Professional Documents
Culture Documents
Production (Utilities) Heavy Water Plant (Manuguru) Gautaminagar - 507 116 Khammam Dist. Telangana State
Production (Utilities) Heavy Water Plant (Manuguru) Gautaminagar - 507 116 Khammam Dist. Telangana State
OPERATION MANUAL
COPY NO.
2. Abbreviations PU/III/87/B 1
5. Preface PU/III/87/E 1
6. Introduction PU/III/87/1 2
2. AM Auxiliary Module
3. AUX Auxiliary
0. MASTER COPY
8. RTC FIELD STAFF OF THE UNIT (Hard copy available in Dy.SS cabin)
Current
New revision
S.No Doc. Page revision
Remarks
. No. No.
No. Date No. Date
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
The copyholder shall make entry in this amendment sheet regarding the details of
amendments.
PREFACE
system as intended. Though every effort has been made to include all details
required for operation, it may be noted that it is difficult to foresee each and every
contingency that may arise during operation of the system and no amount of written
preparing final OTOs which depends on conditions of the process existing at that
time and also one may have to ascertain the conditions from field.
Sd/-
(M. SUBBARAMAIAH)
1.0 The Captive Power Plant, HWP (M) has Uninterrupted Power Supply
(UPS) System of 2 X 80 KVA, 110V AC, 1 phase, 50 Hz rating as the
CLASS-II power supply. These power are used for the following purposes
for Unit-1, 2, 3 and common system-
a) Control desk Operator Stations.
b) MP, NT, BMS and TG I&P CPUs and related network switches.
c) Field Analyzer panels such as On line Oxygen Analysers
d) Turbovisory Panels & SER Supervisory Station
e) Generator Relay Panels, Thyristor Panel and Annunciation.
f) TCP, BCP, GCP and Hydra step.
g) Sampling system
h) Unit Variable Frequency Drives.
i) Air compressors control system.
j) Common MP and NT CPUs
1.1 The present UPS system is commissioned due to increased class II loads.
1.2 The input power supplies for UPS system are taken from NESG, Fire
Protection MCC and DGSWGR.
1.3 For details of power circuit refer to the Drg. No-0-87-FS-01
1.4 In case of failure of UPS supply of 110V (Class-II), following system will be
affected:-
a) TG-1, 2&3 will trip on shaft vibration very high.
b) All running air compressors will trip.
c) All VFD related motors will trip.
d) Following protections of Generators will become non-functional.
1) Negative sequence
2) Rotor earth fault
3) Over fluxing protection of generator transformer
e) Hydra step will not function. Drum level protection based on hydra
step will be non functional.
f) CPUs are powered through UPS hence no information and
communication from and to system and monitors of all units will go
off. However system will be in service with I/O module based on field
inputs to the system.
g) SER (Sequence Event recorder) will not work.
h) All analyzers i.e., water, steam & on- line O 2 meter will not function
and will show zero value.
i) Telephonic communication (fed from UPS) will be non-functional.
Captive Power Plant, HWP (M) has Uninterrupted Power Supply (UPS) System
of 2 X 80 KVA, 110V AC, 1 phase, 50 Hz rating as the CLASS-II power supply.
2.1Components of UPS system:-
Main Distribution Unit:-This unit is a part of our installation. It distributes the
Mains (utility) and/or Generator power to our facility and supplies input power to
our UPS system.
Auxiliary Module: - An auxiliary module consisting of a Servo control Voltage
stabilizer to provide a stable alternate supply to the load incase of failure of both
UPS modules.
UPS module: - Consist of two UPS module (without battery).
Battery module: - This module comprises the battery pack for supplying power to
the UPS module in the event of a mains failure.
Output Distribution Module:- Output of the UPS system needs to be distributed to
various loads. Each module comprises switches, fuses for each load.
List of distribution modules are attached in annexure
Auxiliary
Module
L
Mains Distribution UPS
Output
Distribution
O
Unit Module Module A
D
S
Battery
Module
2.3 UPS Module:- In CPP UPS system two UPS module are used as a parallel
redundant configuration system. Each UPS modules are having following
components:
A rectifier
An inverter
Battery
Static switch
input and output circuit breakers
Keypad-LCD-LED Mimic console
an annunciation system
Rectifier: - It converts the AC mains to regulated DC power, supplies DC power to
the inverter and charges the battery when main power supply is present.
Battery: - Stores energy while main supply is present. Delivers energy (DC
supply) to the inverter when main supply is absent.
Static Switch THS4 & THS5:- It is Bi-directional, solid state transfer switch.
