Mechanics Electrician Drilling Crew Welders / Safety

Pre-move assignments: Pre Move: Pre Move:


- Welding Cut On The Ditches (Drain Channels) Prior Moving The
Maintenance Tasks: Secure all split A/C Units and flood lights, (15Hrs) R/D The Flair Lines And Swap Out The Choke Manifold Before Move Mud System. Pre
HPU mechanical PM, Inspection And Function Test, Inspection On Hydraulic Remove the lights on It To New Location. Move: Lifting and Handling Equipment inspections 1) Big
Hose On The Sub And Mast Lines, Change The Quick Couplings. Change The shaker tank that is above the allowed limit. (3Hrs) Clean Mud System and Rig Down for Pre Move (12 Hrs) bag lifting Gantry winch – Inspection & Blue Sticker – Expire on 26
Oil Filters (4 Hrs). Drilling PM On Mud Pumps: Replacing Mud Pumps Liners To 6 Dec 2020
Rig Down On Mud System
Disconnect two mud pumps (4Hrs) 1/2"", Check Fluid End, Seat And Valves, Open And Clean Suction. 2) BOP Winch – Inspection & Blue Sticker – Expire on 26 Dec 2020
Mechanical Rig Down / Planned Operations: disconncct two generators. (3Hrs) Pm Task On The Bop. Open Inspect And Clean And Dressed 3) Hydraulic Winch (DS- SN 1352563) – Inspection & Blue Sticker –
For Move (2 Hrs).Disconnect Accumulator Suit Case / Connections (4 Hrs). Rig Down On Mud Tanks, Pull And Secure Power Back.As Per Drilling Pm Tack. Expire on 26 Dec 2020
Start Rig Down On Mud System If Instructed (2 Hr). Install And Control Cables . (12 Hrs) Advance Loads: Chemicals, Tubulars Baskets, Main Camp, Loose 4) Monkey Board Winch – Inspection & Blue Sticker – Expire on 26
secondary containment diesel tanks rig camp and main camp 3hrs. Rig down Prepare all tower lights are in working condition and Make Material, Aramco Loads, Catwalk, Bop. Rig Down Ditches. Dec 2020
main camps split each building, 1-2 days ready (3Hrs) Pre-Move The Main Camp (If Allowed). 5) Man Rider Winch – Inspection & Blue Sticker – Expire on 26 Dec
Disconnect Cement Tank, (4Hrs) 2020
Rig down flare ignition system. (2 Hrs. ) 6) Non-rotating wire of man rider winch – Inspection – Expire on 26
Disconnect all pason sensors and cables on mud tanks(mud Dec 2020
flow sensor,casing pressure sesnor,........etc) (2Hrs) 7) Chain Blocks – Inspection – Expire on 30 Dec 2020
8) Big Bag Ring – Inspection – Expire on 30 Dec 2020
9) Lifting Pad Eyes – Inspection & NDT – Expire on 2 Jan 2021
10) Wire Rope Slings – Inspection – Expire on 29 Dec 2020
11) Shackles – Inspection – Expire on 29 Dec 2020
12) Turnbuckles – Inspection – Expire on 9 Jan 2020
13) Barrel Lifter – Inspection – Expire on 30 Dec 2020
14) Master skid lifting lugs and container lifting point – Inspection –
Expire on 27 Dec 2020 / NDT – Expire on 6 Feb 2021
15) Lifting Swivels – Inspection – Expire on 6 Jan 2021
16) Cross Bar – Inspection & NDT – Expire on 30 Dec 2020
17) Elevator Links – CAT III – Expire on 5 Jan 2020 / CAT IV –
Expire on 10 Jan 2021
18) Drill Pipe Elevators / Drill Collars Elevators/ single joint elevator –
CAT IV – Expire on 20 Dec 2020
19) Slips – CAT III – Expire on 6 Jan 2021
20) Manual Tong – CAT III – Expire on 6 Jan 2021
21) Safety Clamps – CAT IV – Expire on 6 Jan 2021
22) Lifting Caps – CAT III – Expire on 6 Jan 2021
23) Mast & Sub Structure – CAT II – to be done before rig move
24) Hydraulic Winch (ODS) wire rope needs to be replaced
(damage)
25) High pressure flexible hoses – Inspection as per new Aramco
required inspections
27) Water Tanks Cleaning from 3rd party
28) Check MB SRL’s
Day 1 Maintenance Tasks: Day 1 Day 1 Maintenance Tasks: Day 1 Maintenance Tasks:

Electrical Rig Down / Planned Operations: Operational Rig Down: Rig Down Mud System remove shakers and Welders Should Work On The Ditch Lines As Per Aramco
Mechanical Rig Down / Planned Operations: Disconnect Accumulator cables And Secure Cable (4 Hr). mud cleaners, Load And Move All Tanks, Poorboy Degasser, Choke Requirment. The Ditch Lines Must Be Up From The Ground
Disconnect Diesel Lines, Rig Down Mast And Substructure disconnect muster points cables, (2Hrs) Manifold, Accumulator Unit, Rig Down Mast, Separate Traveling Welding Cut On The Ditches (Drain Channels) Prior Moving The
After Rig Release (8 Hrs). Block From Tds Needs CAT III, Remove TDS. Secure All Cables Mud System.
disconnet H2s System in rig and camp rooms from individual
Disconnect All Rig Water Lines / Supply Hoses / Secure (2 Hrs). Inside The Mast, Service Loop And Rotary Hoses keep in lower 2- Work on dismantle caravans.
Disconnect Fire Fighting Distribution Lines (2 Hrs). caravans (5 Hr). section. Unspool Secure All Utility Wires And Manrider Winch.
DISCONECT ALL DIESEL LINES AND MOFFLERS FRONM C-27 (5Hr.) continue rig down for the mud tanks , pull the cables and Remove Bop Hoists.
Disconnect Bop Hyd Control Hoses / Secure Hoses (2 Hrs). secure them(10Hrs) Oes To Perform Drop Object Survey On Mast, Monkey Board And
Disconnect Driller Panels Pneumatic Connections / Secure (1 Hr). disconnect remaining mud pump (2Hrs) Sub Structure.
Remove Bop Hoists (1 Hr). disconnect remaining generator(2Hrs) Initiated Rig Up Of Mud System On New Location.
Mechanical Rig Down On Drawworks (1 Hr). Tear Down Flare Lines And Vent Lines.
Remove Cascade System & Secure Them (3 Hr).

