Weekly Report 21
Weekly Report 21
11 – 17 Januari 2021
1. QUANTITY
2. QUALITY CONTROL
3. PROGRESS LAPANGAN
4. MONITORING PRODUKSI CONCRETE BLOCK LINING
5. RENCANA MINGGU - 22
6. PERMASALAHAN
1. QUANTITY
1.1. Physical Progress of Main Canal System Works Period up to J 29th, 2020
1.2. Physical Progress against the 2020 budget of Main Canal System Works Period up to November
29th, 2020
Physical Progress Towards The
Contract (%)
No Project
Plan Actual Deviation
% % %
I ICB Package LMS-02: Utara
Main Canal Upgrading Works
for Rentang Irrigation
Modernization Project
1.3.Realisasi dilapangan
Bobot
Progress Sampai
Presentasi
No Item Nama Item Satuan Minggu Ke- Minggu
(%)
15 Ke-15
(%)
Contractor's
temporary
I-1 Ls 0 0.384 70.000
facilities: Office,
Quarters
Contractor's
laboratory and
I-2 Ls 0 0.189 70.000
laboratory
equipment
Assistance to
Engineer's staff
I-3 and site survey Ls 0.006 0.0602 11.1157
and setting out of
the works
Construction
I-4 drawings and as - Ls 0.006 0.0428 11.1157
built drawings
Reports and
I-5 Ls 0 0.014 22.000
photographs
Furnishing steel-
sheet piles for
Temporary
I-8 Coffering for m 0 2.404 83
canal works
(Type-II, width =
400 mm)
'Furnishing steel-
sheet piles Type-II
(for temporary
I - 10 m 6551.00 1.042 100
works of
dewatering of
structures)
2-1-1 Clearing and
grubbing type - A M2 5.000 0.041 83.101
Bobot
Progress Sampai
Presentasi
No Item Nama Item Satuan Minggu Ke- Minggu
(%)
15 Ke-15
(%)
2-1-4 Stripping of top
soil including M3 300 0.018 8.726
disposal
Excavation type -
2-1-6 m3 0 8.436 8.4362801
B
Hauling materials
on the land with
2-1-11 m3 0 0.018 4.3038335
hauling distance 1
- 3 km
2-1-14 Earthfill type - B m3 0 0.215 5.799459
Hauling materials
on the land with
2-1-19 0 0.473 22.037316
hauling distance
30 - 40 km
Hauling materials
on the land with
2-1-20 m3 0 0.236 5.7561556
hauling distance
40 - 50 km
Reinforcement
2-2-9 steel bar, ton 0 0.226 3.2574141
deformed bar
Fabrication of
concrete block,
2-2-13 m2 120 0.2645 2.138
1.00m x1.00m x
0.07m
Furnishing steel-
3-4-7 sheet piles type-II m 0 0.048 100
for structures
2. QUALITY CONTROL
Paket : LMS-02
Contractor : PT. Hutama Karya
Pengambilan sampel
aggregate kasar (split) dan
agregat halus (pasir) di
Batching Plant PT.
HAKAASTON tanggal 14
Januari 2021.
2.2.Concrete Block Lining
• Pengujian Kuat Tekan Umur 7 Dan 28 Hari
Tabel 1.1. QC Chart 7-days And 28-days Compressive Strength Test.
