CUADRO RESUMEN DE VALORIZACIONES

CUADRO DE VALORIZACIONES PAGADAS

OBRA CONTRACTUAL
TOTAL VAL
VAL N° 01 VAL N° 02 VAL N° 03 VAL N° 04 VAL N° 05 VAL N° 06 VAL N° 07 VAL N° 08 VAL N° 09 VAL N° 10 VAL N° 11 VAL N° 12 VAL N° 13 VAL N° 14 VAL N° 15 VAL N° 16 CONTRACTUAL
ITEMS PARTIDAS COSTO
8/14/2017 9/1/2017 10/1/2017 11/1/2017 12/1/2017 1/1/2018 2/1/2018 3/1/2018 4/1/2018 5/15/2018 6/1/2018 7/1/2018 8/1/2018 9/1/2018 10/1/2018 11/1/2018
8/31/2017 9/30/2017 10/31/2017 11/30/2017 12/31/2017 1/31/2018 2/28/2018 3/31/2018 4/13/2018 5/31/2018 6/30/2018 7/31/2018 8/31/2018 9/30/2018 10/31/2018 11/25/2018
18.00 30.00 31.00 30.00 31.00 31.00 28.00 31.00 13.00 17.00 30.00 31.00 31.00 30.00 31.00 25.00

F 01 ARQUITECTURA Y SEÑALIZACIÓN 2,037,708.24 S/.0.00 S/.0.00 S/.0.00 S/.64,142.12 S/.113,456.46 S/.61,974.31 S/.216,870.60 S/.133,840.95 S/.13,208.01 S/.151,453.72 S/.69,572.38 S/.244,491.94 S/.350,162.80 S/.211,348.93 S/.102,785.17 S/.304,400.86 S/.2,037,708.24
F 02 ESTRUCTURA 5,025,568.10 S/.907,977.37 S/.505,659.50 S/.792,680.68 S/.221,979.26 S/.1,088,112.34 S/.23,830.48 S/.1,912.56 S/.146.87 S/.0.00 S/.0.00 S/.316,067.79 S/.424,895.34 S/.222,562.70 S/.271,852.03 S/.168,055.80 S/.79,835.47 S/.5,025,568.10
F 03 INSTALACIONES SANITARIAS 476,888.89 S/.0.00 S/.0.00 S/.4,573.84 S/.0.00 S/.15,168.39 S/.53,073.81 S/.22,382.55 S/.7,355.90 S/.57,934.36 S/.12,505.48 S/.3,118.03 S/.27,829.72 S/.28,859.58 S/.30,190.43 S/.143,783.68 S/.70,113.20 S/.476,888.89
F 04 INSTALACIONES ELECTRICAS Y COMUNICACIÓN 801,608.31 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.7,079.83 S/.64,599.54 S/.4,917.61 S/.35,971.12 S/.71,948.68 S/.114,328.02 S/.20,481.58 S/.22,820.96 S/.41,483.36 S/.11,551.41 S/.181,225.47 S/.225,200.78 S/.801,608.31
F 05 INSTALACIONES ELECTROMECANICAS 219,710.48 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.3,000.00 S/.31,924.38 S/.2,450.00 S/.182,336.10 S/.219,710.48
F 06 SEGURIDAD 59,088.30 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.18,740.12 S/.14,055.09 S/.4,685.03 S/.0.00 S/.10,733.58 S/.2,306.71 S/.5,578.13 S/.2,989.64 S/.59,088.30
F 07 MITIGACION DE IMPACTO AMBIENTAL 123,800.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.0.00 S/.49,900.00 S/.48,700.00 S/.2,050.00 S/.0.00 S/.18,500.00 S/.1,100.00 S/.2,600.00 S/.950.00 S/.123,800.00

SUB TOTAL 8,744,372.32 S/. 907,977.37 S/. 505,659.50 S/. 797,254.52 S/. 286,121.38 S/. 1,223,817.02 S/. 203,478.14 S/. 246,083.32 S/. 177,314.84 S/. 211,731.17 S/. 341,042.31 S/. 415,974.81 S/. 720,037.96 S/. 675,302.02 S/. 560,273.89 S/. 606,478.25 S/. 865,826.05 S/. 8,744,372.32
COSTO DIRECTO S/. 8,744,372.32 S/. 907,977.37 S/. 505,659.50 S/. 797,254.52 S/. 286,121.38 S/. 1,223,817.02 S/. 203,478.14 S/. 246,083.32 S/. 177,314.84 S/. 211,731.17 S/. 341,042.31 S/. 415,974.81 S/. 720,037.96 S/. 675,302.02 S/. 560,273.89 S/. 606,478.25 S/. 865,826.05 S/. 8,744,372.32
GASTOS GENERALES (10.00%) S/. 874,437.23 S/. 90,797.74 S/. 50,565.95 S/. 79,725.45 S/. 28,612.14 S/. 122,381.70 S/. 20,347.81 S/. 24,608.33 S/. 17,731.48 S/. 21,173.12 S/. 34,104.23 S/. 41,597.48 S/. 72,003.80 S/. 67,530.20 S/. 56,027.39 S/. 60,647.83 S/. 86,582.60 S/. 874,437.23
UTILIDAD (10.00%) S/. 874,437.23 S/. 90,797.74 S/. 50,565.95 S/. 79,725.45 S/. 28,612.14 S/. 122,381.70 S/. 20,347.81 S/. 24,608.33 S/. 17,731.48 S/. 21,173.12 S/. 34,104.23 S/. 41,597.48 S/. 72,003.80 S/. 67,530.20 S/. 56,027.39 S/. 60,647.83 S/. 86,582.60 S/. 874,437.23
SUB TOTAL S/. 10,493,246.78 S/. 1,089,572.85 S/. 606,791.40 S/. 956,705.42 S/. 343,345.66 S/. 1,468,580.42 S/. 244,173.76 S/. 295,299.98 S/. 212,777.80 S/. 254,077.41 S/. 409,250.77 S/. 499,169.77 S/. 864,045.56 S/. 810,362.42 S/. 672,328.67 S/. 727,773.91 S/. 1,038,991.25 S/. 10,493,246.78
I.G.V. (18.00%) S/. 1,888,784.42 S/. 196,123.11 S/. 109,222.45 S/. 172,206.98 S/. 61,802.22 S/. 264,344.48 S/. 43,951.28 S/. 53,154.00 S/. 38,300.00 S/. 45,733.93 S/. 73,665.14 S/. 89,850.56 S/. 155,528.20 S/. 145,865.24 S/. 121,019.16 S/. 130,999.30 S/. 187,018.43 S/. 1,888,784.42
PRESUPUESTO S/. 12,382,031.20 S/. 1,285,695.96 S/. 716,013.85 S/. 1,128,912.40 S/. 405,147.88 S/. 1,732,924.90 S/. 288,125.04 S/. 348,453.98 S/. 251,077.80 S/. 299,811.34 S/. 482,915.91 S/. 589,020.33 S/. 1,019,573.76 S/. 956,227.66 S/. 793,347.83 S/. 858,773.21 S/. 1,226,009.68 S/. 12,382,031.20
FACTOR DE RELACION (1.00) S/. 12,382,031.20 S/. 1,285,695.96 S/. 716,013.85 S/. 1,128,912.40 S/. 405,147.88 S/. 1,732,924.90 S/. 288,125.04 S/. 348,453.98 S/. 251,077.80 S/. 299,811.34 S/. 482,915.91 S/. 589,020.33 S/. 1,019,573.76 S/. 956,227.66 S/. 793,347.83 S/. 858,773.21 S/. 1,226,009.68 S/. 12,382,031.20
TOTAL PRESUPUESTO S/. 12,382,031.20 S/. 1,285,695.96 S/. 716,013.85 S/. 1,128,912.40 S/. 405,147.88 S/. 1,732,924.90 S/. 288,125.04 S/. 348,453.98 S/. 251,077.80 S/. 299,811.34 S/. 482,915.91 S/. 589,020.33 S/. 1,019,573.76 S/. 956,227.66 S/. 793,347.83 S/. 858,773.21 S/. 1,226,009.68 S/. 12,382,031.20
TOTAL PRESUPUESTO INC/IGV S/. 12,382,031.20 S/. 1,285,695.96 S/. 716,013.85 S/. 1,128,912.40 S/. 405,147.88 S/. 1,732,924.90 S/. 288,125.04 S/. 348,453.98 S/. 251,077.80 S/. 299,811.34 S/. 482,915.91 S/. 589,020.33 S/. 1,019,573.76 S/. 956,227.66 S/. 793,347.83 S/. 858,773.21 S/. 1,226,009.68 S/. 12,382,031.20

PENALIDADES

REINTEGROS PRESUPUESTO GENERAL

REINTEGROS NO CORRESPONDEN ADELANTO DIRECTO


REINTEGROS NO CORRESPONDEN ADELANTO MATERIALES

AMORTIZACION DE ADELANTO DIRECTO INC/IGV S/. 619,101.56 S/. 64,285.84 S/. 35,800.69 S/. 56,445.62 S/. 20,257.39 S/. 85,131.64 S/. 14,406.25 S/. 17,422.70 S/. 12,553.89 S/. 14,990.57 S/. 24,145.80 S/. 29,451.02 S/. 50,978.69 S/. 47,811.38 S/. 39,667.39 S/. 105,752.69 S/. - S/. 619,101.56
AMORTIZACION DE ADELANTO DE MATERIALES INC/IGV S/. 1,238,203.12 S/. 128,569.60 S/. 71,601.39 S/. 112,891.24 S/. 40,514.79 S/. 170,263.28 S/. 31,841.71 S/. 34,845.40 S/. 25,107.78 S/. 29,981.13 S/. 48,291.59 S/. 58,902.03 S/. 101,957.38 S/. 95,622.77 S/. 79,334.78 S/. 208,478.25 S/. - S/. 1,238,203.12
AMORTIZACION DEL SEGUNDO ADELANTO DE MATERIALES INC/IGV S/. 1,238,203.12 S/. 28,812.50 S/. 34,845.40 S/. 25,107.78 S/. 29,981.13 S/. 48,291.59 S/. 58,902.03 S/. 101,957.38 S/. 334,679.68 S/. 575,625.63 S/. - S/. - S/. 1,238,203.12

PAGO TOTAL AL CONTRATISTA S/. 1,092,840.52 S/. 608,611.77 S/. 959,575.54 S/. 344,375.70 S/. 1,477,529.98 S/. 213,064.58 S/. 261,340.48 S/. 188,308.35 S/. 224,858.51 S/. 362,186.93 S/. 441,765.25 S/. 764,680.31 S/. 478,113.83 S/. 98,720.04 S/. 544,542.27 S/. 1,226,009.68 S/. 9,286,523.40
I.G.V. (18.00%) S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. -
TOTAL PRESUPUESTO S/. 1,092,840.52 S/. 608,611.77 S/. 959,575.54 S/. 344,375.70 S/. 1,477,529.98 S/. 213,064.58 S/. 261,340.48 S/. 188,308.35 S/. 224,858.51 S/. 362,186.93 S/. 441,765.25 S/. 764,680.31 S/. 478,113.83 S/. 98,720.04 S/. 544,542.27 S/. 1,226,009.68 S/. 9,286,523.40

N° DE FACTURA 0001-000391 0001-000400 0001-000409 0001-000420 0001-000424 E001-12 E001-13 E001-14 E001-21 E001-22 E001-29 E001-32 E001-34 E001-37 E001-41 E001-48

TOTAL PAGADO AL CONTRATISTA S/. 608,611.77 S/. 959,575.54 S/. 344,375.70 S/. 1,457,444.41 S/. 213,064.58 S/. 261,340.48 S/. 188,308.35 S/. 224,858.51 S/. 362,186.93 S/. 441,765.25 S/. 764,680.31 S/. 478,113.83 S/. 98,720.04 S/. 544,542.27 S/. 1,226,009.68
CONSORCIO VIRGEN DEL CARMEN

RESUMEN DE VALORIZACIONES

OBRA : "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE MARGOS - HUANUCO - HUANUCO"

CONTRATO : N° 241-2017-MDM/A

MODALIDAD : A SUMA ALZADA

CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE

SUPERVISION DE OBRA : ING. JOEL ABIGAEL BEDON VASQUEZ

AVANCE PROGRAMADO AVANCE REAL


VALORIZACION
% Mensual % Acumulado Costo Mensual Acumulado % Mensual % Acumulado Costo Mensual Acumulado

1 Aug-17 4.10% 4.10% 507,663.28 507,663.28 10.38% 10.38% 1,285,695.96 1,285,695.96

2 Sep-17 5.75% 9.85% 711,966.79 1,219,630.07 5.78% 16.17% 716,013.85 2,001,709.81

3 Oct-17 7.25% 17.10% 897,697.26 2,117,327.34 9.12% 25.28% 1,128,912.40 3,130,622.21

4 Nov-17 8.64% 25.74% 1,069,807.50 3,187,134.83 3.27% 28.56% 405,147.88 3,535,770.09

5 Dec-17 9.91% 35.65% 1,227,059.29 4,414,194.12 14.00% 42.55% 1,732,924.90 5,268,694.99

6 Jan-18 6.71% 42.36% 830,834.29 5,245,028.42 2.33% 44.88% 288,125.04 5,556,820.03

7 Feb-18 6.03% 48.39% 746,636.48 5,991,664.90 2.81% 47.69% 348,453.98 5,905,274.01

8 Mar-18 7.61% 56.00% 942,272.57 6,933,937.47 2.03% 49.72% 251,077.80 6,156,351.81

9 Apr-18 7.15% 63.15% 885,315.23 7,819,252.70 2.42% 52.14% 299,811.34 6,456,163.15

10 May-18 4.22% 67.37% 522,521.72 8,341,774.42 3.90% 56.04% 482,915.91 6,939,079.06

11 Jun-18 6.29% 73.66% 778,829.76 9,120,604.18 4.76% 60.80% 589,020.33 7,528,099.39

12 Jul-18 8.12% 81.78% 1,005,420.93 10,126,025.12 8.23% 69.03% 1,019,573.76 8,547,673.15

13 Aug-18 4.85% 86.63% 600,528.51 10,726,553.63 7.72% 76.75% 956,227.66 9,503,900.81

14 Sep-18 5.11% 91.74% 632,721.79 11,359,275.42 6.41% 83.16% 793,347.83 10,297,248.64

15 Oct-18 4.15% 95.89% 513,854.29 11,873,129.72 6.94% 90.10% 858,773.21 11,156,021.85

16 Nov-18 4.11% 100.00% 508,901.48 12,382,031.20 9.90% 100.00% 1,226,009.68 12,382,031.20


ITEMS PARTIDAS COSTO

8,744,372.32
F 01 ARQUITECTURA Y SEÑALIZACIÓN 2,037,708.24
F 02 ESTRUCTURA 5,025,568.10
F 03 INSTALACIONES SANITARIAS 476,888.89
F 04 INSTALACIONES ELECTRICAS Y COMUNICACIÓN 801,608.31
F 05 INSTALACIONES ELECTROMECANICAS 219,710.48
F 06 SEGURIDAD 59,088.30
F 07 MITIGACION DE IMPACTO AMBIENTAL 123,800.00

SUB TOTAL 8,744,372.32


COSTO DIRECTO S/. 8,744,372.32
GASTOS GENERALES (10.00%) S/. 874,437.23
UTILIDAD (10.00%) S/. 874,437.23
SUB TOTAL S/. 10,493,246.78
I.G.V. (18.00%) S/. 1,888,784.42
PRESUPUESTO S/. 12,382,031.20
FACTOR DE RELACION (1.00) S/. 12,382,031.20
TOTAL PRESUPUESTO S/. 12,382,031.20
TOTAL PRESUPUESTO INC/IGV S/. 12,382,031.20
RESUMEN DE LIQUIDACIÓN

ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

PROCESO DE SELECCIÓN : LICITACION PÚBLICA N° 002-2017-MDM/CS


: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE MARGOS - HUANUCO -
NOMBRE DE LA OBRA
HUANUCO"

CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE

RESIDENTE DE LA OBRA : ING. FERNANDO ESPINOZA SOTO

SUPERVISOR DE LA OBRA : ING. JOEL ABIGAEL BEDON VASQUEZ

MONTO CONTRATADO - CONTRACTUAL 8,744,372.32 MONTO REAL DE LA JECUCIÓN - CONTRACTUAL 12,382,031.20

MONTOS MONTOS DIFERENCIA


No. CONCEPTO
RECALCULADOS PAGADOS A PAGAR
1.00 CONTRACTUAL
Pago Valorizacion N° 01 - AGOSTO 2017 1,092,840.52 1,092,840.52 0.00
Pago Valorizacion N° 02 - SEPTIEMBRE 2017 608,611.77 608,611.77 0.00
Pago Valorizacion N° 03 - OCTUBRE 2017 959,575.54 959,575.54 0.00
Pago Valorizacion N° 04 - NOVIEMBRE 2017 344,375.70 344,375.70 0.00
Pago Valorizacion N° 05 - DICIEMBRE 2017 1,477,529.98 1,457,444.41 20,085.57
Se hizo la detracción de la Factura N°000423 el cual fue anulado, sin embrago se debió
hacer la detracción de la Factura N°000424 el cual es de un monto menor, habiendo un
saldo a favor 11,019.23 11,019.23
Pago Valorizacion N° 06 - ENERO 2018 213,064.58 213,064.58 0.00
Pago Valorizacion N° 07 - FEBRERO 2018 261,340.48 261,340.48 0.00
Pago Valorizacion N° 08 - MARZO 2018 188,308.35 188,308.35 0.00
Pago Valorizacion N° 09 - ABRIL 2018 224,858.51 224,858.51 0.00
Pago Valorizacion N° 10 - MAYO 2018 362,186.93 362,186.93 0.00
Pago Valorizacion N° 11 - JUNIO 2018 441,765.25 441,765.25 0.00
Pago Valorizacion N° 12 - JULIO 2018 764,680.31 764,680.31 0.00
Pago Valorizacion N° 13 - AGOSTO 2018 478,113.83 478,113.83 0.00
Pago Valorizacion N° 14 - SETIEMBRE 2018 98,720.04 98,720.04 0.00
Pago Valorizacion N° 15 - OCTUBRE 2018 544,542.27 544,542.27 0.00
Pago Valorizacion N° 16 - NOVIEMBRE 2018 1,226,009.68 1,226,009.68 0.00
TOTAL 9,297,542.97 9,266,438.17 31,104.80

2.00 REAJUSTES - CONTRACTUAL


Pago Valorizacion N° 01 - AGOSTO 2017 11,161.92 0.00 11,161.92
Pago Valorizacion N° 02 - SEPTIEMBRE 2017 19,129.96 0.00 19,129.96
Pago Valorizacion N° 03 - OCTUBRE 2017 22,717.70 0.00 22,717.70
Pago Valorizacion N° 04 - NOVIEMBRE 2017 12,000.38 0.00 12,000.38
Pago Valorizacion N° 05 - DICIEMBRE 2017 38,167.51 0.00 38,167.51
Pago Valorizacion N° 06 - ENERO 2018 8,155.39 0.00 8,155.39
Pago Valorizacion N° 07 - FEBRERO 2018 1,856.34 0.00 1,856.34
Pago Valorizacion N° 08 - MARZO 2018 4,632.01 0.00 4,632.01
Pago Valorizacion N° 09 - ABRIL 2018 2,485.68 0.00 2,485.68
Pago Valorizacion N° 10 - MAYO 2018 6,899.50 0.00 6,899.50
Pago Valorizacion N° 11 - JUNIO 2018 33,832.98 0.00 33,832.98
Pago Valorizacion N° 12 - JULIO 2018 46,767.84 0.00 46,767.84
Pago Valorizacion N° 13 - AGOSTO 2018 24,860.31 0.00 24,860.31
Pago Valorizacion N° 14 - SETIEMBRE 2018 15,664.35 0.00 15,664.35
Pago Valorizacion N° 15 - OCTUBRE 2018 29,754.34 0.00 29,754.34
Pago Valorizacion N° 16 - NOVIEMBRE 2018 31,294.10 0.00 31,294.10
TOTAL 309,380.31 0.00 309,380.31
3.00 ADELANTOS OTORGADOS
ADELANTO DIRECTO 619,101.56 619,101.56 0.00
ADELANTO PARA MATERIALES 1,238,203.12 1,238,203.12 0.00
ADELANTO PARA MATERIALES (2) 1,238,203.12 1,238,203.12 0.00

4.00 DEDUCCION
ADELANTO DIRECTO 19,483.34 0.00 19,483.34
ADELANTO PARA MATERIALES 38,870.23 0.00 38,870.23
ADELANTO PARA MATERIALES (2) 40,549.65 0.00 40,549.65
TOTAL 98,903.22 0.00 98,903.22

5.00 INTERESES POR MORA DE PAGOS 2,036.18 0.00 2,036.18


6.00 MAYORES GASTOS GENERALES 209,080.81 0.00 209,080.81
7.00 GASTOS DEL PROCESO DE SELECCIÓN 0.00 0.00 0.00

MONTO DEL CONTRATO VIGENTE (S/.) 12,814,644.85 12,361,945.97 452,698.88


COSTO TOTAL DE LA OBRA (SIN. IGV) 12,814,644.85 12,361,945.97 452,698.88
PENALIDADES Y DESCUENTOS
POR SALDO POR
No. CONCEPTO DESCONTADO
DESCONTAR DESCONTAR
8.00 PENALIDADES 0.00 0.00 0.00
SALDO A FAVOR DEL CONTRATISTA 12,814,644.85 12,361,945.97 452,698.88
MONTOS MONTOS DIFERENCIA
No. CONCEPTO
RECALCULADOS PAGADOS A PAGAR
9.00 MONTO TOTAL DE LA LIQUIDACION DE OBRA 12,814,644.85 12,361,945.97 452,698.88

10.01 MONTO TOTAL A FACTURAR (INC IGV) C: 452,698.88


RESUMEN DE LIQUIDACIÓN ECONOMICA

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO


DE MARGOS - HUANUCO - HUANUCO"
►OBRA
►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE
►SUPERVISOR #NAME?
►JEFE DE SUPERVISION : ING. FERNANDO ESPINOZA SOTO
►RESIDENTE : ING. JOEL ABIGAEL BEDON VASQUEZ
►SISTEMA DE CONTRATACION : A SUMA ALZADA

MONTOS MONTOS DIFERENCIA


No. CONCEPTO
RECALCULADOS PAGADOS A PAGAR

1.00 CONTRACTUAL
MONTO CONTRATADO 9,297,542.97 9,266,438.17 0.00

MONTO DE CONTRATO FINAL 3,449,556.66 9,266,438.17 -5,816,881.51

#NAME? #NAME? #NAME? #NAME? #NAME?