.
Drain Oil From Tds & Start Dismantling It From Rig Floor (1 Hr).
Rig Down Choke Manifold Lines (2Hr).and all sesnsors on rig floor.(4 Hr.)
Function Test Hpu And Bleed Off Air In Hyd System. Connect Raising Cylinder
On Substructure (6 Hrs).

DAY 2: DAY 2: DAY 2 DAY 2


TUBULAR INSPECTION (DS1) ON BHA AND DPS…
MAINTENANCE TASKS: ELECTRICAL RIG DOWN / PLANNED OPERATIONS: CONTINUOUS PROCESS. 2-CONTINUE WELDING CUT ON THE DITCHES (DRAIN
REMOVE TDS OUT OF THE TORQUE TUBE (MONORAIL) AND REMOVE Remove the A/C units for the VFD House and secure(3Hrs) SERVICE VALVES FOR HIGH PRESSURE LINES AND STAND CHANNELS).
MONO RAIL NOV TECH. TDS COMPLETE SERVICE . VISUALLY CHECK Disconnect TDS Cables(3Hrs) PIPE MANIFOLD (DRILLING PM FOR HIGH PRESSURE LINES 2-'WORK ON DISMANTLING CARAVANS.
FRAME, GUARD, MOUNTS AND SUPPORTS FOR CRACKS OR DAMAGE, VALVES).
- disconnect mast cables (2Hrs)
CONDITION OF ALL BOLTED CONNECTIONS, PINS AND PIN HOLES, CONTINUE OPERATIONAL RIG DOWN ON ANDR 584 AND RIG
HYDRAULIC CYLINDERS, HOSES, FITTINGS AND CONNECTORS, CHECK -disconnect subbase cables(2Hrs) UP PROCESS ON ABHD 155.
FOR ANY OIL LEAKS, PREPARE FOR LOWER SUBBASE, EXTEND AND PINNING
TDS INSPECTION, SUBBASE RAISING CYLINDERS (DOUBLE CHECK EFFECTIVE
PM. CROWN & TRAVELLING PINNING).
BLOCK INSPECTION. DRAWWORKS PM & INSPECTION. CAT WALK COMPLETE SUBSTRUCTURE LOWERING CHECKLIST AND
INSPECTION. ( ??) DEAD LINE ANCHOR & ROTARY LOWER SUBSTRUCTURE (RIG FLOOR).
TABLE INSPECTION. MAINTENANCE TASKS: PREPARE FOR LOWER MAST, EXTEND AND PINNING MAST
-Replace the inverter#3 for DWB Drive. RAISING CYLINDERS (DOUBLE CHECK EFFECTIVE PINNING).
DAY 2: DAY 2: DAY 2 DAY 2
TUBULAR INSPECTION (DS1) ON BHA AND DPS…
MAINTENANCE TASKS: ELECTRICAL RIG DOWN / PLANNED OPERATIONS: CONTINUOUS PROCESS. 2-CONTINUE WELDING CUT ON THE DITCHES (DRAIN
REMOVE TDS OUT OF THE TORQUE TUBE (MONORAIL) AND REMOVE Remove the A/C units for the VFD House and secure(3Hrs) SERVICE VALVES FOR HIGH PRESSURE LINES AND STAND CHANNELS).
MONO RAIL NOV TECH. TDS COMPLETE SERVICE . VISUALLY CHECK Disconnect TDS Cables(3Hrs) PIPE MANIFOLD (DRILLING PM FOR HIGH PRESSURE LINES 2-'WORK ON DISMANTLING CARAVANS.
FRAME, GUARD, MOUNTS AND SUPPORTS FOR CRACKS OR DAMAGE, VALVES).
CONDITION OF ALL BOLTED CONNECTIONS, PINS AND PIN HOLES,
- disconnect mast cables (2Hrs) CONTINUE OPERATIONAL RIG DOWN ON ANDR 584 AND RIG
HYDRAULIC CYLINDERS, HOSES, FITTINGS AND CONNECTORS, CHECK -disconnect subbase cables(2Hrs) UP PROCESS ON ABHD 155.
FOR ANY OIL LEAKS, PREPARE FOR LOWER SUBBASE, EXTEND AND PINNING
TDS INSPECTION, SUBBASE RAISING CYLINDERS (DOUBLE CHECK EFFECTIVE
PM. CROWN & TRAVELLING PINNING).
BLOCK INSPECTION. DRAWWORKS PM & INSPECTION. CAT WALK COMPLETE SUBSTRUCTURE LOWERING CHECKLIST AND
INSPECTION. ( ??) DEAD LINE ANCHOR & ROTARY LOWER SUBSTRUCTURE (RIG FLOOR).
TABLE INSPECTION. MAINTENANCE TASKS: PREPARE FOR LOWER MAST, EXTEND AND PINNING MAST
-Replace the inverter#3 for DWB Drive. RAISING CYLINDERS (DOUBLE CHECK EFFECTIVE PINNING).
MECHANICAL RIG DOWN / PLANNED OPERATIONS: (4Hrs) - install the two new COMPLETE MAST LOWERING CHECKLIST AND LOWER MAST
batteries for the Driller shack PLC (1Hr) (LANDING ON MAST STANDS)
REMOVE MONKEYBOARD
DISCONNECT FUEL SUPPLY/RETURN LINES OF ENGINES / SECURE, DISCONNECT RAISING CYLINDERS AND LAY ON STORAGE
REMOVE ALL 5 EXHAUST- MOFFLERS FROM ROOF (10HRS) POSITION.
LOWER SUB BASE & MAST. RECOVER AND ARRANGE DRILL LINE FOR TRANSPORTATION.
INSTALL 5TH WHEEL BUNK BELOW CROWN CLUSTER AND
CONNECT MAST ON DOLLY.
MOVE MAST TO NEW LOCATION.
CONTINUE R/U MUD SYSTEM ON FZRN 213.

