SUMMARY OF DELAYED ACTIVITIES FOR PIPING AND MECHANICAL

LOCATION DELAYED Grand Total


(RAS/SAS) Recirculated / Surplus activated Sludge Pumping station120 5 5
Fabrication of Pipe spool and Fittings 1 1
U/g Trenching works 1 1
(blank) 1 1
Installation of Equipments - Excess Sludge pumps ,Monorail, I Beam ( For or all RAS Tank) 1 1
Bolting and Alignment 1 1
Blower building - 065 1 1
U/g Trenching works 1 1
Inlet Distribution Chamber 2 2
Fabrication of Pipe spools and fittings 1 1
U/g Trenching works 1 1
Plant drain Pumping station 180 1 1
Fabrication of Pipe spool and Fittings 1 1
Sand Filter - 090 4 4
( Air/Water) Dirty backwash line from filters to ReTank -500Dia grp (700d/72mt,700d/140,400d/140) 1 1
Pressure testing of U/G pipes 1 1
U/g Trenching works 1 1
(blank) 1 1
SecondarySedimentation Tank (Clarifier - 080/070) 3 3
Fabrication of Pipe spool and Fittings 1 1
Install Pipes Drive to Distribution chamber - Area 2 (effluent shaft line) 1 1
Installation of Pipes FST to RAS PS DN500 (GRP) + SPS DN150 (HDPE) (4nos) - Area 2 1 1
Fine screens 030 1 1
Installation of Screening Wash press ( Compactor) 1 1
Grit and Grease Removal- 040 1 1
Installation of Penstock -Inlet and Outlet 1 1
Biological Tanks - 050 / 060 AST 7 7
Fabrication of Pipe spool and Fittings 1 1
U/g Trenching works 1 1
(blank) 1 1
Installation of Mixers ( All 3 biotank) 1 1
Installation of Aeration diffuser system 1 1
Installation of Pipes from AT to FST DC (GRP) - 1400 - Area 2 1 1
Installation of Pipes from AT to FST DC (GRP) - 1400 - Area 3 1 1
Grand Total 25 25