Project Management
Project Management
D,9
20 50
I,15
E,15 F,5
A,7
J,10
B,17
10 40 70 90
M,10
G,8 K,10
C,12 N,7
H,11 L,8
30 60
C,12 N,7
H,11 L,8
30 60 80
90
N,7
N,7
Immdiate Duration
Activity Predessor ES EF LS LF Float
A - 5 0 5 10 15 10
B - 14 0 14 0 14 0
C A 11 5 16 15 26 10
D B 7 14 21 14 21 0
E C 8 16 24 26 34 10
F B,C 8 16 24 32 40 16
G D 12 21 33 21 33 0
H E 6 24 30 34 40 10
I F,H 5 30 35 40 45 10
J G 12 33 45 33 45 0
K G 6 33 39 48 54 15
L I,J 9 45 54 45 54 0
Project Duration 54
Immdiate Duration
Activity Predessor
A - 4 1
B A 9 2
C A 11 3
D B 6 4
E B 13
F C 7
G E,F 5
H F 11
I D 8
J I,G 9
K H,J 6
Draw Netwrok Diagram
Calculate ES, EF, LS, LF and Free Float for each activity
Find the optimal project duration
Identify the critical activities