Professional Documents
Culture Documents
JSA Formet New Roof Sheeting Activity For Elevator
JSA Formet New Roof Sheeting Activity For Elevator
LTD
JOB SAFETY ANALYSIS OF ROOF SHEETING ACTIVITY FOR ELEVATOR
2.
2.1.1 Don’t allow the person to lift
more than one sheet from one place
to another.-work area must be free
Page 1 of 6
from obstacles
1 Hit by object. 2.1.2 Effective job supervision to be
ensured.
2 Pinch point. 2.1.3 Access must be cleared.
Engineer,
Supervisor, 3 Use of 2.2.1 Ensure workmen keep their
Material Handling (Manually) Fitter, rigger protrude M hand/leg away from pinching point / L Site Engineer/
and helper material. sharp edge. RCM
2.2.2 Ensure proper communication
4 Ergonomic & co-ordination between worker
issue and supervisor.
2.2.3 Ensure/provide job specific
PPE’s.
3.
3.1.1Before starting the job by Site Engineer/
crawler crane check the work area RCM
soil condition (should be plane &
compacted).
3.1.2 Ensure should not cross the
SWL capacity and no overload to be
lifted.
3.1.3 Material shall be lifted as per
load chart.
Crawler Crane, 1 Toppling of 3.1.4 Skilled operator to be engaged.
Slings, D- lifting 3.1.5 Qualified foreman to be
Page 2 of 6
shackle, equipment. deployed.
Lifting arrangement of roof sheet Engineer, H 3.1.6 Ensure physical condition of L
by 150 MT crane. Supervisor, 2. Fall of Crawler crane/wire sling/web
Fitter and material. sling/D-shackle
Rigger
3.2.1 Only tested lifting tools
tackles shall be used, which is
certified by competent person.
3.2.2 Ensure no one stand under the
suspended load at any
circumstances.
3.2.3 Lifting area must be barricade.
3.2.5 Tag line to be ensured.
Page 3 of 6
4.1.10 Ensure all the sheeting
erection activity must be prohibited
in case of bad weather condition.
4.1.11 All the materials are to be
secured and work is to be
discontinued until weather condition
are suitable.
4.1.12 Maintain the wind speed
during working hour. (25m/s)
Page 4 of 6
material be kept at height or elevated area.
Engineer, 5.2.3 Loose materials must be
Drilling & fixing of roof sheet. Supervisor, secured.
Fitter and 5.2.4 Below job area must be
Rigger barricaded.
5.2.5 Tools bag to be used if
required.
1.
Tripping
Housekeeping & close Hand tools /slipping 6.1.1 Housekeeping shall be
Site Engineer/
6. of work for the day hazard due H maintained after completion of work L
RCM
to poor for the day.
housekeepin
g.
1. Extreme 7.1.1Effective TBT shall include
weather about whether condition.
condition 7.2.1Emergency Response at
2. Leakage of workplace. Site Engineer/
7. H L
Emergency Response toxic or 7.2.2 Ensure emergency vehicle RCM
flammable arrangement at workplace.
gases. 7.2.3 Ensure availability of First aid
box at workplace.
1) Pre job discussion/tool box meeting should be done before starts the job.
2) Required job permit shall be obtained from concern authority.
3) Job supervisor/Eng. should be present at site during activity.
Page 5 of 6
4) During erection weather condition should be considered & job shall not be performed during heavy rain and
wind.
Page 6 of 6