Professional Documents
Culture Documents
Specs For Precast Sub Elements
Specs For Precast Sub Elements
Specs For Precast Sub Elements
Date 4/7/16
Description:
Work under this item shall consist of furnishing, erecting and installing all precast substructure
elements for bridge substructures including all necessary materials and equipment to complete
the work as shown on the plans. The use of cast-in-place concrete will not be considered for
substitution.
Submittals:
The submittals requiring written approval from the Engineer are as follows:
o. Include methods of forming closure pours for precast wall panel joints, including
the use of backer rods. Do not assume that the backer rods will restrain the
pressure from the grout in vertical grout joints. Provide additional forming to
retain the backer rod.
p. Include a list of personnel that will be responsible for the grouting of the
reinforcing splice couplers. Include proof of completion of two successful
installations within the last two years. Training of new personnel within three
months of installation by a manufacturer’s technical representative is an
acceptable substitution for this experience. In this case, provide proof of training.
q. Prepare the plan under the seal of a Connecticut Professional Engineer.
Submit an independent test report that includes data for each supplied coupler size. Use the same
grout in the construction that was used in the testing. Submit the specification requirements for
the grout including required strength gain to develop the specified minimum yield strength of the
connected reinforcing bar.
Defects and breakage of precast elements: Submit proposed written repair procedures for
approval.
Grout substitution in the couplers: Refer to this Section, Materials, Grouted Splice Couplers.
Installation of elements: Refer to this Section, Construction Methods, Procedure for Installation
of Elements, paragraph A for changes warranted due to varying site conditions.
Materials:
Concrete: All concrete used to construct precast substructure elements shall meet the provisions
of Section 6.01 for Standard Mix Class A.
Fly Ash: The fly ash shall conform to the requirements of Article M.03.01-13.
Coarse Aggregate: The coarse aggregate shall conform to the requirements of Article
M.03.01 and the mix shall be designed utilizing a maximum size of No. 8 aggregate.
Water Reducing Admixture: The Contractor may submit, for the approval of the
Engineer, a water reducing admixture for the purpose of increasing workability and
reducing the water requirements for the concrete.
Calcium Chloride: The addition of calcium chloride to the mix will not be permitted.
High Early Strength Concrete: The high early strength concrete shall conform to one of the
following:
a. The Contractor shall design a high early strength concrete mix and shall submit such
design mix to the Engineer for approval. This mix shall be air-entrained and shall be
composed of Portland cement, fine and coarse aggregates, approved admixtures and
additives, and water. The mix shall contain between 4% to 7% entrained air, shall attain
a 6-hour compressive strength of 2,500 psi and shall have a minimum 7-day ultimate
compressive strength of 5,000 psi. Additionally, the mix shall contain shrinkage
compensating additives such that there will be no shrinkage or separation of the patched
area from the adjoining concrete to which the concrete is to be poured against. This
shrinkage-compensating additive shall be utilized so as to produce expansion in the high
early strength concrete of no more than 3 percent.
b. In lieu of the above high early strength concrete mix, the Contractor may propose to use a
proprietary type mix that will meet the same physical requirements as those stated above.
A mix design shall be submitted for this material, stating the percentage of each
component to be utilized.
Regardless of the type of high early strength concrete proposed by the Contractor, substantive
data that demonstrates the ability of the material to meet the specification requirements shall be
submitted with the proposed mix design at least two weeks prior to its use.
Non-Shrink Grout: Use structural non-shrink grout conforming to Section M.03.01-12 for joints
between precast elements as shown on the plans. Use structural non-shrink grout that meets a
minimum compressive strength of 5,000 psi within 24 hours when tested as specified in
AASHTO T 106.
Grouted Splice Couplers: Use grouted splice couplers to join precast elements as shown on the
plans. Provide couplers that use cementitious grout placed inside a steel casting. Threaded
connections may be used for the portions of the coupler that are placed within the precast
element if the strength of the coupler meets or exceeds the requirements of this specification.
The following reinforcing splice couplers are acceptable for use provided that the requirements
of this specification are met:
a. NMB Splice Sleeve
Splice Sleeve North America, Inc.
192 Technology Drive, Suite J,
Irvine, California 92618-2409
www.splicesleeve.com
b. Dayton Superior DB Grout Sleeve
Dayton Superior
Corporate Headquarters
Use grouted splice couplers that are epoxy coated and can join epoxy coated reinforcing steel
without removal of the epoxy coating on the spliced bar when splicing epoxy coated bars. Use
grouted splice couplers that can provide 100 percent of the specified tensile strength of the
connected bar. This equates to 90 ksi for reinforcing conforming to ASTM A 615 and 80ksi for
reinforcing conforming to ASTM A 706. Supply grout for the inside the couplers from the
manufacturer of the coupler that is matched to the certified test report for the coupler. Do not
substitute any other grout in the couplers unless additional certified test reports are submitted for
the grout/coupler system.
Corrugated Metal Pipe: Conform to AASHTO Standard Specifications for Highway Bridges and
AASHTO M 36 or AASHTO M 245
Leveling Devices: The plans show fabricated steel leveling devices (to be designed by
Contractor). Alternate devices may be used provided that they can support the anticipated loads.
