QUANTITY SHEET

Estimate Take-off Sheet


Company: IAG INTERNATIONAL LLC Estimator: Date: 06/12/2020
Project: CONSTRCUCTION OF HANDWASHBASIN Checked by: Date:
Address: OFFICE 4TH FLOOR, BLCK B THE GADOI REGENCY
TARBUNKA AVENUE, MOGADISHU SOMALIA
IAG DEPARTMENT: ENGINEERING

Description Q = Qty L = Length W = Width D = Depth T = Thickness H = Height Calculation Total/ Unit
Earthwork in Excavation in
1 3 0.6 0.6 0.35 0.378 Cu M
Foundation:

2 Earth Filling in Pad foundation 3 0.6 0.4 0.35 0.25 Cu M

3 Concrete in Wash Hand Base 2 0.8 0.8 0.075 0.10 Cu M

4 Concrete for Hand Basin 3 1 0.1 0.475 0.14 Cu M


4 0.8 0.1 0.475 0.15 Cu M
Total 0.29 Cu M

6 BlockWork 3 1 0.875 2.63 Sq M


1 SQM=13BLOCKS 34 Blocks

7 Concrete in BLOCKS 0.31 Cu M

10 Plaster 2 1 0.025 1 2 Sq M
2 1.9 0.025 0.475 2 Sq M
10 0.8 0.025 0.4 3.2 Sq M
Total 7 Sq M

Total Concrete Requirement 0.70 Cu M

PREPARED BY OG 1 OF 1 Date:12/6/2020