and the setting should not be adjusted.
Caution! Make sure that cleaning products are suitable for copper tubes.
Note! Use the overhaul kit for the 5000 hour maintenance.
6 - 20
Compressed air system
General Information
JobID: 231 Type: HL2/120
Unit: Starting air unit TSA901 Manufacturer: Sperre
Component: Starting air compressor D001, D002
Work Information
Type of job: overhaul Work time: 16 Hours
Stop time: 16 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
10000 Hours Mechanical, On-engine 1 16 component
This is a 10,000 hour overhaul replacing the 5000 hour and 1000 hour service
Make sure that overhaul kits are in stock before starting the overhaul of the
compressor according to 10.000 hour service. Follow the installation instructions
included in the kit.
Required spareparts
Spcode Qty Description
SPE-7967 1 Overhaul kit - 10,000 hour maintenance
SPE-3035MK2 1 Overhaul kit (valve springs, plates and
gaskets)
SPE-3038MK2 1 Overhaul kit (valve springs, plates and
gaskets)
SPE-3035MK 1 Overhaul kit (valve and necessary copper
rings and/or gaskets)
SPE-3038MK 1 Overhaul kit (valve and necessary copper
rings and/or gaskets)
6 - 21
Compressed air system
Caution! The air pressure should not exceed the maximum working pressure + 10%.
Note! The safety valves are sealed and the setting should not be adjusted.
Caution! Make sure that cleaning products are suitable for copper tubes.
6 - 22
Compressed air system
Content
Inspecting the start air vessel (4 year)
Inspecting the start air vessel (8 year)
V3
year)
(4
vessel
air
start
the
Inspecting
General Information
JobID: 206 Type: 125L - 3000L
Unit: Compressed air system Manufacturer: Uwira
Component: Starting air vessel TSB901
Work Information
Type of job: check_job Work time:
Stop time:
Intervals Service personnel
Interval: Type Number Hours Multiplied by
4 Years O&M Supervisor 1 component
Note! For specific spare parts numbers, refer to the component drawings. Use
only original spare parts.
Remove the valve head and flanges and carefully inspect the inside of the vessel.
1 Secure the vessel from the compressed air source.
2 Drain the vessel of compressed air.
Work Information
Type of job: inspection Work time:
Stop time:
6 - 23
Compressed air system
Work Information
Intervals Service personnel
Interval: Type Number Hours Multiplied by
8 Years O&M Supervisor 1 component
Note! For specific spare parts numbers, refer to the component drawings. Use
only original spare parts.
Perform a pressure test, inspect the inside of the vessel and check the equipment
and gauges.
1 Secure the vessel from the compressed air source.
2 Drain the vessel of compressed air
3 Perform a hydraulic pressure test using at least 1,43 times the maximum working
pressure.
Follow recommended hydraulic test procedures for this test.
4 Inspect the inside of the vessel.
a ) Remove the valve head and flanges. This provides access for the internal
inspection.
b ) Inspect the inner surface of the vessel.
c ) Carefully make a visual inspect all welding joints. Additional inspections can
be made by ultrasonic, dye penetrant, or X-ray testing.
d ) Install the valve head and flanges. Use new gaskets for all flange
connections.
5 Check the condition of the tank supports and possible additional support
construction.
6 Perform an operation test
Check that all equipment and gauges are working properly.
6 - 24
Cooling system
Cooling system
Content
Maintenance water tank ..............................................................................................................................7 - 2
Water pump
External cooling devices .............................................................................................................................7 - 4
Radiator
7-1
Cooling system
Content
Water pump
Inspecting the water pump bearings, 6 Months ..................................................................................7 - 3
Inspection of water pump bearings.
pump
Water
7-2
Cooling system
General Information
JobID: wca0326 Type: Water pump
Unit: Maintenance water tank VBA901 Manufacturer: MAKO
Component: Water pump D001
Work Information
Type of job: check_job Work time: 1 Hours
Stop time: 1 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
6 Months Mechanical, Off-engine 1 1 component
Warning! Before servicing, disconnect the pump from the electrical supply and make
sure that it cannot be started accidentally.