(1) 0.00 #NAME? #NAME?
(2) 0.00 #NAME? #NAME?

TOTAL #NAME? #NAME? #NAME?

2.00 REINTEGRO
REAJUSTE DEL CONTRATO PRINCIPAL 309,380.31 0.00 309,380.31
#NAME? #NAME? #NAME? #NAME? #NAME?

TOTAL #NAME? #NAME? #NAME?

3.00 ADELANTOS OTORGADOS


ADELANTO DIRECTO 619,101.56
AMORTIZACION ADELANTO EN EFECTIVO 619,101.56 0.00
ADELANTO DE MATERIALES 1,238,203.12
AMORTIZACION ADELANTO MATERIALES 1,238,203.12 0.00
TOTAL 0.00 0.00

4.00 DEDUCCION DE REITEGROS


ADELANTO DIRECTO 16,511.30 0.00 16,511.30
ADELANTO DE MATERIALES 34,364.11 0.00 34,364.11
TOTAL 50,875.42 0.00 50,875.42

5.00 COSTOS ADICIONALES 0.00 0.00 0.00

6.00 MAYORES GASTOS GENERALES 177,187.13 0.00 177,187.13

7.00 INTERESES POR MORA DE PAGOS -7,887.47 0.00 -7,887.47

8.00 GASTOS DEL PROCESO DE SELECCIÓN 0.00 0.00 0.00

MONTO DEL CONTRATO VIGENTE (S/.) #NAME? #NAME? #NAME?


COSTO TOTAL DE LA OBRA #NAME? #NAME? #NAME?
PENALIDADES Y DESCUENTOS
POR SALDO POR
No. CONCEPTO DESCONTADO
DESCONTAR DESCONTAR

8.00 MULTA POR ATRASO DE OBRA 0.00 0.00 0.00

#NAME? #NAME? #NAME? #NAME?


RESUMEN DE LIQUIDACIÓN ECONOMICA

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO


DE MARGOS - HUANUCO - HUANUCO"
►OBRA
►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE
►SUPERVISOR #NAME?
►JEFE DE SUPERVISION : ING. FERNANDO ESPINOZA SOTO
►RESIDENTE : ING. JOEL ABIGAEL BEDON VASQUEZ
►SISTEMA DE CONTRATACION : A SUMA ALZADA

MONTOS MONTOS DIFERENCIA


No. CONCEPTO
RECALCULADOS PAGADOS A PAGAR

9.00 RENUNCIA VOLUNTARIA AL SALDO A FAVOR DEL CONTRATIS 0.00 0.00 0.00

MONTOS MONTOS DIFERENCIA


No. CONCEPTO
RECALCULADOS PAGADOS A PAGAR

10.00 MONTO TOTAL DE LA LIQUIDACION #NAME? #NAME? #NAME?

NOTA: Monto Final del Contrato Vigente, determinado con IGV de 18%, en concordancia a la Ley N° 29666 y en aplicación del
Comunicado N° 006-2011-OSCE/PRE sobre la reducción del IGV.

(1) Se realizo la emicion de la Factura F101-20 de fecha 23 de marzo del 2017, por el monto de S/. 3'064,211,57 I/IGV el cual
es por pago a cuenta del equipamiento; a la fecha, la referida factura no se realizo el pago total, por lo tanto el Consorcio
Unheval emite la Nota de Credito Electronica F101-70 de fecha 20 de Diciembre del 2017 por el monto no pagado de
S/.79,529.37 I/IGV; quedando como monto pagado S/. 2'529,391.69 S/IGV.
(2) Se realizo la emicion de la Factura F101-123 de fecha 08 de enero del 2017, por el monto de S/. 663,588.00 I/IGV el cual
es por pago a cuenta de la valorizacion N°05 del adicional N° 08 .
LIQUIDACION FINAL DEL CONTRATO DE OBRA
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE


MARGOS - HUANUCO - HUANUCO"
►OBRA
►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE
►SUPERVISOR : ING. JOEL ABIGAEL BEDON VASQUEZ
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

I AUTORIZADOS Y PAGADOS
1.1.0 AUTORIZADOS
1.1.1 CONTRACTUALES
CONTRATO PRINCIPAL S/. 9,297,542.97
1.1.2 REINTEGRO
CONTRATO PRINCIPAL S/. 309,380.31
1.1.3 DEDUCCION
Adelanto Directo (inlcuido en el reajuste contrato principal) S/. 19,483.34
Adelanto de Materiales( incluido en el reajuste contrato principal) S/. 38,870.23
Adelanto de Materiales 2 ( incluido en el reajuste contrato principal) S/. 40,549.65

1.1.4 COSTOS ADICIONALES S/. -


1.1.5 MAYORES GASTOS GENERALES S/. 209,080.81

1.1.6 INTERESES POR DEMORA DE PAGOS S/. 2,036.18 S/. 9,719,137.05


1.2.0 PAGADOS
1.2.1 CONTRACTUAL
CONTRATO PRINCIPAL
S/. 9,266,438.17
1.2.2 REITEGRO (REAJUSTE)
CONTRATO PRINCIPAL S/. -
1.2.3 DEDUCCION
Adelanto Directo (inlcuido en el reajuste contrato principal) S/. -
Adelanto de Materiales( incluido en el reajuste contrato principal) S/. -
1.2.4 COSTOS ADICIONALES S/. -
1.2.5 MAYORES GASTOS GENERALES S/. -
1.2.6 INTERESES POR DEMORA DE PAGOS S/. - S/. 9,266,438.17
SALDO A FAVOR DEL CONTRATISTA
En Efectivo S/. 452,698.88
II ADELANTOS (s/IGV)
2.1.0 CONCEDIDOS
2.1.1 Directo 619,101.56
2.1.2 Materiales 1,238,203.12
2.1.2 Materiales 1,238,203.12 S/. 3,095,507.80
2.2.0 AMORTIZADOS
2.2.1 Directo 619,101.56
2.2.2 Materiales 1,238,203.12
2.2.2 Materiales 1,238,203.12 S/. 3,095,507.80
SALDO A FAVOR DEL CONTRATISTA
En Efectivo S/. -

III GASTOS DEL PROCESO DE SELECCIÓN


3.1.0 EFECTUADOS S/. -
3.2.0 DESCONTADOS S/. -
SALDO A FAVOR DEL CONTRATISTA
S/. -
IV MULTA POR MORA EN EJECUCION DE OBRA
4.1.0 AUTORIZADOS S/. -
4.2.0 DESCONTADOS S/. -
SALDO A FAVOR DEL CONTRATISTA
S/. -
B. RESUMEN DE SALDOS (Expresado en Nuevos Soles)
A CARGO DEL CONTRATISTA A FAVOR DEL CONTRATISTA
No. CONCEPTO
EFECTIVO EFECTIVO
I AUTORIZADOS Y PAGADOS
En Efectivo S/. - S/. 452,698.88
II ADELANTOS S/. - S/. -
III GASTOS DEL PROCESO DE SELECCIÓN S/. - S/. -
IV MULTA POR MORA EN LA EJECUCION DE OBRA S/. - S/. -
TOTAL S/. S/. - S/. 452,698.88
SALDO A FAVOR DEL CONTRATISTA
- En Efectivo S/. 452,698.88

SALDO A CARGO DEL CONTRATISTA


- En Efectivo S/. 0.00

SALDO A FAVOR DEL CONTRATISTA S/. 452,698.88

RENUNCIA VOLUNTARIA AL SALDO A FAVOR DEL CONTRATISTA


- En Efectivo S/. 0.00
LIQUIDACION FINAL DEL CONTRATO DE OBRA
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE


MARGOS - HUANUCO - HUANUCO"
►OBRA
►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE
►SUPERVISOR : ING. JOEL ABIGAEL BEDON VASQUEZ
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

MONTO TOTAL DE LA LIQUIDACION S/. 452,698.88


CÁLCULO DE ÍNTERES
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS
PROCESO DE SELECCIÓN : LICITACION PÚBLICA N° 002-2017-MDM/CS
NOMBRE DE LA OBRA : "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE MARGOS - HUANUCO -
HUANUCO"
CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE
SUPERVISIÓN DE OBRA : ING. JOEL ABIGAEL BEDON VASQUEZ
RESIDENTE DE LA OBRA : ING. FERNANDO ESPINOZA SOTO
SUPERVISOR DE LA OBRA : ING. JOEL ABIGAEL BEDON VASQUEZ
MONTO CONTRATADO : 12,382,031.20 INC. IGV
BASE LEGAL : Artículo 197 del Reglamento de la Ley de Contrataciones del Estado, aprobado mediante Decreto Supremo N° 184-2008-EF.

TILEMN final: TASA DE INTERES LEGAL EFECTIVA EN MONEDA


NACIONAL, a la fecha real de pago de la valorización.
INTERESES LEGALES
I = Monto x ( TILEMN final / TILEMN inicio - 1)
ACUMULADOS: TILEMN inicio:TASA DE INTERES LEGAL EFECTIVA EN MONEDA
NACIONAL, a la fecha máxima de pago de la
valorización.
FECHA INICIO DE FECHA REAL TILEMN TILEMN
PAGOS DE VALORIZACIONES FECHA MAXIMA DE DIAS DE INTERESES
INTERES DE PAGO (Inicio) (Final)
PAGO MORA
Nº MES C.P N° FACTURAS N° MONTO (a) (b) (a) (b) I
CONTRACTUAL
1 AGOSTO 2017 0935,0937,0938,F 0001-000391 S/. 1,092,840.52 9/30/2017 10/1/2017 9/7/2017 0 0.00000 0.00000 0.00
2 SEPTIEMBRE 2017 01131, 01132 0001-000400 S/. 608,611.77 10/31/2017 11/1/2017 10/16/2017 0 0.00000 0.00000 0.00
3 OCTUBRE 2017 01264, 01265, 01266, 01267 0001-000409 S/. 959,575.54 11/30/2017 12/1/2017 11/7/2017 0 0.00000 0.00000 0.00
4 NOVIEMBRE 2017 01457,01458 0001-000420 S/. 344,375.70 12/31/2017 1/1/2018 12/13/2017 0 0.00000 0.00000 0.00
5 DICIEMBRE 2017 1451,1452,1453,1454,1455 0001-000424 S/. 1,457,444.41 1/31/2018 2/1/2018 12/29/2017 0 0.00000 0.00000 0.00
6 ENERO 2018 000658 E001-12 S/. 213,064.58 2/28/2018 3/1/2018 5/14/2018 75 7.34049 7.37406 974.40
7 FEBRERO 2018 000659 E001-13 S/. 261,340.48 3/31/2018 4/1/2018 5/14/2018 44 7.35477 7.37406 685.44
8 MARZO 2018 000662 E001-14 S/. 188,308.35 4/30/2018 5/1/2018 5/16/2018 16 7.36832 7.37494 169.18
9 ABRIL 2018 000803 E001-21 S/. 224,858.51 5/31/2018 6/1/2018 6/14/2018 14 7.38214 7.38808 180.93
10 MAYO 2018 000805,00807 E001-22 S/. 362,186.93 6/30/2018 7/1/2018 6/14/2018 0 0.00000 0.00000 0.00
11 JUNIO 2018 000964, 000963 E001-29 S/. 441,765.25 7/31/2018 8/1/2018 7/20/2018 0 0.00000 0.00000 0.00
12 JULIO 2018 0001083,001082,0001081 E001-32 S/. 764,680.31 8/31/2018 9/1/2018 8/9/2018 0 0.00000 0.00000 0.00
13 AGOSTO 2018 0001193,0001194 E001-34 S/. 478,113.83 9/30/2018 10/1/2018 9/17/2018 0 0.00000 0.00000 0.00
14 SETIEMBRE 2018 0001337 E001-37 S/. 98,720.04 10/31/2018 11/1/2018 11/5/2018 5 7.45328 7.45526 26.23
15 OCTUBRE 2018 - E001-41 S/. 544,542.27 11/30/2018 12/1/2018 11/13/2018 0 0.00000 0.00000 0.00
16 NOVIEMBRE 2018 - E001-48 S/. 1,226,009.28 12/31/2018 1/1/2019 12/20/2018 0 0.00000 0.00000 0.00

INTERESES A FAVOR DEL CONTRATISTA = 2,036.18

TOTAL DE INTERESES 2,036.18


Página 9
http://www.sbs.gob.pe/app/pp/EstadisticasSAEEPortal/Paginas/TILegalEfectiva.aspx

Página 10
RESUMEN CRONOGRAMA VALOR
OBRA

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE MARGOS - HUANUCO - HUANUCO"

MES 01 MES 02 MES 03 MES 04 MES 05 MES 06


ITEMS PARTIDAS COSTO 8/14/2017 9/1/2017 10/1/2017 11/1/2017 12/1/2017 1/1/2018
8/31/2017 9/30/2017 10/31/2017 11/30/2017 12/31/2017 1/31/2018
18 30 31 30 31 31

"MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL


CENTRO DE SALUD MARGOS, DISTRITO DE MARGOS - 8,744,372.32
HUANUCO - HUANUCO"
F 01 ARQUITECTURA Y SEÑALIZACIÓN 2,037,708.24 0.00 0.00 0.00 90,681.57 84,909.02 220,215.39
F 02 ESTRUCTURA 5,025,568.10 315,308.50 482,495.08 617,060.67 648,025.88 657,079.07 222,236.12
F 03 INSTALACIONES SANITARIAS 476,888.89 0.00 0.00 0.00 0.00 108,772.89 0.00
F 04 INSTALACIONES ELECTRICAS Y COMUNICACIÓN 801,608.31 0.00 0.00 0.00 0.00 0.00 130,489.55
F 05 INSTALACIONES ELECTROMECANICAS 219,710.48 0.00 0.00 0.00 0.00 0.00 0.00
F 06 SEGURIDAD 59,088.30 13,010.77 3,806.32 3,806.32 3,806.32 3,806.32 3,806.32
F 07 MITIGACION DE IMPACTO AMBIENTAL 123,800.00 30,200.00 16,500.00 13,100.00 13,000.00 12,000.00 10,000.00

SUB TOTAL 8,744,372.32 358,519.27 502,801.40 633,966.99 755,513.77 866,567.30 586,747.38


COSTO DIRECTO 8,744,372.32 358,519.27 502,801.40 633,966.99 755,513.77 866,567.30 586,747.38
GASTOS GENERALES (10.00%) 874,437.23 35,851.93 50,280.14 63,396.70 75,551.38 86,656.73 58,674.74
UTILIDAD (10.00%) 874,437.23 35,851.93 50,280.14 63,396.70 75,551.38 86,656.73 58,674.74
SUB TOTAL 10,493,246.78 430,223.12 603,361.68 760,760.39 906,616.52 1,039,880.76 704,096.86
I.G.V. (18.00%) 1,888,784.42 77,440.16 108,605.11 136,936.87 163,190.97 187,178.53 126,737.43
PRESUPUESTO 12,382,031.20 507,663.28 711,966.79 897,697.26 1,069,807.50 1,227,059.29 830,834.29
FACTOR DE RELACION (1.00) 12,382,031.20 507,663.28 711,966.79 897,697.26 1,069,807.50 1,227,059.29 830,834.29
TOTAL PRESUPUESTO 12,382,031.20 507,663.28 711,966.79 897,697.26 1,069,807.50 1,227,059.29 830,834.29
PORCENTAJE PARCIAL 4.10% 5.75% 7.25% 8.64% 9.91% 6.71%
PORCENTAJE ACUMULADO 4.10% 9.85% 17.10% 25.74% 35.65% 42.36%
CRONOGRAMA VALORIZADO

ANUCO"
TIEMPO DE EJECUCION
TOTAL
MES 07 MES 08 MES 09 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16
2/1/2018 3/1/2018 4/1/2018 5/15/2018 6/1/2018 7/1/2018 8/1/2018 9/1/2018 10/1/2018 11/1/2018
2/28/2018 3/31/2018 4/13/2018 5/31/2018 6/30/2018 7/31/2018 8/31/2018 9/30/2018 10/31/2018 11/27/2018 440
28 31 13 17 30 31 31 30 31 27

61,245.58 238,195.53 285,250.49 17,147.53 33,765.73 248,129.41 392,893.59 158,510.64 130,361.73 76,402.03 2,037,708.24
454,233.75 302,874.68 301,413.43 285,644.67 452,278.16 280,871.80 0.00 6,046.29 0.00 0.00 5,025,568.10
0.00 103,337.58 26,752.38 5,905.43 0.00 127,216.19 27,370.03 54,815.84 22,718.55 0.00 476,888.89
0.00 8,232.62 0.00 56,508.45 63,977.13 53,825.63 3,838.44 227,464.65 190,054.87 67,216.95 801,608.31
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,756.30 199,954.18 219,710.48
3,806.32 3,806.32 3,806.32 3,806.43 0.00 0.00 0.00 0.00 0.00 11,820.54 59,088.30
8,000.00 9,000.00 8,000.00 0.00 0.00 0.00 0.00 0.00 0.00 4,000.00 123,800.00

527,285.65 665,446.73 625,222.62 369,012.51 550,021.02 710,043.03 424,102.06 446,837.42 362,891.45 359,393.70 8,744,372.32
527,285.65 665,446.73 625,222.62 369,012.51 550,021.02 710,043.03 424,102.06 446,837.42 362,891.45 359,393.70 8,744,372.32
52,728.57 66,544.67 62,522.26 36,901.25 55,002.10 71,004.30 42,410.21 44,683.74 36,289.15 35,939.37 874,437.23
52,728.57 66,544.67 62,522.26 36,901.25 55,002.10 71,004.30 42,410.21 44,683.74 36,289.15 35,939.37 874,437.23
632,742.78 798,536.08 750,267.14 442,815.01 660,025.22 852,051.64 508,922.47 536,204.90 435,469.74 431,272.44 10,493,246.78
113,893.70 143,736.49 135,048.09 79,706.71 118,804.54 153,369.29 91,606.04 96,516.88 78,384.55 77,629.04 1,888,784.42
746,636.48 942,272.57 885,315.23 522,521.72 778,829.76 1,005,420.93 600,528.51 632,721.79 513,854.29 508,901.48 12,382,031.20
746,636.48 942,272.57 885,315.23 522,521.72 778,829.76 1,005,420.93 600,528.51 632,721.79 513,854.29 508,901.48 12,382,031.20
746,636.48 942,272.57 885,315.23 522,521.72 778,829.76 1,005,420.93 600,528.51 632,721.79 513,854.29 508,901.48 12,382,031.20
6.03% 7.61% 7.15% 4.22% 6.29% 8.12% 4.85% 5.11% 4.15% 4.11% 100.00%
48.39% 56.00% 63.15% 8.32% 14.61% 22.73% 27.58% 32.69% 36.84% 26.84%
FORMULAS POLINOMICAS CONTRACTUAL
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 01 ARQUITECTURA Y SEÑALIZACIÓN

K = 0.057*(Mr / Mo) + 0.062*(Ar / Ao) + 0.137*(Dr / Do) + 0.144*(Ir / Io) + 0.218*(Ar / Ao) + 0.382*(Mr / Mo)

MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI


IU INCIDENCIA INCIDENCIA Material
1 M 49 MAQUINARIA Y EQUIPO IMPORTADO 0.057 100.000% 0.057
2 A 02 ACERO DE CONSTRUCCIÓN LISO 0.062 100.000% 0.062
3 D 30 DÓLAR (GENERAL PONDERADO) 0.137 100.000% 0.137
4 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.144 100.000% 0.144
5 A 04 AGREGADO FINO 0.218 100.000% 0.218
6 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.382 100.000% 0.382
Ʃ 1.000
FORMULA N° 2 ESTRUCTURA

K = 0.050*(Fr / Fo) + 0.074*(Ir / Io) + 0.094*(Ar / Ao) + 0.112*(Tr / To) + 0.125*(Mr / Mo) + 0.182*(Ar / Ao) + 0.363*(Mr / Mo)

MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI


IU INCIDENCIA INCIDENCIA Material
1 F 32 FLETE TERRESTRE 0.050 100.000% 0.050
2 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.074 100.000% 0.074
3 A 02 ACERO DE CONSTRUCCION LISO 0.094 100.000% 0.094
4 T 65 TUBERIA DE ACERO NEGRO Y/O GALVANIZADO 0.112 100.000% 0.112
5 M 48 MAQUINARIA Y EQUIPO NACIONAL 0.125 100.000% 0.125
6 A 05 AGREGADO GRUESO 0.182 100.000% 0.182
7 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.363 100.000% 0.363
Ʃ 1.000

FORMULA N° 3 INSTALACIONES SANITARIAS

K = 0.077*(Ir / Io) + 0.091*(Ar / Ao) + 0.108*(Mr / Mo) + 0.112*(Tr / To) + 0.182*(Ar / Ao) + 0.430*(Mr / Mo)

MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI


IU INCIDENCIA INCIDENCIA Material
1 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.077 100.000% 0.077
2 A 04 AGREGADO FINO 0.091 100.000% 0.091
3 M 48 MAQUINARIA Y EQUIPO NACIONAL 0.108 100.000% 0.108
4 T 72 TUBERIA DE PVC PARA AGUA 0.112 100.000% 0.112
5 A 02 ACERO DE CONSTRUCCION LISO 0.182 100.000% 0.182
6 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.430 100.000% 0.430
Ʃ 1.000

FORMULA N° 4 INSTALACIONES ELECTRICAS Y COMUNICACIÓN

K = 0.057*(Ar / Ao) + 0.063*(Fr / Fo) + 0.087*(Mr / Mo) + 0.130*(Dr / Do) + 0.182*(Mr / Mo) + 0.222*(Ir / Io) + 0.259*(Ar / Ao)

MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI


IU INCIDENCIA INCIDENCIA Material
1 A 02 ACERO DE CONSTRUCCION LISO 0.057 100.000% 0.057
2 F 32 FLETE TERRESTRE 0.063 100.000% 0.063
3 M 48 MAQUINARIA Y EQUIPO NACIONAL 0.087 100.000% 0.087
4 D 30 DÓLAR (GENERAL PONDERADO) 0.130 100.000% 0.130
5 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.182 100.000% 0.182
6 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.222 100.000% 0.222
7 A 06 ALAMBRE Y CABLE DE COBRE DESNUDO 0.259 100.000% 0.259
Ʃ 1.000