Test Result
7 Days (Kgf/cm2) 28 Days (Kgf/cm2)
Date of
Sampling Slump Slump
X1 X2 X3 Average (cm) X1 X2 X3 Average (cm)
26/11/ 2020 226.71 251.05 234.36 237.37 12.00 340.07 339.38 321.99 333.81 12.00
27/11/ 2020 245.49 250.36 221.85 239.23 12.00 319.21 330.33 315.04 321.53 12.00
28/11/ 2020 285.13 284.44 277.48 282.35 12.00 315.73 317.12 347.03 326.63 12.00
29/11/ 2020 385.27 392.92 395.71 391.30 12.00 326.16 332.42 333.12 330.57 12.00
30/11/ 2020 266.35 246.19 262.88 258.47 12.00 571.65 454.12 379.71 468.49 12.00
01/12/ 2020 228.10 217.67 258.70 234.82 12.00 355.37 346.33 358.85 353.52 12.00
02/12/ 2020 232.28 269.83 273.31 258.47 12.00 328.94 324.77 317.12 323.61 12.00
03/12/ 2020 276.09 255.23 257.31 262.88 9.00 346.33 337.29 336.59 340.07 12.00
04/12/ 2020 219.06 212.81 200.29 210.72 12.00 350.50 341.46 353.98 348.65 12.00
07/12/ 2020 250.36 241.32 226.02 239.23 12.00 349.11 335.20 351.20 345.17 12.00
08/12/ 2020 269.14 280.26 262.18 270.53 12.00 350.50 356.07 343.55 350.04 12.00
10/12/ 2020 244.80 241.32 243.40 243.17 12.00 356.76 342.16 345.63 348.18 12.00
11/12/ 2020 242.01 213.50 226.71 227.41 12.00 340.77 345.63 338.58 341.66 12.00
12/12/ 2020 216.98 214.89 220.46 217.44 12.00 345.63 367.89 338.68 350.73 12.00
13/12/ 2020 221.85 218.37 236.45 225.56 12.00 390.14 353.28 392.92 378.78 12.00
14/12/ 2020 242.71 256.62 250.36 249.90 12.00 404.75 413.79 468.03 428.86 12.00
15/12/ 2020 246.88 246.19 246.19 246.42 12.00 376.23 409.62 536.88 440.91 12.00
16/12/ 2020 211.41 219.06 225.32 218.60 12.00 362.33 363.72 283.04 336.36 12.00
17/12/ 2020 224.63 229.50 237.84 230.66 12.00 502.80 505.59 520.19 509.53 12.00
18/12/ 2020 235.75 232.97 230.89 233.20 12.00 0.00
19/12/ 2020 225.32 222.54 220.46 222.77 12.00 0.00
20/12/ 2020 244.80 253.84 255.23 251.29 12.00 0.00
21/12/ 2020 255.23 246.19 202.37 234.60 12.00 0.00
22/12/ 2020 235.06 239.93 230.19 235.06 12.00 0.00
23/12/ 2020 234.36 231.58 223.24 229.73 12.00 0.00
24/12/ 2020 230.19 235.06 232.28 232.51 12.00 0.00
26/12/ 2020 216.98 228.10 218.37 221.15 12.00 0.00
27/12/ 2020 231.58 243.40 237.84 237.61 12.00 0.00
28/12/ 2020 249.66 235.75 243.40 242.94 12.00 0.00
29/12/ 2020 237.15 256.62 272.61 255.46 12.00 0.00
30/12/ 2020 215.59 240.62 207.94 221.38 12.00 0.00
02/01/ 2021 307.39 301.82 338.68 315.96 12.00 0.00
3. Soil Investigation
• Boring
Tabel 1.2. Hasil Laporan Harian Pekerjaan Boring.
