Professional Documents
Culture Documents
Sashas Most Updated Project Plan - Artifact2
Sashas Most Updated Project Plan - Artifact2
Sashas Most Updated Project Plan - Artifact2
Re-
Planned Re- Planned Actual Actual Actual
Planned Planned
Product Tasks Subtasks End Planned time to Start End time Contingency plans
Start Date Start Risk Assessment
Date End Date invest Date Date invested
Date
Watch and
Learn through
submit a quiz on
an interview
Conversation a video that Sister-In law’s baby In case of family obligation, technical issues,
that indicates a
with a PM demonstrates an shower for close family power outage, sickness, and work overload from
PMs 8/20/20 8/22/20 8/22/20 8/22/20 4 hours 8/22/20 8/22/20 2 hours
Part 1 Video understanding of due to COVID. my current job, a two-day cushion should be
experience in
Quiz concepts in a allowed to complete the assignment.
managing a
conversation
project.
with a PM.
Learn through
Watch and Sister-In law’s baby In case of family obligation, technical issues,
an interview
submit a quiz on shower for close family power outage, sickness, and work overload from
that indicates a
a video that due to COVID. my current job, a two-day cushion should be
PMs 8/20/20 8/22/20 8/22/20 8/22/20 4 hours 8/22/20 8/22/20 2 hours
demonstrates an allowed to complete the assignment.
experience in
understanding of
managing a
concepts in a
project.
conversation
with a PM.
Conversation Review saved 8/22/20 8/22/20 8/22/20 8/22/20 15 mins 8/22/20 8/22/20 10 mins
with a PM PlayPosit
Part 1 Video questions and Technical issues Incase unable to save Q&A from video quiz. I will
Quiz answers from saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project.
Learn new
Watch and Issues with accessing In case of technical issues, power outage,
concepts and
submit a quiz on video. sickness, and work overload from my current job,
Baseline try to apply on
a video that a two-day cushion should be allowed to complete
Assessment my own 8/23/20 8/25/20 8/25/20 8/25/10 8 hours 8/25/20 8/25/20 2 hours
demonstrates an the assignment.
Video Quiz Baseline
understanding of
Assessment
what a Baseline
Video
is and how it is
important.
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 8/25/20 8/25/20 8/25/20 8/25/20 10 mins 8/25/20 8/25/20 6 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project
Practice
recording to
avoid any
errors and
audio issues
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 8/29/20 8/29/20 8/29/20 8/29/20 8 mins 8/29/20 8/29/20 6 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 8/29/20 8/29/20 8/29/20 8/29/20 8 mins 8/29/20 8/29/20 6 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project
Engage in
De Reyck In case of technical issues, power outage,
reading material Look for ways
2010 about sickness, and work overload from my current job,
from De Reyck to engage and
Effective 8/30/20 9/1/20 9/1/20 9/1/20 6 Hours 9/1/20 9/1/20 3 hours Possible issues with a two-day cushion should be allowed to complete
2010 about apply concepts
Project Perusal transferring the assignment.
Effective Project with the clients
Planning my grade.
Planning
Watch Planning Learn to In case of technical issues, power outage,
Planning for for understand sickness, and work overload from my current job,
Contingencie Contingencies concepts in a 9/1/20 9/3/20 9/3/20 9/3/20 4 hours 9/3/20 9/3/20 2 hours Issues with accessing a two-day cushion should be allowed to complete
s video Quiz video and project video. the assignment.
complete quiz planning video.
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 9/3/20 9/3/20 9/3/20 9/3/20 8 mins 9/3/20 9/3/20 6 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply fron video.
concepts for
the project
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 9/3/20 9/3/20 9/3/20 9/3/20 8 mins 9/3/20 9/3/20 6 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply fron video.
concepts for
the project
Read and
In case of technical issues, power outage,
Work Break engage in Look for ways
sickness, and work overload from my current job,
Down learning material to engage and
9/3/20 9/5/20 9/4/20 9/5/20 6 hours 9/5/20 9/5/20 3 hours Possible issues with a two-day cushion should be allowed to complete
Structures about work apply concepts
Perusal transferring the assignment.
(WBS) break down with the clients.
my grade.
structures
Practice with Labor Day possible In case of holiday, technical issues, power
Create a list of
an exercise of Celebrations or need outage, sickness, and work overload from my
Products, task and
properly apply for extra work hours current job, a two-day cushion should be allowed
Tasks, and subtasks and
products, 9/3/20 9/5/20 9/4/20 9/5/20 6 hours 9/5/20 9/5/20 4 hours this week. to complete the assignment.
