REKAPITULASI PENAWARAN HARGA

Pekerjaan
Sandblasting & Painting

Biaya
No. Diskripsi
Volume Rp
A MOBILISASI & DEMOBILISASI (Alat, Material & Tenaga Kerja) 1 Lot 11,250,000.00
B Rapid + Antigen 5 Orang 1 Lot 1,500,000.00
C Material (Pasir Kuarsa) 1 Lot 4,500,000.00
D Upah + Sewa Alat 1 Lot 24,585,000.00
E Nilai Total (A +B+C+D) 41,835,000.00
D TOTAL DIBULATKAN 41,835,000.00

Terbilang : EMPAT PULUH SATU JUTA DELAPAN RATUS TIGA PULUH LIMA RIBU RUPIAH

Kondisi Penawaran
- Sudah Termasuk Biaya Mobilisasi dan Demobilisasi Alat & Peralatan
- Lokasi / Area / Blasting Room / Tool Storage disediakan oleh Pemberi Kerja
- Handling Material & Alat berat (cranre, Forklift, Trailer, Sling acessories) disediakan Pemberi Kerja
- Mess Pekerja disediakan Oleh Pemberi Kerja

Dibuat Oleh :

Hendra Gunawan
Pemborong
Company :
REV. 1
Handling Unit : Date : August 19, 2020

Work Tracking No.


OKI Mill Plant Project : SANDBLASTING COST - SSPC10 - SA 2.1/2 : DFT 275 micron - 300micron
Tittle SAP Doc. No.
Unit Price (Rp.) Price (Rp.)
No. Work Description Unit Qty Remarks
Wage Material Wage Material Sub Total
A PREPARATION

A.1 Mobilization & Demobilization Ls 1.00 - BY PT. BRIKASA

A.2 Overhead & Profit Ls 1.00 - BY PT. BRIKASA

B SITE PREPARATION_WORKS

Pekerjaan Persiapan (Blasting Room, Blasting Area,


B.1 Handling Material, mob & demob material & install Ls 1.00 BY PT. BRIKASA
Material)

C SANDBLASTING_WORKS

C.1 Sandblasting SA 2.1/2 M2 1.00 60,000.00 37,500.00 60,000.00 37,500.00 97,500.00

D PAINTING_WORKS

D.1 Primer : Organic Zinc Rich Primer / JOTUN (DFT M2 1.00 20,000.00 20,000.00 20,000.00
125micron - 175micron)

Intermediate / Second Coat : polyamide cured epoxy /


D.2 M2 1.00 26,200.00 26,200.00 26,200.00
JOTUN (DFT 80micron - 150micron)

Finish / Top Coat : Polyurethane / JOTUN (DFT 50micron


D.3 M2 1.00 29,150.00 29,150.00 29,150.00
- 100micron)

TOTAL : 135,350.00 37,500.00 172,850.00