Professional Documents
Culture Documents
Rig Move Plan TO ABHD 155 AD-68
Rig Move Plan TO ABHD 155 AD-68
Electrical Rig Down / Planned Operations: Operational Rig Down: Rig Down Mud System remove shakers and Welders Should Work On The Ditch Lines As Per Aramco
Mechanical Rig Down / Planned Operations: Disconnect Accumulator cables And Secure Cable (4 Hr). mud cleaners, Load And Move All Tanks, Poorboy Degasser, Choke Requirment. The Ditch Lines Must Be Up From The Ground
Disconnect Diesel Lines, Rig Down Mast And Substructure disconnect muster points cables, (2Hrs) Manifold, Accumulator Unit, Rig Down Mast, Separate Traveling Welding Cut On The Ditches (Drain Channels) Prior Moving The
After Rig Release (8 Hrs). Block From Tds Needs CAT III, Remove TDS. Secure All Cables Mud System.
disconnet H2s System in rig and camp rooms from individual
Disconnect All Rig Water Lines / Supply Hoses / Secure (2 Hrs). Inside The Mast, Service Loop And Rotary Hoses keep in lower 2- Work on dismantle caravans.
Disconnect Fire Fighting Distribution Lines (2 Hrs). caravans (5 Hr). section. Unspool Secure All Utility Wires And Manrider Winch.
DISCONECT ALL DIESEL LINES AND MOFFLERS FRONM C-27 (5Hr.) continue rig down for the mud tanks , pull the cables and Remove Bop Hoists.
Disconnect Bop Hyd Control Hoses / Secure Hoses (2 Hrs). secure them(10Hrs) Oes To Perform Drop Object Survey On Mast, Monkey Board And
Disconnect Driller Panels Pneumatic Connections / Secure (1 Hr). disconnect remaining mud pump (2Hrs) Sub Structure.
Remove Bop Hoists (1 Hr). disconnect remaining generator(2Hrs) Initiated Rig Up Of Mud System On New Location.
Mechanical Rig Down On Drawworks (1 Hr). Tear Down Flare Lines And Vent Lines.
Remove Cascade System & Secure Them (3 Hr).
.
Drain Oil From Tds & Start Dismantling It From Rig Floor (1 Hr).
Rig Down Choke Manifold Lines (2Hr).and all sesnsors on rig floor.(4 Hr.)
Function Test Hpu And Bleed Off Air In Hyd System. Connect Raising Cylinder
On Substructure (6 Hrs).
MECHANICAL Meaintenance on Traweling and Crown Block, Inspect seheaves SEPARATE BOTH SECTION OF THE TORQUE TUBE FOR OPEN WORK ON MUD SYSTEM DITCH LINE AS PER ARAMCO
of taggers and manriders. TDS Monorail- Electrical Rig Down / Planned Operations: ROOM TO MECHANIC IN ORDER TO INSTALL THE TORQUE REQUIRMENT.
check with Technician fgor asst… Inspect MPI TDS -Connecting the Mud Tank System and water tanks and Diesel TUBE NEW HYDRAULIC CYLINDER, AS PER SCHEDULED
carriage if TDS on the ground. Change shout pin and IBOPactuator hydraulic MAINTENANCE PLAN (LINK BETWEEN TOP AND
tank (20Hrs)
(5Hr) remove main engine INTERMEDIATE TORQUE TRACK SECTIONS.
mufflers (4 hrs) MAINTENANCE TASKS: REPLACE SRL ATTACHED TO THE CROWN BY A NEW ONE. (1
-Annual PM for Top Drive motors (6 Hrs) HR)
-Quarterly PM for the Top Drive Unit. (4Hrs) INSTALL SPARE KELLY HOSES (CURRENTLY IN USE) IN
SECONDARY STAND PIPE UPON RECEIVE A NEW ONE TO BE
-check and clean transformers check and USE AS PRIMARY ONE.
clean dynamic brake resistors (6 Hrs) CHECK AND CONFIRM CORRECT LOCATION OF THE SLB
DIRECTIONAL DRILLER SENSOR ON PRIMARY STAND PIPE.
SCHEDULED DRILLING MONTHLY PM ON TDS (1 HR).
SCHEDULED DRILLING MONTHLY PM ON TRAVELING BLOCK
(1 HR).
SCHEDULED DRILLING MONTHLY PM ON CROWN BLOCK (1
DAY 4: DAY 4: DAY
HR). 4: LADDERS AND HANDRAILS.
INSTALL
START OESGUIDE
MASTON MAST LADDER
INSPECTION FOR OBJECT
AND DROP PROPERSURVEY (4
ALIGNMENT OF LAD-SAFE CABLE, UPON MATERIAL
HRS).
Electrical Rig Down / Planned Operations: SCHEDULED
RECEIVED (1DRILLING
HR). QUARTERLY PM ON HPU (2 HRS).