DAY 3: DAY 3: DAY 3: DAY 3

MECHANICAL Meaintenance on Traweling and Crown Block, Inspect seheaves SEPARATE BOTH SECTION OF THE TORQUE TUBE FOR OPEN WORK ON MUD SYSTEM DITCH LINE AS PER ARAMCO
of taggers and manriders. TDS Monorail- Electrical Rig Down / Planned Operations: ROOM TO MECHANIC IN ORDER TO INSTALL THE TORQUE REQUIRMENT.
check with Technician fgor asst… Inspect MPI TDS -Connecting the Mud Tank System and water tanks and Diesel TUBE NEW HYDRAULIC CYLINDER, AS PER SCHEDULED
carriage if TDS on the ground. Change shout pin and IBOPactuator hydraulic MAINTENANCE PLAN (LINK BETWEEN TOP AND
tank (20Hrs)
(5Hr) remove main engine INTERMEDIATE TORQUE TRACK SECTIONS.
mufflers (4 hrs) MAINTENANCE TASKS: REPLACE SRL ATTACHED TO THE CROWN BY A NEW ONE. (1
-Annual PM for Top Drive motors (6 Hrs) HR)
-Quarterly PM for the Top Drive Unit. (4Hrs) INSTALL SPARE KELLY HOSES (CURRENTLY IN USE) IN
SECONDARY STAND PIPE UPON RECEIVE A NEW ONE TO BE
-check and clean transformers check and USE AS PRIMARY ONE.
clean dynamic brake resistors (6 Hrs) CHECK AND CONFIRM CORRECT LOCATION OF THE SLB
DIRECTIONAL DRILLER SENSOR ON PRIMARY STAND PIPE.
SCHEDULED DRILLING MONTHLY PM ON TDS (1 HR).
SCHEDULED DRILLING MONTHLY PM ON TRAVELING BLOCK
(1 HR).
SCHEDULED DRILLING MONTHLY PM ON CROWN BLOCK (1
DAY 4: DAY 4: DAY
HR). 4: LADDERS AND HANDRAILS.
INSTALL
START OESGUIDE
MASTON MAST LADDER
INSPECTION FOR OBJECT
AND DROP PROPERSURVEY (4
ALIGNMENT OF LAD-SAFE CABLE, UPON MATERIAL
HRS).
Electrical Rig Down / Planned Operations: SCHEDULED
RECEIVED (1DRILLING
HR). QUARTERLY PM ON HPU (2 HRS).
ADJUST COUNTERBALANCE WEIGHT SUITABLE TO
MECHANICAL TEAR DOWN ON RIG CAMP, LOADING, OFFLOADING AND Rig down and rig up for the main camp in the new location (24
CONNECT (RIG UP) IN NEW LOCATION
HANDLE HT65 RIG TONGS.
Hrs)
SET UP ENGINES, DIESEL TANKS & FUEL LINES (5.0 HRS). LIFT AND PINNING MONKEY BOARD ON MAST.
continue connect the mud tanks(4 Hrs) 3RD STAGE R/U MAST TANDEM LIFT (3 CRANES), LIFT
CONNECT HOSES ON MAST AND SUBSTRUCTURE.
HOOK UP FIRE WATER DISTRIBUTION LINES & OTHER SUPPLY LINES
connect the generators (8Hrs) MAST AND PINNING ON SUBSTRUCTURE.
connect cables of the mud pumps(6 Hrs) 4TH STAGE R/U MAST TANDEM LIFT (3 CRANES), LIFT
connet rig floor cables (6 Hrs) MAST, DETACH CROWN CLUSTER FROM 5TH WHEEL
MAINTENANCE TASKS: TRUCK, LIFT AND SET MAST ON STANDS.
check the space heaters of the TDS motors and make sure CONNECT HYDRAULIC MAST RAISING CYLINDERS
they are working (4Hrs) (DOUBLE CHECK EFFECTIVE PINNING).
DRILLING PM ON ESCAPE DEVICE (1 HRS).