Página 13
FORMULAS POLINOMICAS CONTRACTUAL
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 5 INSTALACIONES ELECTROMECANICAS


K = 1*(Dr / Do)

MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI


IU INCIDENCIA INCIDENCIA Material

1 D 30 DOLAR (GENERAL PONDERADO) 1.000 100.000% 1.000


Ʃ 1.000

FORMULA N° 6 SEGURIDAD
K = 0.203*(Dr / Do) + 0.224*(Mr / Mo) + 0.275*(Ir / Io) + 0.298*(Hr / Ho)

MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI


IU INCIDENCIA INCIDENCIA Material

1 D 30 DOLAR (GENERAL PONDERADO) 0.203 100.000% 0.203


2 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.224 100.000% 0.224
3 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.275 100.000% 0.275
4 H 37 HERRAMIENTA MANUAL 0.298 100.000% 0.298
Ʃ 1.000

FORMULA N° 7 MITIGACION DE IMPACTO AMBIENTAL


K = 0.066*(Mr / Mo) + 0.934*(Ir / Io)

MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI


IU INCIDENCIA INCIDENCIA Material

1 D 47 MANO DE OBRA INC. LEYES SOCIALES 0.066 100.000% 0.066


2 M 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.934 100.000% 0.934
Ʃ 1.000

Página 14
CALCULO DE LOS COEFICIENTES DE REAJUSTES (K)
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 1 ARQUITECTURA Y SEÑALIZACIÓN


K = 0.057*(Mr / Mo) + 0.062*(Ar / Ao) + 0.137*(Dr / Do) + 0.144*(Ir / Io) + 0.218*(Ar / Ao) + 0.382*(Mr / Mo)

VAL 01 - AGO 2017 VAL 02- SET 2017 VAL 03- OCT 2017 VAL 04- NOV 2017 VAL 05 - DIC 2017 VAL 06 - ENE 2018 VAL 07 - FEB 2018 VAL 08 - MAR 2018 VAL 09 - ABR 2019 VAL 10 - MAY 2018 VAL 11 - JUN 2018 VAL 12 - JUL 2018 VAL 13 - AGO 2018 VAL 14 - SET 2018 VAL 15 - OCT 2018 VAL 16 - NOV 2018
MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI Io IND. ADEL. EFECT. (Ia) IND. ADEL. MAT. (Ia) IND. ADEL. MAT. (Ia) SETIEMBRE 2017 (Ir) OCTUBRE 2017 (Ir) NOVIEMBRE 2017 (Ir) DICIEMBRE 2017 (Ir) ENERO 2018 (Ir) FEBRERO 2018 (Ir) MARZO 2018 (Ir) ABRIL 2018 (Ir) MAYO 2018 (Ir) JUNIO 2018 (Ir) JULIO 2019 (Ir) AGOSTO 2018 (Ir) SETIEMBRE 2018 (Ir) OCTUBRE 2018 (Ir) NOVIEMBRE 2018 (Ir) DICIEMBRE 2018 (Ir)
IU INCIDENCIA INCIDENCIA Material FEB ´17 AGO ´17 COEFIC. AGO ´17 COEFIC. DIC´17 COEFIC. Sep-17 COEFIC. Oct-17 COEFIC. Nov-17 COEFIC. Dec-17 COEFIC. Jan-18 COEFIC. Feb-18 COEFIC. Mar-18 COEFIC. Apr-18 COEFIC. May-18 COEFIC. Jun-18 COEFIC. Jul-19 COEFIC. Aug-18 COEFIC. Sep-18 COEFIC. Oct-18 COEFIC. Nov-18 COEFIC. Dec-18 COEFIC.
1 M 49 MAQUINARIA Y EQUIPO IMPORTADO 0.057 100.000% 0.057 293.65 292.36 0.057 292.36 0.057 293.24 0.057 293.03 0.057 293.18 0.057 292.27 0.057 293.24 0.057 290.65 0.056 294.48 0.057 295.18 0.057 294.12 0.057 298.68 0.058 298.83 0.058 299.69 0.058 302.20 0.059 304.74 0.059 307.20 0.060 311.07 0.060 311.16 0.060
2 A 02 ACERO DE CONSTRUCCIÓN LISO 0.062 100.000% 0.062 468.50 474.70 0.063 474.70 0.063 491.28 0.065 485.11 0.064 488.45 0.065 482.69 0.064 491.28 0.065 497.78 0.066 528.59 0.070 529.67 0.070 526.55 0.070 534.75 0.071 532.76 0.071 532.40 0.070 546.81 0.072 550.63 0.073 555.22 0.073 560.33 0.074 560.07 0.074
3 D 30 DÓLAR (GENERAL PONDERADO) 0.137 100.000% 0.137 461.49 462.48 0.137 462.48 0.137 466.75 0.139 464.58 0.138 467.61 0.139 465.87 0.138 466.75 0.139 462.02 0.137 469.31 0.139 471.87 0.140 469.88 0.139 478.04 0.142 479.58 0.142 481.37 0.143 483.02 0.143 486.67 0.144 490.47 0.146 497.53 0.148 494.24 0.147
4 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.144 100.000% 0.144 438.80 444.64 0.146 444.64 0.146 442.30 0.145 444.57 0.146 442.48 0.145 441.61 0.145 442.30 0.145 442.87 0.145 443.97 0.146 446.14 0.146 445.52 0.146 445.61 0.146 447.10 0.147 448.81 0.147 449.40 0.147 450.26 0.148 450.63 0.148 451.18 0.148 452.00 0.148
5 A 04 AGREGADO FINO 0.218 100.000% 0.218 1067.44 1,041.51 0.213 1,041.51 0.213 1,035.47 0.211 1,035.99 0.212 1,036.19 0.212 1,038.03 0.212 1,035.47 0.211 1,038.06 0.212 1,041.37 0.213 1,036.83 0.212 1,039.22 0.212 1,036.79 0.212 1,036.79 0.212 1,036.46 0.212 1,036.18 0.212 1,036.45 0.212 1,041.35 0.213 1,045.57 0.214 1,049.40 0.214
6 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.382 100.000% 0.382 563.25 580.90 0.394 580.90 0.394 580.90 0.394 580.90 0.394 580.90 0.394 580.90 0.394 580.90 0.394 582.52 0.395 582.52 0.395 582.52 0.395 582.52 0.395 582.52 0.395 602.11 0.408 602.11 0.408 602.11 0.408 602.11 0.408 602.11 0.408 602.11 0.408 602.11 0.408
Ʃ 1.000000 Ka(AGO )= 1.010 Ka(AGO )= 1.010 Ka(DIC )= 1.011 Kr(SET )= 1.011 Kr(OCT )= 1.012 Kr(NOV )= 1.010 Kr(DIC )= 1.011 Kr(ENE )= 1.011 Kr(FEB )= 1.020 Kr(MAR )= 1.020 Kr(ABR )= 1.019 Kr(MAY )= 1.024 Kr(JUN )= 1.038 Kr(JUL )= 1.038 Kr(AGO )= 1.041 Kr(SET )= 1.044 Kr(OCT )= 1.048 Kr(NOV )= 1.052 Kr(DIC )= 1.051

FORMULA N° 2 ESTRUCTURA
K = 0.050*(Fr / Fo) + 0.074*(Ir / Io) + 0.094*(Ar / Ao) + 0.112*(Tr / To) + 0.125*(Mr / Mo) + 0.182*(Ar / Ao) + 0.363*(Mr / Mo)

VAL 01 - AGO 2017 VAL 02- SET 2017 VAL 03- OCT 2017 VAL 04- NOV 2017 VAL 05 - DIC 2017 VAL 06 - ENE 2018 VAL 07 - FEB 2018 VAL 08 - MAR 2018 VAL 09 - ABR 2019 VAL 10 - MAY 2018 VAL 11 - JUN 2018 VAL 12 - JUL 2018 VAL 13 - AGO 2018 VAL 14 - SET 2018 VAL 15 - OCT 2018 VAL 16 - NOV 2018
MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI Io IND. ADEL. EFECT. (Ia) IND. ADEL. MAT. (Ia) IND. ADEL. MAT. (Ia) SETIEMBRE 2017 (Ir) OCTUBRE 2017 (Ir) NOVIEMBRE 2017 (Ir) DICIEMBRE 2017 (Ir) ENERO 2018 (Ir) FEBRERO 2018 (Ir) MARZO 2018 (Ir) ABRIL 2018 (Ir) MAYO 2018 (Ir) JUNIO 2018 (Ir) JULIO 2019 (Ir) AGOSTO 2018 (Ir) SETIEMBRE 2018 (Ir) OCTUBRE 2018 (Ir) NOVIEMBRE 2018 (Ir) DICIEMBRE 2018 (Ir)
IU INCIDENCIA INCIDENCIA Material FEB ´17 AGO ´17 COEFIC. AGO ´17 COEFIC. DIC´17 COEFIC. Sep-17 COEFIC. Oct-17 COEFIC. Nov-17 COEFIC. Dec-17 COEFIC. Jan-18 COEFIC. Feb-18 COEFIC. Mar-18 COEFIC. Apr-18 COEFIC. May-18 COEFIC. Jun-18 COEFIC. Jul-19 COEFIC. Aug-18 COEFIC. Sep-18 COEFIC. Oct-18 COEFIC. Nov-18 COEFIC. Dec-18 COEFIC.
1 F 32 FLETE TERRESTRE 0.050 100.000% 0.050 463.60 467.18 0.050 467.18 0.050 468.42 0.051 468.00 0.050 468.00 0.050 468.00 0.050 468.42 0.051 468.42 0.051 468.42 0.051 468.41 0.051 468.41 0.051 468.41 0.051 470.47 0.051 470.47 0.051 470.47 0.051 468.39 0.051 468.39 0.051 468.39 0.051 469.40 0.051
2 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.074 100.000% 0.074 438.80 444.64 0.075 444.64 0.075 442.30 0.075 444.57 0.075 442.48 0.075 441.61 0.074 442.30 0.075 442.87 0.075 443.97 0.075 446.14 0.075 445.52 0.075 445.61 0.075 447.10 0.075 448.81 0.076 449.40 0.076 450.26 0.076 450.63 0.076 451.18 0.076 452.00 0.076
3 A 02 ACERO DE CONSTRUCCION LISO 0.094 100.000% 0.094 468.50 474.70 0.095 474.70 0.095 491.28 0.099 485.11 0.097 488.45 0.098 482.69 0.097 491.28 0.099 497.78 0.100 528.59 0.106 529.67 0.106 526.55 0.106 534.75 0.107 532.76 0.107 532.40 0.107 546.81 0.110 550.63 0.110 555.22 0.111 560.33 0.112 560.07 0.112
4 T 65 TUBERIA DE ACERO NEGRO Y/O GALVANIZADO 0.112 100.000% 0.112 215.22 216.20 0.113 216.20 0.113 244.12 0.127 228.52 0.119 235.92 0.123 233.92 0.122 244.12 0.127 245.62 0.128 246.90 0.128 243.56 0.127 247.66 0.129 250.41 0.130 250.53 0.130 254.51 0.132 253.41 0.132 256.39 0.133 257.21 0.134 259.07 0.135 262.51 0.137
5 M 48 MAQUINARIA Y EQUIPO NACIONAL 0.125 100.000% 0.125 365.19 366.02 0.125 366.02 0.125 363.24 0.124 366.18 0.125 363.30 0.124 363.07 0.124 363.24 0.124 363.04 0.124 362.79 0.124 365.55 0.125 365.01 0.125 368.95 0.126 368.82 0.126 369.08 0.126 369.15 0.126 372.23 0.127 370.70 0.127 371.13 0.127 370.72 0.127
6 A 05 AGREGADO GRUESO 0.182 100.000% 0.182 414.50 416.99 0.183 416.99 0.183 421.04 0.185 420.47 0.185 418.45 0.184 420.51 0.185 421.04 0.185 423.40 0.186 426.06 0.187 422.53 0.186 420.58 0.185 422.12 0.185 423.80 0.186 425.85 0.187 425.00 0.187 426.88 0.187 424.45 0.186 426.74 0.187 428.54 0.188
7 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.363 100.000% 0.363 563.25 580.90 0.374 580.90 0.374 580.90 0.374 580.90 0.374 580.90 0.374 580.90 0.374 580.90 0.374 582.52 0.375 582.52 0.375 582.52 0.375 582.52 0.375 582.52 0.375 602.11 0.388 602.11 0.388 602.11 0.388 602.11 0.388 602.11 0.388 602.11 0.388 602.11 0.388
Ʃ 1.000000 Ka(AGO )= 1.015 Ka(AGO )= 1.015 Ka(DIC )= 1.035 Kr(SET )= 1.025 Kr(OCT )= 1.028 Kr(NOV )= 1.026 Kr(DIC )= 1.035 Kr(ENE )= 1.039 Kr(FEB )= 1.046 Kr(MAR )= 1.045 Kr(ABR )= 1.046 Kr(MAY )= 1.049 Kr(JUN )= 1.063 Kr(JUL )= 1.067 Kr(AGO )= 1.070 Kr(SET )= 1.072 Kr(OCT )= 1.073 Kr(NOV )= 1.076 Kr(DIC )= 1.079

FORMULA N° 3 INSTALACIONES SANITARIAS


K = 0.077*(Ir / Io) + 0.091*(Ar / Ao) + 0.108*(Mr / Mo) + 0.112*(Tr / To) + 0.182*(Ar / Ao) + 0.430*(Mr / Mo)

VAL 01 - AGO 2017 VAL 02- SET 2017 VAL 03- OCT 2017 VAL 04- NOV 2017 VAL 05 - DIC 2017 VAL 06 - ENE 2018 VAL 07 - FEB 2018 VAL 08 - MAR 2018 VAL 09 - ABR 2019 VAL 10 - MAY 2018 VAL 11 - JUN 2018 VAL 12 - JUL 2018 VAL 13 - AGO 2018 VAL 14 - SET 2018 VAL 15 - OCT 2018 VAL 16 - NOV 2018
MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI Io IND. ADEL. EFECT. (Ia) IND. ADEL. MAT. (Ia) IND. ADEL. MAT. (Ia) SETIEMBRE 2017 (Ir) OCTUBRE 2017 (Ir) NOVIEMBRE 2017 (Ir) DICIEMBRE 2017 (Ir) ENERO 2018 (Ir) FEBRERO 2018 (Ir) MARZO 2018 (Ir) ABRIL 2018 (Ir) MAYO 2018 (Ir) JUNIO 2018 (Ir) JULIO 2019 (Ir) AGOSTO 2018 (Ir) SETIEMBRE 2018 (Ir) OCTUBRE 2018 (Ir) NOVIEMBRE 2018 (Ir) DICIEMBRE 2018 (Ir)
IU INCIDENCIA INCIDENCIA Material FEB ´17 AGO ´17 COEFIC. AGO ´17 COEFIC. DIC´17 COEFIC. Sep-17 COEFIC. Oct-17 COEFIC. Nov-17 COEFIC. Dec-17 COEFIC. Jan-18 COEFIC. Feb-18 COEFIC. Mar-18 COEFIC. Apr-18 COEFIC. May-18 COEFIC. Jun-18 COEFIC. Jul-19 COEFIC. Aug-18 COEFIC. Sep-18 COEFIC. Oct-18 COEFIC. Nov-18 COEFIC. Dec-18 COEFIC.
1 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.077 100.000% 0.077 438.80 444.64 0.078 444.64 0.078 442.30 0.078 444.57 0.078 442.48 0.078 441.61 0.077 442.30 0.078 442.87 0.078 443.97 0.078 446.14 0.078 445.52 0.078 445.61 0.078 447.10 0.078 448.81 0.079 449.40 0.079 450.26 0.079 450.63 0.079 451.18 0.079 452.00 0.079
2 A 04 AGREGADO FINO 0.091 100.000% 0.091 1067.44 1,041.51 0.089 1,041.51 0.089 1,035.47 0.088 1,035.99 0.088 1,036.19 0.088 1,038.03 0.088 1,035.47 0.088 1,038.06 0.088 1,041.37 0.089 1,036.83 0.088 1,039.22 0.089 1,036.79 0.088 1,036.79 0.088 1,036.46 0.088 1,036.18 0.088 1,036.45 0.088 1,041.35 0.089 1,045.57 0.089 1,049.40 0.089
3 M 48 MAQUINARIA Y EQUIPO NACIONAL 0.108 100.000% 0.108 365.19 366.02 0.108 366.02 0.108 363.24 0.107 366.18 0.108 363.30 0.107 363.07 0.107 363.24 0.107 363.04 0.107 362.79 0.107 365.55 0.108 365.01 0.108 368.95 0.109 368.82 0.109 369.08 0.109 369.15 0.109 372.23 0.110 370.70 0.110 371.13 0.110 370.72 0.110
4 T 72 TUBERIA DE PVC PARA AGUA 0.112 100.000% 0.112 412.75 416.90 0.113 416.90 0.113 426.06 0.116 416.95 0.113 426.35 0.116 425.95 0.116 426.06 0.116 424.54 0.115 424.19 0.115 427.74 0.116 429.31 0.116 431.66 0.117 434.23 0.118 434.41 0.118 435.02 0.118 436.21 0.118 437.54 0.119 439.71 0.119 432.82 0.117
5 A 02 ACERO DE CONSTRUCCION LISO 0.182 100.000% 0.182 468.50 474.70 0.184 474.70 0.184 491.28 0.191 485.11 0.188 488.45 0.190 482.69 0.188 491.28 0.191 497.78 0.193 528.59 0.205 529.67 0.206 526.55 0.205 534.75 0.208 532.76 0.207 532.40 0.207 546.81 0.212 550.63 0.214 555.22 0.216 560.33 0.218 560.07 0.218
6 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.430 100.000% 0.430 563.25 580.90 0.443 580.90 0.443 580.90 0.443 580.90 0.443 580.90 0.443 580.90 0.443 580.90 0.443 582.52 0.445 582.52 0.445 582.52 0.445 582.52 0.445 582.52 0.445 602.11 0.460 602.11 0.460 602.11 0.460 602.11 0.460 602.11 0.460 602.11 0.460 602.11 0.460
Ʃ 1.000000 Ka(AGO )= 1.015 Ka(AGO )= 1.015 Ka(DIC )= 1.023 Kr(SET )= 1.018 Kr(OCT )= 1.022 Kr(NOV )= 1.019 Kr(DIC )= 1.023 Kr(ENE )= 1.026 Kr(FEB )= 1.039 Kr(MAR )= 1.041 Kr(ABR )= 1.041 Kr(MAY )= 1.045 Kr(JUN )= 1.060 Kr(JUL )= 1.061 Kr(AGO )= 1.066 Kr(SET )= 1.069 Kr(OCT )= 1.073 Kr(NOV )= 1.075 Kr(DIC )= 1.073

FORMULA N° 4 INSTALACIONES ELECTRICAS Y COMUNICACIÓN


K = 0.057*(Ar / Ao) + 0.063*(Fr / Fo) + 0.087*(Mr / Mo) + 0.130*(Dr / Do) + 0.182*(Mr / Mo) + 0.222*(Ir / Io) + 0.259*(Ar / Ao)

VAL 01 - AGO 2017 VAL 02- SET 2017 VAL 03- OCT 2017 VAL 04- NOV 2017 VAL 05 - DIC 2017 VAL 06 - ENE 2018 VAL 07 - FEB 2018 VAL 08 - MAR 2018 VAL 09 - ABR 2019 VAL 10 - MAY 2018 VAL 11 - JUN 2018 VAL 12 - JUL 2018 VAL 13 - AGO 2018 VAL 14 - SET 2018 VAL 15 - OCT 2018 VAL 16 - NOV 2018
MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI Io IND. ADEL. EFECT. (Ia) IND. ADEL. MAT. (Ia) IND. ADEL. MAT. (Ia) SETIEMBRE 2017 (Ir) OCTUBRE 2017 (Ir) NOVIEMBRE 2017 (Ir) DICIEMBRE 2017 (Ir) ENERO 2018 (Ir) FEBRERO 2018 (Ir) MARZO 2018 (Ir) ABRIL 2018 (Ir) MAYO 2018 (Ir) JUNIO 2018 (Ir) JULIO 2019 (Ir) AGOSTO 2018 (Ir) SETIEMBRE 2018 (Ir) OCTUBRE 2018 (Ir) NOVIEMBRE 2018 (Ir) DICIEMBRE 2018 (Ir)
IU INCIDENCIA INCIDENCIA Material FEB ´17 AGO ´17 COEFIC. AGO ´17 COEFIC. DIC´17 COEFIC. Sep-17 COEFIC. Oct-17 COEFIC. Nov-17 COEFIC. Dec-17 COEFIC. Jan-18 COEFIC. Feb-18 COEFIC. Mar-18 COEFIC. Apr-18 COEFIC. May-18 COEFIC. Jun-18 COEFIC. Jul-19 COEFIC. Aug-18 COEFIC. Sep-18 COEFIC. Oct-18 COEFIC. Nov-18 COEFIC. Dec-18 COEFIC.