ADJUST COUNTERBALANCE WEIGHT SUITABLE TO
MECHANICAL TEAR DOWN ON RIG CAMP, LOADING, OFFLOADING AND Rig down and rig up for the main camp in the new location (24
CONNECT (RIG UP) IN NEW LOCATION
HANDLE HT65 RIG TONGS.
Hrs)
SET UP ENGINES, DIESEL TANKS & FUEL LINES (5.0 HRS). LIFT AND PINNING MONKEY BOARD ON MAST.
continue connect the mud tanks(4 Hrs) 3RD STAGE R/U MAST TANDEM LIFT (3 CRANES), LIFT
CONNECT HOSES ON MAST AND SUBSTRUCTURE.
HOOK UP FIRE WATER DISTRIBUTION LINES & OTHER SUPPLY LINES
connect the generators (8Hrs) MAST AND PINNING ON SUBSTRUCTURE.
connect cables of the mud pumps(6 Hrs) 4TH STAGE R/U MAST TANDEM LIFT (3 CRANES), LIFT
connet rig floor cables (6 Hrs) MAST, DETACH CROWN CLUSTER FROM 5TH WHEEL
MAINTENANCE TASKS: TRUCK, LIFT AND SET MAST ON STANDS.
check the space heaters of the TDS motors and make sure CONNECT HYDRAULIC MAST RAISING CYLINDERS
they are working (4Hrs) (DOUBLE CHECK EFFECTIVE PINNING).
DRILLING PM ON ESCAPE DEVICE (1 HRS).
DAY 18
complete all project and testing (1Day)
connect TDS Cables and test run(4Hrs)
rig up remaining cables in rig floor(4Hrs)
DAY 20:
MAINTENANCE TASKS:
.instrumentation service and sensor calibration(4Hrs)
install all window A/C again and srvice for split A/C
Units(12Hrs)
close action items for all audits(6Hrs)
workig in prespud checl list to be ready for rig acceptance.(12
Hrs)
RIG MOVE Time Breakdown
Rig Name/No. From Well: To Well:
APPROVED PLANNED
AD-68 ANDR-584 MAINTENANCE HR. NONE ABHD 155
Rig Released On: Input data in Green and White cells Only. Rig Accepted On: MAST DISMENTALED YES Actual Move Days: Input data in Green and White cells Only.
12/25/2020 Do not change Yellow cells Rig Move Do not change Yellow cells
1/10/2021 Actual Rig 15.88
Hours
Move Hours
Aramco KPI (Days): ADC KPI (Days): DISTANCE: 300 ADC KPI Var (Days):
15.00 12.00 336.00 381.00 -3.88
Un reeved Drill line from Drum & Disconnect 1.50 11.00 0.00 Air Tugger, Man Rider DRL, FM (3) , Elec. D/N
6
Disconnect standpipe manifold S Pipe & 1.50 15.00 0.00 Genny, Crane D/N
8
Disconnect Draw works, Driller Shelter and 3.00 18.00 0.00 Crane 2 FMs D/N
9
1.00 24.00 0.00 HPU wireless remote Ch. Mech, RS, D-crew D
Load Driller Shelter & Stand pipe shelter 7.14% 0.00%
34.00 0.00
10.12% 0.00%
Move Mast to new location 8.00 42.00 0.00 2 Cranes, Genny Driller, 4 FMs, D/N Secure service loops on
Rig Move
12.50% 0.00%
Rigger-1 , Ch. Mech, Mast. On New location spot
19
8.00 79.50 0.00 Crane, man lift, Fork lift RS, Rigger-1, D-Crew D
R/Up Engine line and prepare for power up.
