Project :

SMPP RIVERSIDE CO.,LTD.


TRIBE PHNOM PENH HOTEL

METHOD STATEMENT SUBMISSION

Date 22/11/2019 Ref. No. SMPP-LBL-TRH-MDS-STR-001-A


To AGENT TOMMY Attention M. Kariwat
From LBL Approv. req. by 29/11/2019

Name Works method statement of sheet pile installation and removal


Location/Area General
Intended for -
Description

Comments

Approval status
□ Approved □ Approved with comments □ Rejected

RECOMMEND FOR APPROVAL BY APPROVAL BY

Signature Signature

Fullname: THORNG Olivia Fullname:................................

Date : 22/11/2019 Date :..................................

Notes:
2 signed copies must be submitted
One copy to be retained by the receiver and another copy to be returned signed by the receiver to the sender.

Page 1/1
PROJECT: TRIBE PHNOM PENH HOTEL

WORKS METHOD STATEMENT


OF SHEET PILE INSTALLATION AND REMOVAL

Content
1. INTRODUCTION ............................................................................................2
2. RELEVANT DOCUMENT ...............................................................................2
3. RESPONSIBILITY ..........................................................................................2
4. LAYOUT PLAN ..............................................................................................3
5. GENERAL ......................................................................................................4
A. INTROCUCTION .................................................................................4
B. DEFINITION ........................................................................................4
C. WORK PROCESS ...............................................................................4
6. PROCEDURE.................................................................................................7
A. SITE PROCEDURES AND METHODOLOGY .....................................7
B. WORK METHODOLOGY OF DRIVING SHEET PILE .........................7
7. RECOURCE ALLOCATION ...........................................................................7
A. LIST OF MANPOWER .........................................................................7
B. LIST OF MACHINERY .........................................................................8
C. LIST OF MATERIAL ............................................................................8
8. QUALITY ASSURANCE AND QUALITY CONTROL ......................................8
A. RECORD OF INSTALLATION .............................................................8
B. INSPECTION .......................................................................................9
9. HEALTH AND SAFETY ................................................................................10
A. SAFETY OFFICER ............................................................................10
B. EMERGENCY PLAN .........................................................................10
C. SAFETY RISK ASSESSMENT ..........................................................10
10. ATTACHED REFERENCE PHOTOS ...........................................................11
11. ANNEX 1 SHEET PILE LAYOUT .................................................................12
12. ANNEX 2 BENCHMARK LAYOUT ...............................................................13

MS SHEET PILE INSTALLATION AND REMOVAL Page: 1 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

1- INTRODUCTION

The purpose of this document is to point out the various steps to be carried out for the
sheet pile works to meet the requirements of the Contract Works.

This work Method Statement has been arranged to give a clear guidance to the people
working at project site and to ascertain the limits and controls for the quality of works.

In this MDS, LBL International shall be identified as the ‘’Main Contractor’’,


SANTHAYA + ASSOCIATES as the ‘’Consultant’’ and SMPP REVERSIDE as the
“Client”.

2- RELEVANT DOCUMENTS

Relevant documents shall be composed of the following:

1. Safety Plan
2. Approved Construction Drawings
3. This method statement

The documents mentioned above form part of this “Work Method Statement of Sheet
Pile Works” and serve as reference if disputes between both Parties occur.
The Method Statement may change according to actual site condition.

3- RESPONSIBILITIES

1.0 The Construction Manager or his Representatives shall be responsible


for:

1.1 Managing the construction of sheet pile works ensuring that these
construction works are carried out in accordance with the approved
documents listed above as well as the requirements of the Contract
Specifications.

1.2 Liaising with the Consultant whenever there is any actual


interference of the sheet pile works, which constitute a revision of
drawing.

2.0 The QAQC Officer (Mr. Noy Sophannara) shall be responsible in leading
and directly supervising the Quality Assurance and Quality Control of the
aforesaid Works.

MS SHEET PILE INSTALLATION AND REMOVAL Page: 2 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

3.0 Safety Officer (Mr. Khat Sarat) is tasked to ensure that the major
objectives of the plan will be implemented properly to provide
comprehensive measures that will ensure the protection of life and
properties as well as to provide construction efficiency through selective
use of safe work practices and working conditions.
3.1 A personal to guard site access.
3.2 Safety manager to check work safety daily at the beginning of work
shifts such as soil stability condition, ingress and egress to the
excavation area, equipment conditions.

