CONCRETE CALCULATION AND BORING DEPTH ALONG WITH LOCATION OF BORES

Actual
Calculated With Wastage of
S. Pile Depth Plant Concerete Sum
Date Location Concrete 2.5 m3 (Slush/Bore
No Type (ft) Concrete (m3)
(m3) Wash)
(m3)
Anchor Pile
1 15 December 2020 P3 55 5.485705184 7.985705184 12.5 110
(4th R & 3rd C)
2 18 December 2020 P2 43 1st R & 1st C 4.41776562 6.91776562 8 Bores Depth (ft)
Test Pile
3 20 December 2020 P3 50 5.040730365 7.540730365 7.5 631
(5th R & 3rd C)
4 22 December 2020 P2 38 1st R & 2nd C 3.972790801 6.472790801 8 Nos. of P3
Anchor Pile
5 23 December 2020 P3 42 4.328770656 6.828770656 7 6
(6th R & 3rd C)
6 26 December 2020 P3 50 6th R & 2nd C 5.040730365 7.540730365 6 Nos. of P2

7 28 December 2020 P2 39.5 2nd R & 1st C 4.106283247 6.606283247 11 8

8 28 December 2020 P3 42 7th R & 2nd C 4.328770656 6.828770656 8.5 Nos. of P1

9 31 December 2021 P2 48 3rd R & 1st C 4.862740438 7.362740438 8 0

10 1 January 2021 P3 46 8th R & 2nd C 4.684750511 7.184750511 6.5

11 7 January 2021 P2 48 2nd R & 2nd C 4.862740438 7.362740438 10

12 7 January 2021 P2 40.5 6th R & 1st C 4.19527821 6.69527821 10

13 9 January 2021 P2 46 3rd R & 2nd C 4.684750511 7.184750511 7

14 P2 43 7th R & 1st C 4.41776562 6.91776562