DAY 5: DAY5: DAY 5:


Electrical Rig Down / Planned Operations:
MAINTENANCE TASKS: Connect flare ignition cables, (3Hrs) CONTINUE OPERATIONAL RIG UP ON ABHD155.
connect the power and control cables for REPLACED THE DRILLING SPOOL WITH ANEW ONE.
accumulator(6 Hrs) -connect two muster points DROP OBJECT SURVEY AND ACTION ITEMS TO BE
MECHANICAL RIG UP / PLANNED OPERATIONS:
(2Hrs) -inspection to the CLOSE .
INSTALL DRAWWORKS. (2.5 HR)
HOOK UP AIR CONNECTION OF MANRIDER WINCHES (1.5 HR). mast and subbase lights and repair or repalce when PERFORM TANDEM LIFT FOR INSTALL DRAWWORKS ON
ALIGN ACCUMULATOR SUITCASE & HOOK UP CONNECTIONS PM required(two led lights to be replaced and one flood light to be PONY SUB BASE (MUD BOAT).
Accoumulators (5.0 HR). repaired)(6 Hrs) DRILLING PM ON DS & ODS HYDRAULIC TAGGERS (2
-relocate the monkey board camera (3Hrs) HRS).
FILL UP OIL IN TDS & CHECK ALL FUNCTION (4.0 HR).PM completed REPLACE STAND PIPE MANIFOLD 5” O-RING SEALS BY
DAY 5: DAY5: DAY 5:
Electrical Rig Down / Planned Operations:
MAINTENANCE TASKS: Connect flare ignition cables, (3Hrs) CONTINUE OPERATIONAL RIG UP ON ABHD155.
connect the power and control cables for REPLACED THE DRILLING SPOOL WITH ANEW ONE.
accumulator(6 Hrs) -connect two muster points DROP OBJECT SURVEY AND ACTION ITEMS TO BE
MECHANICAL RIG UP / PLANNED OPERATIONS:
INSTALL DRAWWORKS. (2.5 HR)
(2Hrs) -inspection to the CLOSE .
HOOK UP AIR CONNECTION OF MANRIDER WINCHES (1.5 HR). mast and subbase lights and repair or repalce when PERFORM TANDEM LIFT FOR INSTALL DRAWWORKS ON
ALIGN ACCUMULATOR SUITCASE & HOOK UP CONNECTIONS PM required(two led lights to be replaced and one flood light to be PONY SUB BASE (MUD BOAT).
Accoumulators (5.0 HR). repaired)(6 Hrs) DRILLING PM ON DS & ODS HYDRAULIC TAGGERS (2
-relocate the monkey board camera (3Hrs) HRS).
FILL UP OIL IN TDS & CHECK ALL FUNCTION (4.0 HR).PM completed REPLACE STAND PIPE MANIFOLD 5” O-RING SEALS BY
NEW ONES.

DAY6: DAY6: 'DAY 6: PLATFORMS


Check
and inspect Catwalk 2(days) connect all 'Electrical Rig Down / Planned Operations: CONTINUE OPERATIONAL RIG UP ON ABHD155.
lines for mud system connect hoses UN-SPOOL DRILLING LINE LONG ENOUGH (+/-150 FT) OUT OF
and lines for mast and subbase PM for monkey connectcables of the cement tank . (4Hrs) THE DRILLING SPOOL
board winch PM for both bop DROP OBJECT SURVEY AND ACTION ITEMS TO BE CLOSE AS
winches
run test for all loads. (6Hrs) PREPARATION FOR RAISING MAST, COMPLETE CHECKLIST
working on grounding for rig side .(4Hrs) AND RAISING MAST.
Testeing the H2S/LEL Aarms.(2Hrs) PREPARE FOR RAISING SUBBASE, COMPLETE CHECKLIST
-connect all cables on the mast (2Hrs) AND RAISING SUBSTRUCTURE (RIG FLOOR).
-connect all cables to the subbase (2Hrs)
-connect cables to the monkey board(1Hr) DRILLING PM ON DS & ODS HYDRAULIC TAGGERS (2 HRS).
REPLACE STAND PIPE MANIFOLD 5” O-RING SEALS BY NEW
ONES.

DAY 7: DAY 7: DAY 7: WORK ON MUD SYSTEM


Rig
down ad rig up for the rig camp in the new location(24Hrs) Rnstall rig down and rig up for the rig camp in the new location(12Hrs) SCHEDULED MAINTENANCE (DAY 7).
main engine mufflers (4 hrs) start install air conditions for the VFD House(4Hrs) CALL FOR SERVICE AND COMPLETE LOAD TEST ON BOTH
working to change 2-ea agitators (2 days) continue any remaining maintenance(6Hrs) SUPER SACK PNEUMATIC HOISTS (1 HR).
SERVICE CHOKE MANIFOLD (LUBRICATION), OPEN AND
SERVICE REAR VALVE FOR FLARE LINE # 2 (BLUE LINE).
DRILLING MONTHLY PM ON NEW RECEIVED BOP ANNULAR
PREVENTER.
DRILLING MONTHLY PM ON VACUUM DEGASSER (1 HRS).
DRILLING MONTHLY PM ON MUD CLEANER (2 HRS).
PREPARE FOR RAISING SUBBASE, COMPLETE CHECKLIST
AND RAISING SUBSTRUCTURE (RIG FLOOR).