Subtasks submit through a
tasks, and
Assignment group
subtasks in a
discussion.
project plan.
Create and
Review quality Problems with In case of technical issues, power outage,
submit a project
criteria to submitting plan or sickness, and work overload from my current job,
Project Plan plan by using 9/5/20 9/8/20 9/6/20 9/8/20 8 hours 9/7/20 9/8/20 5 hours
develop project uploading from a two-day cushion should be allowed to complete
what has been
plan. MSWord. the assignment.
learned so far.
Compare Inability to load other In case of technical issues, power outage,
Review Peers
Project plans peers Project Plans or sickness, and work overload from my current job,
project plans to
Peer Reviews to see if my issues with Canvas. a two-day cushion should be allowed to complete
gain better
of Project plan is 9/8/20 9/10/20 9/9/20 9/10/20 8 hours 9/10/20 9/10/20 2 hours the assignment.
understanding
Plan. following
and have a client
quality
prospective.
assurances.
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 9/12/20 9/12/20 9/12/20 910/6/20 15 mins 9/12/20 9/12/20 4 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 9/15/20 9/15/20 9/15/20 9/15/20 15 mins 9/15/20 9/15/20 4 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project
Review saved 9/17/20 9/17/20 9/17/20 9/17/20 15 mins 9/17/20 9/17/20 10 mins
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project.
Read and
Halvorson
engage in In case of technical issues, power outage,
and Rock Connect with
learning material sickness, and work overload from my current job,
(2015) and the material
about Beyond 9/15/20 9/17/20 9/16/20 9/17/20 4 hours 9/17/20 9/17/20 2.5 hours Possible issues with a two-day cushion should be allowed to complete
Desjardins and client’s
Bias by Heidi Perusal transferring the assignment.
(2018) thoughts on it.
Grant Halvorson my grade.
Contributions
and David Rock
Read and
In case of technical issues, power outage,
engage in Connect with
Cottrell sickness, and work overload from my current job,
learning material the material
(2011) Critical 9/17/20 9/19/20 9/18/20 9/19/20 8 hours 9/19/20 9/19/20 2 hours Possible issues with a two-day cushion should be allowed to complete
about critical and client’s
Thinking Perusal transferring the assignment.
thinking by thoughts on it.
my grade.
Cottrell 2011.
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 9/19/20 9/19/20 9/19/20 9/19/20 15 mins 9/19/20 9/19/20 10 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project
Read and
PMBOK 6th engage in Connect with In case of technical issues, power outage,
Edition (2017) learning material the material sickness, and work overload from my current job,
Project about (PMBOK) and client’s Possible issues with a two-day cushion should be allowed to complete
9/20/20 9/22/20 9/22/20 9/22/20 4 hours 9/22/20 9/22/20 2 hours
Management Project thoughts on it. Perusal transferring the assignment.
Overview and Management my grade.
processes Body of
Knowledge.
PM to demonstrate
Processes understanding Take video 9/23/20 9/25/20 9/25/20 9/25/20 8 hours 9/25/20 9/25/20 30 mins In case of technical issues, power outage,
Case Study about the quiz to sickness, and work overload from my current job,
1,2, and 3 concept through demonstrate Issues with accessing a two-day cushion should be allowed to complete
Quiz each case study.
understanding video. the assignment.
on case study
1,2, and 3 in
project
management
processes.
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 9/25/20 9/25/20 9/25/20 9/25/20 15 mins 9/25/20 9/25/20 10 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project
Read and
why people Reflect on this In case of technical issues, power outage,
engage in
fail to project and sickness, and work overload from my current job,
learning material
recognize personal Possible issues with a two-day cushion should be allowed to complete
about why
their own behaviors that 10/04/20 10/6/20 10/6/20 10/6/20 4 hours 10/6/20 10/6/20 3 hours Perusal transferring the assignment.
people fail to
incompetence may have my grade.
recognize their
reading hinder
own
article success.
incompetence
Review saved
PlayPosit
questions and Technical issues Incase unable to save Q&A from video quiz. I will
answers from 10/6/20 10/6/20 10/6/20 910/6/20 15 mins 10/6/20 10/6/20 10 mins saving PlayPosit Q&A screen shot quiz answers.
video to apply from video.
concepts for
the project