1 A 02 ACERO DE CONSTRUCCION LISO 0.057 100.000% 0.057 468.50 474.70 0.058 474.70 0.058 491.28 0.060 485.11 0.059 488.45 0.059 482.69 0.059 491.28 0.060 497.78 0.061 528.59 0.064 529.67 0.064 526.55 0.064 534.75 0.065 532.76 0.065 532.40 0.065 546.81 0.067 550.63 0.067 555.22 0.068 560.33 0.068 560.07 0.068
2 F 32 FLETE TERRESTRE 0.063 100.000% 0.063 463.60 467.18 0.063 467.18 0.063 468.42 0.064 468.00 0.064 468.00 0.064 468.00 0.064 468.42 0.064 468.42 0.064 468.42 0.064 468.41 0.064 468.41 0.064 468.41 0.064 470.47 0.064 470.47 0.064 470.47 0.064 468.39 0.064 468.39 0.064 468.39 0.064 469.40 0.064
3 M 48 MAQUINARIA Y EQUIPO NACIONAL 0.087 100.000% 0.087 365.19 366.02 0.087 366.02 0.087 363.24 0.087 366.18 0.087 363.30 0.087 363.07 0.086 363.24 0.087 363.04 0.086 362.79 0.086 365.55 0.087 365.01 0.087 368.95 0.088 368.82 0.088 369.08 0.088 369.15 0.088 372.23 0.089 370.70 0.088 371.13 0.088 370.72 0.088
4 D 30 DÓLAR (GENERAL PONDERADO) 0.130 100.000% 0.130 461.49 462.48 0.130 462.48 0.130 466.75 0.131 464.58 0.131 467.61 0.132 465.87 0.131 466.75 0.131 462.02 0.130 469.31 0.132 471.87 0.133 469.88 0.132 478.04 0.135 479.58 0.135 481.37 0.136 483.02 0.136 486.67 0.137 490.47 0.138 497.53 0.140 494.24 0.139
5 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.182 100.000% 0.182 563.25 580.90 0.188 580.90 0.188 580.90 0.188 580.90 0.188 580.90 0.188 580.90 0.188 580.90 0.188 582.52 0.188 582.52 0.188 582.52 0.188 582.52 0.188 582.52 0.188 602.11 0.195 602.11 0.195 602.11 0.195 602.11 0.195 602.11 0.195 602.11 0.195 602.11 0.195
6 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.222 100.000% 0.222 438.80 444.64 0.225 444.64 0.225 442.30 0.224 444.57 0.225 442.48 0.224 441.61 0.223 442.30 0.224 442.87 0.224 443.97 0.225 446.14 0.226 445.52 0.225 445.61 0.225 447.10 0.226 448.81 0.227 449.40 0.227 450.26 0.228 450.63 0.228 451.18 0.228 452.00 0.229
7 A 06 ALAMBRE Y CABLE DE COBRE DESNUDO 0.259 100.000% 0.259 831.00 847.68 0.264 847.68 0.264 915.64 0.285 892.79 0.278 899.02 0.280 907.22 0.283 915.64 0.285 925.49 0.288 944.54 0.294 943.48 0.294 932.93 0.291 945.80 0.295 939.31 0.293 944.94 0.295 928.00 0.289 923.10 0.288 925.71 0.289 940.07 0.293 937.20 0.292
Ʃ 1.000000 Ka(AGO )= 1.015 Ka(AGO )= 1.015 Ka(DIC )= 1.039 Kr(SET )= 1.032 Kr(OCT )= 1.034 Kr(NOV )= 1.034 Kr(DIC )= 1.039 Kr(ENE )= 1.041 Kr(FEB )= 1.053 Kr(MAR )= 1.056 Kr(ABR )= 1.051 Kr(MAY )= 1.060 Kr(JUN )= 1.066 Kr(JUL )= 1.070 Kr(AGO )= 1.066 Kr(SET )= 1.068 Kr(OCT )= 1.070 Kr(NOV )= 1.076 Kr(DIC )= 1.075
FORMULA N° 5 INSTALACIONES ELECTROMECANICAS
K = 1*(Dr / Do)

VAL 01 - AGO 2017 VAL 02- SET 2017 VAL 03- OCT 2017 VAL 04- NOV 2017 VAL 05 - DIC 2017 VAL 06 - ENE 2018 VAL 07 - FEB 2018 VAL 08 - MAR 2018 VAL 09 - ABR 2019 VAL 10 - MAY 2018 VAL 11 - JUN 2018 VAL 12 - JUL 2018 VAL 13 - AGO 2018 VAL 14 - SET 2018 VAL 15 - OCT 2018 VAL 16 - NOV 2018
MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI Io IND. ADEL. EFECT. (Ia) IND. ADEL. MAT. (Ia) IND. ADEL. MAT. (Ia) SETIEMBRE 2017 (Ir) OCTUBRE 2017 (Ir) NOVIEMBRE 2017 (Ir) DICIEMBRE 2017 (Ir) ENERO 2018 (Ir) FEBRERO 2018 (Ir) MARZO 2018 (Ir) ABRIL 2018 (Ir) MAYO 2018 (Ir) JUNIO 2018 (Ir) JULIO 2019 (Ir) AGOSTO 2018 (Ir) SETIEMBRE 2018 (Ir) OCTUBRE 2018 (Ir) NOVIEMBRE 2018 (Ir) DICIEMBRE 2018 (Ir)
IU INCIDENCIA INCIDENCIA Material FEB ´17 AGO ´17 COEFIC. AGO ´17 COEFIC. DIC´17 COEFIC. Sep-17 COEFIC. Oct-17 COEFIC. Nov-17 COEFIC. Dec-17 COEFIC. Jan-18 COEFIC. Feb-18 COEFIC. Mar-18 COEFIC. Apr-18 COEFIC. May-18 COEFIC. Jun-18 COEFIC. Jul-19 COEFIC. Aug-18 COEFIC. Sep-18 COEFIC. Oct-18 COEFIC. Nov-18 COEFIC. Dec-18 COEFIC.

1 D 30 DOLAR (GENERAL PONDERADO) 1.000 100.000% 1.000 461.49 462.48 1.002 462.48 1.002 466.75 1.011 464.58 1.007 467.61 1.013 465.87 1.009 466.75 1.011 462.02 1.001 469.31 1.017 471.87 1.022 469.88 1.018 478.04 1.036 479.58 1.039 481.37 1.043 483.02 1.047 486.67 1.055 490.47 1.063 497.53 1.078 494.24 1.071
Ʃ 1.000000 Ka(AGO )= 1.002 Ka(AGO )= 1.002 Ka(DIC )= 1.011 Kr(SET )= 1.007 Kr(OCT )= 1.013 Kr(NOV )= 1.009 Kr(DIC )= 1.011 Kr(ENE )= 1.001 Kr(FEB )= 1.017 Kr(MAR )= 1.022 Kr(ABR )= 1.018 Kr(MAY )= 1.036 Kr(JUN )= 1.039 Kr(JUL )= 1.043 Kr(AGO )= 1.047 Kr(SET )= 1.055 Kr(OCT )= 1.063 Kr(NOV )= 1.078 Kr(DIC )= 1.071

FORMULA N° 6 SEGURIDAD
K = 0.203*(Dr / Do) + 0.224*(Mr / Mo) + 0.275*(Ir / Io) + 0.298*(Hr / Ho)

VAL 01 - AGO 2017 VAL 02- SET 2017 VAL 03- OCT 2017 VAL 04- NOV 2017 VAL 05 - DIC 2017 VAL 06 - ENE 2018 VAL 07 - FEB 2018 VAL 08 - MAR 2018 VAL 09 - ABR 2019 VAL 10 - MAY 2018 VAL 11 - JUN 2018 VAL 12 - JUL 2018 VAL 13 - AGO 2018 VAL 14 - SET 2018 VAL 15 - OCT 2018 VAL 16 - NOV 2018
MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI Io IND. ADEL. EFECT. (Ia) IND. ADEL. MAT. (Ia) IND. ADEL. MAT. (Ia) SETIEMBRE 2017 (Ir) OCTUBRE 2017 (Ir) NOVIEMBRE 2017 (Ir) DICIEMBRE 2017 (Ir) ENERO 2018 (Ir) FEBRERO 2018 (Ir) MARZO 2018 (Ir) ABRIL 2018 (Ir) MAYO 2018 (Ir) JUNIO 2018 (Ir) JULIO 2019 (Ir) AGOSTO 2018 (Ir) SETIEMBRE 2018 (Ir) OCTUBRE 2018 (Ir) NOVIEMBRE 2018 (Ir) DICIEMBRE 2018 (Ir)
IU INCIDENCIA INCIDENCIA Material FEB ´17 AGO ´17 COEFIC. AGO ´17 COEFIC. DIC´17 COEFIC. Sep-17 COEFIC. Oct-17 COEFIC. Nov-17 COEFIC. Dec-17 COEFIC. Jan-18 COEFIC. Feb-18 COEFIC. Mar-18 COEFIC. Apr-18 COEFIC. May-18 COEFIC. Jun-18 COEFIC. Jul-19 COEFIC. Aug-18 COEFIC. Sep-18 COEFIC. Oct-18 COEFIC. Nov-18 COEFIC. Dec-18 COEFIC.
1 D 30 DOLAR (GENERAL PONDERADO) 0.203 100.000% 0.203 461.49 462.48 0.203 462.48 0.203 466.75 0.205 464.58 0.204 467.61 0.206 465.87 0.205 466.75 0.205 462.02 0.203 469.31 0.206 471.87 0.208 469.88 0.207 478.04 0.210 479.58 0.211 481.37 0.212 483.02 0.212 486.67 0.214 490.47 0.216 497.53 0.219 494.24 0.217
2 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.224 100.000% 0.224 563.25 580.90 0.231 580.90 0.231 580.90 0.231 580.90 0.231 580.90 0.231 580.90 0.231 580.90 0.231 582.52 0.232 582.52 0.232 582.52 0.232 582.52 0.232 582.52 0.232 602.11 0.239 602.11 0.239 602.11 0.239 602.11 0.239 602.11 0.239 602.11 0.239 602.11 0.239
3 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.275 100.000% 0.275 438.80 444.64 0.279 444.64 0.279 442.30 0.277 444.57 0.279 442.48 0.277 441.61 0.277 442.30 0.277 442.87 0.278 443.97 0.278 446.14 0.280 445.52 0.279 445.61 0.279 447.10 0.280 448.81 0.281 449.40 0.282 450.26 0.282 450.63 0.282 451.18 0.283 452.00 0.283
4 H 37 HERRAMIENTA MANUAL 0.298 100.000% 0.298 295.83 297.47 0.300 297.47 0.300 301.24 0.303 297.54 0.300 298.08 0.300 301.15 0.303 301.24 0.303 304.98 0.307 303.68 0.306 304.11 0.306 304.20 0.306 304.54 0.307 303.74 0.306 305.61 0.308 305.79 0.308 306.17 0.308 310.13 0.312 321.12 0.323 321.04 0.323
Ʃ 1.000000 Ka(AGO )= 1.013 Ka(AGO )= 1.013 Ka(DIC )= 1.016 Kr(SET )= 1.014 Kr(OCT )= 1.014 Kr(NOV )= 1.016 Kr(DIC )= 1.016 Kr(ENE )= 1.020 Kr(FEB )= 1.022 Kr(MAR )= 1.026 Kr(ABR )= 1.024 Kr(MAY )= 1.028 Kr(JUN )= 1.036 Kr(JUL )= 1.040 Kr(AGO )= 1.041 Kr(SET )= 1.043 Kr(OCT )= 1.049 Kr(NOV )= 1.064 Kr(DIC )= 1.062
FORMULA N° 7 MITIGACION DE IMPACTO AMBIENTAL
K = 0.066*(Mr / Mo) + 0.934*(Ir / Io)

VAL 01 - AGO 2017 VAL 02- SET 2017 VAL 03- OCT 2017 VAL 04- NOV 2017 VAL 05 - DIC 2017 VAL 06 - ENE 2018 VAL 07 - FEB 2018 VAL 08 - MAR 2018 VAL 09 - ABR 2019 VAL 10 - MAY 2018 VAL 11 - JUN 2018 VAL 12 - JUL 2018 VAL 13 - AGO 2018 VAL 14 - SET 2018 VAL 15 - OCT 2018 VAL 16 - NOV 2018
MONOMIO SIMBOLO CODIGO DESCRIPCION COEF. DE % DE CI Io IND. ADEL. EFECT. (Ia) IND. ADEL. MAT. (Ia) IND. ADEL. MAT. (Ia) SETIEMBRE 2017 (Ir) OCTUBRE 2017 (Ir) NOVIEMBRE 2017 (Ir) DICIEMBRE 2017 (Ir) ENERO 2018 (Ir) FEBRERO 2018 (Ir) MARZO 2018 (Ir) ABRIL 2018 (Ir) MAYO 2018 (Ir) JUNIO 2018 (Ir) JULIO 2019 (Ir) AGOSTO 2018 (Ir) SETIEMBRE 2018 (Ir) OCTUBRE 2018 (Ir) NOVIEMBRE 2018 (Ir) DICIEMBRE 2018 (Ir)
IU INCIDENCIA INCIDENCIA Material FEB ´17 AGO ´17 COEFIC. AGO ´17 COEFIC. DIC´17 COEFIC. Sep-17 COEFIC. Oct-17 COEFIC. Nov-17 COEFIC. Dec-17 COEFIC. Jan-18 COEFIC. Feb-18 COEFIC. Mar-18 COEFIC. Apr-18 COEFIC. May-18 COEFIC. Jun-18 COEFIC. Jul-19 COEFIC. Aug-18 COEFIC. Sep-18 COEFIC. Oct-18 COEFIC. Nov-18 COEFIC. Dec-18 COEFIC.
1 D 47 MANO DE OBRA INC. LEYES SOCIALES 0.066 100.000% 0.066 563.25 580.90 0.068 580.90 0.068 580.90 0.068 580.90 0.068 580.90 0.068 580.90 0.068 580.90 0.068 582.52 0.068 582.52 0.068 582.52 0.068 582.52 0.068 582.52 0.068 602.11 0.071 602.11 0.071 602.11 0.071 602.11 0.071 602.11 0.071 602.11 0.071 602.11 0.071
2 M 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.934 100.000% 0.934 438.80 444.64 0.946 444.64 0.946 442.30 0.941 444.57 0.946 442.48 0.942 441.61 0.940 442.30 0.941 442.87 0.943 443.97 0.945 446.14 0.950 445.52 0.948 445.61 0.948 447.10 0.952 448.81 0.955 449.40 0.957 450.26 0.958 450.63 0.959 451.18 0.960 452.00 0.962
Ʃ 1.000000 Ka(AGO )= 1.014 Ka(AGO )= 1.014 Ka(DIC )= 1.009 Kr(SET )= 1.014 Kr(OCT )= 1.010 Kr(NOV )= 1.008 Kr(DIC )= 1.009 Kr(ENE )= 1.011 Kr(FEB )= 1.013 Kr(MAR )= 1.018 Kr(ABR )= 1.016 Kr(MAY )= 1.016 Kr(JUN )= 1.023 Kr(JUL )= 1.026 Kr(AGO )= 1.028 Kr(SET )= 1.029 Kr(OCT )= 1.030 Kr(NOV )= 1.031 Kr(DIC )= 1.033
INDICES UNIFICADOS DE PRECIOS AL CONSUMIDOR CONTRACTUAL

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS


►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"
►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 1 ARQUITECTURA Y SEÑALIZACIÓN


IU INSUMO FEB´17 AGOS´17 SET´17 OCT´17 NOV´17 DIC´17 ENE´18 FEB´18 MAR´18 ABR´18 MAY´18 JUN´18 JUL´18 AGOS´18 SET´18 OCT´18 NOV´18 DIC´18
49 MAQUINARIA Y EQUIPO IMPORTADO 293.65 292.36 293.03 293.18 292.27 293.24 290.65 294.48 295.18 294.12 298.68 298.83 299.69 302.20 304.74 307.20 311.07 311.16
02 ACERO DE CONSTRUCCIÓN LISO 468.50 474.70 485.11 488.45 482.69 491.28 497.78 528.59 529.67 526.55 534.75 532.76 532.40 546.81 550.63 555.22 560.33 560.07
30 DÓLAR (GENERAL PONDERADO) 461.49 462.48 464.58 467.61 465.87 466.75 462.02 469.31 471.87 469.88 478.04 479.58 481.37 483.02 486.67 490.47 497.53 494.24
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 438.80 444.64 444.57 442.48 441.61 442.30 442.87 443.97 446.14 445.52 445.61 447.10 448.81 449.40 450.26 450.63 451.18 452.00
04 AGREGADO FINO 1,067.44 1,041.51 1,035.99 1,036.19 1,038.03 1,035.47 1,038.06 1,041.37 1,036.83 1,039.22 1,036.79 1,036.79 1,036.46 1,036.18 1,036.45 1,041.35 1,045.57 1,049.40
47 MANO DE OBRA INC. LEYES SOCIALES 563.25 580.90 580.90 580.90 580.90 580.90 582.52 582.52 582.52 582.52 582.52 602.11 602.11 602.11 602.11 602.11 602.11 602.11

FORMULA N° 2 ESTRUCTURA
IU INSUMO FEB´17 AGOS´17 SET´17 OCT´17 NOV´17 DIC´17 ENE´18 FEB´18 MAR´18 ABR´18 MAY´18 JUN´18 JUL´18 AGOS´18 SET´18 OCT´18 NOV´18 DIC´18
32 FLETE TERRESTRE 463.60 467.18 468.00 468.00 468.00 468.42 468.42 468.42 468.41 468.41 468.41 470.47 470.47 470.47 468.39 468.39 468.39 469.40
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 438.80 444.64 444.57 442.48 441.61 442.30 442.87 443.97 446.14 445.52 445.61 447.10 448.81 449.40 450.26 450.63 451.18 452.00
02 ACERO DE CONSTRUCCION LISO 468.50 474.70 485.11 488.45 482.69 491.28 497.78 528.59 529.67 526.55 534.75 532.76 532.40 546.81 550.63 555.22 560.33 560.07
65 TUBERIA DE ACERO NEGRO Y/O GALVANIZADO 215.22 216.20 228.52 235.92 233.92 244.12 245.62 246.90 243.56 247.66 250.41 250.53 254.51 253.41 256.39 257.21 259.07 262.51
48 MAQUINARIA Y EQUIPO NACIONAL 365.19 366.02 366.18 363.30 363.07 363.24 363.04 362.79 365.55 365.01 368.95 368.82 369.08 369.15 372.23 370.70 371.13 370.72
05 AGREGADO GRUESO 414.50 416.99 420.47 418.45 420.51 421.04 423.40 426.06 422.53 420.58 422.12 423.80 425.85 425.00 426.88 424.45 426.74 428.54
47 MANO DE OBRA INC. LEYES SOCIALES 563.25 580.90 580.90 580.90 580.90 580.90 582.52 582.52 582.52 582.52 582.52 602.11 602.11 602.11 602.11 602.11 602.11 602.11

FORMULA N° 3 INSTALACIONES SANITARIAS


IU INSUMO FEB´17 AGOS´17 SET´17 OCT´17 NOV´17 DIC´17 ENE´18 FEB´18 MAR´18 ABR´18 MAY´18 JUN´18 JUL´18 AGOS´18 SET´18 OCT´18 NOV´18 DIC´18
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 438.80 444.64 444.57 442.48 441.61 442.30 442.87 443.97 446.14 445.52 445.61 447.10 448.81 449.40 450.26 450.63 451.18 452.00
04 AGREGADO FINO 1,067.44 1,041.51 1,035.99 1,036.19 1,038.03 1,035.47 1,038.06 1,041.37 1,036.83 1,039.22 1,036.79 1,036.79 1,036.46 1,036.18 1,036.45 1,041.35 1,045.57 1,049.40
48 MAQUINARIA Y EQUIPO NACIONAL 365.19 366.02 366.18 363.30 363.07 363.24 363.04 362.79 365.55 365.01 368.95 368.82 369.08 369.15 372.23 370.70 371.13 370.72
72 TUBERIA DE PVC PARA AGUA 412.75 416.90 416.95 426.35 425.95 426.06 424.54 424.19 427.74 429.31 431.66 434.23 434.41 435.02 436.21 437.54 439.71 432.82
02 ACERO DE CONSTRUCCION LISO 468.50 474.70 485.11 488.45 482.69 491.28 497.78 528.59 529.67 526.55 534.75 532.76 532.40 546.81 550.63 555.22 560.33 560.07
47 MANO DE OBRA INC. LEYES SOCIALES 563.25 580.90 580.90 580.90 580.90 580.90 582.52 582.52 582.52 582.52 582.52 602.11 602.11 602.11 602.11 602.11 602.11 602.11

Página 16
INDICES UNIFICADOS DE PRECIOS AL CONSUMIDOR CONTRACTUAL

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS


►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"
►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 4 INSTALACIONES ELECTRICAS Y COMUNICACIÓN


IU INSUMO FEB´17 AGOS´17 SET´17 OCT´17 NOV´17 DIC´17 ENE´18 FEB´18 MAR´18 ABR´18 MAY´18 JUN´18 JUL´18 AGOS´18 SET´18 OCT´18 NOV´18 DIC´18
02 ACERO DE CONSTRUCCION LISO 468.50 474.70 485.11 488.45 482.69 491.28 497.78 528.59 529.67 526.55 534.75 532.76 532.40 546.81 550.63 555.22 560.33 560.07
32 FLETE TERRESTRE 463.60 467.18 468.00 468.00 468.00 468.42 468.42 468.42 468.41 468.41 468.41 470.47 470.47 470.47 468.39 468.39 468.39 469.40
48 MAQUINARIA Y EQUIPO NACIONAL 365.19 366.02 366.18 363.30 363.07 363.24 363.04 362.79 365.55 365.01 368.95 368.82 369.08 369.15 372.23 370.70 371.13 370.72
30 DÓLAR (GENERAL PONDERADO) 461.49 462.48 464.58 467.61 465.87 466.75 462.02 469.31 471.87 469.88 478.04 479.58 481.37 483.02 486.67 490.47 497.53 494.24
47 MANO DE OBRA INC. LEYES SOCIALES 563.25 580.90 580.90 580.90 580.90 580.90 582.52 582.52 582.52 582.52 582.52 602.11 602.11 602.11 602.11 602.11 602.11 602.11
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 438.80 444.64 444.57 442.48 441.61 442.30 442.87 443.97 446.14 445.52 445.61 447.10 448.81 449.40 450.26 450.63 451.18 452.00
06 ALAMBRE Y CABLE DE COBRE DESNUDO 831.00 847.68 892.79 899.02 907.22 915.64 925.49 944.54 943.48 932.93 945.80 939.31 944.94 928.00 923.10 925.71 940.07 937.20

FORMULA N° 5 INSTALACIONES ELECTROMECANICAS


IU INSUMO FEB´17 AGOS´17 SET´17 OCT´17 NOV´17 DIC´17 ENE´18 FEB´18 MAR´18 ABR´18 MAY´18 JUN´18 JUL´18 AGOS´18 SET´18 OCT´18 NOV´18 DIC´18
30 DOLAR (GENERAL PONDERADO) 461.49 462.48 464.58 467.61 465.87 466.75 462.02 469.31 471.87 469.88 478.04 479.58 481.37 483.02 486.67 490.47 497.53 494.24

