M3Topic1 Initial Project Coordination and Project Launch Meeting NEW

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

PROJECT MANAGEMENT

Module 3
Project Planning

Topic 1
Initial Project Coordination and Project Launch Meeting

by:
Dr. Madel Miraña-Poot
Project Planning

• The primary purpose of planning is to establish a set of


directions in enough detail to tell the project team exactly
what must be done
• The purpose of planning is to facilitate later accomplishment
Initial Project Coordination

• It is crucial that the project’s objectives be clearly tied to


the overall mission of the firm
– A project launch meeting is an initial coordinating
meeting that serves as a visible symbol of top
management’s commitment to the project
– The project launch meeting’s success is absolutely
dependent on the existence of a well-defined set of
objectives
Project Launch Meeting
Should not allow plans, schedules, and budgets to go
beyond the most aggregated level at the launch meeting
The outcomes should be:
– 1. Technical Scope is established
– 2. Basic areas of performance responsibility
are accepted by the participants
– 3. Some tentative overall schedules and
budgets are spelled out
Composite Plan
• Each individual/unit accepting responsibility for a portion
of the project should agree to deliver a preliminary plan
about how that responsibility will be accomplished

• These plans should contain descriptions of the required


tasks, and estimates of the budgets and schedules

• These plans are then scrutinized by the group and


combined into a composite project plan
Composite Plan
• The composite plan, still not completely firm, is approved
by each participating group, by the project manager, and
then by senior organizational management

• Each subsequent approval hardens the plan, and when


senior management has endorsed it, any further changes
in the project’s scope must be made by processing a
formal change order
Composite Plan
• The composite plan, still not completely firm, is approved
by each participating group, by the project manager, and
then by senior organizational management

• Each subsequent approval hardens the plan, and when


senior management has endorsed it, any further changes
in the project’s scope must be made by processing a
formal change order
Companies Who Do Projects for External Clients
• Must select which projects they will bid on
• Generally based on…
• Their own expertise and track record
• Resources they have available
• Their chance of winning the bid
• Preparing a bid is expensive
• They do not want to waste that effort on bids where they
are unlikely to be successful
Companies Considering Internal Projects
• Must decide which potential projects they will pursue
(sometimes among many competing projects)
• Available capital is the major constraint
• Profitability is often the major criteria
• Must evaluate approaches when there is more than one
project that can accomplish a particular business goal
Reference:
Project Management: A Managerial Approach 8th edition
By Jack R. Meredith and Samuel J. Mantel, Jr.
Published by John Wiley & Sons, Inc.

THANK YOU
Stay safe and GOD bless!

You might also like