Normally it connects the inverters output to the load through CBI, rectifier,
inverter, static switch (THS4) and MIS. Automatically it transfers the load to an
Alternate supply if both UPS fails or overload, through CB1, SCVS, CBA, static
switch (THS5) and MIS and again automatically re-transfers the load from the
alternate supply to the UPS module, once the inverters are healthy or the
overload condition has ceased.
If both UPS modules are to be given for maintenance then 110V supply can
be extended through CB1, SCVS and by manual closing of CBO. In that case
both MIS; both CBA and both CBI must be in open condition. This can be done
parallelly or independently as per requirement.
Flow of Power: - The input supply voltage is 415V, 3-phase, 50 Hz, AC for UPS-
1, 2 and Alternate power supply (bypass) which are getting power supplies from
DGSWGR, fire protection MCC and NESWGR respectively. It is stepped down to
380V, 3 phases, 50 Hz AC in UPS-1&2 by input isolation transformer (TF1)and
415V, 3 phase to 1-phase through bypass transformer.
In Alternate input of UPS system after TF1, 1PH, AC is fed to SCVS and output is
1PH, 110V AC. This 110V AC is fed to UPS loads via static switch (THS5) or via
CBO as per our requirement.
4.1 Startup of UPS system from cold i.e. from fully shutdown condition:-
Note: Ensure that all the work permits on the system are cleared and startup
authorisation is existing.
Preconditions:-
Procedure:-
Procedure:-
Note:
The START/STOP key must be kept depressed for aprox 3 sec,s in order to
initiate the action.
The UPS inverter is designed for continuous operation, as such start / stop
operation may not be required.
It is recommended that the UPS be left ON as far as possible.
Procedure:-
S.
Alarm Possible cause Actions
No.
1. Input Under 1. Mains failure/ 1. If supply problem, restore
voltage supply problem the same.
(-15% of 415V) 2. Calibration error 2. If the condition is persist,
Inform E/M.
Sl.
Module No. & Switchgear Purpose
No.
AC DISTRIBUTION BOARD – 1
FEEDER
DESCRIPTION TYPE RATIN
NUMBER
G
INCOME
INCOMER FROM UPS MCB 800 A
R
TIE BKR TIE FROM ACDB-4 MCB 400 A
01 BMS CPU PANEL FF
02 NT CPU PANEL FF
03 MP CPU PANEL FF
04 GENERATOR CONTROL DESK FF
05 GRP, THYRISTOR, ANNUNCIATION FF
06 SAMPLING FF
07 FIELD ANALYZER FF
08 TURVOVISORY PANEL, SER FF
09 GCP, TCP, BCP, HYDRASTEP FF
10 TGIP CPU PANEL FF
11 SG VFD FEEDER-1 FF
12 SG VFD FEEDER-2 FF
AC DISTRIBUTION BOARD – 2
INCOME
INCOMER FROM UPS MCB 800 A
R
TIE BKR TIE FROM ACDB-4 MCB 400 A
01 BMS CPU PANEL FF
02 NT CPU PANEL FF
03 MP CPU PANEL FF
04 GENERATOR CONTROL DESK FF
05 GRP, THYRISTOR, ANNUNCIATION FF
06 SAMPLING FF
07 FIELD ANALYZER FF
08 SER, TURVOVISORY PANEL FF
09 GCP, TCP, BCP, HYDRASTEP FF
10 TGIP CPU PANEL FF
11 SG VFD FEEDER-1 FF
12 SG VFD FEEDER-2 FF
AC DISTRIBUTION BOARD – 3
FEEDER
DESCRIPTION TYPE RATIN
NUMBER
G
INCOME
INCOMER FROM UPS MCB 800 A
R
TIE BKR TIE FROM ACDB-4 MCB 400 A
01 BMS CPU PANEL FF
02 NT CPU PANEL FF
03 MP CPU PANEL FF
04 GENERATOR CONTROL DESK FF
05 GRP, THYRISTOR, ANNUNCIATION FF
06 SAMPLING FF
07 FIELD ANALYZER FF
08 TURVOVISORY PANEL, SER FF
09 GCP, TCP, BCP, HYDRASTEP FF
10 TGIP CPU PANEL FF
11 SG VFD FEEDER-1 FF
12 SG VFD FEEDER-2 FF
AC DISTRIBUTION BOARD – 4
INCOME
INCOMER FROM UPS MCB 800 A
R
TIE BKR U-1 TIE TO ACDB-1 MCB 400 A
TIE BKR U-2 TIE TO ACDB-2 MCB 400A
TIE BKR U-3 TIE TO ACDB-3 MCB 400A
110/230 VOLT T/F HOST COMPUTER
01 FF
ROOM
02 COOLING WATER PUMP HOUSE FF
03 `SPARE FF
AIR COMPRESSOR CONTROL
04 FF
SUPPLY
05 U-1 MP PANEL-56 FF
06 COMMON MP AND NT CPU PANEL FF
07 CCP FF
08 6C COMMON FF
SPARE FF
SPARE FF
110/230V TRANSFORMER IN HOST COMPUTER ROOM FEEDS ENGINEER
STATION, TELEPHONE EXCHANGE, DYSS AND L-DESK COMPUTERS,
WALKIE-TALKIE CHARGERS, MASTER STATION AND 230V IN MCR.