DAY 8 to DAY 17 Scheduled Maintenece DAY 8 to Day 17 WORK ON MUD SYSTEM


1-Upgrade VFD Lifting and Handling Equipment Inspection due on 1st Qrt of 2021 at
replace shot pin /adjust hydraulic system of top drive MPI
Continue working to replace 2-ea agitators -install all the panels inside the VFD by NOV Engineer with new location (ABHD 155) 1)
for carriage TDS ODS
Replace flexible joint for engine no 2 the help of ADC Crew (two weeks) Hydraulic winch (DS) – quarterly & blue sticker due on 10 Feb 2021
need repair by AFI company modify
Install rubber elemnt for main engine 3512 coupling -download the new software by Ensign 2) Single / Multi Sheaves Blocks (snatch blocks) – Bi-annual
the line up of bop winches PM for
Replace filters for air dryers inspection due on21 Mar 2021
both mixing winch PM for Engineer (1 day) 3) BOP Lifting Plates – Annual inspection due on 12 Apr 2021 and
drawwork PM for Air 2-Upgrade Mud System NDT/MPI due on 14 Mar 2021
dryer PM for both -install the new plug boards (6 4) Eye bolts – Bi-annual inspection due on 20 Mar 2021
cathead cylinder main camp Hrs) -reroute the cables 5) Master Skid lifting lugs – NDT/MPI due on 6 Feb 2021
engine 2 (6000 hrs) annual PM for on the newcables trays(24 Hrs) -cut the 6) Derrick Escape Device – Annual inspection due on 3 Apr 2021
mud pump 1 & 2 & 3 PM for rotary and
cables and install the connectors on the plug bords(2 Days) (KANOO)
transmission
7) Crown block – CAT III (6 monthly) due on 21 Mar 2021
3-Relocate MCC 8) High Pressure Mud lines – CAT III (Annual) due on 2 Apr 2021
- remove the generators and 9) TDS – CAT III (6 monthly) due on 22 Mar 2021
prepare the skid (two Days) -Move the 10) TDS rail – CAT III (6 monthly) due on 23 Mar 2021
11) Deadline anchor – CAT III (6 monthly) due on 21 Mar 2021
Scheduled Maintenece DAY 8 to Day 17 WORK ON MUD SYSTEM
1-Upgrade VFD Lifting and Handling Equipment Inspection due on 1st Qrt of 2021 at
-install all the panels inside the VFD by NOV Engineer with new location (ABHD 155) 1)
the help of ADC Crew (two weeks) Hydraulic winch (DS) – quarterly & blue sticker due on 10 Feb 2021
-download the new software by Ensign 2) Single / Multi Sheaves Blocks (snatch blocks) – Bi-annual
inspection due on21 Mar 2021
Engineer (1 day) 3) BOP Lifting Plates – Annual inspection due on 12 Apr 2021 and
2-Upgrade Mud System NDT/MPI due on 14 Mar 2021
-install the new plug boards (6 4) Eye bolts – Bi-annual inspection due on 20 Mar 2021
Hrs) -reroute the cables 5) Master Skid lifting lugs – NDT/MPI due on 6 Feb 2021
on the newcables trays(24 Hrs) -cut the 6) Derrick Escape Device – Annual inspection due on 3 Apr 2021
cables and install the connectors on the plug bords(2 Days) (KANOO)
7) Crown block – CAT III (6 monthly) due on 21 Mar 2021
3-Relocate MCC 8) High Pressure Mud lines – CAT III (Annual) due on 2 Apr 2021
- remove the generators and 9) TDS – CAT III (6 monthly) due on 22 Mar 2021
prepare the skid (two Days) -Move the 10) TDS rail – CAT III (6 monthly) due on 23 Mar 2021
MCC to the new location (2Hrs) - 11) Deadline anchor – CAT III (6 monthly) due on 21 Mar 2021
12) Loops / Chicksan – CAT II (Annual) due on 23 Mar 2021
run the cables from the VFD to the MCC in the new
13) PRV – Annual due on 25 Mar 2021
location(6Hrs)
5-supply to the rig camp
remove one rig camp generator and install the
transformer(1 Day)
run the new cables from the the transformer
to the VFD House (6Hrs)
install new conectors and lugs to
the rig camp new cables(4Hrs)

DAY 18
complete all project and testing (1Day)
connect TDS Cables and test run(4Hrs)
rig up remaining cables in rig floor(4Hrs)

DAY 19 DAY 19 WORK ON MUD SYSTEM.


run the engines and check for any upnormal alarm or noise (2Hrs) run the engines and check for any upnormal alarm
run top drive / mud pump/ new agitators / drawwork and function test or noise (2Hrs)
test mud pumps and check the input
voltage,current and temperature (6Hrs)
test rotary and check the new
inverters if working probely(3Hrs)
test remainng loads(4Hrs)

DAY 20:

connect cellar pumps (2Hrs)


keep monitoring for the VFD House especially the panels
installed for any upnormal issue continue
working with any remaining job in the mcc relocation or rig camp
supply(4Hrs)
DAY 21:

MAINTENANCE TASKS:
.instrumentation service and sensor calibration(4Hrs)
install all window A/C again and srvice for split A/C
Units(12Hrs)
close action items for all audits(6Hrs)
workig in prespud checl list to be ready for rig acceptance.(12
Hrs)
RIG MOVE Time Breakdown
Rig Name/No. From Well: To Well:
APPROVED PLANNED
AD-68 ANDR-584 MAINTENANCE HR. NONE ABHD 155
Rig Released On: Input data in Green and White cells Only. Rig Accepted On: MAST DISMENTALED YES Actual Move Days: Input data in Green and White cells Only.
12/25/2020 Do not change Yellow cells Rig Move Do not change Yellow cells
1/10/2021 Actual Rig 15.88
Hours
Move Hours
Aramco KPI (Days): ADC KPI (Days): DISTANCE: 300 ADC KPI Var (Days):
15.00 12.00 336.00 381.00 -3.88

Total Total Limitation


Operation Category Main Task KPI Hrs KPI Hrs Actual Hrs Actual Hrs Equipment Requirement Personnel Requirement (Day/Night) KPI% Actual % Parallel Task NPT Remark

