PROJECT: PROPOSED TWO STOREY ZEN TYPE RESIDENTIAL BUILDING WITH FIREWALL
Scope of Works to be done Quantity Unit Unit Cost Material Cost Labor Cost TOTAL
(Labor &
Equipment)
I. GENERAL REQUIREMENTS
a. Temporary Facilities for
0 l.s - - - -
Engineer
b. Bunkhouse 0 l.s - - - -
Sub total - - -
II. MOBILIZATION
0 l.s - - - -
Sub total - - -
III. EARTHWORKS
a. Clearing & grubbing 54 sq.m ₱30.00 ₱1,620.00 ₱486.00 ₱2,106.00
b. Structure excavation 133.26 cu. m ₱200.00 ₱26,652.00 ₱7,995.60 ₱34,647.60
c. Backfilling & compaction 133.26 cu. m ₱200.00 ₱26,652.00 ₱7,995.60 ₱34,647.60
d. Select Fill 52 cu. m ₱823.00 ₱42,796.00 ₱12,838.80 ₱55,634.80
d1. Gravel bedding 9 cu. m ₱3,000.00 ₱27,000.00 ₱8,100.00 ₱35,100.00
e. Soil Poisoning 54 sq.m ₱16.42 ₱886.68 ₱266.00 ₱1,152.68
Sub total ₱125,606.68 ₱37,682.00 ₱163,288.68
IV. REINFORCED CONCRETE WORKS
a. 16mm RSB 186 pcs ₱295.00 ₱54,870.00 ₱16,461.00 ₱71,331.00
b. 12mm RSB 132 pcs ₱165.00 ₱21,780.00 ₱6,534.00 ₱28,314.00
c. 10mm RSB 1363 pcs ₱110.00 ₱149,930.00 ₱44,979.00 ₱194,909.00
c. 20mm RSB 73 pcs ₱500.00 ₱36,500.00 ₱10,950.00 ₱47,450.00
d. Tie wire 442 kg ₱70.00 ₱30,940.00 ₱9,282.00 ₱40,222.00
e. Portland cement 392 bags ₱208.00 ₱81,536.00 ₱24,460.80 ₱105,996.80
f. 3/4 Gravel 45.6 cu. m ₱3,000.00 ₱136,800.00 ₱41,040.00 ₱177,840.00
g. S-1 Sand 25.65 cu. m ₱1,500.00 ₱38,475.00 ₱11,542.50 ₱50,017.50
Sub total ₱550,831.00 ₱165,249.30 ₱716,080.30
V. MASONRY WORKS
a. 4" CHB 4298 pcs ₱15.00 ₱64,470.00 ₱19,341.00 ₱83,811.00
c. Portland Cement 183 bags ₱208.00 ₱38,064.00 ₱11,419.20 ₱49,483.20
d. S-1 Sand 16 cu. m ₱1,500.00 ₱24,000.00 ₱7,200.00 ₱31,200.00
Sub total ₱126,534.00 ₱37,960.20 ₱164,494.20
VI. FINISHING WORKS
a. Portland Cement 168 bags 208.00 34,944.00 10,483.20 45,427.20
b. S-1 Sand 10 cu. m 1,500.00 15,000.00 4,500.00 19,500.00
c. 60x60 unglazed floor tiles 0 pcs 150.00 - - -
d. 30x30 unglazed floor tiles 2708 pcs 40.00 108,320.00 32,496.00 140,816.00
e. 20x30 glazed wall tiles 0 pcs 15.00 - - -
f. Cement 21 bags 240.00 5,040.00 1,512.00 6,552.00
g. Cement filler 122 kg 70.00 8,540.00 2,562.00 11,102.00
h. Tile adhesive 27 bags 230.00 6,210.00 1,863.00 8,073.00
i.Metal Railings 3 l.s 5,000.00 15,000.00 4,500.00 19,500.00
j. Stair Grills 1 l.s 5,000.00 5,000.00 1,500.00 6,500.00
Sub total 198,054.00 59,416.20 257,470.20
VII. FABRICATED WORKS
a. Doors
Panel Type Door 5 pcs 4,000.00 20,000.00 6,000.00 26,000.00
Sliding Type Door 0 pcs - - - -
Flushed Type Door 4 pcs 1,100.00 4,400.00 1,320.00 5,720.00
b. Windows 6.6075 sq. ft 320.00 2,114.40 634.32 2,748.72
Sub total 26,514.40 7,954.32 34,468.72
VIII. ROOF AND FRAMING WORKS
a. 10' pcs of roof sheet 56 pcs ₱300.00 ₱16,800.00 ₱5,040.00 ₱21,840.00