I. EARTHWORKS
QUANTITY DESCRIPTION UNIT COST AMOUNT
23.8 cu.m. - Excavation - 500.00 - Php 11,900.00
18.7 cu.m. - Backfill - 500.00 - Php 9,350.00
21,250.00
IV. REINFORCEMENTS
A. Materials
QUANTITY DESCRIPTION UNIT COST AMOUNT
170 pcs. - 16mm Ø x 6.00m Deformed Bars - Php 320.00 - Php 54,400.00
357 pcs. - 10mm Ø x 6.00m Deformed Bars - Php 130.00 - Php 46,410.00
37 kgs. - Ga. No. 16 G.I. Tie Wires - Php 60.00 - Php 2,220.00
Php 103,030.00
V. CEILING
A. Materials
QUANTITY DESCRIPTION UNIT COST AMOUNT
14 pcs. - Hardiflex 1/4" - Php 320.00 - Php 4,480.00
61 pcs. - 2" x 2" x 12' Eco Wood - Php 184.00 - Php 11,224.00
2 kgs. - 3" CWN - Php 70.00 - Php 140.00
1.5 kgs. - 2 1/2" CWN - Php 70.00 - Php 105.00
1 box - 1" Wood Screw - 250.00 - Php 250.00
Php 16,199.00
B. Septic Tank:
QUANTITY DESCRIPTION UNIT COST AMOUNT
170 pcs - 4" CHB - Php 9.00 - Php 1,530.00
11 pcs - 10mm Ø x 6.00m Deformed Bars - Php 130.00 - Php 1,430.00
1 kg - Ga. No. 16 G.I. Tie Wires - Php 60.00 - Php 60.00
1 cu.m - Washed Sand - Php 380.00 - Php 380.00
0.5 cu.m - Screened Gravel 3/4" - Php 400.00 - Php 200.00
10 bags - Portland Cement - Php 210.00 - Php 2,100.00
175 pcs - 5" CHB - Php 14.00 - Php 2,450.00
1 pcs - 4" PVP Pipe Orange 10' - Php 350.00 - Php 350.00
8,500.00
R E C A P I T U L A T I O N
I. EARTHWORKS - Php 21,250.00
II. CONCRETE WORKS - Php 43,620.00
III. MASONRY WORKS - Php 93,005.00
IV. REINFORCEMENTS - Php 103,030.00
V. CEILING - Php 16,199.00
VI. PREFAB/FABRICATED MATERIALS , including D - Php 51,550.00
VII. TRUSS AND ROOFINGS - Php 28,693.00
VIII. ELECTRICAL WORKS - Php 10,031.00
IX. PLUMBING AND PLUMBING FIXTURES - Php 28,208.00
X. PAINTWORKS - Php 15, 000.00
TOTAL ESTIMATED PROJECT COST - Php 395,586.00