4. LAYOUT PLAN

MS SHEET PILE INSTALLATION AND REMOVAL Page: 3 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

5. GENERAL

A. INTRODUCTION

This method statement describes in general the installation of Driving Sheet


Pile.
 Provide and supply Hydraulic Vibro Hammer for driving and extracting
sheet piles. Sheet piles length 12m, 9m, and 7m. Please refer to layout
above.
 This method statement described about the installation of sheet pile.
Detail of construction and earth work will be described in separate
method statement.

Figure. 1

B. DEFINITION

Sheet piles are primarily to retain or support earth and commonly used for
bulkheads and cofferdam s and when excavation depths or soil conditions
require temporary or permanent bracing to support the lateral loads imposed
by the soil or by the soil and adjacent structures.

C. WORK PROCESS

Step 1: ground preparation and driving sheet pile 9m and 12m


Step 2: excavation ~4.4m (refer to pile cap drawing)
Step 3: ground preparation and driving sheet pile length 7m

MS SHEET PILE INSTALLATION AND REMOVAL Page: 4 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

Step2: excavation ~4.4m (refer to pile cap dwg)

MS SHEET PILE INSTALLATION AND REMOVAL Page: 5 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

Working Flow Charts

MS SHEET PILE INSTALLATION AND REMOVAL Page: 6 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

6. PROCEDURE

A. SITE PROCEDURES AND METHODOLOGY

 Material preparation: Due to the raw sheet pile is 237m length, 7m, 9m,
12m length of sheet pile shall pre‐spliced by fillet welding with
400x125x13mm thk. Splice plate on both side.

 Sheet pile installation: Use modified excavator vibro hydraulic to drive sheet
pile to design level, and splice location of sheet pile shall be under
excavation level.

 Security measures: Before the start of installation work, proper barricade


shall be erected around the vacant land where it is to be carried out.

 Sign boards: All installation works will be carried out within the barricaded
work area. Watchman shall be assigned. For night operation, warning lights
shall be arranged.

B. WORK METHODOLOGY OF DRIVING SHEET PILE

 Setting out the alignment for sheet pile position. (Exact alignment shall be
given)
 Inspection underground services along the alignment for sheet pile to avoid
any damage.
 Prepare firm working platform to withstanding the pilling machine.
 Mobilization of labors, material and machineries to site.
 Driving of sheet pile to the level require or until hard material encounter.

7. RESOURCE ALLOCATION

A. LIST OF MANPOWER

No. Occupation Nos.


1 Construction Manager 1
2 Technical engineer (Technician) 1
3 Safety officer / supervisor 1
4 Surveyor 1
5 QA/QC officer 1
6 Sheet pile machine operator 3
7 General worker 5
Total 13

MS SHEET PILE INSTALLATION AND REMOVAL Page: 7 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

B. LIST OF MACHINERY

Item Equipment/Machinery Q'ty Remarks


1 Vibro hydraulic 1 Driving sheet pile
2 Excavator 1 Shoring works
3 Cargo Crane 1 Lifting sheet pile (if required)

C. LIST OF MATERIAL

Item Material Q'ty Remarks


1 Sheet pile 605 Driving sheet pile
2 Steel plate 4 Access road (if required)

8. QUALITY ASSURANCE AND QUALITY CONTROL

LBL will employ sufficient qualified sheet pile supervisors in addition to the
experienced site workers and foremen to supervise the works.

A. RECORDS OF INSTALLATION

A sheet pile driving shall be observed during installation of steel sheet piling
unless stated otherwise below.
The sheet pile driving record shall include:
‐ Sheet pile identification number and location, sheet pile type, dimension,
weight, thickness
‐ Date and time of driving, starting and completion time, re‐driving including
stopping and delay, including field splice
‐ Sheet pile inclination
‐ Type of equipment (Vibro‐Hydraulic)
‐ Effective driving depth
‐ Effective sheet pile length
‐ Final level of sheet pile head
‐ Final level of sheet pile point
‐ All information regarding obstructions, delays and other interruptions to the
sequence of work.

MS SHEET PILE INSTALLATION AND REMOVAL Page: 8 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

B. INSPECTION

Immediately after the driving works along the sheet pilling all joints/interlocks
shall be investigated by the Engineer. Any irregularities, especially jumping of
the interlocks, shall be documented and described in detail.

