IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
:Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD : ISSUED TO : M/s New Royal Electrical
1|P ag e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
CONTENTS
1. PURPOSE: ....................................................................................................................................................................................................................................................................... 3
2. SCOPE: ........................................................................................................................................................................................................................................................................... 3
2|P ag e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
1. PURPOSE:
This document describes the methodology for the installation method of ACSR conductor, and to ensure that all concerned persons are familiar with the sequence of
activities, utilization of resources, and execution of the works in compliance with applicable safety and quality procedures, reference documents and specification.
2. SCOPE:
This method statement identifies the general steps, arrangements and precautions required for execution of all the major stringing activities in 220KV/400KV
switchyard using ACSR Conductor for Stringing & installation work.
Stringing is the activity which will be commenced after tower erection. This activity involves installation of phase conductors in all the spans (between towers) in a
section, installation of insulator strings and conductor / earth wire fittings, with the help of machines and other stringing tools.
Stringing Jump rings SPACER
3|P ag e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
3. REFERENCE DOCUMENTS:
SL. NO DESCRIPTION DOCUMENT NUMBER (Write Manually)
01 Switchyard layout
02 Erection key diagram
03 ACSR schedule
04 Stringing hardware drawing
05 Sag tension sheet
06 Risk Assessment sheet
07 Manufacturer documents for ACSR conductor
08 Packing list of material
Safety Precautions: All below PPE’s are mandatory to carry the work. Additional PPE’s to be worn as per work
requirements or MSDS requirements.
4|P ag e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
Rope Grab Fall Arrester Twisted rope Anchorage lifeline Full Body Harness PN 56 Full Body Harness PN 43
Note: Actual Resource Plan both Tools & tackle and manpower will be review & finalized by Site in- charge.
5|P ag e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/00
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
5. RESOURCE PLANNING
A. TOOLS AND TACKLES:
No Item Description Quantity Remarks
1 Hydra/ Farana 01
2 Nylon lifting belt, PP rope 02 (Roll) As required length
3 Wire rope sling 01 (Roll) As required length
4 Guide rope 02 (Roll) As required length
5 Mechanical Tool Kit 02 With Spanners and all small tools
6 Four sheave pulley 02 With hook latch or closed pulley
7 Double sheave pulley 02 With hook latch or closed pulley
8 Balancing pulley 02 With hook latch or closed pulley
9 Cum along clamp (Shield wire) 02 Including one Spare
13 Measurement tape 01
14 Torque wrench 02
CLOVE HITCH PULLEYS COME ALONG CLAMP FOR COME ALONG CLAMP FOR CONDUCTOR ROLLERS HYDRAULIC CUTTER
CONDUCTOR SHIELD WIRE
6|P ag e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
b. Weight of Peak (in Ton): c) The recommended maximum angle between the
168.96 KG vertical and any leg of a sling is 45°
c. Capacity of Crane: 14 Ton.
d. Crane distance to be
maintained from Gentry: 1.5
to 2 meter Nylon lifting belt
Farana SWL- 3 tons, Width-75 mm d) A sling should not be pulled from under a load
when the load is resting on the sling.
7|P ag e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
6. SAFETY PRECAUTIONS:
1. The worker executing the job should be competent and medically fit for the job.
2. Work permits (PTW) to be obtained before starting installation activity.
3. Concerned engineer or Supervisor deputed for the work must be competent to the job.
4. Tool box talk shall be conducted prior to start the job daily for manual understanding of the workers involved in the job & report to be submitted.
5. Identified hazards and control measures shall be explained to team/work men through TBT/3Q meeting every day on start of the activity.
6. Risk assessment shall be done well in advance by concerned engineer and reviewed & approved by Safety officer, Site in charge / Client.
7. TPI (third party Inspection Certificate) of all the lifting tools tackles and equipment’s are to be submitted prior to entry site.
8. All lifting tools & tackles (Slings, D-shackles, pulley, wire rope slings & hydra itself) shall be inspected visually for safe use.
9. Man lifter/Farana/ Winch/ Crane are to be checked visually before starting installation.
10.Working area to be barricaded with warning tape to avoid entry of unauthorized persons.
11.Unauthorized person shall not be allowed to enter the work area during the work.
12.First aid box shall be made available with required medicines in adequate quantity at prominent locations.
13.All workers shall be explained about the provisions of first aid, assembly point and contact numbers etc.
14.Emergency rescue plan shall be explained to the all the workers and supervisors. Mock drill should be done for emergency rescue procedures.
15.Emergency vehicle shall be made available at site for meeting emergency needs.
8|P ag e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
7. PROCEDURES:
Steps / Task Work Description Safety Measures Pictures/ References
A. RECEIPT AND I. After receiving material and completing 1. All slings and crane TPI certificates are to be
UNLOADING OF inward formalities, packages are shifted submitted to Siemens prior to start the job.
ACSR to lay-down area in truck and unloading 2. There should be no sharp object on ground like
CONDUCTOR steel bars & Area should be clean.
DRUMS IN THE LAY is done with the help of crane or farana.
