EPC Template

This EPC contract contemplates that a single contractor will be responsible for the entire project -- from
design through construction and testing.

ARTICLE 3 - THE WORK

3.1 - Scope of Work. Contractor shall provide or perform the Work or cause the Work to
be provided or performed, in accordance with the terms of this Agreement. Without
limiting the foregoing, the Work shall include conducting, performing, providing or
procuring when and as necessary to permit progress of the Work to proceed in
accordance with the Project Schedule:
3.1.1 all design and engineering activities, procurement activities and services
necessary to conduct the Work and complete as per agreed timelines

ARTICLE 4 - CONTRACTOR’S RIGHTS AND RESPONSIBILITIES

4.1 - Engineering, Procurement and Construction of the Facility; Performance of the


Work. Contractor, on behalf of the Owner, shall act as the general contractor for the
Project and shall be solely responsible for the engineering, procurement and construction
of the Work, including, without limitation, the overall oversight and coordination of
construction of the Facility in accordance with: (a) the Specifications; (b) the
Authorizations for the Facility; (c) the terms of this Agreement; (d) the Traffic Control
Plan, the Safety Plan and the Security Plan; and (e) all applicable Laws. Contractor shall
coordinate the activities of Engineer, PM/CM, the Prime Subcontractors, the Safety
Director, the QA/QC Director and other persons providing labor and materials to the
Project to design, engineer and procure the equipment and materials for and complete the
construction of the Facility and act as the interface between the Owner and such persons
all in accordance with applicable Law and Good Utility Practice.