Drlr & F/M,


4.00 4.00 0.00 Air Tugger, manrider, crane D/N Disconnect and load the
1

Rig down drilling equipment & clear RF. 1.19% 0.00%


mud system if not
2.00 6.00 0.00 Air Tugger, manrider, crane Driller, Floor Man (3) D/N completed yet as per pre-
2

Remove TDS’s Rotary hose Mechanic 1.79% 0.00%


Secure TDS & Removed Travelling block from 1.00 7.00 0.00 Air Tugger, Man Rider Driller, Floor Man (3) D/N
release plan, Move & spot
3

TDS Mechanic, Elec. 2.08% 0.00% the mud tanks on new


Secure Travelling block In Mast 1.00 8.00 0.00 140 T Crane D/N
location. R/U Mud System
4

Driller, Floor Man (3), 2.38% 0.00%

Prepare to lower Sub base and complete the on New location.


1.50 9.50 0.00 Man Rider, Air Tugger D/N
5

checklist & Lower Sub base (Lower Sub base in


10 Min) Driller, Floor Man (3) 2.83% 0.00%

Un reeved Drill line from Drum & Disconnect 1.50 11.00 0.00 Air Tugger, Man Rider DRL, FM (3) , Elec. D/N
6

from Dead Line Anchor. 3.27% 0.00%

Disconnect HYD hoses from Sub base Raising


2.50 13.50 0.00 Air Tugger, Crane D/N
7

cylinder & R/Up hoses on Mast Raising Cylinder


& Raised Mast cylinders Driller, Floor Man (3) , Elec 4.02% 0.00%
Rig Down

Disconnect standpipe manifold S Pipe & 1.50 15.00 0.00 Genny, Crane D/N
8

Driller, Floor Man (3),


Vibrator hoses Mech 4.46% 0.00%

Disconnect Draw works, Driller Shelter and 3.00 18.00 0.00 Crane 2 FMs D/N
9

Grasshopper Cables. 5.36% 0.00%

PJSM & Lower Mast in stand (Lower mast in 20


10

1.00 19.00 0.00 Crane Driller, 3 Floor Man, Elec D/N


Min). 5.65% 0.00%
Conduct Mast OES Survey as per IDS
11

2.00 21.00 0.00 Genny Mech, 3 FM, DRL D


Requirement 6.25% 0.00%
Disconnect Mono Rail Lay down TDS & Secure
12

1.00 22.00 0.00 Crane Driller, AD,2 Floor Man D/N


in Skid Due to Change TDS motor driller side 6.55% 0.00%

Disconnect Mast Raising Cylinder from mast &


13

1.00 23.00 0.00 Crane D/N


secure TDS lope & Kelly hose in side mast. Driller, Floor Man (2) 6.85% 0.00%
14

1.00 24.00 0.00 HPU wireless remote Ch. Mech, RS, D-crew D
Load Driller Shelter & Stand pipe shelter 7.14% 0.00%

Move Mast & connect to prime mover and


15

2.00 26.00 0.00


shifted in Mast Dolly Used four crane & Pin up
Mast in dolly 7.74% 0.00%
16

8.00 34.00 0.00


Dismantle the mast (if needed)
18 17

34.00 0.00
10.12% 0.00%

Move Mast to new location 8.00 42.00 0.00 2 Cranes, Genny Driller, 4 FMs, D/N Secure service loops on
Rig Move

12.50% 0.00%
Rigger-1 , Ch. Mech, Mast. On New location spot
19

8.00 50.00 0.00 4 Cranes, Genny D


Move Sub base and mud system to new location Driller, D crew 14.88% 0.00% PCR, Engines, workshops &
stores.
21 20

8.00 58.00 0.00 Genny Elec D/N


Move remaining rig equipment to new location 17.26% 0.00%
58.00 0.00
R/U Mud System, R/U MP
17.26% 0.00%
# 3 & 2.
Spot Sub base, Spot Rotary table Skid, Spot Dig out ditches line around
22

3.00 61.00 0.00 Forklift, 4 cranes D


Draw work Skid & DW. RS, Rigger-1, D-Crew 18.15% 0.00% mud tank. Cont. R/Up Mud
Move Mast in place, Remove Drill line Spool, Tanks. Changed butterfly
Spot HPU, Disconnect Mast Dolly pin & Spot valve of mud tank in
23

1.50 62.50 0.00 Crane Driller, 2 FM D/N


Mast in place and pin in Mast & Disconnect progress. Load PCR, Power
prime mover & Lower Mast on Mast stand. 18.60% 0.00%
Pack, Diesel tank & Spot
Connect Hydraulic hoses & Raise Mast Raising Koomey. Fill up water in
24

1.00 63.50 0.00 Crane RS, Rigger-1, D-Crew D


cylinder both side 18.90% 0.00%
water tank & hydro test mud
system. Cont. prepare spud
25

1.00 64.50 0.00 2 CRANES RS, Rigger-1, D-Crew D


Removed Kelly hose & TDS loops 19.20% 0.00%
mud in progress. Spot
Spot driller shelter, Manifold shelter & spot kommey in place, Hydraulic
26

1.50 66.00 0.00 RS, Rigger-1, D-Crew D


stand pipe skid. 19.64% 0.00%
D/N ( IF HAVE hose skid, X over basket,
PROPER
PJSM & Raise Mast & Disconnect mast raising
Driller, (Rigger-1 if with 2 Hyd Cat walk. Conduct Pre
27

1.00 67.00 0.00 1 OR 2 cranes LENGTH SLINGS


cranes), D crew
cylinder and hose (Raised Mast in 16 Min). POSSIBLE WITH
1 CRANE. 19.94% 0.00% spud meeting
Spot Mud Pump # 1, 2, 3 & Connected Rigger-1, Driller, 3 FM
29 28

1.50 68.50 0.00 2 Cranes, Genny D


Grasshopper 20.39% 0.00%
1.00 69.50 0.00 Forklift, Crane D
PJSM & Raise Subbase Rigger, Driller, AD, 3 FMs 20.68% 0.00%
2 Cranes
Rig Up

Disconnect Subbase Cylinder & Closed pistons.


