KAMLESH KUMAR SINGH ENGINEERS PVT.

LTD
JOB SAFETY ANALYSIS OF ROOF SHEETING ACTIVITY FOR ELEVATOR

JOB NO 25511378 Date: 14/08/2020


Project Location : New NHT/CCR. JSA No.: 32
P&M and Equipment, Crawler Crane 150Ton , D-shackle, Wire rope Sling, Web Rev. No.: 0
Tools & tackles involved Sling, Ladder, fall arrestor, Lifeline, PP rope etc.
Job Description: Roof Sheeting Activity for elevator. Prepared By: Mr. Birbal Ray
(Contractor Site
Eng. Sup)
Job Classification: Mechanical. Reviewed By: Mr. Saket Kumar
Sequence of Operation – Activity Tools &tackles Risk Safety measures / precautions
Sl.
Steps used &
Hazards
level
(Contractor Risk level
Responsibility
No. involved at HSEM) after
manpower H/M/ Action by
various steps control
Name of the Site deployed L Approved By: Mr. Sajal Sarkar
Mr. Birbal Ray
Engineer: (Contractor
1.1.1 JSTIRCM/Site
shall be done before start
the job. Manager)

PPE / safety device Safety shoes,1.Safety


Engineer,
Safety helmet, goggles, Dotted1.1.2 TheStatus.
Lack of work to be started after Issued for
required hand gloves, Supervisor,
awareness/
Full body harness, Fall arrester, Nose obtaining
mask work permit. implementation/Site
review
Engineer/
Pre-task Assignment/ Assessment Fitter and communication 1.1.3 Job supervisor shall ensure the RCM
1. etc. gap. M L
rigger activity and communicate the task
as per job role.

2.
2.1.1 Don’t allow the person to lift
more than one sheet from one place
to another.-work area must be free

Page 1 of 6
from obstacles
1 Hit by object. 2.1.2 Effective job supervision to be
ensured.
2 Pinch point. 2.1.3 Access must be cleared.
Engineer,
Supervisor, 3 Use of 2.2.1 Ensure workmen keep their
Material Handling (Manually) Fitter, rigger protrude M hand/leg away from pinching point / L Site Engineer/
and helper material. sharp edge. RCM
2.2.2 Ensure proper communication
4 Ergonomic & co-ordination between worker
issue and supervisor.
2.2.3 Ensure/provide job specific
PPE’s.

2.3.1Supervisor ensure deploying


their workmen as per limited size
and capacity of load unless use
mechanically.
2.3.2 Ensure unauthorised person
entry prohibited.

2.4.1 Job rotation to be ensured.


2.4.2 Ensure interval of continuous
job/activity.
2.4.3 Ensure minimum load lifting
by the workmen.

3.
3.1.1Before starting the job by Site Engineer/
crawler crane check the work area RCM
soil condition (should be plane &
compacted).
3.1.2 Ensure should not cross the
SWL capacity and no overload to be
lifted.
3.1.3 Material shall be lifted as per
load chart.
Crawler Crane, 1 Toppling of 3.1.4 Skilled operator to be engaged.
Slings, D- lifting 3.1.5 Qualified foreman to be

Page 2 of 6
shackle, equipment. deployed.
Lifting arrangement of roof sheet Engineer, H 3.1.6 Ensure physical condition of L
by 150 MT crane. Supervisor, 2. Fall of Crawler crane/wire sling/web
Fitter and material. sling/D-shackle
Rigger
3.2.1 Only tested lifting tools
tackles shall be used, which is
certified by competent person.
3.2.2 Ensure no one stand under the
suspended load at any
circumstances.
3.2.3 Lifting area must be barricade.
3.2.5 Tag line to be ensured.

4. 4.1.1 To be ensure the scaffolding L


standard, proper access & working
platform before start the job. Site Engineer/
4.1.2 Proper lifeline to be provided RCM
(vertical & horizontal).
4.1.3 Double lanyard with shock
absorber safety harness to be used.
4.1.4 Hand tools to be secured
while used height.
4.1.5 Employees are to be
instructed and supervised to ensure
they position their body over a roof
truss at all times and that they
refrain from over reaching.
1. Erection of 4.1.6 Ensure all the loose materials
roof sheeting, H must be tied-up properly.
Slip, Trip, fall 4.1.7 Use job specific PPE’S.
Engineer, of material & 4.1.8 Adequate access to be
Erection of roof sheeting Supervisor, person. provided.
Fitter and
Rigger 4.1.9 Ensure edge protection of
2. roof.
Electrocution

Page 3 of 6
4.1.10 Ensure all the sheeting
erection activity must be prohibited
in case of bad weather condition.
4.1.11 All the materials are to be
secured and work is to be
discontinued until weather condition
are suitable.
4.1.12 Maintain the wind speed
during working hour. (25m/s)

4.2.1 All the power tools shall be


connected through ELCB/RCCB.
4.2.2 Body earthing to be provided.

5. 1 Slip, Trip, M 5.1.1 Supervisor shall be available L


Cut always at job site and competent
supervision must be ensured. Site Engineer/
2 Fall of 5.1.2 Fixing of sheet with trained RCM
materials workers.
5.1.3 Unauthorized entry to be
3 Person prohibited.
Electrocution
5.2.1 Where practicable all cutting
of sheets should be done at ground
.
Power tools, level.
Cladding 5.2.2 Ensure no loose materials to

Page 4 of 6
material be kept at height or elevated area.
Engineer, 5.2.3 Loose materials must be
Drilling & fixing of roof sheet. Supervisor, secured.
Fitter and 5.2.4 Below job area must be
Rigger barricaded.
5.2.5 Tools bag to be used if
required.

5.3.1 Power tools and extension


leads are to be inspected daily
before use.
5.3.2 Trained person to be engaged.
5.3.3 Body earthing to be provided.
5.3.4 All the power tools must be
gone through ELCB/RCCB.

1.
Tripping
Housekeeping & close Hand tools /slipping 6.1.1 Housekeeping shall be
Site Engineer/
6. of work for the day hazard due H maintained after completion of work L
RCM
to poor for the day.
housekeepin
g.
1. Extreme 7.1.1Effective TBT shall include
weather about whether condition.
condition 7.2.1Emergency Response at
2. Leakage of workplace. Site Engineer/
7. H L
Emergency Response toxic or 7.2.2 Ensure emergency vehicle RCM
flammable arrangement at workplace.
gases. 7.2.3 Ensure availability of First aid
box at workplace.

General precaution for Demolition:

1) Pre job discussion/tool box meeting should be done before starts the job.
2) Required job permit shall be obtained from concern authority.
3) Job supervisor/Eng. should be present at site during activity.

Page 5 of 6
4) During erection weather condition should be considered & job shall not be performed during heavy rain and
wind.

Page 6 of 6