Professional Documents
Culture Documents
Improved Inspection of Clad Pipe Girth Welding
Improved Inspection of Clad Pipe Girth Welding
Background
Corrosion resistant alloy pipe materials are finding increasing use for the transport of hot and corrosive fluids
in flow lines and associated risers in oil and gas production systems. Although initial material and installation
costs are high compared to carbon steel, significant savings in life cycle costs can be accrued since
corrosion inhibitor injection is not required and inspection and maintenance are generally reduced. Solid
CRA pipe materials contain expensive alloying elements, particularly for the more highly alloyed materials
used in sour environments. Since high strength substrates can be used with CRA clad pipes, wall
thicknesses and pipeline weight can be reduced when compared to solid CRAs. Corrosion resistant alloy
pipe materials, both solid and clad, are, however, more difficult to weld than carbon steel, and laying rates
are relatively low for such pipelines. Today, the relatively high costs of pipeline materials and offshore
installation have limited CRA pipe materials usage to those applications where no technically acceptable
alternative solution exists.
Clad pipe normally comprises a steel pipe with a 2-3mm thick internally clad layer of CRA material eg 316L,
Alloy 825 or Alloy 625. Corrosion resistant alloy clad pipes are manufactured in two forms ie metallurgically-
bonded or mechanically-lined. Metallurgically-bonded pipes tend to be more expensive than mechanically-
Due to the dissimilar materials abutting at the weld joint, both radiography and ultrasonic inspection
techniques have limited capability for the detection of flaws at the dissimilar materials interface. Given that
the combined use of automated ultrasonic testing (AUT) and ECA for the development of acceptance criteria
for C-Mn pipeline girth welds is now commonplace, this limitation could have adverse effects on lay rates.
Engineering critical assessment of any component requires a good knowledge of materials and mechanical
properties. For the case of clad pipe, the stress-strain curves and fracture toughness of all constituents of the
weld need to be determined, along with the stress intensity factor solution, limit load solution and residual
stress state, taking account of the mismatch in physical and mechanical properties between CRA, weld metal
and substrate. A robust clad pipeline ECA procedure has yet to be established.
These limitations in current clad pipeline welding and inspection practice have a significant effect on
installation costs and pipeline integrity. This project will address these issues through the development of
improved welding procedures, the use of alternative filler materials, and the development of an ECA
approach to defect sizing and reliable inspection techniques.
For those applications requiring the transport of The clad pipe type, size, backing steel grade and
hot, sour or highly corrosive fluids, operators are CRA cladding composition will be discussed at the
being driven towards the use of CRA pipeline project launch meeting and agreed with the
material for reliability and safety reasons. The Project Sponsors at the beginning of the project.
additional pipeline material and installation costs
will be justified on the basis of the risk and Procedures for increased productivity and
consequence of failure rather than on an improved weld quality
economic argument. Clearly the need to minimise Mechanised TIG welding is commonly used for
the risk of environmental damage and ensuring the deposition of the root and hot passes.
adequate worker safety will be paramount. Controlled short circuit transfer MIG process eg
Nevertheless it is envisaged that the project will Lincoln Electric surface tension transfer (STT) is
have a significant impact on the cost and reliability also used commonly, providing increased welding
of clad pipeline installation. speeds and thicker weld deposits. Root welding is
normally performed without an internal root