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (N) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
B.Ut.2 x 9273961.18 PT. Suwanda
19/12/2020 22/12/2020 Divission Structure With Off-take y 202712.79 20 m 50 Karya Mandiri
z 13936
B.Ut.3 x 9275700.1 PT. Suwanda
19/12/2021 22/12/2021 Divission Structure With Off-take y 203111.48 20 m 43 Karya Mandiri
z 11.865
B.Ut.4 x 9277220.49 PT. Suwanda di kedalaman
22/12/2020 23/12/2020 Divission Structure With Off-take y 203554.228 20 m 14 Karya Mandiri 13.56 - 14.02 m nilai
z 10.571 N mencapai > 50
B.Ut.9.1c x 9283704.8 PT. Suwanda
22/12/2020 23/12/2020 Road bridge + Washing step y 201051.449 20 m 42 Karya Mandiri
z 7.092
B.Ut.9.1n x 9283884.78 PT. Suwanda
24/12/2020 26/12/2020 Road bridge + Washing step y 200927.696 20 m 37 Karya Mandiri
z 7.037
B.Ut.10.1p x 9286230.41 PT. Suwanda
24/12/2020 26/12/2020 Road bridge + Washing step y 200260.407 20 m 20 Karya Mandiri
z 6.223
B.Ut.10.1ay x 9287435.63 PT. Suwanda
27/12/2020 28/12/2020 Road bridge + Pipe crossing y 200441.283 20 m 43 Karya Mandiri
z 6.107
26/12/2020 28/12/2020 B.Ut.10.1aab x 9287435.63 20 m 16 PT. Suwanda
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (N) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
Road bridge + Pipe crossing y 200425.956 Karya Mandiri
z 6.107
B. Ut. 10 x 9288811.73 PT. Suwanda
28/12/2020 31/12/2020 Divission Structure y 199993.02 20 m 30 Karya Mandiri
z 5.358
B.Ut.11.1c x 9288811.73 PT. Suwanda
29/12/2020 31/12/2020 Road bridge + Washing step y 199455.665 20 m 29 Karya Mandiri
z 5.077
B. Ut. 11. 1e x 9290146.84 PT. Suwanda
1/12/2020 2/1/2021 Road Bridge y 199450.441 20 m 45 Karya Mandiri
z 4.786
B. Ut. 11. 1f x 9290320.18 PT. Suwanda
2/12/2020 2/1/2021 Road Bridge y 199447.311 20 m 19 Karya Mandiri
z 4.786
B. Ut. 11. 1h x 9290993.46 PT. Suwanda
2/1/2021 4/1/2021 Road Bridge y 199430.306 20 m 172 Karya Mandiri
z 5.033
B. Ut. 16a x *hasil PT. Argopitu
7/1/2021 9/1/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut. 15 x *hasil PT. Argopitu
9/1/2021 11/1/2021 Divission structure + Road bridge y 20 m belum Ishana
z diperoleh
B. Ut. 12. 1j x 9291656.22 PT. Suwanda
2/1/2021 4/1/2021 Road Bridge y 199414.817 20 m 15 Karya Mandiri
z 4.814
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (N) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
B. Ut. 12. 1t x 9291838.75 PT. Suwanda
5/1/2021 6/1/2021 Road bridge + Pipe crossing y 199494.828 20 m 34 Karya Mandiri
z 4.249
B. Ut. 12. 1u x 9291922.97 PT. Suwanda
5/1/2021 6/1/2021 Road Bridge y 199538.417 20 m 16 Karya Mandiri
z 4.462
B. Ut. 12. 1w x 9292040.45 *hasil PT. Suwanda
6/1/2021 8/1/2021 Road Bridge y 199598.346 20 m belum Karya Mandiri
z 4.355 diperoleh
B. Ut. 12 b x 929144.67 *hasil PT. Suwanda
6/1/2021 8/1/2021 Road bridge + Pipe crossing y 199663.762 20 m belum Karya Mandiri
z 3.933 diperoleh
B. Ut. 12 d x *hasil PT. Argopitu
11/1/2021 13/01/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut. 12 h x 9292551.7 *hasil PT. Suwanda
6/1/2021 8/1/2021 Road bridge + Pipe crossing y 199875.206 20 m belum Karya Mandiri
z 4.035 diperoleh
B. Ut. 12 x *hasil PT. Suwanda
8/1/2021 10/1/2021 Road bridge + Pipe crossing y 20 m belum Karya Mandiri
z diperoleh
B. Ut. 13i x *hasil PT. Suwanda
8/1/2021 10/1/2021 Road Bridge y 20 m belum Karya Mandiri
z diperoleh
B. Ut. 14e x PT. Suwanda
8/1/2021 10/1/2021 20 m
Road bridge + Washing step y Karya Mandiri
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (N) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
*hasil
belum
z diperoleh
B. Ut. 14i x *hasil PT. Argopitu
10/1/2021 12/1/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut.14k x *hasil PT. Argopitu
10/1/2021 12/1/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut. 14l x *hasil PT. Argopitu
10/1/2021 12/1/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut. 17ai x 9295276.37 PT. Argopitu
4/1/2021 6/1/2021 Road bridge + Pipe crossing y 200048.792 20 m 4/30 Ishana
z 2.771
B. Ut. 18 x 9296770.89 PT. Argopitu
2/1/2021 6/1/2021 Divission structure + Road bridge y 199589.418 20 m 4/30 Ishana
z 2.643
• DCPT
Tabel 1.3. Hasil Laporan Harian Pekerjaan DCPT.