S.
Fault Possible cause Actions
No.
1. DC over voltage 1.Rectifier control 1. Inform E/M
problem 2. Inform E/M
2. Calibration error
2. Inverter over 1. Inverter 1. Inform E/M
voltage control
problem.
2. Calibration
error.
3. Inverter 1. The inverter 1. Remove the excess load.
Overload trip. output was 2. Try starting the inverter & if
(This trip is severely unsuccessful. Inform E/M
inverse time overloaded &
acting i.e. more Alt supply
the overload was not
faster the trip) available for
transfer.
2. Calibration
error
4. Inverter Limb 1 1. The inverter 1. Try starting the inverter
or Limb 2 fault- output was severely & if unsuccessful. Inform
Trip overloaded & Alt E/M
supply was not
available for transfer.
ANNEXURES
b) Output:
i) Module output rating KVA : 80 KVA
KW : 64 KW
ii) Output voltage : 110V AC, 1 phase, 2 wires
iii) Output frequency : 50 Hz
iv) Full load current : 727 amps.
v) Load power factor : 0.8
vi) Voltage adjustment range : +5%,
vii) Voltage regulation O-FL : +1%,
viii) 1. Mains synchronization : 50 Hz ± 0.01 % free run
tracking 50 Hz ± 5% Bypass
2. Slew Rate : 0.1 Hz/Sec.
ix) Output voltage harmonics : THD<2.5% for Linear loads
: THD<4.5% for non linear loads
x) Overload rating : 125% for 600 sec.
150% for 10 sec.
300% for 1 cycle
the modules.
Automatic transfer
(synchronous)
1) OTO FOR MAINTENANCE OF UPS-1 & 2 SYSTEMS & its ALTERNATE SUPLLY.
Order to operate must be listed in the order in which the issuer intends them to be performed and
must be performed in the order in which they are listed.The operator who is delegated to perform the
operations listed shall check the positions and tagging of any devices which must be in any particular
position while the operations are being performed. State the required condition or position of the
apparatus. The order meant that the equipment must be left in the state or position indicated.
_________________________________________________________________________
PURPOSE OF ORDER: TO ISOLATE UPS FOR PREVENTIVE MAINTENANCE
Permit No To issue [ ] To clear [ ] (Tick whichever is applicable)
S.NO EQUIPMENT STATUS REQUIRED TAG NOS. INITIALS
PLACE
01 Take approval for giving UPS system for maintenance.
02 Inform I/M Regarding Shut Down Of UPS. They Will Make Arrangements For
Keeping their Disks Un-erased. Alternate Supply To Be Arranged For Air Compressor
Control Supply.
03 Telephone Exchange Has A Battery Bank Which Can Serve Upto 8 Hrs. Work On
UPS Should Be Completed Within This Time.
04 O/G Module No.6.4F On NESG To OFF, REMOVE FUSES &
UPS(bypass) TAG
05 O/G Module No.6.4R On Fire Protection OFF, REMOVE FUSES &
MCC To UPS-2 TAG
06 O/G Module No.8.8F On DGSWGR To OFF, REMOVE FUSES &
UPS-1 TAG
07 Fuses Near UPS Battery Bank To Be
Removed By E/M
08
Total no. of Tags : 3
Prepared by Time Date
Checked by Time Date
Issued by Time Date
Performed by Time Date
Sheet 1/1
Order to operate must be listed in the order in which the issuer intends them to be performed and
must be performed in the order in which they are listed.The operator who is delegated to perform the
operations listed shall check the positions and tagging of any devices which must be in any particular
position while the operations are being performed. State the required condition or position of the
apparatus. The order meant that the equipment must be left in the state or position indicated.
_________________________________________________________________________
PURPOSE OF ORDER: TO ISOLATE for UPS-1 MAINTENANCE.
Permit No To issue [ ] To clear [ ] (Tick whichever is applicable)
S.NO EQUIPMENT STATUS REQUIRED TAG NOS. INITIALS
PLACE
01 Take approval for giving UPS MODULE - 1 for maintenance.
02 Ensure that the load of UPS module-1 has been shifted to UPS module-2 or Alternate
supply.(Note down the currents before & after load shifting)
03 Open the static switch THS4 & THS5 of UPS ENSURE OPEN
module-1 with the help of E/M.