FORMULA N° 6 SEGURIDAD
IU INSUMO FEB´17 AGOS´17 SET´17 OCT´17 NOV´17 DIC´17 ENE´18 FEB´18 MAR´18 ABR´18 MAY´18 JUN´18 JUL´18 AGOS´18 SET´18 OCT´18 NOV´18 DIC´18
30 DOLAR (GENERAL PONDERADO) 461.49 462.48 464.58 467.61 465.87 466.75 462.02 469.31 471.87 469.88 478.04 479.58 481.37 483.02 486.67 490.47 497.53 494.24
47 MANO DE OBRA INC. LEYES SOCIALES 563.25 580.90 580.90 580.90 580.90 580.90 582.52 582.52 582.52 582.52 582.52 602.11 602.11 602.11 602.11 602.11 602.11 602.11
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 438.80 444.64 444.57 442.48 441.61 442.30 442.87 443.97 446.14 445.52 445.61 447.10 448.81 449.40 450.26 450.63 451.18 452.00
37 HERRAMIENTA MANUAL 295.83 297.47 297.54 298.08 301.15 301.24 304.98 303.68 304.11 304.20 304.54 303.74 305.61 305.79 306.17 310.13 321.12 321.04

FORMULA N° 7 MITIGACION DE IMPACTO AMBIENTAL


IU INSUMO FEB´17 AGOS´17 SET´17 OCT´17 NOV´17 DIC´17 ENE´18 FEB´18 MAR´18 ABR´18 MAY´18 JUN´18 JUL´18 AGOS´18 SET´18 OCT´18 NOV´18 DIC´18
47 MANO DE OBRA INC. LEYES SOCIALES 563.25 580.90 580.90 580.90 580.90 580.90 582.52 582.52 582.52 582.52 582.52 602.11 602.11 602.11 602.11 602.11 602.11 602.11
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 438.80 444.64 444.57 442.48 441.61 442.30 442.87 443.97 446.14 445.52 445.61 447.10 448.81 449.40 450.26 450.63 451.18 452.00

Página 17
CUADRO DE REAJUSTES

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

MONTO CONTRATADO (S/ IGV) 10,493,246.78 SIN IGV

CUADRO DE REAJUSTES (Con los K del mes siguiente de la Valorización)


CALCULO DEL REAJUSTE DE LA OBRA
VALORES CALCULADOS SIN IGV

FORMULA N° 1 ARQUITECTURA Y SEÑALIZACIÓN


REAJUSTE DEDUCCION REINTEGRO
VALORIZACION K C= VALx(Kr-1) ADELANTOS
REINTEGRO BRUTO
No MES PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO AUTORIZADO DIRECTO MATERIALES MATERIALES RECONOCIDO
1 Aug-17 S/. - S/. - 1.011 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
2 Sep-17 S/. - S/. - 1.012 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
3 Oct-17 S/. - S/. - 1.010 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
4 Nov-17 S/. 108,817.88 S/. 76,970.54 1.011 S/. 1,197.00 S/. 846.68 S/. 846.68 S/. 3.81 S/. 7.62 S/. - S/. 835.25
5 Dec-17 S/. 101,890.82 S/. 136,147.76 1.011 S/. 1,120.80 S/. 1,497.63 S/. 1,120.80 S/. 6.62 S/. 13.24 S/. - S/. 1,100.93
6 Jan-18 S/. 264,258.47 S/. 74,369.17 1.020 S/. 5,285.17 S/. 1,487.38 S/. 1,487.38 S/. 36.82 S/. 81.37 S/. 66.20 S/. 1,302.99
7 Feb-18 S/. 73,494.70 S/. 260,244.72 1.020 S/. 1,469.89 S/. 5,204.89 S/. 1,469.89 S/. 128.83 S/. 257.67 S/. 231.67 S/. 851.72
8 Mar-18 S/. 285,834.64 S/. 160,609.15 1.019 S/. 5,430.86 S/. 3,051.57 S/. 3,051.57 S/. 71.56 S/. 143.12 S/. 127.09 S/. 2,709.81
9 Apr-18 S/. 342,300.59 S/. 15,849.61 1.024 S/. 8,215.21 S/. 380.39 S/. 380.39 S/. 10.98 S/. 21.97 S/. 20.38 S/. 327.06
10 Aug-18 S/. 20,577.04 S/. 181,744.46 1.038 S/. 781.93 S/. 6,906.29 S/. 781.93 S/. 251.92 S/. 503.85 S/. 485.37 -S/. 459.21
11 Jun-18 S/. 40,518.88 S/. 83,486.86 1.038 S/. 1,539.72 S/. 3,172.50 S/. 1,539.72 S/. 115.72 S/. 231.45 S/. 222.96 S/. 969.58
12 Jul-18 S/. 297,755.29 S/. 293,390.32 1.041 S/. 12,207.97 S/. 12,029.00 S/. 12,029.00 S/. 450.25 S/. 900.50 S/. 870.59 S/. 9,807.65
13 Aug-18 S/. 471,472.31 S/. 420,195.36 1.044 S/. 20,744.78 S/. 18,488.60 S/. 18,488.60 S/. 707.26 S/. 1,414.52 S/. 4,800.45 S/. 11,566.37
14 Sep-18 S/. 190,212.77 S/. 253,618.71 1.048 S/. 9,130.21 S/. 12,173.70 S/. 9,130.21 S/. 477.10 S/. 954.21 S/. 6,734.55 S/. 964.35
15 Oct-18 S/. 156,434.08 S/. 123,342.21 1.052 S/. 8,134.57 S/. 6,413.79 S/. 6,413.79 S/. 631.62 S/. 1,245.15 S/. - S/. 4,537.02
16 Nov-18 S/. 91,682.44 S/. 365,281.04 1.051 S/. 4,675.80 S/. 18,629.33 S/. 4,675.80 S/. - S/. - S/. - S/. 4,675.80
TOTALES S/. 2,445,249.89 S/. 2,445,249.91 S/. 79,933.91 S/. 90,281.75 S/. 61,415.76 S/. 2,892.51 S/. 5,774.67 S/. 13,559.27 S/. 39,189.31
REINTEGRO TOTAL S/. 39,189.31

Página 18
CUADRO DE REAJUSTES

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 2 ESTRUCTURA
REAJUSTE DEDUCCION REINTEGRO
VALORIZACION K C= VALx(Kr-1) ADELANTOS
REINTEGRO BRUTO
No MES PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO AUTORIZADO DIRECTO MATERIALES MATERIALES RECONOCIDO
1 Aug-17 S/. 378,370.20 S/. 1,089,572.85 1.025 S/. 9,459.25 S/. 27,239.32 S/. 9,459.25 S/. 536.74 S/. 1,073.47 S/. - S/. 7,849.04
2 Sep-17 S/. 578,994.10 S/. 606,791.40 1.028 S/. 16,211.83 S/. 16,990.16 S/. 16,211.83 S/. 388.59 S/. 777.17 S/. - S/. 15,046.07
3 Oct-17 S/. 740,472.80 S/. 951,216.82 1.026 S/. 19,252.29 S/. 24,731.64 S/. 19,252.29 S/. 515.44 S/. 1,030.88 S/. - S/. 17,705.98
4 Nov-17 S/. 777,631.06 S/. 266,375.12 1.035 S/. 27,217.09 S/. 9,323.13 S/. 9,323.13 S/. 262.44 S/. 524.88 S/. - S/. 8,535.81
5 Dec-17 S/. 788,494.88 S/. 1,305,734.80 1.039 S/. 30,751.30 S/. 50,923.66 S/. 30,751.30 S/. 1,516.74 S/. 3,033.48 S/. - S/. 26,201.08
6 Jan-18 S/. 266,683.34 S/. 28,596.58 1.046 S/. 12,267.43 S/. 1,315.44 S/. 1,315.44 S/. 43.67 S/. 96.52 S/. 30.39 S/. 1,144.86
7 Feb-18 S/. 545,080.50 S/. 2,295.08 1.045 S/. 24,528.62 S/. 103.28 S/. 103.28 S/. 3.39 S/. 6.78 S/. 2.22 S/. 90.89
8 Mar-18 S/. 363,449.62 S/. 176.25 1.046 S/. 16,718.68 S/. 8.11 S/. 8.11 S/. 0.27 S/. 0.54 S/. 0.19 S/. 7.12
9 Apr-18 S/. 361,696.12 S/. - 1.049 S/. 17,723.11 S/. - S/. - S/. - S/. - S/. - S/. -
10 Aug-18 S/. 342,773.60 S/. - 1.063 S/. 21,594.74 S/. - S/. - S/. - S/. - S/. - S/. -
11 Jun-18 S/. 542,733.79 S/. 379,281.35 1.067 S/. 36,363.16 S/. 25,411.85 S/. 25,411.85 S/. 971.56 S/. 1,943.12 S/. 1,172.66 S/. 21,324.52
12 Jul-18 S/. 337,046.16 S/. 509,874.40 1.070 S/. 23,593.23 S/. 35,691.21 S/. 23,593.23 S/. 1,381.43 S/. 2,762.87 S/. 1,724.21 S/. 17,724.72
13 Aug-18 S/. - S/. 267,075.24 1.072 S/. - S/. 19,229.42 S/. - S/. 749.92 S/. 1,499.83 S/. 3,341.67 -S/. 5,591.41
14 Sep-18 S/. 7,255.55 S/. 326,222.43 1.073 S/. 529.66 S/. 23,814.24 S/. 529.66 S/. 932.06 S/. 1,864.13 S/. 8,690.28 -S/. 10,956.81
15 Oct-18 S/. - S/. 201,666.96 1.076 S/. - S/. 15,326.69 S/. - S/. 1,492.49 S/. 2,942.26 S/. - -S/. 4,434.75
16 Nov-18 S/. - S/. 95,802.57 1.079 S/. - S/. 7,568.40 S/. - S/. - S/. - S/. - S/. -
TOTALES S/. 6,030,681.72 S/. 6,030,681.85 S/. 256,210.39 S/. 257,676.55 S/. 135,959.37 S/. 8,794.74 S/. 17,555.92 S/. 14,961.61 S/. 94,647.10
REINTEGRO TOTAL S/. 94,647.10

Página 19
CUADRO DE REAJUSTES

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 3 INSTALACIONES SANITARIAS


REAJUSTE DEDUCCION REINTEGRO
VALORIZACION K C= VALx(Kr-1) ADELANTOS
REINTEGRO BRUTO
No MES PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO AUTORIZADO DIRECTO MATERIALES MATERIALES RECONOCIDO
1 Aug-17 S/. - S/. - 1.018 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
2 Sep-17 S/. - S/. - 1.022 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
3 Oct-17 S/. - S/. 5,488.60 1.019 S/. - S/. 104.28 S/. - S/. 1.08 S/. 2.16 S/. - -S/. 3.24
4 Nov-17 S/. - S/. - 1.023 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
5 Dec-17 S/. 130,527.47 S/. 18,202.07 1.026 S/. 3,393.71 S/. 473.25 S/. 473.25 S/. 9.69 S/. 19.38 S/. - S/. 444.18
6 Jan-18 S/. - S/. 63,688.57 1.039 S/. - S/. 2,483.85 S/. - S/. 75.30 S/. 166.43 S/. 99.61 -S/. 341.33
7 Feb-18 S/. - S/. 26,859.07 1.041 S/. - S/. 1,101.22 S/. - S/. 34.40 S/. 68.80 S/. 47.26 -S/. 150.46
8 Mar-18 S/. 124,005.10 S/. 8,827.08 1.041 S/. 5,084.21 S/. 361.91 S/. 361.91 S/. 11.31 S/. 22.61 S/. 15.53 S/. 312.46
9 Apr-18 S/. 32,102.86 S/. 69,521.24 1.045 S/. 1,444.63 S/. 3,128.46 S/. 1,444.63 S/. 102.74 S/. 205.48 S/. 149.51 S/. 986.90
10 Aug-18 S/. 7,086.52 S/. 15,006.58 1.060 S/. 425.19 S/. 900.39 S/. 425.19 S/. 33.27 S/. 66.53 S/. 54.28 S/. 271.12
11 Jun-18 S/. - S/. 3,741.63 1.061 S/. - S/. 228.24 S/. - S/. 8.48 S/. 16.96 S/. 13.90 -S/. 39.33
12 Jul-18 S/. 152,659.43 S/. 33,395.66 1.066 S/. 10,075.52 S/. 2,204.11 S/. 2,204.11 S/. 83.90 S/. 167.80 S/. 140.37 S/. 1,812.04
13 Aug-18 S/. 32,844.04 S/. 34,631.50 1.069 S/. 2,266.24 S/. 2,389.57 S/. 2,266.24 S/. 92.12 S/. 184.25 S/. 545.03 S/. 1,444.84
14 Sep-18 S/. 65,779.01 S/. 36,228.51 1.073 S/. 4,801.87 S/. 2,644.68 S/. 2,644.68 S/. 103.51 S/. 207.02 S/. 1,284.76 S/. 1,049.39
15 Oct-18 S/. 27,262.26 S/. 172,540.42 1.075 S/. 2,044.67 S/. 12,940.53 S/. 2,044.67 S/. 1,256.00 S/. 2,476.04 S/. - -S/. 1,687.37
16 Nov-18 S/. - S/. 84,135.84 1.073 S/. - S/. 6,141.92 S/. - S/. - S/. - S/. - S/. -
TOTALES S/. 572,266.67 S/. 572,266.77 S/. 29,536.04 S/. 35,102.41 S/. 11,864.68 S/. 1,811.79 S/. 3,603.47 S/. 2,350.25 S/. 4,099.18
REINTEGRO TOTAL S/. 4,099.18

Página 20
CUADRO DE REAJUSTES

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 4 INSTALACIONES ELECTRICAS Y COMUNICACIÓN


REAJUSTE DEDUCCION REINTEGRO
VALORIZACION K C= VALx(Kr-1) ADELANTOS
REINTEGRO BRUTO
No MES PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO AUTORIZADO DIRECTO MATERIALES MATERIALES RECONOCIDO
1 Aug-17 S/. - S/. - 1.032 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
2 Sep-17 S/. - S/. - 1.034 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
3 Oct-17 S/. - S/. - 1.034 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
4 Nov-17 S/. - S/. - 1.039 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
5 Dec-17 S/. - S/. 8,495.79 1.041 S/. - S/. 348.33 S/. - S/. 10.69 S/. 21.38 S/. - -S/. 32.07
6 Jan-18 S/. 156,587.46 S/. 77,519.44 1.053 S/. 8,299.14 S/. 4,108.53 S/. 4,108.53 S/. 145.11 S/. 320.73 S/. 104.45 S/. 3,538.23
7 Feb-18 S/. - S/. 5,901.13 1.056 S/. - S/. 330.46 S/. - S/. 11.92 S/. 23.84 S/. 9.66 -S/. 45.41
8 Mar-18 S/. 9,879.14 S/. 43,165.34 1.051 S/. 503.84 S/. 2,201.43 S/. 503.84 S/. 76.55 S/. 153.10 S/. 49.85 S/. 224.34
9 Apr-18 S/. - S/. 86,338.42 1.060 S/. - S/. 5,180.31 S/. - S/. 191.39 S/. 382.78 S/. 174.50 -S/. 748.68
10 Aug-18 S/. 67,810.14 S/. 137,193.62 1.066 S/. 4,475.47 S/. 9,054.78 S/. 4,475.47 S/. 344.67 S/. 689.35 S/. 356.52 S/. 3,084.93
11 Jun-18 S/. 76,772.56 S/. 24,577.90 1.070 S/. 5,374.08 S/. 1,720.45 S/. 1,720.45 S/. 66.59 S/. 133.18 S/. 73.33 S/. 1,447.35
12 Jul-18 S/. 64,590.76 S/. 27,385.16 1.066 S/. 4,262.99 S/. 1,807.42 S/. 1,807.42 S/. 68.80 S/. 137.60 S/. 71.16 S/. 1,529.85
13 Aug-18 S/. 4,606.13 S/. 49,780.04 1.068 S/. 313.22 S/. 3,385.04 S/. 313.22 S/. 129.97 S/. 259.93 S/. 486.30 -S/. 562.98
14 Sep-18 S/. 272,957.58 S/. 13,861.69 1.070 S/. 19,107.03 S/. 970.32 S/. 970.32 S/. 37.56 S/. 75.11 S/. 300.08 S/. 557.57
15 Oct-18 S/. 228,065.84 S/. 217,470.57 1.076 S/. 17,333.00 S/. 16,527.76 S/. 16,527.76 S/. 1,609.45 S/. 3,172.83 S/. - S/. 11,745.48
16 Nov-18 S/. 80,660.34 S/. 270,240.94 1.075 S/. 6,049.53 S/. 20,268.07 S/. 6,049.53 S/. - S/. - S/. - S/. 6,049.53
TOTALES S/. 961,929.95 S/. 961,930.04 S/. 65,718.30 S/. 65,902.90 S/. 36,476.54 S/. 2,692.70 S/. 5,369.84 S/. 1,625.87 S/. 26,788.14
REINTEGRO TOTAL S/. 26,788.14

Página 21
CUADRO DE REAJUSTES

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 5 INSTALACIONES ELECTROMECANICAS


REAJUSTE DEDUCCION REINTEGRO
VALORIZACION K C= VALx(Kr-1) ADELANTOS
REINTEGRO BRUTO
No MES PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO AUTORIZADO DIRECTO MATERIALES MATERIALES RECONOCIDO
1 Aug-17 S/. - S/. - 1.007 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
2 Sep-17 S/. - S/. - 1.013 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
3 Oct-17 S/. - S/. - 1.009 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
4 Nov-17 S/. - S/. - 1.011 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
5 Dec-17 S/. - S/. - 1.001 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
6 Jan-18 S/. - S/. - 1.017 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
7 Feb-18 S/. - S/. - 1.022 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
8 Mar-18 S/. - S/. - 1.018 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
9 Apr-18 S/. - S/. - 1.036 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
10 Aug-18 S/. - S/. - 1.039 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
11 Jun-18 S/. - S/. - 1.043 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
12 Jul-18 S/. - S/. - 1.047 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
13 Aug-18 S/. - S/. 3,600.00 1.055 S/. - S/. 198.00 S/. - S/. 9.52 S/. 19.04 S/. 48.37 -S/. 76.93
14 Sep-18 S/. - S/. 38,309.26 1.063 S/. - S/. 2,413.48 S/. - S/. 116.61 S/. 233.22 S/. 1,285.83 -S/. 1,635.66
15 Oct-18 S/. 23,707.56 S/. 2,940.00 1.078 S/. 1,849.19 S/. 229.32 S/. 229.32 S/. 27.46 S/. 54.13 S/. - S/. 147.73
16 Nov-18 S/. 239,945.02 S/. 218,803.32 1.071 S/. 17,036.10 S/. 15,535.04 S/. 15,535.04 S/. - S/. - S/. - S/. 15,535.04
TOTALES S/. 263,652.58 S/. 263,652.58 S/. 18,885.29 S/. 18,375.84 S/. 15,764.36 S/. 153.59 S/. 306.40 S/. 1,334.20 S/. 13,970.17
REINTEGRO TOTAL S/. 13,970.17

Página 22
CUADRO DE REAJUSTES

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 6 SEGURIDAD
REAJUSTE DEDUCCION REINTEGRO
VALORIZACION K C= VALx(Kr-1) ADELANTOS
REINTEGRO BRUTO
No MES PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO AUTORIZADO DIRECTO MATERIALES MATERIALES RECONOCIDO
1 Aug-17 S/. 15,612.92 S/. - 1.014 S/. 218.58 S/. - S/. - S/. - S/. - S/. - S/. -
2 Sep-17 S/. 4,567.58 S/. - 1.014 S/. 63.95 S/. - S/. - S/. - S/. - S/. - S/. -
3 Oct-17 S/. 4,567.58 S/. - 1.016 S/. 73.08 S/. - S/. - S/. - S/. - S/. - S/. -
4 Nov-17 S/. 4,567.58 S/. - 1.016 S/. 73.08 S/. - S/. - S/. - S/. - S/. - S/. -
5 Dec-17 S/. 4,567.58 S/. - 1.020 S/. 91.35 S/. - S/. - S/. - S/. - S/. - S/. -
6 Jan-18 S/. 4,567.58 S/. - 1.022 S/. 100.49 S/. - S/. - S/. - S/. - S/. - S/. -
7 Feb-18 S/. 4,567.58 S/. - 1.026 S/. 118.76 S/. - S/. - S/. - S/. - S/. - S/. -
8 Mar-18 S/. 4,567.58 S/. - 1.024 S/. 109.62 S/. - S/. - S/. - S/. - S/. - S/. -
9 Apr-18 S/. 4,567.58 S/. 22,488.14 1.028 S/. 127.89 S/. 629.67 S/. 127.89 S/. 16.65 S/. 33.30 S/. 42.35 S/. 35.59
10 Aug-18 S/. 4,567.72 S/. 16,866.11 1.036 S/. 164.44 S/. 607.18 S/. 164.44 S/. 19.15 S/. 38.29 S/. 45.13 S/. 61.87
11 Jun-18 S/. - S/. 5,622.03 1.040 S/. - S/. 224.88 S/. - S/. 7.49 S/. 14.98 S/. 17.27 -S/. 39.75
12 Jul-18 S/. - S/. - 1.041 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
13 Aug-18 S/. - S/. 12,880.30 1.043 S/. - S/. 553.85 S/. - S/. 19.07 S/. 38.15 S/. 151.91 -S/. 209.13
14 Sep-18 S/. - S/. 2,768.05 1.049 S/. - S/. 135.63 S/. - S/. 4.92 S/. 9.84 S/. 79.62 -S/. 94.38
15 Oct-18 S/. - S/. 6,693.75 1.064 S/. - S/. 428.40 S/. - S/. 41.50 S/. 81.81 S/. - -S/. 123.31
16 Nov-18 S/. 14,184.65 S/. 3,587.56 1.062 S/. 879.45 S/. 222.43 S/. 222.43 S/. - S/. - S/. - S/. 222.43
TOTALES S/. 70,905.96 S/. 70,905.94 S/. 2,020.69 S/. 2,802.04 S/. 514.76 S/. 108.78 S/. 216.37 S/. 336.28 -S/. 146.67
REINTEGRO TOTAL -S/. 146.67

Página 23
CUADRO DE REAJUSTES

►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DELCENTRO DE SALUD MARGOS"