If any damage or failure in the interlocks or other parts of the sheet pilling should
be detected in the course of these inspections, any requirement has to repair
them and make them good, to the complete satisfaction of the Engineer.

9- HEALTH AND SAFETY

A. SAFETY OFFICER (SO)

The Safety Officer is tasked with ensuring that the major objectives of the plan
will be implemented properly to provide comprehensive measures that will
ensure the protection of life and properties as well as to provide construction
efficiency through selective use of safe work practices and working conditions.

B. EMERGENCY PLANS

The Contractor will make necessary arrangements with a general hospital near
the vicinity of the site for providing proper and expeditious medical care during
the execution of the works. Safety Personnel shall be assigned to carry our
first aid treatment prior to shifting the patient to hospital if necessary and shall
be available at all times within the vicinity of the working site.

The emergency may result from an accident or injury, landslip or other


potentially dangerous occurrence. Natural disaster including electrical storms,
floods, plant or machinery fire etc. may also present hazards to the working
operations. The contractor will plan for such matters and ensure that
appropriate control measures are in place. The risk assessment will take into
account the following factors:
 nature of hazard and possible emergencies;
 size and location of place of work;
 number and mobility of persons at the workplace;
 location of nearest emergency services.

An emergency vehicle equipped with mobile phone will be assigned for carrying the
sick/injured to the hospital. The vehicle driver shall have the same communication to
receive any emergency call relative to Safety matters and shall be available always

MS SHEET PILE INSTALLATION AND REMOVAL Page: 9 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

within the vicinity of the working site. The (SO) will immediately report to the
Consultant the particulars of any accident or any unusual or unforeseen occurrences
on the site, whether or not they are likely to affect the progress of works.

C. SAFETY RISK ASSESMENT

The Safety Officer shall identify the hazard, the people who might be harmed,
evaluate the risks and decide on precautions, in accordance with the safety
plan.
In order to evaluate the hazard assessment, the Contractor shall conduct
inspections of all workplaces to determine the need for PPE and help in
selecting the proper PPE for each tasks performed. Each survey will document
the workplace surveyed, date of survey, the identified source of hazards and
precautions to be implemented.

The Contractor ensures that the PPE program is implemented in the work area;
defective or damaged equipment are to be immediately replaced; workers must
attend required training sessions and records on hazard assessments are
maintained.
The safety program is to be regularly reviewed, evaluated and if necessary,
updated according to site and working conditions.

LBL will ensure the environment’s protection by implementing the following


measures:

- Air pollution Control


o Minimize dust by methods of watering, covering; undertake dusty works
in sheltered areas when / if possible
o Reduce the risk of smoke by well maintaining plants and / or equipment
o Provide enclosure around dust-generating activities
o Ensure that the hoardings are well maintained and fixed if damaged

- Water pollution Control


o Provide Water Discharge Licenses
o Treat waste water and ensure that the treatment system is well
maintained
o Ensure that U-Channels & Manholes are maintained (free of silts and
sediment, covered)
o Properly store and / or clean items & equipment

MS SHEET PILE INSTALLATION AND REMOVAL Page: 10 of 13


PROJECT: TRIBE PHNOM PENH HOTEL

- Noise Control
o Provide Construction Noise Permit
o Reduce Noise by ensuring that machines are being operated with doors
closed or that idle plant / equipment are turned off

- Waste Management
o Ensure that site is clean and waste disposed in nominated area
o Waste Area to label type of waste in order to facilitate recycling and
ensure proper disposal
o Ensure that Waste is disposed on a regular basis
o Well maintaining equipment/plants which may be at the origin of waste
(e.i. oil spillage)

- Storage of Chemicals and Dangerous Goods


o Chemical and Hazardous Waste to be labeled and stored properly
o Provide measures to control oil or chemical spillage

- Resource Conservation
o Recycle water when possible (e.g. to prevent dusting)
o Reduce energy consumption by preventing leakage, shutting down idle
equipment
o Maintain materials to prevent deterioration

10. ATTACHED REFERENCE PHOTOS

MS SHEET PILE INSTALLATION AND REMOVAL Page: 11 of 13


ANNEX 1: SHEET PILE LAYOUT

MS for Excavation work Page: 12 of 13


ANNEX 2: BENCHMARK LAYOUT

MS for Excavation work Page: 13 of 13