JADWAL WAKTU PELAKSANAAN ( KURVA

PEKERJAAN : PENYIAPAN LAHAN TBBM TANJUNG BATU


LOKASI : BALIKPAPAN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
TAHUN : 2019-2020 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

NOVEMBER '19 DESEMBER '19 JANUARI '20 FEBRUARI '20 MARET '20 APRIL '20 MEI '20 JUNI '20
NO JENIS PEKERJAAN VOLUME BOBOT (%) M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34
5 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22
10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28

A ENGINEERING
1 Pembuatan shop drawing 1.00 0.08 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - - - -

2 Pembuatan as built drawing dan foto dokumentasi 1.00 0.12 - - - - - - - - - - - - 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
B PROCUREMENT - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

1. Geocomposite Strip 3,121.25 0.70 - - - - - - - - - 0.14 0.14 0.14 0.14 0.14 - - - - - - - - - - - - - - - -

2 Geotextile Non Woven 49,674.83 1.39 - - - - - - - - - 0.28 0.28 0.28 0.28 0.28 - - - - - - - - - - - - - - - -

3 Conrrugated Concrete Sheet Pile 9,140.00 22.14 - - - - - - - 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 - - - - - - - - - - - - - -

C CONSTRUCTION
I. PEKERJAAN PERSIAPAN
1 Administrasi, perijinan dan keamanan 1.00 0.22 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03

2 Pengukuran elevasi tanah asli dilapangan / persiapan serta pengukuran selama pekerjaan timbunan
1.00 (include surveyor,
0.00 alat ukur, dll) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 Pekerjaan Bouwplank 1.00 0.16 - - 0.05 0.05 0.05

4 Pekerjaan fasilitas sementara Workshop, Gudang, Site Office (include furniture, ATK, Fasilitas komunikasi
1.00 dan informasi)
2.41 listrik kerja, air kerja 0.40 0.40 0.40 0.40 0.40 0.40

5 Mobilisasi/demobilisasi alat peralatan kerja 1.00 3.86 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26

6 HSE 1.00 0.91 0.18 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03

7 Temporary Jetty 1.00 0.16 - - 0.04 0.04 0.04 0.04

II. PEKERJAAN LAND CLEARING, STRIPPING & GRUBBING


1 Penebasan semak belukar, penebangan pohon, dan pembersihan humus 35,287.70 2.72 0.54 0.54 0.54 0.54 0.54

III. PEMBONGKARAN BANGUNAN EKSISTING 1.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

1. Pembongkaran bangunan eksiting 4,242.00 0.97 - - - - - - - - - - - - - - - - - - - - - 0.24 0.24 0.24 0.24 - - - - -


- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
IV. PEKERJAAN DINDING PENAHAN TANAH
Slope stability elevasi 10.00 m - elevasi 35.00

LEBARAN
SOIL NAILING - Aplikasi untuk slope elevasi 25.00 - 35.00 m
1 Pekerjaan soil nailing penahan lereng, tinggi 10m, el. 25-35 m length 249.7
- Temporary wall facing tebal 7.5 cm 3,121.25 2.64 - - - - - - - - - - - - - - - - - 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 - - - - -

- Rebar for wall facing , wiremesh M 8-150 3,121.25 0.66 - - - - - - - - - - - - - - - - - 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 - - - - -

- Permanent wall facing 15 cm precast per 1 m x 1 m 3,121.25 3.79 - - - - - - - - - - - - - - - - - - - 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 - -

- Rebar for wall facing , wiremesh M 8-150 3,121.25 0.66 - - - - - - - - - - - - - - - - - - - 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 - -

- Nailing per 4 m horizontal and 3 m layer vertical, nailing diameter 19 mm deform panjang 10
189.00
m termasuk centralizer
2.81 dengan mortar
- grouting
- type cement
- 2 dengan
- minimum
- fc' = -210 kg/cm2
- - - - - - RENCANA
- - -AWAL
- - - 0.28 0.28 0.28 0.28 0.28 0.28 0.28 0.28 0.28 0.28 - -