(While Connected S Pipe on manifold & vibrator
hose. Power up Draw works. 23.66% 0.00%
Disconnect Block & Connected with TDS. 4.00 86.50 0.00 Crane, man lift, Fork lift Driler, AD, 3 FM D/N
25.74% 0.00%
34
2.00 100.50 0.00 Driller, D-crew D/N R/U H2S & Cascade
Pressure test surface lines witnessed by client 29.91% 0.00%
Driller, Floor Man (4), RAP, Systems.Fill water in Mud
Roustabout (2), Chief
Mechanic, Jr Mechanic,
System & Mixing Spud
Mud. mix mud/brine, hydro
50
34.97% 0.00%
56
117.50 0.00
TOTAL HOURS TOTAL NPT 0.00
140.00
120.00
100.00
80.00
KPI HOURS
60.00
40.00
20.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Total KPI Hours vs Total Actual Hours
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 3
Total KPI Hrs Total Actual Hrs Actual %
100.00%
90.00%
80.00%
70.00%
KPI Precentage
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
30 31 32 33 34 35 36 37 38 39 40 41 42 43
RIG MOVE VEHICLE LOAD REPORT AD-68
From Well: To Well: DISTANCE:
ANDR-584 ABHD 155 300
DATE 28-Jan-20 29-Jan-20 30-Jan-20 31-Jan-20 1-Feb-20 2-Feb-20 3-Feb-20 4-Feb-20 5-Feb-20 6-Feb-20 7-Feb-20 8-Feb-20 9-Feb-20 10-Feb-20 11-Feb-20 12-Feb-20 13-Feb-20 14-Feb-20 15-Feb-20 TOTAL
LOW BED 0
LOW BED WITH ROLLER 0
HIGH BED 0
FLAT BED 0
KEN-WORTH HIGH BED 0
KEN-WORTH LOW BED 0
SUPER TRUCK 0
CRANE 0
FORK LIFT 0
RIGGER 0
NIGHT CRANE OPERATOR 0
NIGHT FORKLIFT OPERATOR 0
S FB HH LB
S FB HH LB
RIG MOVE DISTANCES Vs AVERAGE DURATION:
1 2 3 4 5 6 7 8
20 50 100 200 350 500 700
Upto 20 21 to 50 51 to 100 101 to 200 201 to 350 351 to 500 501 to 700
KM KM KM KM KM KM KM
Duration Duration Duration Duration Duration Duration 3
0.5 1 1.5 2 2.5 3.5
AD-12 3.75 4.25 4.75 5.25 5.75 6.25 6.75
AD-14 3.75 4.25 4.75 5.25 5.75 6.25 6.75
AD-15 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-16 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-21 7.50 8.00 8.50 9.00 9.50 10.00 11.00
AD-23 7.50 8.00 8.50 9.00 9.50 10.00 11.00
AD-28 3.75 4.25 4.75 5.25 5.75 6.25 6.75
AD-29 3.75 4.25 4.75 5.25 5.75 6.25 6.75
AD-31 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-32 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-34 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-35 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-36 7.50 8.00 8.50 9.00 9.50 10.00 11.00
AD-41 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-42 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-43 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-44 3.75 4.25 4.75 5.25 5.75 6.25 7.25
AD-45 3.75 4.25 4.75 5.25 5.75 6.25 7.25
AD-46 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-47 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-48 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-49 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-51 10.50 11.00 11.50 12.00 12.50 13.00 14.00
AD-52 10.50 11.00 11.50 12.00 12.50 13.00 14.00
AD-53 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-54 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-55 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-56 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-57 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-58 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-59 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-61 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-62 5.50 6.00 6.50 7.00 7.50 8.00 8.50
AD-63 5.50 6.00 6.50 7.00 7.50 8.00 8.50
AD-64 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-65 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-66 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-67 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-68 5.50 6.00 6.50 7.00 7.50 8.00 8.50
AD-12 AD-12, AD-12, AD-12,
AD-14 AD-14, AD-14,
AD-15 AD-15, AD-15,
AD-16 AD-16, AD-16,
AD-21 AD-21, AD-21,
AD-23 AD-23, AD-23,
AD-28 AD-28, AD-28,
AD-29 AD-29, AD-29,
AD-31 AD-31, AD-31,
AD-32 AD-32, AD-32,
AD-34 AD-34, AD-34,
AD-35 AD-35, AD-35,
AD-36 AD-36, AD-36,
AD-41 AD-41, AD-41,
AD-42 AD-42, AD-42,
AD-43 AD-43, AD-43,
AD-44 AD-44, AD-44,
AD-45 AD-45, AD-45,
AD-46 AD-46, AD-46,
AD-47 AD-47, AD-47,
AD-48 AD-48, AD-48,
AD-49 AD-49, AD-49,
AD-51 AD-51, AD-51,
AD-52 AD-52, AD-52,
AD-53 AD-53, AD-53,
AD-54 AD-54, AD-54,
AD-55 AD-55, AD-55,
AD-56 AD-56, AD-56,
AD-57 AD-57, AD-57,
AD-58 AD-58, AD-58,
AD-59 AD-59, AD-59,
AD-61 AD-61, AD-61,
AD-62 AD-62, AD-62,
AD-63 AD-63, AD-63,
AD-64 AD-64, AD-64,
AD-65 AD-65, AD-65,
AD-66 AD-66, AD-66,
AD-67 AD-67, AD-67,
AD-68 AD-68, AD-68
AD-14, AD-15, AD-16, AD-21, AD-23, AD-28, AD-29, AD-31, AD-32,
AD-34, AD-35, AD-36, AD-41, AD-42, AD-43, AD-44, AD-45, AD-46,
AD-47, AD-48, AD-49, AD-51, AD-52, AD-53, AD-54, AD-55, AD-56,
AD-57, AD-58, AD-59, AD-61, AD-62, AD-63, AD-64, AD-65, AD-66,
AD-67, AD-68