Vertical Joint Seals: Use natural rubber or neoprene sheet with a durometer of 50-60, meeting the
requirements of ASTM D 2240.
Quality Assurance:
Permanently mark each precast element with date of casting and supplier identification. Stamp
markings in fresh concrete. Prevent cracking or damage of precast elements during handling and
storage.
The plant will document all test results. The quality control file will contain at least the
following information:
a. Element identification
b. Date and time of cast
c. Concrete cylinder test results
d. Quantity of used concrete and the batch printout
e. Form-stripping date and repairs if applicable
f. Location/number of blockouts and lifting inserts
g. Temperature and moisture of curing period
h. Document lifting device details, requirements, and inserts
The performance of grouted splice couplers is related to the embedment length of the bars and
the compressive strength of the grout.
a. Check the length of rebar anchor dowel to make sure they meet the minimum
embedment specified in the manufacturer’s manual.
b. Monitor shim thickness between the precast elements to ensure that the
reinforcing extensions are within the manufacturers recommended tolerance.
c. Monitor the grout mixing, water to grout ratio, mixing time, and shelf life of the
grout for conformance with the manufacturers written instructions.
d. Monitor the grouting operation to verify that all sleeves have been filled.
e. Make four sets of three - two inch cube molds in heavy brass molds with cover
plates for testing according to AASHTO T 106.
f. Verify that all sleeves are protected from any vibration, shock, or other excessive
movement until temporary bracing is removed.
g. Check the temperature of the sleeve at the time of grouting (50 degrees F
minimum) and during curing.
Construction Methods:
Fabrication: Do not place concrete in the forms until the Engineer has inspected and approved all
the materials in the elements. Provide the Engineer a tentative casting schedule at least two
weeks in advance to make inspection and testing arrangements. A similar notification is required
for the shipment of precast elements to the job site. Do not place concrete in the forms until the
Engineer has inspected the form and has approved the placement of all materials in the precast
elements. Finish the precast elements according to Section 6.01. Trowel finish the top surface of
all precast concrete elements.
Procedure for Installation of Elements:
A. Review the approved assembly plan. If changes are warranted due to varying site
conditions, resubmit the plan for review and approval.
D. Check the condition of the receiving bonding surface prior to connecting elements
and take any necessary measures to remove items such as dust, rust, and debris to
provide the satisfactory bonding required between the protruding reinforcing bars
element and the grouted couplers.
E. Place elements in the sequence and according to the methods outlined in the
assembly plan. Adjust the height of each element by means of leveling devices or
shims.
A. Use personnel that are familiar with installation and grouting of splice couplers
that have completed at least two successful projects in the last two years.
1. Training of new personnel within three months of installation by a
manufacturer’s technical representative is an acceptable substitution for
this experience.
B Remove and clean all debris from the joints prior to application of non-shrink
grout.
C. Keep bonding surfaces free from laitance, dirt, dust, paint, grease oil, or any
contaminants other than water.
D. Saturate Surface DRY (SSD) all joint surfaces prior to connecting the elements.
F. Follow the recommendations of the manufacturer for the installation and grouting
of the couplers.
Wall Panels:
B. Lift wall panel element as shown in the assembly plan using lifting devices as
shown on the shop drawings.
tolerances. Remove and adjust the shims and reset the panel if the panel is
not within tolerance.
3. Set the panel and install the couplers as described in this Section,
Construction Methods, Connection Procedure Using Grouted Splice
Couplers, once the connection geometry is established and checked.
4. Install temporary bracing if specified in the assembly plan.
5. Allow the grout in the coupler to cure until the coupler can resist 100
percent of the specified minimum yield strength of the bar prior to
removal of bracing and proceeding with installation of components above
the panel. The required strength of the grout for this is based on the
certified test report. Verify the strength of the grout by testing cube
samples according to AASHTO T 106.
6. Place concrete inside the blockouts and cure if the panels contain
corrugated pipe blockouts.
Abutment Stems:
A. Lift abutment stem element as shown in the assembly plan using lifting devices as
shown on the shop drawings.
B. Survey the elevation of the wall panel directly below the cap. Provide shims to
bring the bottom of the cap to the required elevation. Measure the elevation of the
top of the shim stack and verify that the elevations are within specified tolerances.
C. A dry fit of the stem is recommended until work crews become more familiar
with the process. Set stem in the proper horizontal location. Check for proper
horizontal and vertical alignment within specified tolerances. Remove and adjust
the shims and reset the stem if the cap is not within tolerance.
D. Install shear key reinforcement as specified in the plans and set the stem. Once
the connection geometry is established and checked, High Early Strength
Concrete may be poured to fill shear keys.
Method of Measurement:
This work shall be measured for payment by the actual volume in cubic yards of precast
substructure elements placed in accordance with the plans or as ordered by the engineer.
Basis of Payment:
Payment for this work will be made at the contract unit price per cubic yard for “Precast
Substructure Elements”, complete and in place, which price shall include all materials,
equipment, tools, labor and work incidental thereto, including heating and cooling, curing and all
admixtures. Unit price includes all concrete, form-liner, reinforcement, grout, leveling devices,
and splicers required to install the precast substructure elements in accordance with the plans or
as ordered by the engineer.