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
19/12/2020 21/12/2020 Divission Structure With Off-take y 202735757 19.20 m qt 210 Ishana
z 13.83
23/12/2020 23/12/2020 Divission Structure With Off-take y 203090909 15.60 m qt 210 Ishana
z 11.859
z 13958
23/12/2020 23/12/2020 Divission Structure With Off-take y 203524328 12.60 m qt 245 Ishana
z 10553
z 9.128
24/12/2020 24/12/2020 Road bridge + Washing step y 201049.463 15.40 m qt 205 Karya Mandiri
z 7.117
z 8.486
24/12/2020 24/12/2020 Road bridge + Pipe crossing y 200932.193 17.80 m qt 209 Karya Mandiri
z 7.141
26/12/2020 26/12/2020 Road bridge + Washing step y 200281701 10.00 m qt 225 Karya Mandiri
z 6.24
27/12/2020 27/12/2020 Divission Structure With Off-take y 200049.128 14.40 m qt 210 Karya Mandiri
z
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
27/12/2020 27/12/2020 Road bridge + Pipe crossing y 15.60 m qt 210 Karya Mandiri
28/12/2020 28/12/2020 Road bridge + Pipe crossing y 200443.63 14.80 m qt 215 Karya Mandiri
28/12/2020 29/12/2020 Road bridge + Washing step y 16.40 m qt 220 Karya Mandiri
z 4.25
z 4.75
z 4.575
z 4.797
z 4.1
z 4.578
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
z 4.523
z 4.604
z 4.727
z 4.614
z 4.846
z 4.271
z 4.14
z 4.21
z 4.312
(*) : Pekerjaan Tes DCPT tidak dapat dilanjutkan karena pipa alat tidak dapat menembus kedalaman berikutnya (Jika dipaksa, resiko
pipa alat dapat rusak/bengkok).
• Hand Auger
Tabel 1.4. Hasil Laporan Harian Pekerjaan Hand Auger.
