Concrete Calculation and Boring Depth Along With Location of Bores
Concrete Calculation and Boring Depth Along With Location of Bores
Actual
Calculated With Wastage of
S. Pile Depth Plant Concerete Sum
Date Location Concrete 2.5 m3 (Slush/Bore
No Type (ft) Concrete (m3)
(m3) Wash)
(m3)
Anchor Pile
1 15 December 2020 P3 55 5.485705184 7.985705184 12.5 110
(4th R & 3rd C)
2 18 December 2020 P2 43 1st R & 1st C 4.41776562 6.91776562 8 Bores Depth (ft)
Test Pile
3 20 December 2020 P3 50 5.040730365 7.540730365 7.5 631
(5th R & 3rd C)
4 22 December 2020 P2 38 1st R & 2nd C 3.972790801 6.472790801 8 Nos. of P3
Anchor Pile
5 23 December 2020 P3 42 4.328770656 6.828770656 7 6
(6th R & 3rd C)
6 26 December 2020 P3 50 6th R & 2nd C 5.040730365 7.540730365 6 Nos. of P2