ID Task WBS Task Name Duration Start Finish Cost Half 1, 2012 Half 2, 2012

Mode J F M A M J J A S O
1 1 PRELIMINARIES 11 days Mon 20/2/12 Mon 5/3/12 RM70,200.00
2 1.1 Preliminaries 5 days Mon 20/2/12 Fri 24/2/12 RM64,200.00
3 1.1.1 Order Building Materials 1 day Mon 20/2/12 Mon 20/2/12 RM62,000.00
4 1.1.2 Site Layout 2 days Tue 21/2/12 Wed 22/2/12 RM700.00
5 1.1.3 Request Temporary Water & 1 day Thu 23/2/12 Thu 23/2/12 RM1,000.00
Electical Supply
6 1.1.4 Setting Out & Side Rail 1 day Fri 24/2/12 Fri 24/2/12 RM500.00
7 1.2 Frabicating Work 5 days Tue 28/2/12 Mon 5/3/12 RM6,000.00
8 1.2.1 Formwork 3 days Tue 28/2/12 Thu 1/3/12 RM3,200.00
9 1.2.2 Rebar 2 days Fri 2/3/12 Mon 5/3/12 RM2,800.00
10
11 2 SUB STRUCTURE 37 days Fri 2/3/12 Mon 23/4/12 RM37,800.00
12 2.1 Excavation/Installation/Concreting 16 days Fri 2/3/12 Fri 23/3/12 RM14,300.00
13 2.1.1 Excavation Site Base 3 days Fri 2/3/12 Tue 6/3/12 RM3,800.00
14 2.1.2 Grid Line Allignment 2 days Wed 7/3/12 Thu 8/3/12 RM1,000.00
15 2.1.3 Install Formwork 3 days Fri 9/3/12 Tue 13/3/12 RM2,500.00
16 2.1.4 Install Steel Bar 3 days Wed 14/3/12 Fri 16/3/12 RM3,000.00
17 2.1.5 Base Concrete Work 5 days Mon 19/3/12 Fri 23/3/12 RM4,000.00
18 2.2 Dismantling Work 6 days Fri 23/3/12 Fri 30/3/12 RM5,000.00
19 2.2.1 Dismantle Formwork 4 days Fri 23/3/12 Wed 28/3/12 RM3,000.00
20 2.2.2 Ground Bury Work 2 days Thu 29/3/12 Fri 30/3/12 RM2,000.00
21 2.3 Construct Ground Beam 11 days Sat 31/3/12 Mon 16/4/12 RM9,900.00
22 2.3.1 Grid Line Allignment/Levelling 3 days Sat 31/3/12 Tue 3/4/12 RM1,900.00

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PROPOSED OF A DOUB
Summary Manual Summary Rollup Progress
Date: Thu 31/12/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task WBS Task Name Duration Start Finish Cost Half 1, 2012 Half 2, 2012
Mode J F M A M J J A S O
23 2.3.2 Install Formwork 4 days Wed 4/4/12 Mon 9/4/12 RM3,200.00
24 2.3.3 Install Steel Bar 3 days Tue 10/4/12 Thu 12/4/12 RM3,000.00
25 2.3.4 Tie Up /Support Formwork 2 days Fri 13/4/12 Mon 16/4/12 RM1,800.00
26 2.4 Ground Floor Slab 14 days Wed 4/4/12 Mon 23/4/12 RM8,600.00
27 2.4.1 Filling Ground/Sand/Hardcore 3 days Wed 4/4/12 Fri 6/4/12 RM2,300.00
28 2.4.2 Laying Plastic Sheet 4 days Mon 9/4/12 Thu 12/4/12 RM2,000.00
29 2.4.3 Spread BRC 2 days Fri 13/4/12 Mon 16/4/12 RM1,800.00
30 2.4.4 Concrete Pouring to Slab 5 days Tue 17/4/12 Mon 23/4/12 RM2,500.00
31
32 3 SUPER STRUCTURE 107 days Fri 20/4/12 Mon 17/9/12 RM125,200.00
33 3.1 Building Pillars 19 days Fri 20/4/12 Wed 16/5/12 RM18,700.00
34 3.1.1 Grid Line Alignment Levelling 3 days Fri 20/4/12 Tue 24/4/12 RM1,800.00
35 3.1.2 Install Iron/Rebar 5 days Wed 25/4/12 Tue 1/5/12 RM4,500.00
36 3.1.3 Install Formwork 4 days Wed 2/5/12 Mon 7/5/12 RM3,200.00
37 3.1.4 Checking Verticality and Tie-up 2 days Tue 8/5/12 Wed 9/5/12 RM1,200.00
Formwork
38 3.1.5 Concrete Pouring to Column 5 days Thu 10/5/12 Wed 16/5/12 RM8,000.00
39 3.2 Building Roof Beam 25 days Thu 17/5/12 Wed 20/6/12 RM27,600.00
40 3.2.1 Provide/ Increase T-support/Staging 5 days Thu 17/5/12 Wed 23/5/12 RM3,000.00
41 3.2.2 Install Roof Beam Below Formwork 4 days Thu 24/5/12 Tue 29/5/12 RM4,500.00
42 3.2.3 Install Roof Beam Side Formwork 3 days Wed 30/5/12 Fri 1/6/12 RM3,900.00
43 3.2.4 Insert Iron Reinforcement/Re-bar 4 days Mon 4/6/12 Thu 7/6/12 RM4,000.00
44 3.2.5 Tie-up Roof Beamwork Formwork 2 days Fri 8/6/12 Mon 11/6/12 RM200.00

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PROPOSED OF A DOUB
Summary Manual Summary Rollup Progress
Date: Thu 31/12/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task WBS Task Name Duration Start Finish Cost Half 1, 2012 Half 2, 2012
Mode J F M A M J J A S O
45 3.2.6 Concrete Pouring to Roof Beam 7 days Tue 12/6/12 Wed 20/6/12 RM12,000.00
46 3.3 Roof Works 12 days Tue 19/6/12 Wed 4/7/12 RM8,000.00
47 3.3.1 Install the Wall Plate and Truss 6 days Tue 19/6/12 Tue 26/6/12 RM3,000.00
48 3.3.2 Laying Aluminium Foil/Timber Battern
2 days Wed 27/6/12 Thu 28/6/12 RM1,800.00
49 3.3.3 Install Roof Tiles 4 days Fri 29/6/12 Wed 4/7/12 RM3,200.00
50 3.4 Brick Works, Plaster & Ceiling 53 days Thu 5/7/12 Mon 17/9/12 RM70,900.00
51 3.4.1 Cold Water 10 days Thu 5/7/12 Wed 18/7/12 RM12,800.00
Plumbing/Sanitary/Sewerage
52 3.4.2 Electrical Works 12 days Thu 19/7/12 Fri 3/8/12 RM20,100.00
53 3.4.3 Finishing Works 21 days Mon 6/8/12 Mon 3/9/12 RM20,000.00
54 3.4.4 External Works 10 days Tue 4/9/12 Mon 17/9/12 RM18,000.00

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PROPOSED OF A DOUB
Summary Manual Summary Rollup Progress
Date: Thu 31/12/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only