7-3
Cooling system
Content
Radiator
Inspecting the radiator, 1 Months ........................................................................................................7 - 5
The radiator for the cooling water system is inspected monthly.
Radiator
7-4
Cooling system
General Information
JobID: 132 Type: FBLGE
Unit: External cooling devices Manufacturer: FINCOIL
Component: Radiator VCA011, VCA012
Work Information
Type of job: inspection Work time: 2 Hours
Stop time: 1 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Months Mechanical, Off-engine 1 2 component
7-5
Cooling system
2 Check the condition of the heat transfer section and clean, if necessary.
Note! The heat transfer section needs cleaning only if over 30% of fin space is
blocked-up or if the cooling capacity is remarkably reduced.
Caution! Ensure that the cleaning does not damage the heat transfer section.
Caution! Don’t use alkaline detergents or acids. The detergent has to be suitable for
aluminium, copper and galvanized steel. See manufacturer's
recommendations.
7-6
Charge air and exhaust gas system
Content
Exhaust gas silencer ...................................................................................................................................8 - 2
Silencer
Charge air filter ............................................................................................................................................8 - 4
Filter
Charge air silencer ......................................................................................................................................8 - 8
Silencer
8-1
Charge air and exhaust gas system
Content
Silencer
Inspecting the exhaust gas silencer, 4000 Hours ...............................................................................8 - 3
Check spark arrestors, if applicable.
Silencer
8-2
Charge air and exhaust gas system
General Information
JobID: 205 Type: RI-P-CWAEXG
NS1300 / 45 dB(A)
Unit: Exhaust gas silencer NHA011 Manufacturer: JTK-POWER
Component: Silencer B005
Work Information
Type of job: Wash/Clean Work time: 1 Hours
Stop time: 1 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
4000 Hours Mechanical, On-engine 1 1 component
6 Months
8-3
Charge air and exhaust gas system
Content
Filter
Removing sludge from the filter, 1 Months .........................................................................................8 - 5
Remove sludge from the charge air filter every month.
Inspecting the MultiDuty filter, 6 Months .............................................................................................8 - 7
The inspection includes checking of timer and testing the condition of the viscosine oil.
Filter
8-4
Charge air and exhaust gas system
General Information
JobID: 023 Type: MultiDuty
Unit: Charge air filter NGA011, NGA012 Manufacturer: AAF
Component: Filter
Work Information
Type of job: Wash/Clean Work time: 1 Hours
Stop time: 0 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Months Mechanical, Off-engine 1 1 component
Required spareparts
Spcode Qty Description
Viscosine
Required tools
Code Description
Sludge scraper
Note! When filling with new viscosine, make sure that there is no sludge left at
the bottom of the viscosine oil tank.
8-5
Charge air and exhaust gas system
8-6
Charge air and exhaust gas system
General Information
JobID: 022 Type: Multiduty
Unit: Charge air filter NGA011, NGA012 Manufacturer: AAF
Component: Filter
Work Information
Type of job: inspection Work time: 2 Hours
Stop time: 0 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
6 Months Mechanical, Off-engine 1 2 component
The inspection includes checking of timer and testing the condition of the viscosine oil.
Check the timer and take a viscosine sample.
1 Check if the timer works properly. The filter is equipped with a timer which
operates the curtain at 15 minutes intervals so that the filter curtain makes a
complete revolution in 24 hours.
2 Take a viscosine sample from the tank.
a ) Put the sample into a graduated glass around 1 litre.
b ) Let the viscosine settle for 48 hours.
c ) If sludge deposit is above or equal to ¼ of oil height, replace viscosine.
8-7
Charge air and exhaust gas system
Content
Silencer
Inspecting the charge air silencer, 3 Months ......................................................................................8 - 9
Remove condensation water from the silencer.
Silencer
8-8
Charge air and exhaust gas system
General Information
JobID: 204 Type: SCAS.