3. Proper space is to be maintained for free
DOWN AREA: II. Material is to be inspected and any movement of Farana/Trucks
damages are to be informed to client & 4. Conductor drums are unloaded in vertical position
back office. (on their flanges) by using hydra/crane.
III. Drum number and its length shall be 5. Manual unloading by pushing the drum is strictly
noted down for records and reference. prohibited.
6. The drums shall be stored on a well-drained hard
IV. Tagging & numbering is to be provided
surface so that they do not sink in the ground
on each drum as per drum number for causing rot and damage to the cable drums.
clear identification. 7. There should also be suitable ventilation between
drums.
8. ACSR drums will be directly unloaded on
compacted land by putting suitable shaft in the
drum holes & fixing the ceiling on both side of rod.
Suitable space between structures for crane/hydra
movements.
9. Two packing (Stopper) should be provided bellow
the drum so that drum will not move on both side.
10. ACSR Drums will not be stacked one above other.
9|P ag e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
10 | P a g e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
11 | P a g e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
12 | P a g e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
13 | P a g e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
Fixing of the jumpers from the stringing 1. Use man lifter for the fixing of the jumper from the
with the insulator or the bus bar. stringing conductor.
1.Take the length from the stringing 2. Use spacer cycle or man lifter for the height
conductor to the connecting clamp access and safe works.
connector on equipment s or bus bar. 3. Spacer will be lifted to the conductor height with
E. JUMP RING
2.Ensure to include the length of required slim ropes. Carrying spacer with hand not allowed.
curve during measurements. 4. Follow the SWMS for use of Man lifter for the safe
3.Fix the both end on top and down. use at site.
4.Fix the number of spacers in between the
conductors as per the drawings.
Fixing of the spacers between the
conductors.
1. Spacers will be fitted among the
conductors in certain distance as per
F. SPACER FIXING
drawings.
2. Ensure the spacers are fitted in exact
distance and right angle.
14 | P a g e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
Emergency Preparedness.
Follow emergency response plan & preparedness in case of emergency
Despite of all processes and fall arrest systems in place due to manual error or ill health of
person the possibility of person falling and arrested by safety harness cannot be ruled out.
Hence it is imperative to have a rescue plan in place before the work commences.
Thus we Introduced KARAM, PN 652 Rescue Kit for fulfilling the Rescue Operations If a
worker falls and is suspended by a full body safety harness,
Training to designated crew of Concerned Contractor earmarked to perform the work has
been given. This training includes on the job demonstration by working at height safety
expert
Contents of this training focuses on use of PN 652 rescue kit and its practical use. The crew
has been demonstrated how to use the equipment while they conduct the rescue operation.
Apart from this process, cherry picker will be available at site for emergency rescue if
emergency takes place.
15 | P a g e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
First Aid Box, Drinking Water & Job Location Wise Emergency Assembly Point
16 | P a g e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
As the job location varies there might be scarcity of Drinking water in Remote
locations of the working area so we must assure about the availability of Drinking
water in the work location / must be informed to task force to carry drinking water
along with them during mobilisation.
17 | P a g e
METHOD STATEMENT Doc. No. :
IMS/4.4.6.1/MS/MNR-NKD/01
ACSR CONDUCTOR STRINGING
Project : Package 2 - Lot A Construction of Nadukuda 220/33kV Grid Sub Station & Augmentation of Mannar 220/33kV Grid Sub Station Date :
Client : CEYLON Electricity Board Rev. No. : 01
ISSUED BY : SIEMENS LTD ISSUED TO : M/s New Royal Electrical
Do’s Don’ts
1. Always wear a PPE while Working. Wear dry, insulated gloves in good 1. Enter the site without proper PPE’s
condition and protective clothing. 2. Move in the Erection area during Lifting.
2. Follow Instructions from Supervisor and Safety Personnel. 3. Dump the debris near the site and working area.
3. Proper Access shall be provided for work area. 4. Conduct any unsafe action.
4. No Supervision, No Work. 5. Tools and materials shall not be thrown from ground to men working at
5. Observe the alertness on the construction site. height. And neither people working at height shall throw tools or
6. Check the tools and tackles before use. materials down.
7. Use the proper and appropriate tools and tackles. 6. Touch an energized electrode with bare hands.
8. Always use guy ropes while lifting and installation. 7. Use damaged undersized or poorly spliced cables for power supply.
9. Use fully insulated electrode holders. 8. Work in high wind pressure/velocity.
10. Always use plug tops and standard electrical joints with appropriate ratings
for cable joints.
11. Check the wind velocity prior to activity & ensure the allowed speed limit for
erection
Safely Closure of the Task
∂ Once the task is finished inform client to resume other agencies job and unblock the traffic block & other hindrances.
∂ Removal of miscellaneous hardware, clamps, connectors, conductor materials & insulators from individual locations and safely shifting to the
customer store.
∂ Removing lifelines from the towers
∂ Winding up of Tools & Tackles
∂ Closing of all work permits of individual locations
∂ Pre visiting & cross examine at all corresponding locations for proper assurance.
AUTHORIZATION
The Site In-charge is responsible person for installation of the ACSR conductor. The Site Engineer will be responsible for all construction activities at the site
and will directly supervise through erection supervisor / skilled workmen the work at site.