30

2.00 71.50 0.00 RS Truck/P, D-crew D


While Spot VFD, Power Pack & Diesel tank. 21.28% 0.00%

Connect Electrical Cable grasshoppers, driller


shelter & Connect Draw work & PCR Cable.
31

8.00 79.50 0.00 Crane, man lift, Fork lift RS, Rigger-1, D-Crew D
R/Up Engine line and prepare for power up.
(While Connected S Pipe on manifold & vibrator
hose. Power up Draw works. 23.66% 0.00%

Function test draw works, Reeve drill line on


32

3.00 82.50 0.00 RS, Rigger-1, D-Crew D


drum & connect in dead line Anchor
24.55% 0.00%
Spool HYD winches & Man Riding winches,
33

Disconnect Block & Connected with TDS. 4.00 86.50 0.00 Crane, man lift, Fork lift Driler, AD, 3 FM D/N
25.74% 0.00%
34

1.00 87.50 0.00 4 Cranes, Genny RS, Rigger-1, D-Crew D


Install BOP winches 26.04% 0.00%

Connect TDS Loops, Install TDS Grapple,. fill


HYD oil & Check and adjust all Pressure.
35

8.00 95.50 0.00 N/A N/A N/A


Function test TDS
36

3.00 98.50 0.00 CRANE, Genny D/N


Change washpipe & saver sub Driller, Crew 29.32% 0.00%
49 37

98.50 0.00 29.32% 0.00%

2.00 100.50 0.00 Driller, D-crew D/N R/U H2S & Cascade
Pressure test surface lines witnessed by client 29.91% 0.00%
Driller, Floor Man (4), RAP, Systems.Fill water in Mud
Roustabout (2), Chief
Mechanic, Jr Mechanic,
System & Mixing Spud
Mud. mix mud/brine, hydro
50

2.00 102.50 0.00 Chief Electrician, Jr D/N


Electrician
Pressure test flare lines witnessed by client 30.51% 0.00%
test flare lines, function test
ignition system, dig the
51

2.00 104.50 0.00


Drill-out rate hole 31.10% 0.00% ditches around the mud
Acceptance

tanks, go through the pre-


52

PU & rack 25 DP stand on Derrick 4.00 108.50 0.00 32.29% 0.00%


spud checklist.
Cont. working on Ditches because client want to
53

4.00 112.50 0.00


level ditches from cellar pad to cutting pit. While
P/Up & M/UP Spud Assay 33.48% 0.00%
Complete pre-acceptance checklist & conduct
H2S Drill
54

5.00 117.50 0.00

34.97% 0.00%
56

117.50 0.00 34.97% 0.00%

117.50 0.00
TOTAL HOURS TOTAL NPT 0.00
140.00

120.00

100.00

80.00
KPI HOURS

60.00

40.00

20.00

0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Total KPI Hours vs Total Actual Hours

13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 3
Total KPI Hrs Total Actual Hrs Actual %
100.00%

90.00%

80.00%

70.00%

KPI Precentage
60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%
30 31 32 33 34 35 36 37 38 39 40 41 42 43
RIG MOVE VEHICLE LOAD REPORT AD-68
From Well: To Well: DISTANCE:
ANDR-584 ABHD 155 300

DATE 28-Jan-20 29-Jan-20 30-Jan-20 31-Jan-20 1-Feb-20 2-Feb-20 3-Feb-20 4-Feb-20 5-Feb-20 6-Feb-20 7-Feb-20 8-Feb-20 9-Feb-20 10-Feb-20 11-Feb-20 12-Feb-20 13-Feb-20 14-Feb-20 15-Feb-20 TOTAL

LOW BED 0
LOW BED WITH ROLLER 0

HIGH BED 0
FLAT BED 0
KEN-WORTH HIGH BED 0
KEN-WORTH LOW BED 0
SUPER TRUCK 0
CRANE 0
FORK LIFT 0
RIGGER 0
NIGHT CRANE OPERATOR 0
NIGHT FORKLIFT OPERATOR 0

PRE MOVE LOAD TOTAL 0


RIG MOVE LOAD TOTAL 0
PRE MOVE ARAMCO CHEMICHAL LOAD 0
RIG MOVE ARAMCO CHEMICHAL LOAD 0
TOTAL PER DAY 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Rig AD-68 Load List DISTANCE:
Length Width Height Weight High Lifting Requirement Crane(s) / Loader Truck
Load No. Description Risk (Slings)
unit unit unit Ton Load Qty. Capacity (Ton) Qty. Capacity (unit) Type
1 ¨
2 ¨
3 ¨
4 ¨
5 ¨
6 ¨
7 ¨
8 ¨
9 ¨
10 ¨
11 ¨
12 ¨
13 ¨
14 ¨
15 ¨
16 ¨
17 ¨
18 ¨
19 ¨
20 ¨
21 ¨
22 ¨
23 ¨
24 ¨
25 ¨
26 ¨
27 ¨
28 ¨
29 ¨
30 ¨
31 ¨
32 ¨
33 ¨
34 ¨
35 ¨
36 ¨
37 ¨
38 ¨
39 ¨
40 ¨
41 ¨
42 ¨
43 ¨
44 ¨
45 ¨
46 ¨
47 ¨
48 ¨
49 ¨
50 ¨