►CONTRATISTA : CONSORCIO VIRGEN DE GUADALUPE


►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

FORMULA N° 7 MITIGACION DE IMPACTO AMBIENTAL


REAJUSTE DEDUCCION REINTEGRO
VALORIZACION K C= VALx(Kr-1) ADELANTOS
REINTEGRO BRUTO
No MES PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO AUTORIZADO DIRECTO MATERIALES MATERIALES RECONOCIDO
1 Aug-17 S/. 36,240.00 S/. - 1.014 S/. 507.36 S/. - S/. - S/. - S/. - S/. - S/. -
2 Sep-17 S/. 19,800.00 S/. - 1.010 S/. 198.00 S/. - S/. - S/. - S/. - S/. - S/. -
3 Oct-17 S/. 15,720.00 S/. - 1.008 S/. 125.76 S/. - S/. - S/. - S/. - S/. - S/. -
4 Nov-17 S/. 15,600.00 S/. - 1.009 S/. 140.40 S/. - S/. - S/. - S/. - S/. - S/. -
5 Dec-17 S/. 14,400.00 S/. - 1.011 S/. 158.40 S/. - S/. - S/. - S/. - S/. - S/. -
6 Jan-18 S/. 12,000.00 S/. - 1.013 S/. 156.00 S/. - S/. - S/. - S/. - S/. - S/. -
7 Feb-18 S/. 9,600.00 S/. - 1.018 S/. 172.80 S/. - S/. - S/. - S/. - S/. - S/. -
8 Mar-18 S/. 10,800.00 S/. - 1.016 S/. 172.80 S/. - S/. - S/. - S/. - S/. - S/. -
9 Apr-18 S/. 9,600.00 S/. 59,880.00 1.016 S/. 153.60 S/. 958.08 S/. 153.60 S/. 5.91 S/. 11.81 S/. 11.81 S/. 124.07
10 Aug-18 S/. - S/. 58,440.00 1.023 S/. - S/. 1,344.12 S/. - S/. 25.93 S/. 51.87 S/. 51.87 -S/. 129.67
11 Jun-18 S/. - S/. 2,460.00 1.026 S/. - S/. 63.96 S/. - S/. 1.46 S/. 2.91 S/. 2.91 -S/. 7.28
12 Jul-18 S/. - S/. - 1.028 S/. - S/. - S/. - S/. - S/. - S/. - S/. -
13 Aug-18 S/. - S/. 22,200.00 1.029 S/. - S/. 643.80 S/. - S/. 16.42 S/. 32.84 S/. 114.94 -S/. 164.20
14 Sep-18 S/. - S/. 1,320.00 1.030 S/. - S/. 39.60 S/. - S/. 1.04 S/. 2.08 S/. 15.11 -S/. 18.24
15 Oct-18 S/. - S/. 3,120.00 1.031 S/. - S/. 96.72 S/. - S/. 6.44 S/. 12.70 S/. - -S/. 19.14
16 Nov-18 S/. 4,800.00 S/. 1,140.00 1.033 S/. 158.40 S/. 37.62 S/. 37.62 S/. - S/. - S/. - S/. 37.62
TOTALES S/. 148,560.00 S/. 148,560.00 S/. 1,943.52 S/. 3,183.90 S/. 191.22 S/. 57.20 S/. 114.21 S/. 196.64 -S/. 176.84
REINTEGRO TOTAL -S/. 176.84

RESUMEN DEL REINTEGRO

TOTALES S/. 10,493,246.76 S/. 10,493,247.09 S/. - S/. 454,248.14 S/. 473,325.39 S/. 262,186.69 S/. 16,511.30 S/. 32,940.88 S/. 34,364.11 S/. 178,370.40

Página 24
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS,


►OBRA
DISTRITO DE MARGOS - HUANUCO - HUANUCO"

►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE


►SUPERVISOR : ING. JOEL ABIGAEL BEDON VASQUEZ
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

DEDUCCION DEL REINTEGRO QUE NO CORRESPONDE


POR EL ADELANTO DIRECTO

FORMULA:

De = A * V / C * ( K / Ka - 1 )

DONDE:

De : Deducción del Reajuste generado por el Adelanto en Efectivo


A : Monto del Adelanto Otorgado en Efectivo
V : Monto de la Valorización Mensual
C : Saldo del Contrato por Valorizar a la fecha del Adelanto
K : Coeficiente de Reajuste obtenido por la Aplicación de la Fórmula Polinomica
Ka: Coeficiente de Reajuste correspondiente al mes en que se canceló el Adelanto

MONTO DEL PRESUPUESTO CONTRATADO 12,382,031.20 INC. IGV


MONTO DEL PRESUPUESTO CONTRATADO 10,493,246.78 SIN IGV

PORCENTAJE DEL ADELANTO 5.00%

ADELANTO DIRECTO = 619,101.56 INC. IGV


ADELANTO DIRECTO = 524,662.34 SIN IGV

FORMULA N° 1 ARQUITECTURA Y SEÑALIZACIÓN


MONTO DEL PRESUPUESTO CONTRATADO 2,885,394.87 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 2,445,249.89 SIN IGV

PORCENTAJE DEL ADELANTO 5.00%

ADELANTO DIRECTO = 144,269.74 INC. IGV


ADELANTO DIRECTO = 122,262.49 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion


Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)
A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 122,262.49 S/. - 0.00% 1.011 1.010 0.00099 0.00
2 Sep-17 S/. - S/. 122,262.49 S/. - 0.00% 1.012 1.010 0.00198 0.00
3 Oct-17 S/. - S/. 122,262.49 S/. - 0.00% 1.010 1.010 0.00000 0.00
4 Nov-17 S/. 76,970.54 S/. 122,262.49 S/. 3,848.53 3.15% 1.011 1.010 0.00099 3.81
5 Dec-17 S/. 136,147.76 S/. 122,262.49 S/. 6,688.39 5.47% 1.011 1.010 0.00099 6.62
6 Jan-18 S/. 74,369.17 S/. 122,262.49 S/. 3,718.46 3.04% 1.020 1.010 0.00990 36.82
7 Feb-18 S/. 260,244.72 S/. 122,262.49 S/. 13,012.24 10.64% 1.020 1.010 0.00990 128.83
8 Mar-18 S/. 160,609.15 S/. 122,262.49 S/. 8,030.46 6.57% 1.019 1.010 0.00891 71.56
9 Apr-18 S/. 15,849.61 S/. 122,262.49 S/. 792.48 0.65% 1.024 1.010 0.01386 10.98
10 May-18 S/. 181,744.46 S/. 122,262.49 S/. 9,087.22 7.43% 1.038 1.010 0.02772 251.92
11 Jun-18 S/. 83,486.86 S/. 122,262.49 S/. 4,174.34 3.41% 1.038 1.010 0.02772 115.72
12 Jul-18 S/. 293,390.32 S/. 122,262.49 S/. 14,669.52 12.00% 1.041 1.010 0.03069 450.25
13 Aug-18 S/. 420,195.36 S/. 122,262.49 S/. 21,009.77 17.18% 1.044 1.010 0.03366 707.26
14 Sep-18 S/. 253,618.71 S/. 122,262.49 S/. 12,680.94 10.37% 1.048 1.010 0.03762 477.10
15 Oct-18 S/. 123,342.21 S/. 122,262.49 S/. 15,188.84 12.42% 1.052 1.010 0.04158 631.62
16 Nov-18 S/. 365,281.04 S/. 122,262.49 S/. - 0.00% 1.051 1.010 0.04059 0.00
TOTAL S/. 2,445,249.91 S/. 112,901.19 2,892.51

DEDUCCION TOTAL S/. 2,892.51

FORMULA N° 2 ESTRUCTURA
MONTO DEL PRESUPUESTO CONTRATADO 7,116,204.43 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 6,030,681.72 SIN IGV

PORCENTAJE DEL ADELANTO 5.00%

ADELANTO DIRECTO = 355,810.22 INC. IGV


ADELANTO DIRECTO = 301,534.09 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion


Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)
A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. 1,089,572.85 S/. 301,534.09 S/. 54,479.53 44.56% 1.025 1.015 0.00985 536.74
2 Sep-17 S/. 606,791.40 S/. 301,534.09 S/. 30,339.57 24.82% 1.028 1.015 0.01281 388.59
3 Oct-17 S/. 951,216.82 S/. 301,534.09 S/. 47,560.84 38.90% 1.026 1.015 0.01084 515.44
4 Nov-17 S/. 266,375.12 S/. 301,534.09 S/. 13,318.75 10.89% 1.035 1.015 0.01970 262.44
5 Dec-17 S/. 1,305,734.80 S/. 301,534.09 S/. 64,145.51 52.47% 1.039 1.015 0.02365 1,516.74
6 Jan-18 S/. 28,596.58 S/. 301,534.09 S/. 1,429.83 1.17% 1.046 1.015 0.03054 43.67
7 Feb-18 S/. 2,295.08 S/. 301,534.09 S/. 114.75 0.09% 1.045 1.015 0.02956 3.39
8 Mar-18 S/. 176.25 S/. 301,534.09 S/. 8.81 0.01% 1.046 1.015 0.03054 0.27
9 Apr-18 S/. - S/. 301,534.09 S/. - 0.00% 1.049 1.015 0.03350 0.00
10 May-18 S/. - S/. 301,534.09 S/. - 0.00% 1.063 1.015 0.04729 0.00
11 Jun-18 S/. 379,281.35 S/. 301,534.09 S/. 18,964.07 15.51% 1.067 1.015 0.05123 971.56
12 Jul-18 S/. 509,874.40 S/. 301,534.09 S/. 25,493.72 20.85% 1.070 1.015 0.05419 1,381.43
13 Aug-18 S/. 267,075.24 S/. 301,534.09 S/. 13,353.76 10.92% 1.072 1.015 0.05616 749.92
14 Sep-18 S/. 326,222.43 S/. 301,534.09 S/. 16,311.12 13.34% 1.073 1.015 0.05714 932.06
15 Oct-18 S/. 201,666.96 S/. 301,534.09 S/. 24,834.06 20.31% 1.076 1.015 0.06010 1,492.49
16 Nov-18 S/. 95,802.57 S/. 301,534.09 S/. - 0.00% 1.079 1.015 0.06305 0.00
TOTAL S/. 6,030,681.85 S/. 310,354.32 8,794.74
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS,


►OBRA
DISTRITO DE MARGOS - HUANUCO - HUANUCO"

►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE


►SUPERVISOR : ING. JOEL ABIGAEL BEDON VASQUEZ
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

DEDUCCION DEL REINTEGRO QUE NO CORRESPONDE


POR EL ADELANTO DIRECTO
DEDUCCION TOTAL S/. 8,794.74

FORMULA N° 3 INSTALACIONES SANITARIAS


MONTO DEL PRESUPUESTO CONTRATADO 675,274.67 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 572,266.67 SIN IGV

PORCENTAJE DEL ADELANTO 5.00%

ADELANTO DIRECTO = 33,763.73 INC. IGV


ADELANTO DIRECTO = 28,613.33 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion


Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)
A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 28,613.33 S/. - 0.00% 1.018 1.015 0.00296 0.00
2 Sep-17 S/. - S/. 28,613.33 S/. - 0.00% 1.022 1.015 0.00690 0.00
3 Oct-17 S/. 5,488.60 S/. 28,613.33 S/. 274.43 0.22% 1.019 1.015 0.00394 1.08
4 Nov-17 S/. - S/. 28,613.33 S/. - 0.00% 1.023 1.015 0.00788 0.00
5 Dec-17 S/. 18,202.07 S/. 28,613.33 S/. 894.19 0.73% 1.026 1.015 0.01084 9.69
6 Jan-18 S/. 63,688.57 S/. 28,613.33 S/. 3,184.43 2.60% 1.039 1.015 0.02365 75.30
7 Feb-18 S/. 26,859.07 S/. 28,613.33 S/. 1,342.95 1.10% 1.041 1.015 0.02562 34.40
8 Mar-18 S/. 8,827.08 S/. 28,613.33 S/. 441.35 0.36% 1.041 1.015 0.02562 11.31
9 Apr-18 S/. 69,521.24 S/. 28,613.33 S/. 3,476.06 2.84% 1.045 1.015 0.02956 102.74
10 May-18 S/. 15,006.58 S/. 28,613.33 S/. 750.33 0.61% 1.060 1.015 0.04433 33.27
11 Jun-18 S/. 3,741.63 S/. 28,613.33 S/. 187.08 0.15% 1.061 1.015 0.04532 8.48
12 Jul-18 S/. 33,395.66 S/. 28,613.33 S/. 1,669.78 1.37% 1.066 1.015 0.05025 83.90
13 Aug-18 S/. 34,631.50 S/. 28,613.33 S/. 1,731.57 1.42% 1.069 1.015 0.05320 92.12
14 Sep-18 S/. 36,228.51 S/. 28,613.33 S/. 1,811.43 1.48% 1.073 1.015 0.05714 103.51
15 Oct-18 S/. 172,540.42 S/. 28,613.33 S/. 21,247.30 17.38% 1.075 1.015 0.05911 1,256.00
16 Nov-18 S/. 84,135.84 S/. 28,613.33 S/. - 0.00% 1.073 1.015 0.05714 0.00
TOTAL S/. 572,266.77 S/. 37,010.90 1,811.79

DEDUCCION TOTAL S/. 1,811.79

FORMULA N° 4 INSTALACIONES ELECTRICAS Y COMUNICACIÓN


MONTO DEL PRESUPUESTO CONTRATADO 1,135,077.34 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 961,929.95 SIN IGV

PORCENTAJE DEL ADELANTO 5.00%

ADELANTO DIRECTO = 56,753.87 INC. IGV


ADELANTO DIRECTO = 48,096.50 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion


Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)
A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 48,096.50 S/. - 0.00% 1.032 1.015 0.01675 0.00
2 Sep-17 S/. - S/. 48,096.50 S/. - 0.00% 1.034 1.015 0.01872 0.00
3 Oct-17 S/. - S/. 48,096.50 S/. - 0.00% 1.034 1.015 0.01872 0.00
4 Nov-17 S/. - S/. 48,096.50 S/. - 0.00% 1.039 1.015 0.02365 0.00
5 Dec-17 S/. 8,495.79 S/. 48,096.50 S/. 417.36 0.34% 1.041 1.015 0.02562 10.69
6 Jan-18 S/. 77,519.44 S/. 48,096.50 S/. 3,875.97 3.17% 1.053 1.015 0.03744 145.11
7 Feb-18 S/. 5,901.13 S/. 48,096.50 S/. 295.06 0.24% 1.056 1.015 0.04039 11.92
8 Mar-18 S/. 43,165.34 S/. 48,096.50 S/. 2,158.27 1.77% 1.051 1.015 0.03547 76.55
9 Apr-18 S/. 86,338.42 S/. 48,096.50 S/. 4,316.92 3.53% 1.060 1.015 0.04433 191.39
10 May-18 S/. 137,193.62 S/. 48,096.50 S/. 6,859.68 5.61% 1.066 1.015 0.05025 344.67
11 Jun-18 S/. 24,577.90 S/. 48,096.50 S/. 1,228.89 1.01% 1.070 1.015 0.05419 66.59
12 Jul-18 S/. 27,385.16 S/. 48,096.50 S/. 1,369.26 1.12% 1.066 1.015 0.05025 68.80
13 Aug-18 S/. 49,780.04 S/. 48,096.50 S/. 2,489.00 2.04% 1.068 1.015 0.05222 129.97
14 Sep-18 S/. 13,861.69 S/. 48,096.50 S/. 693.08 0.57% 1.070 1.015 0.05419 37.56
15 Oct-18 S/. 217,470.57 S/. 48,096.50 S/. 26,780.18 21.90% 1.076 1.015 0.06010 1,609.45
16 Nov-18 S/. 270,240.94 S/. 48,096.50 S/. - 0.00% 1.075 1.015 0.05911 0.00
TOTAL S/. 961,930.04 S/. 50,483.67 2,692.70

DEDUCCION TOTAL S/. 2,692.70

FORMULA N° 5 INSTALACIONES ELECTROMECANICAS


MONTO DEL PRESUPUESTO CONTRATADO 311,110.04 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 263,652.58 SIN IGV

PORCENTAJE DEL ADELANTO 5.00%

ADELANTO DIRECTO = 15,555.50 INC. IGV


ADELANTO DIRECTO = 13,182.63 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion


Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)
A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 13,182.63 S/. - 0.00% 1.007 1.002 0.00499 0.00
2 Sep-17 S/. - S/. 13,182.63 S/. - 0.00% 1.013 1.002 0.01098 0.00
3 Oct-17 S/. - S/. 13,182.63 S/. - 0.00% 1.009 1.002 0.00699 0.00
4 Nov-17 S/. - S/. 13,182.63 S/. - 0.00% 1.011 1.002 0.00898 0.00
5 Dec-17 S/. - S/. 13,182.63 S/. - 0.00% 1.001 1.002 -0.00100 0.00
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS,


►OBRA
DISTRITO DE MARGOS - HUANUCO - HUANUCO"

►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE


►SUPERVISOR : ING. JOEL ABIGAEL BEDON VASQUEZ
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

DEDUCCION DEL REINTEGRO QUE NO CORRESPONDE


POR EL ADELANTO DIRECTO
6 Jan-18 S/. - S/. 13,182.63 S/. - 0.00% 1.017 1.002 0.01497 0.00
7 Feb-18 S/. - S/. 13,182.63 S/. - 0.00% 1.022 1.002 0.01996 0.00
8 Mar-18 S/. - S/. 13,182.63 S/. - 0.00% 1.018 1.002 0.01597 0.00
9 Apr-18 S/. - S/. 13,182.63 S/. - 0.00% 1.036 1.002 0.03393 0.00
10 May-18 S/. - S/. 13,182.63 S/. - 0.00% 1.039 1.002 0.03693 0.00
11 Jun-18 S/. - S/. 13,182.63 S/. - 0.00% 1.043 1.002 0.04092 0.00
12 Jul-18 S/. - S/. 13,182.63 S/. - 0.00% 1.047 1.002 0.04491 0.00
13 Aug-18 S/. 3,600.00 S/. 13,182.63 S/. 180.00 0.15% 1.055 1.002 0.05289 9.52
14 Sep-18 S/. 38,309.26 S/. 13,182.63 S/. 1,915.46 1.57% 1.063 1.002 0.06088 116.61
15 Oct-18 S/. 2,940.00 S/. 13,182.63 S/. 362.04 0.30% 1.078 1.002 0.07585 27.46
16 Nov-18 S/. 218,803.32 S/. 13,182.63 S/. - 0.00% 1.071 1.002 0.06886 0.00
TOTAL S/. 263,652.58 S/. 2,457.50 153.59

DEDUCCION TOTAL S/. 153.59

FORMULA N° 6 SEGURIDAD
MONTO DEL PRESUPUESTO CONTRATADO 83,669.03 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 70,905.96 SIN IGV

PORCENTAJE DEL ADELANTO 5.00%

ADELANTO DIRECTO = 4,183.45 INC. IGV


ADELANTO DIRECTO = 3,545.30 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion


Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)
A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 3,545.30 S/. - 0.00% 1.014 1.013 0.00099 0.00
2 Sep-17 S/. - S/. 3,545.30 S/. - 0.00% 1.014 1.013 0.00099 0.00
3 Oct-17 S/. - S/. 3,545.30 S/. - 0.00% 1.016 1.013 0.00296 0.00
4 Nov-17 S/. - S/. 3,545.30 S/. - 0.00% 1.016 1.013 0.00296 0.00
5 Dec-17 S/. - S/. 3,545.30 S/. - 0.00% 1.020 1.013 0.00691 0.00
6 Jan-18 S/. - S/. 3,545.30 S/. - 0.00% 1.022 1.013 0.00888 0.00
7 Feb-18 S/. - S/. 3,545.30 S/. - 0.00% 1.026 1.013 0.01283 0.00
8 Mar-18 S/. - S/. 3,545.30 S/. - 0.00% 1.024 1.013 0.01086 0.00
9 Apr-18 S/. 22,488.14 S/. 3,545.30 S/. 1,124.41 0.92% 1.028 1.013 0.01481 16.65
10 May-18 S/. 16,866.11 S/. 3,545.30 S/. 843.31 0.69% 1.036 1.013 0.02270 19.15
11 Jun-18 S/. 5,622.03 S/. 3,545.30 S/. 281.10 0.23% 1.040 1.013 0.02665 7.49
12 Jul-18 S/. - S/. 3,545.30 S/. - 0.00% 1.041 1.013 0.02764 0.00
13 Aug-18 S/. 12,880.30 S/. 3,545.30 S/. 644.01 0.53% 1.043 1.013 0.02962 19.07
14 Sep-18 S/. 2,768.05 S/. 3,545.30 S/. 138.40 0.11% 1.049 1.013 0.03554 4.92
15 Oct-18 S/. 6,693.75 S/. 3,545.30 S/. 824.30 0.67% 1.064 1.013 0.05035 41.50
16 Nov-18 S/. 3,587.56 S/. 3,545.30 S/. - 0.00% 1.062 1.013 0.04837 0.00
TOTAL S/. 70,905.94 S/. 3,855.53 108.78

DEDUCCION TOTAL S/. 108.78

FORMULA N° 7 MITIGACION DE IMPACTO AMBIENTAL


MONTO DEL PRESUPUESTO CONTRATADO 175,300.80 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 148,560.00 SIN IGV

PORCENTAJE DEL ADELANTO 5.00%

ADELANTO DIRECTO = 8,765.04 INC. IGV


ADELANTO DIRECTO = 7,428.00 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion


Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)
A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 7,428.00 S/. - 0.00% 1.014 1.014 0.00000 0.00
2 Sep-17 S/. - S/. 7,428.00 S/. - 0.00% 1.010 1.014 -0.00394 0.00
3 Oct-17 S/. - S/. 7,428.00 S/. - 0.00% 1.008 1.014 -0.00592 0.00
4 Nov-17 S/. - S/. 7,428.00 S/. - 0.00% 1.009 1.014 -0.00493 0.00
5 Dec-17 S/. - S/. 7,428.00 S/. - 0.00% 1.011 1.014 -0.00296 0.00
6 Jan-18 S/. - S/. - S/. - 0.00% 1.013 1.014 -0.00099 0.00
7 Feb-18 S/. - S/. - S/. - 0.00% 1.018 1.014 0.00394 0.00
8 Mar-18 S/. - S/. - S/. - 0.00% 1.016 1.014 0.00197 0.00
9 Apr-18 S/. 59,880.00 S/. - S/. 2,994.00 2.45% 1.016 1.014 0.00197 5.91
10 May-18 S/. 58,440.00 S/. 7,428.00 S/. 2,922.00 2.39% 1.023 1.014 0.00888 25.93
11 Jun-18 S/. 2,460.00 S/. - S/. 123.00 0.10% 1.026 1.014 0.01183 1.46
12 Jul-18 S/. - S/. - S/. - 0.00% 1.028 1.014 0.01381 0.00
13 Aug-18 S/. 22,200.00 S/. - S/. 1,110.00 0.91% 1.029 1.014 0.01479 16.42
14 Sep-18 S/. 1,320.00 S/. - S/. 66.00 0.05% 1.030 1.014 0.01578 1.04
15 Oct-18 S/. 3,120.00 S/. 7,428.00 S/. 384.21 0.31% 1.031 1.014 0.01677 6.44
16 Nov-18 S/. 1,140.00 S/. 7,428.00 S/. - 0.00% 1.033 1.014 0.01874 0.00
TOTAL S/. 148,560.00 S/. 7,599.21 57.20

DEDUCCION TOTAL S/. 57.20

RESUMEN DEL DEDUCTIVO

DEDUCTIVO TOTAL S/. 16,511.30


►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE MARGOS -
►OBRA
HUANUCO - HUANUCO"

►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE


►SUPERVISOR : ING. JOEL ABIGAEL BEDON VASQUEZ
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

DEDUCCION DEL REINTEGRO QUE NO CORRESPONDE


POR EL ADELANTO DE MATERIALES

FORMULA:

De = A x VAL / C x ( K / Ka - 1 )

DONDE:

De : Deducción del Reajuste generado por el Adelanto en Efectivo


A : Monto del Adelanto Otorgado en Efectivo
V : Monto de la Valorización Mensual
C : Saldo del Contrato por Valorizar a la fecha del Adelanto
K : Coeficiente de Reajuste obtenido por la Aplicación de la Fórmula Polinomica
Ka: Coeficiente de Reajuste correspondiente al mes en que se canceló el Adelanto

MONTO DEL PRESUPUESTO CONTRATADO 12,382,031.20 INC. IGV


MONTO DEL PRESUPUESTO CONTRATADO 10,493,246.78 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO PARA MATERIALES = 2,476,406.24 INC. IGV


ADELANTO PARA MATERIALES = 2,098,649.36 SIN IGV

FORMULA N° 1 ARQUITECTURA Y SEÑALIZACIÓN


MONTO DEL PRESUPUESTO CONTRATADO 2,885,394.87 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 2,445,249.89 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 577,078.97 INC. IGV


ADELANTO DIRECTO = 489,049.97 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 489,049.97 S/. - 0.00% 1.011 1.010 0.00099 0.00
2 Sep-17 S/. - S/. 489,049.97 S/. - 0.00% 1.012 1.010 0.00198 0.00
3 Oct-17 S/. - S/. 489,049.97 S/. - 0.00% 1.010 1.010 0.00000 0.00
4 Nov-17 S/. 76,970.54 S/. 489,049.97 S/. 7,697.05 1.57% 1.011 1.010 0.00099 7.62
5 Dec-17 S/. 136,147.76 S/. 489,049.97 S/. 13,376.78 2.74% 1.011 1.010 0.00099 13.24
6 Jan-18 S/. 74,369.17 S/. 489,049.97 S/. 8,218.80 1.68% 1.020 1.010 0.00990 81.37
7 Feb-18 S/. 260,244.72 S/. 489,049.97 S/. 26,024.47 5.32% 1.020 1.010 0.00990 257.67
8 Mar-18 S/. 160,609.15 S/. 489,049.97 S/. 16,060.91 3.28% 1.019 1.010 0.00891 143.12
9 Apr-18 S/. 15,849.61 S/. 489,049.97 S/. 1,584.96 0.32% 1.024 1.010 0.01386 21.97
10 May-18 S/. 181,744.46 S/. 489,049.97 S/. 18,174.45 3.72% 1.038 1.010 0.02772 503.85
11 Jun-18 S/. 83,486.86 S/. 489,049.97 S/. 8,348.69 1.71% 1.038 1.010 0.02772 231.45
12 Jul-18 S/. 293,390.32 S/. 489,049.97 S/. 29,339.03 6.00% 1.041 1.010 0.03069 900.50
13 Aug-18 S/. 420,195.36 S/. 489,049.97 S/. 42,019.54 8.59% 1.044 1.010 0.03366 1,414.52
14 Sep-18 S/. 253,618.71 S/. 489,049.97 S/. 25,361.87 5.19% 1.048 1.010 0.03762 954.21
15 Oct-18 S/. 123,342.21 S/. 489,049.97 S/. 29,942.91 6.12% 1.052 1.010 0.04158 1,245.15
16 Nov-19 S/. 365,281.04 S/. 489,049.97 S/. - 0.00% 1.051 1.010 0.04059 0.00
TOTAL S/. 2,445,249.91 S/. 226,149.46 5,774.67

DEDUCCION TOTAL S/. 5,774.67

FORMULA N° 2 ESTRUCTURA
MONTO DEL PRESUPUESTO CONTRATADO 7,116,204.43 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 6,030,681.72 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 1,423,240.89 INC. IGV


ADELANTO DIRECTO = 1,206,136.35 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. 1,089,572.85 S/. 1,206,136.35 S/. 108,957.29 9.03% 1.025 1.015 0.00985 1,073.47
2 Sep-17 S/. 606,791.40 S/. 1,206,136.35 S/. 60,679.14 5.03% 1.028 1.015 0.01281 777.17
3 Oct-17 S/. 951,216.82 S/. 1,206,136.35 S/. 95,121.68 7.89% 1.026 1.015 0.01084 1,030.88
4 Nov-17 S/. 266,375.12 S/. 1,206,136.35 S/. 26,637.51 2.21% 1.035 1.015 0.01970 524.88
5 Dec-17 S/. 1,305,734.80 S/. 1,206,136.35 S/. 128,291.01 10.64% 1.039 1.015 0.02365 3,033.48
6 Jan-18 S/. 28,596.58 S/. 1,206,136.35 S/. 3,160.31 0.65% 1.046 1.015 0.03054 96.52
7 Feb-18 S/. 2,295.08 S/. 1,206,136.35 S/. 229.51 0.05% 1.045 1.015 0.02956 6.78
8 Mar-18 S/. 176.25 S/. 1,206,136.35 S/. 17.62 0.00% 1.046 1.015 0.03054 0.54
9 Apr-18 S/. - S/. 1,206,136.35 S/. - 0.00% 1.049 1.015 0.03350 0.00
10 May-18 S/. - S/. 1,206,136.35 S/. - 0.00% 1.063 1.015 0.04729 0.00
11 Jun-18 S/. 379,281.35 S/. 1,206,136.35 S/. 37,928.13 7.76% 1.067 1.015 0.05123 1,943.12
12 Jul-18 S/. 509,874.40 S/. 1,206,136.35 S/. 50,987.44 10.43% 1.070 1.015 0.05419 2,762.87
13 Aug-18 S/. 267,075.24 S/. 1,206,136.35 S/. 26,707.53 5.46% 1.072 1.015 0.05616 1,499.83
14 Sep-18 S/. 326,222.43 S/. 1,206,136.35 S/. 32,622.24 6.67% 1.073 1.015 0.05714 1,864.13
15 Oct-18 S/. 201,666.96 S/. 1,206,136.35 S/. 48,957.25 10.01% 1.076 1.015 0.06010 2,942.26
16 Nov-18 S/. 95,802.57 S/. 1,206,136.35 S/. - 0.00% 1.079 1.015 0.06305 0.00
TOTAL S/. 6,030,681.85 S/. 620,296.66 17,555.92

DEDUCCION TOTAL S/. 17,555.92

FORMULA N° 3 INSTALACIONES SANITARIAS


MONTO DEL PRESUPUESTO CONTRATADO 675,274.67 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 572,266.67 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 135,054.93 INC. IGV


ADELANTO DIRECTO = 114,453.33 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 114,453.33 S/. - 1.018 1.015 0.00296 0.00


2 Sep-17 S/. - S/. 114,453.33 S/. - 1.022 1.015 0.00690 0.00
3 Oct-17 S/. 5,488.60 S/. 114,453.33 S/. 548.86 1.019 1.015 0.00394 2.16
4 Nov-17 S/. - S/. 114,453.33 S/. - 1.023 1.015 0.00788 0.00
5 Dec-17 S/. 18,202.07 S/. 114,453.33 S/. 1,788.39 1.026 1.015 0.01084 19.38
6 Jan-18 S/. 63,688.57 S/. 114,453.33 S/. 7,038.45 1.44% 1.039 1.015 0.02365 166.43
7 Feb-18 S/. 26,859.07 S/. 114,453.33 S/. 2,685.91 0.55% 1.041 1.015 0.02562 68.80
8 Mar-18 S/. 8,827.08 S/. 114,453.33 S/. 882.71 0.18% 1.041 1.015 0.02562 22.61
9 Apr-18 S/. 69,521.24 S/. 114,453.33 S/. 6,952.12 1.42% 1.045 1.015 0.02956 205.48
10 May-18 S/. 15,006.58 S/. 114,453.33 S/. 1,500.66 0.31% 1.060 1.015 0.04433 66.53
11 Jun-18 S/. 3,741.63 S/. 114,453.33 S/. 374.16 0.08% 1.061 1.015 0.04532 16.96
12 Jul-18 S/. 33,395.66 S/. 114,453.33 S/. 3,339.57 0.68% 1.066 1.015 0.05025 167.80
13 Aug-18 S/. 34,631.50 S/. 114,453.33 S/. 3,463.15 0.71% 1.069 1.015 0.05320 184.25
14 Sep-18 S/. 36,228.51 S/. 114,453.33 S/. 3,622.85 0.74% 1.073 1.015 0.05714 207.02
15 Oct-18 S/. 172,540.42 S/. 114,453.33 S/. 41,886.41 8.56% 1.075 1.015 0.05911 2,476.04
16 Nov-18 S/. 84,135.84 S/. 114,453.33 S/. - 1.073 1.015 0.05714 0.00
TOTAL S/. 572,266.77 S/. 74,083.24 3,603.47

DEDUCCION TOTAL S/. 3,603.47

FORMULA N° 4 INSTALACIONES ELECTRICAS Y COMUNICACIÓN


MONTO DEL PRESUPUESTO CONTRATADO 1,135,077.34 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 961,929.95 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 227,015.47 INC. IGV


ADELANTO DIRECTO = 192,385.99 SIN IGV
Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 192,385.99 S/. - 0.00% 1.032 1.015 0.01675 0.00
2 Sep-17 S/. - S/. 192,385.99 S/. - 0.00% 1.034 1.015 0.01872 0.00
3 Oct-17 S/. - S/. 192,385.99 S/. - 0.00% 1.034 1.015 0.01872 0.00
4 Nov-17 S/. - S/. 192,385.99 S/. - 0.00% 1.039 1.015 0.02365 0.00
5 Dec-17 S/. 8,495.79 S/. 192,385.99 S/. 834.73 0.43% 1.041 1.015 0.02562 21.38
6 Jan-18 S/. 77,519.44 S/. 192,385.99 S/. 8,566.95 1.75% 1.053 1.015 0.03744 320.73
7 Feb-18 S/. 5,901.13 S/. 192,385.99 S/. 590.11 0.12% 1.056 1.015 0.04039 23.84
8 Mar-18 S/. 43,165.34 S/. 192,385.99 S/. 4,316.53 0.88% 1.051 1.015 0.03547 153.10
9 Apr-18 S/. 86,338.42 S/. 192,385.99 S/. 8,633.84 1.77% 1.060 1.015 0.04433 382.78
10 May-18 S/. 137,193.62 S/. 192,385.99 S/. 13,719.36 2.81% 1.066 1.015 0.05025 689.35
11 Jun-18 S/. 24,577.90 S/. 192,385.99 S/. 2,457.79 0.50% 1.070 1.015 0.05419 133.18
12 Jul-18 S/. 27,385.16 S/. 192,385.99 S/. 2,738.52 0.56% 1.066 1.015 0.05025 137.60
13 Aug-18 S/. 49,780.04 S/. 192,385.99 S/. 4,978.00 1.02% 1.068 1.015 0.05222 259.93
14 Sep-18 S/. 13,861.69 S/. 192,385.99 S/. 1,386.17 0.28% 1.070 1.015 0.05419 75.11
15 Oct-18 S/. 217,470.57 S/. 192,385.99 S/. 52,793.78 10.80% 1.076 1.015 0.06010 3,172.83
16 Nov-18 S/. 270,240.94 S/. 192,385.99 S/. - 0.00% 1.075 1.015 0.05911 0.00
TOTAL S/. 961,930.04 S/. 101,015.78 5,369.84

DEDUCCION TOTAL S/. 5,369.84

FORMULA N° 5 INSTALACIONES ELECTROMECANICAS


MONTO DEL PRESUPUESTO CONTRATADO 311,110.04 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 263,652.58 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 62,222.01 INC. IGV


ADELANTO DIRECTO = 52,730.52 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 52,730.52 S/. - 0.00% 1.007 1.002 0.00499 0.00
2 Sep-17 S/. - S/. 52,730.52 S/. - 0.00% 1.013 1.002 0.01098 0.00
3 Oct-17 S/. - S/. 52,730.52 S/. - 0.00% 1.009 1.002 0.00699 0.00
4 Nov-17 S/. - S/. 52,730.52 S/. - 0.00% 1.011 1.002 0.00898 0.00
5 Dec-17 S/. - S/. 52,730.52 S/. - 0.00% 1.001 1.002 -0.00100 0.00
6 Jan-18 S/. - S/. 52,730.52 S/. - 0.00% 1.017 1.002 0.01497 0.00
7 Feb-18 S/. - S/. 52,730.52 S/. - 0.00% 1.022 1.002 0.01996 0.00
8 Mar-18 S/. - S/. 52,730.52 S/. - 0.00% 1.018 1.002 0.01597 0.00
9 Apr-18 S/. - S/. 52,730.52 S/. - 0.00% 1.036 1.002 0.03393 0.00
10 May-18 S/. - S/. 52,730.52 S/. - 0.00% 1.039 1.002 0.03693 0.00
11 Jun-18 S/. - S/. 52,730.52 S/. - 0.00% 1.043 1.002 0.04092 0.00
12 Jul-18 S/. - S/. 52,730.52 S/. - 0.00% 1.047 1.002 0.04491 0.00
13 Aug-18 S/. 3,600.00 S/. 52,730.52 S/. 360.00 0.07% 1.055 1.002 0.05289 19.04
14 Sep-18 S/. 38,309.26 S/. 52,730.52 S/. 3,830.93 0.78% 1.063 1.002 0.06088 233.22
15 Oct-18 S/. 2,940.00 S/. 52,730.52 S/. 713.72 0.15% 1.078 1.002 0.07585 54.13
16 Nov-18 S/. 218,803.32 S/. 52,730.52 S/. - 0.00% 1.071 1.002 0.06886 0.00
TOTAL S/. 263,652.58 S/. 4,904.65 306.40

DEDUCCION TOTAL S/. 306.40

FORMULA N° 6 SEGURIDAD
MONTO DEL PRESUPUESTO CONTRATADO 83,669.03 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 70,905.96 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 16,733.81 INC. IGV


ADELANTO DIRECTO = 14,181.19 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 14,181.19 S/. - 0.00% 1.014 1.013 0.00099 0.00
2 Sep-17 S/. - S/. 14,181.19 S/. - 0.00% 1.014 1.013 0.00099 0.00
3 Oct-17 S/. - S/. 14,181.19 S/. - 0.00% 1.016 1.013 0.00296 0.00
4 Nov-17 S/. - S/. 14,181.19 S/. - 0.00% 1.016 1.013 0.00296 0.00
5 Dec-17 S/. - S/. 14,181.19 S/. - 0.00% 1.020 1.013 0.00691 0.00
6 Jan-18 S/. - S/. 14,181.19 S/. - 0.00% 1.022 1.013 0.00888 0.00
7 Feb-18 S/. - S/. 14,181.19 S/. - 0.00% 1.026 1.013 0.01283 0.00
8 Mar-18 S/. - S/. 14,181.19 S/. - 0.00% 1.024 1.013 0.01086 0.00
9 Apr-18 S/. 22,488.14 S/. 14,181.19 S/. 2,248.81 0.46% 1.028 1.013 0.01481 33.30
10 May-18 S/. 16,866.11 S/. 14,181.19 S/. 1,686.61 0.34% 1.036 1.013 0.02270 38.29
11 Jun-18 S/. 5,622.03 S/. 14,181.19 S/. 562.20 0.11% 1.040 1.013 0.02665 14.98
12 Jul-18 S/. - S/. 14,181.19 S/. - 0.00% 1.041 1.013 0.02764 0.00
13 Aug-18 S/. 12,880.30 S/. 14,181.19 S/. 1,288.03 0.26% 1.043 1.013 0.02962 38.15
14 Sep-18 S/. 2,768.05 S/. 14,181.19 S/. 276.81 0.06% 1.049 1.013 0.03554 9.84
15 Oct-18 S/. 6,693.75 S/. 14,181.19 S/. 1,625.00 0.33% 1.064 1.013 0.05035 81.81
16 Nov-18 S/. 3,587.56 S/. 14,181.19 S/. - 0.00% 1.062 1.013 0.04837 0.00
TOTAL S/. 70,905.94 S/. 7,687.46 216.37

DEDUCCION TOTAL S/. 216.37

FORMULA N° 7 MITIGACION DE IMPACTO AMBIENTAL


MONTO DEL PRESUPUESTO CONTRATADO 175,300.80 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 148,560.00 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 35,060.16 INC. IGV


ADELANTO DIRECTO = 29,712.00 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 29,712.00 S/. - 0.00% 1.014 1.014 0.00000 0.00
2 Sep-17 S/. - S/. 29,712.00 S/. - 0.00% 1.010 1.014 -0.00394 0.00
3 Oct-17 S/. - S/. 29,712.00 S/. - 0.00% 1.008 1.014 -0.00592 0.00
4 Nov-17 S/. - S/. 29,712.00 S/. - 0.00% 1.009 1.014 -0.00493 0.00
5 Dec-17 S/. - S/. 29,712.00 S/. - 0.00% 1.011 1.014 -0.00296 0.00
6 Jan-18 S/. - S/. 29,712.00 S/. - 0.00% 1.013 1.014 -0.00099 0.00
7 Feb-18 S/. - S/. 29,712.00 S/. - 0.00% 1.018 1.014 0.00394 0.00
8 Mar-18 S/. - S/. 29,712.00 S/. - 0.00% 1.016 1.014 0.00197 0.00
9 Apr-18 S/. 59,880.00 S/. 29,712.00 S/. 5,988.00 1.22% 1.016 1.014 0.00197 11.81
10 May-18 S/. 58,440.00 S/. 29,712.00 S/. 5,844.00 1.19% 1.023 1.014 0.00888 51.87
11 Jun-18 S/. 2,460.00 S/. 29,712.00 S/. 246.00 0.05% 1.026 1.014 0.01183 2.91
12 Jul-18 S/. - S/. 29,712.00 S/. - 0.00% 1.028 1.014 0.01381 0.00
13 Aug-18 S/. 22,200.00 S/. 29,712.00 S/. 2,220.00 0.45% 1.029 1.014 0.01479 32.84
14 Sep-18 S/. 1,320.00 S/. 29,712.00 S/. 132.00 0.03% 1.030 1.014 0.01578 2.08
15 Oct-18 S/. 3,120.00 S/. 29,712.00 S/. 757.42 0.15% 1.031 1.014 0.01677 12.70
16 Nov-18 S/. 1,140.00 S/. 29,712.00 S/. - 0.00% 1.033 1.014 0.01874 0.00
TOTAL S/. 148,560.00 S/. 15,187.42 114.21

DEDUCCION TOTAL S/. 114.21

RESUMEN DEL DEDUCTIVO

DEDUCTIVO TOTAL S/. 32,940.88


►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE MARGOS -
►OBRA
HUANUCO - HUANUCO"

►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE


►SUPERVISOR : ING. JOEL ABIGAEL BEDON VASQUEZ
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA

DEDUCCION DEL REINTEGRO QUE NO CORRESPONDE


POR EL ADELANTO DE MATERIALES

FORMULA:

De = A x VAL / C x ( K / Ka - 1 )

DONDE:

De : Deducción del Reajuste generado por el Adelanto en Efectivo


A : Monto del Adelanto Otorgado en Efectivo
V : Monto de la Valorización Mensual
C : Saldo del Contrato por Valorizar a la fecha del Adelanto
K : Coeficiente de Reajuste obtenido por la Aplicación de la Fórmula Polinomica
Ka: Coeficiente de Reajuste correspondiente al mes en que se canceló el Adelanto

MONTO DEL PRESUPUESTO CONTRATADO 12,382,031.20 INC. IGV


MONTO DEL PRESUPUESTO CONTRATADO 10,493,246.78 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO PARA MATERIALES = 2,476,406.24 INC. IGV


ADELANTO PARA MATERIALES = 2,098,649.36 SIN IGV

FORMULA N° 1 ARQUITECTURA Y SEÑALIZACIÓN


MONTO DEL PRESUPUESTO CONTRATADO 2,885,394.87 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 2,445,249.89 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 577,078.97 INC. IGV