- Centralizer per nailing bar dipasang per 2.5 m 756.00 0.02 - - - - - - - - - - - - - - - - - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -

- Nail Head termasuk bearing plate penguat , hex nut ,washer, stud. Dengan size penguat bearing
189.00plate adalah 250
0.13mm x 50 mm,
- thickness
- 19 mm - - - - - - - - - - - - - - - - 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 - -

- Geotextile : Geocomposit strip 3,121.25 0.25 - - - - - - - - - - - - - - - - - 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 - -

- Pipa drain 1.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -


1.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2. Pekerjaan Geotextile non woven (continuous filament atau serabut menerus dengan bahan
49,674.83
polimer polypropylene).
1.30Diaplikasikan
- untuk elevasi
- 10 m- -25 m - - - - - - - - - - 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 - -

termasuk lekukan yang masuk ke dalam slope 1.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -


8.16 457.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
3. - Corrugated Concrete Sheet Pile,20 m Pilling kedalaman 15 m (include accesorry, strut penahan
9,140.00per 6 m) 14.60 - - - - - - - - - - - - - - 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 - -

- Strut diameter 25 mm dengan panjang 8 m dengan grouting fc' 21 Mpa termsuk centralized 77.00
dan head strut. Strut
0.20dipasang per
- 6 m sepanajng
- bibir- pantai - - - - - - - - - - 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 - - - - -

- Pemasangan wale steel diatas coorugated concrete 457.00 0.26 - - - - - - - - - - - - - - - - 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
V. PEKERJAAN CUT AND FILL - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

1. Pemeriksaan sampel tanah urug dengan CBR (California Bearing Ratio) terendam (soaked) test1.00
dan modified proctor
0.42 test setiap
- jarak interval
- maksimal
- 50 m memanjang
- -dan melintang
- per titik- di laboratorium
- mekanika
- tanah- by lembaga
- pendidikan
PROGRES REALISASI
- independen
- 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 - -

2. Pekerjaan timbunan (fill) kualitas baik kondisi padat (120% volume tanah lepas) tebal tiap
157,137.10
layer tidak lebih dari 20
9.28
cm (lepas) di- lokasi dengan
- urutan- kerja : - - - - - - - - - - 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 - -

3. Pekerjaan Galian (cut) termasuk penebasan semak belukar, penebangan pohon dan pembersihan
216,398.00humus 10.04 - - - - - - - - - - - - - 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 - -

4. Pemeriksaan kepadatan tanah dengan sand cone test layer by layer setiap luas maksimal 400 m2
1.00per titik di laboratorium
1.82 mekanika
- tanah- by lembaga
- pendidikan
- independen
- - - - - - - - - 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 - -

5. Soil Disposal 80,432.10 2.75 - - - - - - - - - - - - - - - - - - - - - - 0.46 0.46 0.46 0.46 0.46 0.46 - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
VI PEKERJAAN AKSES ROAD - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

1. Pekerjaan Akses Road lebar 6m buat construction 1,462.60 3.80 - - - - - - - - - - - - - - - - - - - - - - - - 0.95 0.95 0.95 0.95 - -

Pemadatan saja , alternative menggunakan subbase dan base coarse - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

SUB BASE COURSE CRUSHED STONE 200 THK + BASE COURSE GRANULAR COURSE 150 THK - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
VII. PEKERJAAN PENYELESAIAN - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

1 Pekerjaan pembersihan lapangan pada fase pelaksanaan proyek dan pasca proyek 1.00 0.17 - - - - - - - - - - - - - - - - - - - - - - - - 0.04 0.04 0.04 0.04 - -

2 Membangun kembali banguan eksisting yg sudah dibongkar 1,829.00 8.55 - - - - - - - - - - - - - 1.07 1.07 1.07 1.07 1.07 1.07 1.07 1.07 - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
RENCANA (KONTRAK) 100.00 0.21 0.05 0.05 0.05 0.05 0.05 0.05 2.51 2.94 3.36 3.36 3.31 3.58 6.77 6.99 6.99 4.55 4.95 4.70 5.20 5.20 4.37 4.83 4.83 5.82 5.15 5.15 4.89 0.00 0.00