Unit: Charge air silencer NGA010 Manufacturer: JTK-POWER
Component: Silencer B003, B004
Work Information
Type of job: inspection Work time: 1 Hours
Stop time: 0 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
3 Months Mechanical, Off-engine 1 1 component
8-9
Charge air and exhaust gas system
8 - 10
Electrical system
Electrical system
Content
LV-switchgear .............................................................................................................................................9 - 2
Switchgear
Frequency converter ...................................................................................................................................9 - 5
Converter
Step-up transformer ....................................................................................................................................9 - 8
Transformer
Auxiliary transformer .................................................................................................................................9 - 10
Transformer
DC-system ................................................................................................................................................9 - 12
EFORE EIPS
9-1
Electrical system
LV-switchgear
Content
Switchgear
Inspecting the LV switchgear, 1 Years ................................................................................................9 - 3
The thoroughness and frequency of the inspection depends on the age of the equipment and the local
conditions that may cause failures.
Switchgear
9-2
Electrical system
General Information
JobID: wca349 Type: KKBU
Unit: LV-switchgear BFA901 Manufacturer: ELKAMO
Component: Switchgear
Work Information
Type of job: inspection Work time: 4 Hours
Stop time: 4 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Years electrician 4 component
The thoroughness and frequency of the inspection depends on the age of the equipment
and the local conditions that may cause failures.
When ordering service or spare parts, the following information (from the technical
data plate) must be given:
● type of switchgear
● production number
● nominal current
● nominal voltage
● thermic resistance against short circuit
● dynamic resistance against short circuit
● protection class
Required tools
Code Description
Equipment for thermophotography
Inspect and clean the switchgear. Test the air gaps after each coupling
installation.
1 Inspect the internal groundings to ensure that they prescribe to actual
regulations
The checkpoints include all couplings, grounding of measurement transformers
and condition of the groundings.
2 Tighten the joints of row and instrument couplings in all alarm and protection
circuits.
3 Check the service points for the instruments.
Refer to the specific user instructions for more information.
4 Inspect the costruction of the switchgear: protection class and contact shields.
5 Inspect the cable conditions and markings.
6 Clean the switchgear.
Warning! The switchgear must not contain any electrical current while it is being
cleaned.
A vacuum cleaner can be used for dusting. Plastic parts can be washed with
water, alcohol or benzine.
7 The busbar couplings should be thermophotographed once a year.
9-3
Electrical system
9-4
Electrical system
Frequency converter
Content
Converter
Checking the frequency converter, 1 Years ........................................................................................9 - 7
These tasks should be done when necessary and at least annually.
Converter
9-5
Electrical system
9-6
Electrical system
General Information
JobID: 0139 Type: NX
Unit: Frequency converter BLP011 Manufacturer: Vacon
Component: Converter
Work Information
Type of job: inspection Work time: 1 Hours
Stop time: 1 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Years electrician 1 1 component
Warning! The components of the power unit of the frequency converter are live when
Vacon NX is connected to mains potential. Coming into contact with this
voltage is extremely dangerous and may cause death or severe injury.
Warning! The motor terminals U, V, W and the DC-link/brake resistor terminals are
live when Vacon NX is connected to mains, even if the motor is not running.
Warning! After disconnecting the frequency converter from the mains, wait until the
fan stops and the indicators on the keypad go out (if no keypad is attached
see the indicators on the cover). Wait 5 more minutes before doing any
work on Vacon NX connections. Do not even open the cover before this
time has expired.
Warning! The control I/O-terminals are isolated from the mains potential. However,
the relay outputs and other I/O-terminals may have a dangerous control
voltage present even when Vacon NX is disconnected from mains.
Clean the heat sink and check the tightness of the terminals.
1 Clean the heat sink with compressed air.
2 Check the tightening torques of terminals. See the manufacturer's instructions for
the torques.
3 Replace the cooling fan if necessary.
Warning! Before connecting the frequency converter to the mains, make sure that
the Vacon NX front cover and cable covers are closed.