S FB HH LB

Revision 0 - 31-MAR-2015 QHSE.COR.TMP.005.EN


300
Safety
Mitigation
SWI / CL

Revision 0 - 31-MAR-2015 QHSE.COR.TMP.005.EN


Rig Name/No. AD-68 Camp Load List DISTANCE: 300
High Lifting Requirement Safety
Length Width Height Weight (Slings) Crane(s) / Loader Truck Mitigation
Load No. Description Risk
unit unit unit Ton Load Qty. Capacity (Ton) Qty. Capacity (unit) Type SWI / CL
1 ¨
2 ¨
3 ¨
4 ¨
5 ¨
6 ¨
7 ¨
8 ¨
9 ¨
10 ¨
11 ¨
12 ¨
13 ¨
14 ¨
15 ¨
16 ¨
17 ¨
18 ¨
19 ¨
20 ¨
21 ¨
22 ¨
23 ¨
24 ¨
25 ¨
26 ¨
27 ¨
28 ¨
29 ¨
30 ¨
31 ¨
32 ¨
33 ¨
34 ¨
35 ¨
36 ¨
37 ¨
38 ¨
39 ¨
40 ¨
41 ¨
42 ¨
43 ¨
44 ¨
45 ¨
46 ¨
47 ¨
48 ¨
49 ¨
50 ¨

S FB HH LB
RIG MOVE DISTANCES Vs AVERAGE DURATION:
1 2 3 4 5 6 7 8
20 50 100 200 350 500 700
Upto 20 21 to 50 51 to 100 101 to 200 201 to 350 351 to 500 501 to 700
KM KM KM KM KM KM KM
Duration Duration Duration Duration Duration Duration 3
0.5 1 1.5 2 2.5 3.5
AD-12 3.75 4.25 4.75 5.25 5.75 6.25 6.75
AD-14 3.75 4.25 4.75 5.25 5.75 6.25 6.75
AD-15 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-16 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-21 7.50 8.00 8.50 9.00 9.50 10.00 11.00
AD-23 7.50 8.00 8.50 9.00 9.50 10.00 11.00
AD-28 3.75 4.25 4.75 5.25 5.75 6.25 6.75
AD-29 3.75 4.25 4.75 5.25 5.75 6.25 6.75
AD-31 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-32 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-34 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-35 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-36 7.50 8.00 8.50 9.00 9.50 10.00 11.00
AD-41 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-42 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-43 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-44 3.75 4.25 4.75 5.25 5.75 6.25 7.25
AD-45 3.75 4.25 4.75 5.25 5.75 6.25 7.25
AD-46 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-47 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-48 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-49 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-51 10.50 11.00 11.50 12.00 12.50 13.00 14.00
AD-52 10.50 11.00 11.50 12.00 12.50 13.00 14.00
AD-53 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-54 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-55 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-56 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-57 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-58 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-59 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-61 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-62 5.50 6.00 6.50 7.00 7.50 8.00 8.50
AD-63 5.50 6.00 6.50 7.00 7.50 8.00 8.50
AD-64 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-65 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-66 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-67 6.00 6.50 7.00 7.50 8.00 8.50 9.50
AD-68 5.50 6.00 6.50 7.00 7.50 8.00 8.50
AD-12 AD-12, AD-12, AD-12,
AD-14 AD-14, AD-14,
AD-15 AD-15, AD-15,
AD-16 AD-16, AD-16,
AD-21 AD-21, AD-21,
AD-23 AD-23, AD-23,
AD-28 AD-28, AD-28,
AD-29 AD-29, AD-29,
AD-31 AD-31, AD-31,
AD-32 AD-32, AD-32,
AD-34 AD-34, AD-34,
AD-35 AD-35, AD-35,
AD-36 AD-36, AD-36,
AD-41 AD-41, AD-41,
AD-42 AD-42, AD-42,
AD-43 AD-43, AD-43,
AD-44 AD-44, AD-44,
AD-45 AD-45, AD-45,
AD-46 AD-46, AD-46,
AD-47 AD-47, AD-47,
AD-48 AD-48, AD-48,
AD-49 AD-49, AD-49,
AD-51 AD-51, AD-51,
AD-52 AD-52, AD-52,
AD-53 AD-53, AD-53,
AD-54 AD-54, AD-54,
AD-55 AD-55, AD-55,
AD-56 AD-56, AD-56,
AD-57 AD-57, AD-57,
AD-58 AD-58, AD-58,
AD-59 AD-59, AD-59,
AD-61 AD-61, AD-61,
AD-62 AD-62, AD-62,
AD-63 AD-63, AD-63,
AD-64 AD-64, AD-64,
AD-65 AD-65, AD-65,
AD-66 AD-66, AD-66,
AD-67 AD-67, AD-67,
AD-68 AD-68, AD-68
AD-14, AD-15, AD-16, AD-21, AD-23, AD-28, AD-29, AD-31, AD-32,
AD-34, AD-35, AD-36, AD-41, AD-42, AD-43, AD-44, AD-45, AD-46,
AD-47, AD-48, AD-49, AD-51, AD-52, AD-53, AD-54, AD-55, AD-56,
AD-57, AD-58, AD-59, AD-61, AD-62, AD-63, AD-64, AD-65, AD-66,
AD-67, AD-68