KUMULATIF RENCANA (KONTRAK) - 0.21 0.26 0.32 0.37 0.43 0.48 0.54 3.05 6.00 9.36 12.73 16.04 19.62 26.39 33.38 40.37 44.92 49.87 54.57 59.77 64.96 69.33 74.16 78.99 84.81 89.96 95.11 100.00 100.00 100.00

RENCANA (ADDENDUM I) - - - - - - 3.32 2.10 15.52 0.19 0.32 2.26 0.20 0.14 0.16 0.15 0.26 0.04 0.02 0.02 0.03 - - - - - - - - - - - - -

KUMULATIF RENCANA (ADDENDUM I) - - - - - - 3.32 5.41 20.93 21.12 21.45 23.71 23.91 24.05 24.21 24.36 24.62 24.66 24.67 24.69 24.72 24.72 24.72 24.72 24.72 24.72 24.72 24.72 24.72 24.72 24.72 24.72 24.72 24.72

REALISASI PROGRES - - - - - - 3.32 2.10 15.52 0.19 0.32 2.26 0.20 0.14 0.16 0.15 0.26 0.04 0.02 0.02 0.03 - - - - - - -

KUMULATIF REALISASI PROGRES - - - - - - 3.32 5.41 20.93 21.12 21.45 23.71 23.91 24.05 24.21 24.36 24.62 24.66 24.67 24.69 24.72 24.72 24.72 24.72 24.72 24.72 24.72 24.72

DEVIASI (0.21) (0.26) (0.32) (0.37) (0.43) (0.48) 2.78 2.36 14.93 11.76 8.72 7.67 4.29 (2.34) (9.17) (16.01) (20.30) (25.21) (29.90) (35.07) (40.24) (44.61) (49.44) (54.27) (60.09) (65.24) (70.39) (75.28)
JADWAL WAKTU PELAKSANAAN ( KURVA - "S" )
PEKERJAAN : PENYIAPAN LAHAN TBBM TANJUNG BATU
LOKASI : BALIKPAPAN 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68
TAHUN : 2019-2020
WAKTU PELAKSANAAN 22 BULAN
JULI '20 AGUSTUS '20 SEPTEMBER '20 OKTOBER '20 NOVEMBER '20 DESEMBER '20 JANUARI '21 FEBRUARI '21
NO JENIS PEKERJAAN VOLUME BOBOT (%) M35 M36 M37 M38 M39 M40 M41 M42 M43 M44 M45 M46 M47 M48 M49 M50 M51 M52 M53 M54 M55 M56 M57 M58 M59 M60 M61 M62 M63 M64 M65 M66 M67 M68
29 6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15
5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21

A ENGINEERING
1 Pembuatan shop drawing 1.00 0.08 0.01 0.01 0.00 0.00 0.00 0.01 0.01 0.00 0.00 0.00

2 Pembuatan as built drawing dan foto dokumentasi 1.00 0.12 0.02 0.02 0.02 0.02
-
B PROCUREMENT -
1. Geocomposite Strip 3,121.25 0.70 0.13 0.13 0.13 0.13 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02

2 Geotextile Non Woven 49,674.83 1.39 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02

3 Conrrugated Concrete Sheet Pile 9,140.00 22.14

C CONSTRUCTION
I. PEKERJAAN PERSIAPAN
1 Administrasi, perijinan dan keamanan 1.00 0.22 -

2 Pengukuran elevasi tanah asli dilapangan / persiapan serta pengukuran selama pekerjaan timbunan
1.00 (include surveyor,
0.00 alat ukur, dll) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 Pekerjaan Bouwplank 1.00 0.16 0.08 0.02 0.06

4 Pekerjaan fasilitas sementara Workshop, Gudang, Site Office (include furniture, ATK, Fasilitas komunikasi
1.00 dan informasi)
2.41 listrik kerja, air kerja 0.16 0.37 0.36 0.38 0.41

