Professional Documents
Culture Documents
Job Safety Analysis For Civil Work
Job Safety Analysis For Civil Work
Job Safety Analysis For Civil Work
LTD
JOB SAFETY ANALYSIS FOR CIVIL WORK
Page 1 of 9
3. Injury due hazards through daily JSTI.
to pinching or
crushing.
Page 2 of 9
utilities. clearly identified and marked
2. Failure or prior trenching.
topping of 4.1.2 No excavator shall be used
within trial pit.
construction
4.1.3 Goal post shall be provided
Excavator, equipment.
below of power line.
Excavation Activity (Mechanical) JCB. 3. Hit by or
4.2.1 Ensure all construction
injury due to
equipment shall be inspected &
construction
colour coded.
equipment.
4.2.2. Only competent operator
4.Collapse of
shall operate the machine.
trench / cave-
4.2.3 Inspect equipment on daily
in
basis prior to use.
5. Sliding of
4.3.1 Nobody shall be allowed
man and
machinery near to swing area of machinery.
inside the 4.3.2. Swing area of the
trench. excavator has to be barricaded.
4.3.3 Flag man has to be
deployed to warn other vehicles
& pedestrians.
4.4.1 The excavated soil shall be
kept at least 2m far from
excavation edge.
4.4.2 Proper slope shall be
maintained for the trench.
4.4.3 Trench shall be kept open
as less time as possible.
4.5.1 Excavated area should be
hard barricaded with warning
signage.
4.5.2 Excavated sand / soil shall
be used at one side of the trench
as a natural barrier.
Page 3 of 9
5.1.1 Always wear appropriate PPE
during steel fixing work.
1. Hand/Finger 5.1.2 Be careful from Hand/Finger
injury. pinch in between TMT bars & use
Steel fixing work Hand tools 2. Tripping cotton hand glove.
5. M L Site engineer
Hazard. 5.2.1 Ensure no any gap between
3. Use of TMT bars.
damage tools. 5.2.2 Maintain proper housekeeping.
5.3.1 Always use certified &
inspected tools.
6.1.1 Always wear appropriate PPE
during Shuttering & deshutterring
1. Hand/Finger work.
Shuttering & deshutterring work. Hand tools injury. 6.1.2 Use leather gloves when
2. handling rebar and tie-wire.
Sprains/Str 6.2.1 Use legs to lift, do not bend
6. ains M at the waist. L Site engineer
3.Pinch 6.3.1 Use proper hand placement
points on rebar to avoid pinching when
installing rebar for Shuttering
Work.
6.3.2 Use leather hand glove during
Shuttering & deshuterring work.
7. H 7.1.1 Use rubber hand gloves, L Site engineer
safety glasses, Gum boot during
concreting work.
7.1.2 Wash off splattered concrete
with fresh water or neutralizing
solution.
7.2.1 Use power screed whenever
possible to eliminate constant
bending.
1.Chemical 7.2.2 Pulling motion required by
/ Concrete hand screed.
Burns 7.3.1 Use chute man to swing
concrete chute back & forth &
2.Strains/S signal concrete truck driver.
prains 7.3.2 Chute man needs to
Page 4 of 9
commute with rest of crew when
Concreting work Miller & Hand 3.Struck moving chutes or repositioning
tools. by/ truck.
Crushed by 7.3.3 Use a spotter for concrete
4. Slips, trips trucks and all vehicles in tight or
and falls congested areas.
5. Chemical 7.4.1 Inspect work area, move
Burns material that may cause trips prior
to performing work.
7.4.2 Use mesh over rebar to
cover holes produced by rebars.
7.4.3 Exposed mesh will be trip
hazards until concrete placed.
Keep mesh ends tied down.
7.5.1 Secure a fresh water source (
a hose) or use neutralizing
solution.
Page 5 of 9
Hand tools ers displayed for congested area.
6.Congested 8.6.2 Ensure & confirm for which
area type of job is prior & then
7.Dust perform.
inhalation 8.7.1 Ensure all personnel
8.No working for backfilling are using
supervision dust masks, dust covers, etc.
control 8.8.1 Supervisor must be
available at site.
Page 6 of 9
condition( trained to meet any emergency
cold, rain, situation and emergency mock
dust etc ) drills may be conducted to
evaluate the emergency
preparedness.
9.7.1 Ensure night shift
personnel get proper sleep/rest
at day time.
9.8.1 Ensure in the event of
adverse climatic condition (high
wind, rain, dust etc.) the work is
stopped.
Page 7 of 9
Emergency Response toxic or 12.2.2 Ensure emergency vehicle
flammable arrangement at workplace.
gases. 12.2.3 Ensure availability of First
aid box at workplace.
1) Instruction should be given for “NO SMOKING” and ensure that no fire/ hot work occurs nearby.
2) Tools & nails are to be kept in a toolbox never carry the nails in bags or in pockets.
3) Materials shall be kept in arrange way on the ground. The foreman shall ensure good housekeeping.
4) Tie the lifeline while making beam bottom at the outer side.
5) Support the lifeline at every 5 m length.
6) Helpers should not be allowed to work at outer side.
7) Ensure access wherever you work.
8) Check for defective tools.
9) The included angle for the ladder is 75 degree and the ladder should extend at least 1 m beyond the landing platform.
10) The ladder must be secured at the top and bottom. Do not use top rung or top step of the ladder.
11) Never use brittle materials like brick as a packing material for shutter supporting towers.
12) Do barricading/Identified/highlight while doing breaking work at outer side.
13) While demolition keep one helper to remove the nails and stack the shutters properly (neatly) and ensure proper access.
14) 1/3 of portion of the tower only can be projected beyond periphery of the slab as cantilever.
15) In such cases the Wallers to be secured by hooks embedded in concrete.
16) Props used at periphery must be braced adequately.
Page 8 of 9
Page 9 of 9