04 Note down the currents in both the cases (Before & after opening the switches).
05 O/G Module No.8.8F On DG SWGR To OFF, REMOVE FUSES &
UPS module-1 TAG
06 CBI of UPS module-1 OFF and Tag
07 CBB of UPS module-1 OFF and Tag
08 CBA of UPS module-1 OFF and Tag
09 MIS of UPS module-1 OFF and Tag
10 UPS module-1 related fuses to be removed
by E/M for positive isolations.
Order to operate must be listed in the order in which the issuer intends them to be performed and
must be performed in the order in which they are listed.The operator who is delegated to perform the
operations listed shall check the positions and tagging of any devices which must be in any particular
position while the operations are being performed. State the required condition or position of the
apparatus. The order meant that the equipment must be left in the state or position indicated.
_________________________________________________________________________
PURPOSE OF ORDER: TO ISOLATE for UPS-2 MAINTENANCE.
Permit No To issue [ ] To clear [ ] (Tick whichever is applicable)
S.NO EQUIPMENT STATUS REQUIRED TAG NOS. INITIALS
PLACE
01 Take approval for giving UPS MODULE - 2 for maintenance.
02 Ensure that the load of UPS module-2 has been shifted to UPS module-1 or Alternate
supply.(Note down the currents before & after load shifting)
03 Open the static switch THS4 & THS5 of UPS ENSURE OPEN
module-2 with the help of E/M.
04 Note down the currents in both the cases (Before & after opening the switches).
05 O/G Module No.6.4R On Fire Protection OFF, REMOVE FUSES &
MCC To UPS module-2 TAG
06 CBI of UPS module-2 OFF and Tag
07 CBB of UPS module-2 OFF and Tag
08 CBA of UPS module-2 OFF and Tag
09 MIS of UPS module-2 OFF and Tag
Order to operate must be listed in the order in which the issuer intends them to be performed and
must be performed in the order in which they are listed.The operator who is delegated to perform the
operations listed shall check the positions and tagging of any devices which must be in any particular
position while the operations are being performed. State the required condition or position of the
apparatus. The order meant that the equipment must be left in the state or position indicated.
_________________________________________________________________________
PURPOSE OF ORDER: TO ISOLATE for UPS-1 & 2 MAINTENANCE.
Permit No To issue [ ] To clear [ ] (Tick whichever is applicable)
S.NO EQUIPMENT STATUS REQUIRED TAG NOS. INITIALS
PLACE
01 Take approval for giving UPS MODULE -1 & 2 for maintenance.
02 Ensure that the loads of UPS module-1 & 2 have been shifted to Alternate supply by
closing the CBO with the help of E/M.(Note down the currents before & after load
shifting)
03 Open the static switch THS4 & THS5 of UPS ENSURE OPEN
module-1 & 2 with the help of E/M.
04 Note down the currents in both the cases (Before & after opening the switches).
05 O/G Module No.8.8F On DG SWGR To OFF, REMOVE FUSES &
UPS module-1 TAG
06 O/G Module No.6.4R On Fire Protection OFF, REMOVE FUSES &
MCC To UPS module-2 TAG
07 CBI of UPS module-1 & 2 OFF and Tag
08 CBB of UPS module-1 & 2 OFF and Tag
09 CBA of UPS module-1 & 2 OFF and Tag
10 MIS of UPS module-1 & 2 OFF and Tag
Order to operate must be listed in the order in which the issuer intends them to be performed and
must be performed in the order in which they are listed.The operator who is delegated to perform the
operations listed shall check the positions and tagging of any devices which must be in any particular
position while the operations are being performed. State the required condition or position of the apparatus.
The order meant that the equipment must be left in the state or position indicated.
_________________________________________________________________________
PURPOSE OF ORDER: TO ISOLATE FOR MAINTENANCE OF UPS ALTRNATE SUPLLY
System(SCVS).
Permit No To issue [ ] To clear [ ] (Tick whichever is applicable)
S.NO EQUIPMENT STATUS REQUIRED TAG NOS. INITIALS
PLACE
01 Take approval for giving UPS Alternate Supply system (SCVS) for maintenance.
02 Ensure that the any one of the UPS module is in service.
03 Ensure that UPS loads are not feeding by its Alternate Supply system (SCVS). Note
the currents readings
04 Ensure that CBO is in open condition Open and Tag
05 Open the static switch THS5 of UPS Ensure open
module-1 & 2 with the help of E/M.
06 Note down the currents in both the cases (Before & after opening the switches).
07 O/G Module No.6.4F On NESG To UPS OFF, REMOVE FUSES &
TAG
08 CB1 of UPS alternate supply OFF and Tag
09 CBA of UPS module-1 OFF and Tag
10 CBA of UPS module-2 OFF and Tag