5 Mobilisasi/demobilisasi alat peralatan kerja 1.00 3.86 0.45 0.50 0.48 0.50 0.37 0.34

6 HSE 1.00 0.91 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01

7 Temporary Jetty 1.00 0.16 0.04 0.04 0.04 0.04

II. PEKERJAAN LAND CLEARING, STRIPPING & GRUBBING


1 Penebasan semak belukar, penebangan pohon, dan pembersihan humus 35,287.70 2.72 0.84 0.84 0.84 0.19

III. PEMBONGKARAN BANGUNAN EKSISTING 1.00 -


1. Pembongkaran bangunan eksiting 4,242.00 0.97 0.17 0.35 0.35 0.11
-
IV. PEKERJAAN DINDING PENAHAN TANAH
Slope stability elevasi 10.00 m - elevasi 35.00
SOIL NAILING - Aplikasi untuk slope elevasi 25.00 - 35.00 m
1 Pekerjaan soil nailing penahan lereng, tinggi 10m, el. 25-35 m length 249.7
- Temporary wall facing tebal 7.5 cm 3,121.25 2.64 0.17 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.10

- Rebar for wall facing , wiremesh M 8-150 3,121.25 0.66 0.04 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.03

- Permanent wall facing 15 cm precast per 1 m x 1 m 3,121.25 3.79 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.15

- Rebar for wall facing , wiremesh M 8-150 3,121.25 0.66 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.07

- Nailing per 4 m horizontal and 3 m layer vertical, nailing diameter 19 mm deform panjang 10
189.00
m termasuk centralizer
2.81 dengan mortar grouting type cement 2 dengan minimum fc' = 210 kg/cm2 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.31

- Centralizer per nailing bar dipasang per 2.5 m 756.00 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

- Nail Head termasuk bearing plate penguat , hex nut ,washer, stud. Dengan size penguat bearing
189.00plate adalah 250
0.13mm x 50 mm, thickness 19 mm 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.01

- Geotextile : Geocomposit strip 3,121.25 0.25 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03

- Pipa drain 1.00 -


1.00 -
2. Pekerjaan Geotextile non woven (continuous filament atau serabut menerus dengan bahan
49,674.83
polimer polypropylene).
1.30Diaplikasikan untuk elevasi 10 m -25 m 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.06

termasuk lekukan yang masuk ke dalam slope 1.00 -


8.16 457.00 -
3. - Corrugated Concrete Sheet Pile,20 m Pilling kedalaman 15 m (include accesorry, strut penahan
9,140.00per 6 m) 14.60 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53 0.80

- Strut diameter 25 mm dengan panjang 8 m dengan grouting fc' 21 Mpa termsuk centralized 77.00
dan head strut. Strut
0.20dipasang per 6 m sepanajng bibir pantai 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.01

- Pemasangan wale steel diatas coorugated concrete 457.00 0.26 RENCANA ADDENDUM I 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.01
-
V. PEKERJAAN CUT AND FILL -
1. Pemeriksaan sampel tanah urug dengan CBR (California Bearing Ratio) terendam (soaked) test1.00
dan modified proctor
0.42 test setiap jarak interval maksimal 50 m memanjang dan melintang per titik di laboratorium mekanika tanah by lembaga pendidikan
0.08 independen
0.13 0.11 0.11

2. Pekerjaan timbunan (fill) kualitas baik kondisi padat (120% volume tanah lepas) tebal tiap
157,137.10
layer tidak lebih dari 20
9.28
cm (lepas) di lokasi dengan urutan kerja : 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.46

3. Pekerjaan Galian (cut) termasuk penebasan semak belukar, penebangan pohon dan pembersihan
216,398.00humus 10.04 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46

4. Pemeriksaan kepadatan tanah dengan sand cone test layer by layer setiap luas maksimal 400 m2
1.00per titik di laboratorium
1.82 mekanika tanah by lembaga pendidikan independen 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.09