ADELANTO DIRECTO = 489,049.97 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 489,049.97 S/. - 0.00% 1.011 1.011 0.00000 0.00
2 Sep-17 S/. - S/. 489,049.97 S/. - 0.00% 1.012 1.011 0.00099 0.00
3 Oct-17 S/. - S/. 489,049.97 S/. - 0.00% 1.010 1.011 -0.00099 0.00
4 Nov-17 S/. 76,970.54 S/. 489,049.97 S/. - 0.00% 1.011 1.011 0.00000 0.00
5 Dec-17 S/. 136,147.76 S/. 489,049.97 S/. - 0.00% 1.011 1.011 0.00000 0.00
6 Jan-18 S/. 74,369.17 S/. 489,049.97 S/. 7,436.92 1.52% 1.020 1.011 0.00890 66.20
7 Feb-18 S/. 260,244.72 S/. 489,049.97 S/. 26,024.47 5.32% 1.020 1.011 0.00890 231.67
8 Mar-18 S/. 160,609.15 S/. 489,049.97 S/. 16,060.91 3.28% 1.019 1.011 0.00791 127.09
9 Apr-18 S/. 15,849.61 S/. 489,049.97 S/. 1,584.96 0.32% 1.024 1.011 0.01286 20.38
10 May-18 S/. 181,744.46 S/. 489,049.97 S/. 18,174.45 3.72% 1.038 1.011 0.02671 485.37
11 Jun-18 S/. 83,486.86 S/. 489,049.97 S/. 8,348.69 1.71% 1.038 1.011 0.02671 222.96
12 Jul-18 S/. 293,390.32 S/. 489,049.97 S/. 29,339.03 6.00% 1.041 1.011 0.02967 870.59
13 Aug-18 S/. 420,195.36 S/. 489,049.97 S/. 147,068.38 30.07% 1.044 1.011 0.03264 4,800.45
14 Sep-18 S/. 253,618.71 S/. 489,049.97 S/. 184,016.93 37.63% 1.048 1.011 0.03660 6,734.55
15 Oct-18 S/. 123,342.21 S/. 489,049.97 S/. - 0.00% 1.052 1.011 0.04055 0.00
16 Nov-18 S/. 365,281.04 S/. 489,049.97 S/. - 0.00% 1.051 1.011 0.03956 0.00
TOTAL S/. 2,445,249.91 S/. 438,054.74 13,559.27

DEDUCCION TOTAL S/. 13,559.27

FORMULA N° 2 ESTRUCTURA
MONTO DEL PRESUPUESTO CONTRATADO 7,116,204.43 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 6,030,681.72 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 1,423,240.89 INC. IGV


ADELANTO DIRECTO = 1,206,136.35 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. 1,089,572.85 S/. 1,206,136.35 S/. - 0.00% 1.025 1.035 -0.00966 0.00
2 Sep-17 S/. 606,791.40 S/. 1,206,136.35 S/. - 0.00% 1.028 1.035 -0.00676 0.00
3 Oct-17 S/. 951,216.82 S/. 1,206,136.35 S/. - 0.00% 1.026 1.035 -0.00870 0.00
4 Nov-17 S/. 266,375.12 S/. 1,206,136.35 S/. - 0.00% 1.035 1.035 0.00000 0.00
5 Dec-17 S/. 1,305,734.80 S/. 1,206,136.35 S/. - 0.00% 1.039 1.035 0.00386 0.00
6 Jan-18 S/. 28,596.58 S/. 1,206,136.35 S/. 2,859.66 0.58% 1.046 1.035 0.01063 30.39
7 Feb-18 S/. 2,295.08 S/. 1,206,136.35 S/. 229.51 0.05% 1.045 1.035 0.00966 2.22
8 Mar-18 S/. 176.25 S/. 1,206,136.35 S/. 17.62 0.00% 1.046 1.035 0.01063 0.19
9 Apr-18 S/. - S/. 1,206,136.35 S/. - 0.00% 1.049 1.035 0.01353 0.00
10 May-18 S/. - S/. 1,206,136.35 S/. - 0.00% 1.063 1.035 0.02705 0.00
11 Jun-18 S/. 379,281.35 S/. 1,206,136.35 S/. 37,928.13 7.76% 1.067 1.035 0.03092 1,172.66
12 Jul-18 S/. 509,874.40 S/. 1,206,136.35 S/. 50,987.44 10.43% 1.070 1.035 0.03382 1,724.21
13 Aug-18 S/. 267,075.24 S/. 1,206,136.35 S/. 93,476.33 19.11% 1.072 1.035 0.03575 3,341.67
14 Sep-18 S/. 326,222.43 S/. 1,206,136.35 S/. 236,695.67 48.40% 1.073 1.035 0.03671 8,690.28
15 Oct-18 S/. 201,666.96 S/. 1,206,136.35 S/. - 0.00% 1.076 1.035 0.03961 0.00
16 Nov-18 S/. 95,802.57 S/. 1,206,136.35 S/. - 0.00% 1.079 1.035 0.04251 0.00
TOTAL S/. 6,030,681.85 S/. 422,194.36 14,961.61

DEDUCCION TOTAL S/. 14,961.61

FORMULA N° 3 INSTALACIONES SANITARIAS


MONTO DEL PRESUPUESTO CONTRATADO 675,274.67 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 572,266.67 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 135,054.93 INC. IGV


ADELANTO DIRECTO = 114,453.33 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 114,453.33 S/. - 1.018 1.023 -0.00489 0.00


2 Sep-17 S/. - S/. 114,453.33 S/. - 1.022 1.023 -0.00098 0.00
3 Oct-17 S/. 5,488.60 S/. 114,453.33 S/. - 1.019 1.023 -0.00391 0.00
4 Nov-17 S/. - S/. 114,453.33 S/. - 1.023 1.023 0.00000 0.00
5 Dec-17 S/. 18,202.07 S/. 114,453.33 S/. - 1.026 1.023 0.00293 0.00
6 Jan-18 S/. 63,688.57 S/. 114,453.33 S/. 6,368.86 1.30% 1.039 1.023 0.01564 99.61
7 Feb-18 S/. 26,859.07 S/. 114,453.33 S/. 2,685.91 0.55% 1.041 1.023 0.01760 47.26
8 Mar-18 S/. 8,827.08 S/. 114,453.33 S/. 882.71 0.18% 1.041 1.023 0.01760 15.53
9 Apr-18 S/. 69,521.24 S/. 114,453.33 S/. 6,952.12 1.42% 1.045 1.023 0.02151 149.51
10 May-18 S/. 15,006.58 S/. 114,453.33 S/. 1,500.66 0.31% 1.060 1.023 0.03617 54.28
11 Jun-18 S/. 3,741.63 S/. 114,453.33 S/. 374.16 0.08% 1.061 1.023 0.03715 13.90
12 Jul-18 S/. 33,395.66 S/. 114,453.33 S/. 3,339.57 0.68% 1.066 1.023 0.04203 140.37
13 Aug-18 S/. 34,631.50 S/. 114,453.33 S/. 12,121.02 2.48% 1.069 1.023 0.04497 545.03
14 Sep-18 S/. 36,228.51 S/. 114,453.33 S/. 26,286.15 5.37% 1.073 1.023 0.04888 1,284.76
15 Oct-18 S/. 172,540.42 S/. 114,453.33 S/. - 0.00% 1.075 1.023 0.05083 0.00
16 Nov-18 S/. 84,135.84 S/. 114,453.33 S/. - 1.073 1.023 0.04888 0.00
TOTAL S/. 572,266.77 S/. 60,511.16 2,350.25

DEDUCCION TOTAL S/. 2,350.25

FORMULA N° 4 INSTALACIONES ELECTRICAS Y COMUNICACIÓN


MONTO DEL PRESUPUESTO CONTRATADO 1,135,077.34 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 961,929.95 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 227,015.47 INC. IGV


ADELANTO DIRECTO = 192,385.99 SIN IGV
Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 192,385.99 S/. - 0.00% 1.032 1.039 -0.00674 0.00
2 Sep-17 S/. - S/. 192,385.99 S/. - 0.00% 1.034 1.039 -0.00481 0.00
3 Oct-17 S/. - S/. 192,385.99 S/. - 0.00% 1.034 1.039 -0.00481 0.00
4 Nov-17 S/. - S/. 192,385.99 S/. - 0.00% 1.039 1.039 0.00000 0.00
5 Dec-17 S/. 8,495.79 S/. 192,385.99 S/. - 0.00% 1.041 1.039 0.00192 0.00
6 Jan-18 S/. 77,519.44 S/. 192,385.99 S/. 7,751.94 1.59% 1.053 1.039 0.01347 104.45
7 Feb-18 S/. 5,901.13 S/. 192,385.99 S/. 590.11 0.12% 1.056 1.039 0.01636 9.66
8 Mar-18 S/. 43,165.34 S/. 192,385.99 S/. 4,316.53 0.88% 1.051 1.039 0.01155 49.85
9 Apr-18 S/. 86,338.42 S/. 192,385.99 S/. 8,633.84 1.77% 1.060 1.039 0.02021 174.50
10 May-18 S/. 137,193.62 S/. 192,385.99 S/. 13,719.36 2.81% 1.066 1.039 0.02599 356.52
11 Jun-18 S/. 24,577.90 S/. 192,385.99 S/. 2,457.79 0.50% 1.070 1.039 0.02984 73.33
12 Jul-18 S/. 27,385.16 S/. 192,385.99 S/. 2,738.52 0.56% 1.066 1.039 0.02599 71.16
13 Aug-18 S/. 49,780.04 S/. 192,385.99 S/. 17,423.01 3.56% 1.068 1.039 0.02791 486.30
14 Sep-18 S/. 13,861.69 S/. 192,385.99 S/. 10,057.56 2.06% 1.070 1.039 0.02984 300.08
15 Oct-18 S/. 217,470.57 S/. 192,385.99 S/. - 0.00% 1.076 1.039 0.03561 0.00
16 Nov-18 S/. 270,240.94 S/. 192,385.99 S/. - 0.00% 1.075 1.039 0.03465 0.00
TOTAL S/. 961,930.04 S/. 67,688.66 1,625.87

DEDUCCION TOTAL S/. 1,625.87

FORMULA N° 5 INSTALACIONES ELECTROMECANICAS


MONTO DEL PRESUPUESTO CONTRATADO 311,110.04 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 263,652.58 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 62,222.01 INC. IGV


ADELANTO DIRECTO = 52,730.52 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 52,730.52 S/. - 0.00% 1.007 1.016 -0.00886 0.00
2 Sep-17 S/. - S/. 52,730.52 S/. - 0.00% 1.013 1.016 -0.00295 0.00
3 Oct-17 S/. - S/. 52,730.52 S/. - 0.00% 1.009 1.016 -0.00689 0.00
4 Nov-17 S/. - S/. 52,730.52 S/. - 0.00% 1.011 1.016 -0.00492 0.00
5 Dec-17 S/. - S/. 52,730.52 S/. - 0.00% 1.001 1.016 -0.01476 0.00
6 Jan-18 S/. - S/. 52,730.52 S/. - 0.00% 1.017 1.016 0.00098 0.00
7 Feb-18 S/. - S/. 52,730.52 S/. - 0.00% 1.022 1.016 0.00591 0.00
8 Mar-18 S/. - S/. 52,730.52 S/. - 0.00% 1.018 1.016 0.00197 0.00
9 Apr-18 S/. - S/. 52,730.52 S/. - 0.00% 1.036 1.016 0.01969 0.00
10 May-18 S/. - S/. 52,730.52 S/. - 0.00% 1.039 1.016 0.02264 0.00
11 Jun-18 S/. - S/. 52,730.52 S/. - 0.00% 1.043 1.016 0.02657 0.00
12 Jul-18 S/. - S/. 52,730.52 S/. - 0.00% 1.047 1.016 0.03051 0.00
13 Aug-18 S/. 3,600.00 S/. 52,730.52 S/. 1,260.00 0.26% 1.055 1.016 0.03839 48.37
14 Sep-18 S/. 38,309.26 S/. 52,730.52 S/. 27,795.87 5.68% 1.063 1.016 0.04626 1,285.83
15 Oct-18 S/. 2,940.00 S/. 52,730.52 S/. - 0.00% 1.078 1.016 0.06102 0.00
16 Nov-18 S/. 218,803.32 S/. 52,730.52 S/. - 0.00% 1.071 1.016 0.05413 0.00
TOTAL S/. 263,652.58 S/. 29,055.87 1,334.20

DEDUCCION TOTAL S/. 1,334.20

FORMULA N° 6 SEGURIDAD
MONTO DEL PRESUPUESTO CONTRATADO 83,669.03 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 70,905.96 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 16,733.81 INC. IGV


ADELANTO DIRECTO = 14,181.19 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 14,181.19 S/. - 0.00% 1.014 1.009 0.00496 0.00
2 Sep-17 S/. - S/. 14,181.19 S/. - 0.00% 1.014 1.009 0.00496 0.00
3 Oct-17 S/. - S/. 14,181.19 S/. - 0.00% 1.016 1.009 0.00694 0.00
4 Nov-17 S/. - S/. 14,181.19 S/. - 0.00% 1.016 1.009 0.00694 0.00
5 Dec-17 S/. - S/. 14,181.19 S/. - 0.00% 1.020 1.009 0.01090 0.00
6 Jan-18 S/. - S/. 14,181.19 S/. - 0.00% 1.022 1.009 0.01288 0.00
7 Feb-18 S/. - S/. 14,181.19 S/. - 0.00% 1.026 1.009 0.01685 0.00
8 Mar-18 S/. - S/. 14,181.19 S/. - 0.00% 1.024 1.009 0.01487 0.00
9 Apr-18 S/. 22,488.14 S/. 14,181.19 S/. 2,248.81 0.46% 1.028 1.009 0.01883 42.35
10 May-18 S/. 16,866.11 S/. 14,181.19 S/. 1,686.61 0.34% 1.036 1.009 0.02676 45.13
11 Jun-18 S/. 5,622.03 S/. 14,181.19 S/. 562.20 0.11% 1.040 1.009 0.03072 17.27
12 Jul-18 S/. - S/. 14,181.19 S/. - 0.00% 1.041 1.009 0.03171 0.00
13 Aug-18 S/. 12,880.30 S/. 14,181.19 S/. 4,508.10 0.92% 1.043 1.009 0.03370 151.91
14 Sep-18 S/. 2,768.05 S/. 14,181.19 S/. 2,008.40 0.41% 1.049 1.009 0.03964 79.62
15 Oct-18 S/. 6,693.75 S/. 14,181.19 S/. - 0.00% 1.064 1.009 0.05451 0.00
16 Nov-18 S/. 3,587.56 S/. 14,181.19 S/. - 0.00% 1.062 1.009 0.05253 0.00
TOTAL S/. 70,905.94 S/. 11,014.12 336.28

DEDUCCION TOTAL S/. 336.28

FORMULA N° 7 MITIGACION DE IMPACTO AMBIENTAL


MONTO DEL PRESUPUESTO CONTRATADO 175,300.80 INC. IGV
MONTO DEL PRESUPUESTO CONTRATADO 148,560.00 SIN IGV

PORCENTAJE DEL ADELANTO 20.00%

ADELANTO DIRECTO = 35,060.16 INC. IGV


ADELANTO DIRECTO = 29,712.00 SIN IGV

Valorizacion Adel. Otorg. Amortizacion Mes Porcentaje K Ka (K / Ka - 1) Deduccion

Nº MES MONTO (SIN IGV) Pagada Pago Adelanto Ax(VAL/C)x(K/Ka-1)

A (SIN IGV) d e f g= (e / f - 1) h= a x d x g

1 Aug-17 S/. - S/. 29,712.00 S/. - 0.00% 1.014 1.014 0.00000 0.00
2 Sep-17 S/. - S/. 29,712.00 S/. - 0.00% 1.010 1.014 -0.00394 0.00
3 Oct-17 S/. - S/. 29,712.00 S/. - 0.00% 1.008 1.014 -0.00592 0.00
4 Nov-17 S/. - S/. 29,712.00 S/. - 0.00% 1.009 1.014 -0.00493 0.00
5 Dec-17 S/. - S/. 29,712.00 S/. - 0.00% 1.011 1.014 -0.00296 0.00
6 Jan-18 S/. - S/. 29,712.00 S/. - 0.00% 1.013 1.014 -0.00099 0.00
7 Feb-18 S/. - S/. 29,712.00 S/. - 0.00% 1.018 1.014 0.00394 0.00
8 Mar-18 S/. - S/. 29,712.00 S/. - 0.00% 1.016 1.014 0.00197 0.00
9 Apr-18 S/. 59,880.00 S/. 29,712.00 S/. 5,988.00 1.22% 1.016 1.014 0.00197 11.81
10 May-18 S/. 58,440.00 S/. 29,712.00 S/. 5,844.00 1.19% 1.023 1.014 0.00888 51.87
11 Jun-18 S/. 2,460.00 S/. 29,712.00 S/. 246.00 0.05% 1.026 1.014 0.01183 2.91
12 Jul-18 S/. - S/. 29,712.00 S/. - 0.00% 1.028 1.014 0.01381 0.00
13 Aug-18 S/. 22,200.00 S/. 29,712.00 S/. 7,770.00 1.59% 1.029 1.014 0.01479 114.94
14 Sep-18 S/. 1,320.00 S/. 29,712.00 S/. 957.75 0.20% 1.030 1.014 0.01578 15.11
15 Oct-18 S/. 3,120.00 S/. 29,712.00 S/. - 0.00% 1.031 1.014 0.01677 0.00
16 Nov-18 S/. 1,140.00 S/. 29,712.00 S/. - 0.00% 1.033 1.014 0.01874 0.00
TOTAL S/. 148,560.00 S/. 20,805.75 196.64

DEDUCCION TOTAL S/. 196.64

RESUMEN DEL DEDUCTIVO

DEDUCTIVO TOTAL S/. 34,364.11


MAYORES GASTOS GENERALES
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

: "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE MARGOS - HUANUCO - HUANUCO"
►OBRA
►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE
►SUPERVISOR : ING. JOEL ABIGAEL BEDON VASQUEZ
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA
BASE LEGAL: Artículo 203° y 204 del Reglamento de la Ley de Contrataciones del Estado, aprobado mediante Decreto Supremo N° 184-2008-EF.

MONTO DEL VALOR REFERENCIAL (INC/IGV): S/. 12,382,031.20


COSTO DIRECTO: S/. 8,744,372.32

F.R. = 1.00

MAYORES GASTOS GENERALES


Io : Indice Gral. Ip : Indice Gral. MAYORES GASTOS
de precios al de precios al
Consumidor en la fecha de la causal Consumidor en GENERALES (GG
No. DESCRIPCION Ip/Io Diarios * # de dias
fecha del valor de prórroga la fecha de la
referencial (39) causal de de la
ENER/2017 prórroga (39) amplicion*Ip/Io)

1.00 DATOS REQUERIDOS


Gastos Generales Variables del Valor Ref. (Relacionados con el plazo) INC/IGV (GGV) S/. 874,437.23
Gastos Generales Variables del Contrato s/IGV (GGC = GGV*F.R.) S/. 874,437.23
Plazo de Ejecución de la Obra, en Días Calendario (PE) 365

Ampliación de Plazo N° 01 RESOLUCION DE GERENCIA N° Dias Calendario 75


Dias Calendarios ejecutados 73 438.8 Sep-18 444.57 1.013 177,187.13

2.00 CALCULO DE GASTO GENERAL DIARIO (GGD)


GGC S/. 2,395.72
GGD =
PE

3.00 CALCULO DE MAYORES GASTOS GENERALES (MGG) 177,187.13


SUB TOTAL 177,187.13

TOTAL 177,187.13

MAYORES GASTOS GENERALES A RECONOCER (S/IGV) S/. 177,187.13


INTERESES POR MORAS
►ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE MARGOS

►OBRA : "MEJORAMIENTO DE LOS SERVICIOS DE SALUD DEL CENTRO DE SALUD MARGOS, DISTRITO DE MARGOS - HUANUCO - HUANUCO"

►CONTRATISTA : CONSORCIO VÍRGEN DE GUADALUPE


►SUPERVISOR : ING. JOEL ABIGAEL BEDON VASQUEZ
►JEFE DE SUPERVISION : ING. JOEL ABIGAEL BEDON VASQUEZ
►RESIDENTE : ING. FERNANDO ESPINOZA SOTO
►SISTEMA DE CONTRATACION : A SUMA ALZADA
BASE LEGAL: Artículo 203° y 204 del Reglamento de la Ley de Contrataciones del Estado, aprobado mediante Decreto Supremo N° 184-2008-EF.

MONTO DEL VALOR REFERENCIAL (S/IGV): S/. 12,382,031.20


MONTO DEL CONTRATO (S/IGV): S/. 12,382,031.20

F.R. = 1.00
CALCULO DE INTERESES POR MORA EN EL PAGO DE VALORIZACIONES CONTRACTUALES Y ADICIONAL DE OBRA

BASE LEGAL: Artículo 197 del Reglamento de la Ley de Contrataciones del Estado, aprobado mediante Decreto Supremo N° 184-2008-EF.

TILEMN final: TASA DE INTERES LEGAL EFECTIVA EN MONEDA


CON TILE ACUMULADOS: I = Monto x ( TILEMN final / TILEMN inicio - 1 ) NACIONAL, a la fecha real de pago de la valorización.
TILEMN inicio: TASA DE INTERES LEGAL EFECTIVA EN MONEDA
NACIONAL, a la fecha máxima de pago de la valorización.

VALORIZACIONES EVALUACION PREVIA SOBRE PRESENTACION DE LA FECHA MAXIMA FECHA REAL DIAS DE
TILEMN (Inicio) TILEMN (Final) INTERESES
VALORIZACION DE PAGO DE PAGO MORA
Nº MES C/P N° MONTO (S/IGV) FECHA MAX.PREVISTA FECHA REAL COMENTARIO (a) (b) (a) (b) I
CONTRACTUAL
1 Aug-18 7 926,136.03 9/30/2018 4/13/2018 9/30/2018 4/13/2018 -170.00 7.43797 7.43797 0.00
12 Sep-18 5 648,034.16 10/31/2018 4/13/2018 10/31/2018 4/13/2018 -201.00 7.45279 7.43797 -1,288.63
13 Oct-18 6 405,181.21 11/30/2018 4/13/2018 11/30/2018 4/13/2018 -231.00 7.46729 7.43797 -1,590.93
4 Nov-18 9 83,661.05 12/31/2018 8/1/2018 12/31/2018 8/1/2018 -152.00 7.48230 7.41016 -806.61
15 Dec-18 15 461,476.50 1/31/2019 9/12/2018 1/31/2019 9/12/2018 -141.00 7.49776 7.42950 -4,201.31
16 Feb-19 22 Y 23 1,038,991.25 3/31/2019 9/26/2018 OK 3/31/2019 9/26/2018

-7,887.47

TOTAL (S/IGV) -S/.7,887.47


http://www.sbs.gob.pe/app/pp/EstadisticasSAEEPortal/Paginas/TILegalEfectiva.aspx