9-7
Electrical system
Step-up transformer
Content
Transformer
Inspecting the step-up transformer, 1 Years .......................................................................................9 - 9
Transformer
9-8
Electrical system
General Information
JobID: wca0489 Type: THREE-PHASE AIR
TIGHT
Unit: Step-up transformer AET901, AET902 Manufacturer: CELDUC
Component: Transformer
Work Information
Type of job: check_job Work time: 2 Hours
Stop time: 0 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Years electrician 1 2 component
The tank is of hermetic type and is completely filled with liquid. The tank deforms
itself to take up the increase in volume of the dielectric due to heating. It is
therefore necessary to check that the tank does not show any signs of a leak of
dielectric once a year. It is not necessary to check the state of the dielectric liquid
as it is not subject to any oxidation or penetration of humidity.
1 Check that the transformer shows no signs of leakage.
9-9
Electrical system
Auxiliary transformer
Content
Transformer
Dielectric withstand test, 10 Years ....................................................................................................9 - 11
A sample of the dielectric fluid is collected and tested every 10 years.
Transformer
9 - 10
Electrical system
General Information
JobID: 010 Type: Hermetically sealed,
HTMU 12 HA 1600
Unit: Auxiliary transformer Manufacturer: Schneider Electric
Component: Transformer BFB901, AET902
Work Information
Type of job: test Work time: 2 Hours
Stop time: 0 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
10 Years electrician 1 2 component
9 - 11
Electrical system
DC-system
Content
EFORE EIPS
Inspecting the DC-system, 1 Years ..................................................................................................9 - 13
Annual inspection and testing for the DC system.
EIPS
EFORE
9 - 12
Electrical system
General Information
JobID: 009 Type: EIPS-D1
Unit: DC-system Manufacturer: EFORE
Component: EFORE EIPS BEY901
Work Information
Type of job: inspection Work time: 2 Hours
Stop time: 2 Hours
Intervals Service personnel
Interval: Type Number Hours Multiplied by
1 Years electrician 1 2 component
Note! Make sure that the system is in the maintenance mode by switching the
dip switch 3 (maintenance) of the A1 supervisor unit to the ON position
before testing the system.
Warning! Turning off the rectifiers will not necessarily remove power from the bus.
Warning! ● Hazardous energy and voltages are present in the unit and on the
interface cables.
● They can cause shock or serious injury.
● Follow all safety warnings and practices when servicing this equipment.
Check the operation of the rectifiers and the control units. Check the earthing leak
fault operation.
1 Check operation of rectifiers in accordance with the following instructions:
a ) Check the output voltage (U upp, U low )
● Float charge 'U upp' to 122.6 V DC.
● Support level 'U low' to 103.0 V DC.
b ) Test the mains fault
● Open the distribution fuses of all rectifiers. The 'MAINS' and 'FAULT'
indicator LED's light up temporarily for about 15 seconds.
● Check the control/alarm terminals (A1 / x10 / 11-12) to ensure that the
alarm relay in question is working.
● Close the distribution fuses of all rectifiers.
Alarm limits are < 195 V AC and > 275 V AC.
9 - 13
Electrical system
2 Check the functions of the A1 control and monitoring unit and other units A2-A6
of the system in accordance with the following instructions:
a ) Check the voltage measurement. Using the program, check if the voltage
measurements made by the system correspond with the reading of the
multimeter.
b ) Test the AC Fault.
● Set all rectifiers to the support charge level via the terminal program.
● Check the operation of batteries and their voltage.
● Switch off all AC distribution fuses of the rectifiers.
● Check if AC fault signal in the terminal program is ON.
● Switch ON all AC distribution fuses of the rectifiers.
● Check the rectifier PWM control and set the system voltage to a different
voltage from the float charge level.
● Check whether the system has adjusted itself to the correct voltage.
d) Test the Distribution Fuse Fault
● Disconnect the terminal X2 from the distribution fuse monitoring unit; the
signal mode of the alarm in question in the program is ON.
● When the terminal X2 is installed back to its place, the signal mode will
change to OFF.
e) Test the Battery Fuse Fault
● Short circuit the poles of the alarm contacts in the battery fuse.
Note! The battery fuse in question will switch to ON position in the program.
Warning! When conducting the above test, DO NOT open a battery fuse in operation.
9 - 14
Electrical system
Caution! During this test, partial earth leakage is caused. Read first chapter
“Operational Safety” from Installation and Start-Up Manual.
9 - 15
Electrical system
9 - 16