5. Soil Disposal 80,432.10 2.75 0.03 0.34 0.34 0.34 0.34 0.34 0.34 0.34
-
VI PEKERJAAN AKSES ROAD -
1. Pekerjaan Akses Road lebar 6m buat construction 1,462.60 3.80 0.59 0.89 1.18 1.15

Pemadatan saja , alternative menggunakan subbase dan base coarse -


SUB BASE COURSE CRUSHED STONE 200 THK + BASE COURSE GRANULAR COURSE 150 THK -
-
VII. PEKERJAAN PENYELESAIAN -
1 Pekerjaan pembersihan lapangan pada fase pelaksanaan proyek dan pasca proyek 1.00 0.17 0.03 0.02 0.02 0.03

2 Membangun kembali banguan eksisting yg sudah dibongkar 1,829.00 8.55 0.32 1.06 0.99 1.54 0.82 1.70 1.49 0.63
-
34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68
RENCANA (KONTRAK) 100.00
KUMULATIF RENCANA (KONTRAK) -
RENCANA (ADDENDUM I) - - - - - 0.13 0.13 0.13 0.13 - - 0.71 1.87 3.52 5.80 4.57 4.45 3.69 4.57 4.36 3.49 3.30 4.06 3.76 2.69 2.59 2.61 2.93 2.74 2.31 2.18 2.41 2.74 1.35

KUMULATIF RENCANA (ADDENDUM I) 24.72 24.72 24.72 24.72 24.72 24.86 24.99 25.12 25.25 25.25 25.25 25.96 27.83 31.35 37.15 41.72 46.18 49.87 54.44 58.80 62.29 65.59 69.66 73.42 76.11 78.70 81.31 84.24 86.98 89.29 91.48 93.88 96.62 97.97

REALISASI PROGRES
KUMULATIF REALISASI PROGRES
DEVIASI
PEKERJAAN : PENYIAPAN LAHAN TBBM TANJUNG BATU
LOKASI : BALIKPAPAN 69 70 71 72 73 74
TAHUN : 2019-2020

MARET KETERANGAN
NO JENIS PEKERJAAN VOLUME BOBOT (%) M69 M70 M71 M72 M73 M74
22 1 8 15 22 29
28 7 14 21 28 4

A ENGINEERING 100 %
1 Pembuatan shop drawing 1.00 0.08
2 Pembuatan as built drawing dan foto dokumentasi 1.00 0.12 0.04
-
B PROCUREMENT -
1. Geocomposite Strip 3,121.25 0.70
2 Geotextile Non Woven 49,674.83 1.39
90 %
3 Conrrugated Concrete Sheet Pile 9,140.00 22.14

C CONSTRUCTION
I. PEKERJAAN PERSIAPAN
1 Administrasi, perijinan dan keamanan 1.00 0.22
2 Pengukuran elevasi tanah asli dilapangan / persiapan serta pengukuran selama pekerjaan timbunan
1.00 (include surveyor,
0.00 alat ukur, dll)
80 %
3 Pekerjaan Bouwplank 1.00 0.16
4 Pekerjaan fasilitas sementara Workshop, Gudang, Site Office (include furniture, ATK, Fasilitas komunikasi
1.00 dan informasi)
2.41 listrik kerja, air kerja
5 Mobilisasi/demobilisasi alat peralatan kerja 1.00 3.86 0.63 0.34 0.26

6 HSE 1.00 0.91 0.01

7 Temporary Jetty 1.00 0.16

II. PEKERJAAN LAND CLEARING, STRIPPING & GRUBBING 70 %


1 Penebasan semak belukar, penebangan pohon, dan pembersihan humus 35,287.70 2.72

III. PEMBONGKARAN BANGUNAN EKSISTING 1.00 -


1. Pembongkaran bangunan eksiting 4,242.00 0.97
-
IV. PEKERJAAN DINDING PENAHAN TANAH
60 %
Slope stability elevasi 10.00 m - elevasi 35.00
SOIL NAILING - Aplikasi untuk slope elevasi 25.00 - 35.00 m
1 Pekerjaan soil nailing penahan lereng, tinggi 10m, el. 25-35 m length 249.7
- Temporary wall facing tebal 7.5 cm 3,121.25 2.64
- Rebar for wall facing , wiremesh M 8-150 3,121.25 0.66
- Permanent wall facing 15 cm precast per 1 m x 1 m 3,121.25 3.79
50 %
- Rebar for wall facing , wiremesh M 8-150 3,121.25 0.66
- Nailing per 4 m horizontal and 3 m layer vertical, nailing diameter 19 mm deform panjang 10
189.00
m termasuk centralizer
2.81 dengan mortar grouting type cement 2 dengan minimum fc' = 210 kg/cm2
- Centralizer per nailing bar dipasang per 2.5 m 756.00 0.02
- Nail Head termasuk bearing plate penguat , hex nut ,washer, stud. Dengan size penguat bearing
189.00plate adalah 250
0.13mm x 50 mm, thickness 19 mm
- Geotextile : Geocomposit strip 3,121.25 0.25 40 %
- Pipa drain 1.00 -
1.00 -
2. Pekerjaan Geotextile non woven (continuous filament atau serabut menerus dengan bahan
49,674.83
polimer polypropylene).
1.30Diaplikasikan untuk elevasi 10 m -25 m
termasuk lekukan yang masuk ke dalam slope 1.00 -
8.16 457.00 -
3. - Corrugated Concrete Sheet Pile,20 m Pilling kedalaman 15 m (include accesorry, strut penahan
9,140.00per 6 m) 14.60
- Strut diameter 25 mm dengan panjang 8 m dengan grouting fc' 21 Mpa termsuk centralized 77.00
dan head strut. Strut
0.20dipasang per 6 m sepanajng bibir pantai 30 %
- Pemasangan wale steel diatas coorugated concrete 457.00 0.26
-
V. PEKERJAAN CUT AND FILL -
1. Pemeriksaan sampel tanah urug dengan CBR (California Bearing Ratio) terendam (soaked) test1.00
dan modified proctor
0.42 test setiap jarak interval maksimal 50 m memanjang dan melintang per titik di laboratorium mekanika tanah by lembaga pendidikan independen
2. Pekerjaan timbunan (fill) kualitas baik kondisi padat (120% volume tanah lepas) tebal tiap
157,137.10
layer tidak lebih dari 20
9.28
cm (lepas) di lokasi dengan urutan kerja :
3. Pekerjaan Galian (cut) termasuk penebasan semak belukar, penebangan pohon dan pembersihan
216,398.00humus 10.04 0.34 20 %
4. Pemeriksaan kepadatan tanah dengan sand cone test layer by layer setiap luas maksimal 400 m2
1.00per titik di laboratorium
1.82 mekanika tanah by lembaga pendidikan independen
5. Soil Disposal 80,432.10 2.75 0.34
-
VI PEKERJAAN AKSES ROAD -
1. Pekerjaan Akses Road lebar 6m buat construction 1,462.60 3.80
Pemadatan saja , alternative menggunakan subbase dan base coarse - 10 %
SUB BASE COURSE CRUSHED STONE 200 THK + BASE COURSE GRANULAR COURSE 150 THK -
-
VII. PEKERJAAN PENYELESAIAN -
1 Pekerjaan pembersihan lapangan pada fase pelaksanaan proyek dan pasca proyek 1.00 0.17 0.05 0.02

2 Membangun kembali banguan eksisting yg sudah dibongkar 1,829.00 8.55 0%


-
68 69 70 71
RENCANA (KONTRAK) 100.00
KUMULATIF RENCANA (KONTRAK) -
RENCANA (ADDENDUM I) 1.41 0.36 0.26

KUMULATIF RENCANA (ADDENDUM I) 99.38 99.74 100.00

REALISASI PROGRES
KUMULATIF REALISASI PROGRES
DEVIASI