Waktu Kedalaman
Lokasi Koordinat (R/L) Progress Keterangan
Pengerjaan (m)
B.Ut.1.1k x 9272042.138
27/12/2020 Road Bridge y 200851.368 (L) 5 Tercapai Pengambilan sampel UDS. kedalaman 3.5 m
z 38.000
B.Ut.1.1t x 9272525.190
28/12/2020 Off-take y 201083.422 (L) 1.5 Tercapai Pengambilan sampel UDS. kedalaman 1 m
z 34.470
B.Ut.1.1 x 9272731.663
29/12/2020 Off-take y 201222.956 (L) 2.2 Tercapai Pengambilan sampel UDS. Kedalaman 1.5 m
z 35.750
B. Ut. 1 x 9273327.148
30/12/2020 Road Bridge y 201824.526 (L) 2.3 Tercapai Pengambilan sampel UDS. Kedalaman 1.5 m
z 39.370
B. Ut. 2f x 9273459l612
30/12/2020 Road Bridge y 202161.495 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 4 m
z 30.310
B. Ut. 2g x 9273466.767
31/12/2020 Foot Bridge + Off take y 202280.215 (L) 4.2 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 29.500
Waktu Kedalaman
Lokasi Koordinat (R/L) Progress Keterangan
Pengerjaan (m)
z 16.920
B. Ut. 14 x 9293128.259
7/1/2021 Off-take y 200152.487 ('R) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 16.920
B. Ut. 16 x 9293834.362
7/1/2021 Off-take y 199936.634 ('R) 4 Tercapai Pengambilan sampel UDS. Kedalaman 2.5m
z 23.710
B. Ut. 17 s x 9294431.754
8/1/2021 Road Bridge y 200102.514 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3 m
z 17.310
B. Ut. 17 x 9295323.942
8/1/2021 Off-take y 200032.149 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3 m
z 11.360
B. Ut. 18 c x 9295579.537
8/1/2021 Foot Bridge + Off take y 200063.673 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 16.220
B. Ut. 18 d x 9296153.545
8/1/2021 Pump Outlet + Off take y 199601.434 ('R) 4 Tercapai Pengambilan sampel UDS. Kedalaman 2.5m
z 15.620
• Tes PRP
Tabel 1.5. Hasil Laporan Harian Pekerjaan Tes PRP.
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
ZONA 1 (L)
UT. 0 190 100 # * *
1 13/01/2021 UT. 1 200 100 200 100 * *
UT. 2 220 100 200 100 * *
UT. 3 150 100 230 100 * *
UT. 4 130 100 150 100 * *
UT. 5 100 100 180 100 * *
UT. 6 150 100 200 100 * *
2 14/01/2021 UT. 7 140 100 230 100 * *
UT. 8 80 100 220 100 * *
UT. 9 220 100 220 100 * *
UT. 10 60 100 40 100 * *
UT. 11 80 100 # * *
UT. 12 200 100 260 100 # # * *
UT. 13 140 100 180 100 150 100 200 100 * *
UT. 14 250 100 230 70 210 100 220 100 * *
3 16/01/2021 UT. 15 170 100 180 100 270 100 210 100 * *
UT. 16 40 100 40 100 250 100 250 100 * *
UT. 17 70 100 70 100 90 100 140 100 * *
UT. 18 160 100 200 100 250 100 250 100 * *
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
UT. 19 60 100 60 100 170 100 170 100 * *
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
ZONA 1 ('R)
UT. 0 60 95 200 100 * *
UT. 1 80 70 220 100 * *
UT. 2 200 99 130 100 * *
1 13/01/2021
UT. 3 200 100 200 100 * *
UT. 4 40 100 150 100 * *
UT. 5 70 100 220 100 * *
UT. 6 300 100 290 100 * *
2 14/01/2021 UT. 7 200 100 240 100 * *
UT. 8 270 100 230 100 * *
UT. 9 200 100 280 100 * *
UT. 10 170 100 290 100 * *
UT. 11 150 100 190 100 * *
3 15/01/2021
UT. 12 190 100 210 100 * *
UT. 13 # # * *
UT. 14 + 30 100 100 110 100 * *
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
UT. 15 # # * *
UT. 16 # # * *
UT. 17 250 100 220 100 * *
UT. 18 250 100 180 100 * *
UT. 19 230 100 240 100 * *
UT. 20 210 100 230 100 * *
UT. 21 190 100 180 100 * *
UT. 22 70 100 80 100 80 100 180 100 * *
UT. 23 180 100 210 100 220 100 190 100 * *
UT. 24 240 100 220 100 260 100 270 100 * *
UT. 25 60 100 70 100 230 100 260 100 * *
UT. 26 90 100 130 100 140 100 160 100 * *
UT. 27 90 100 100 100 120 100 110 100 * *
4 16/01/2021
UT. 28 130 100 130 100 230 100 220 100 * *
UT. 29 320 100 330 100 130 100 130 100 * *
UT. 30 180 100 170 100 220 100 210 100 * *
UT. 31 290 100 280 100 270 100 250 100 * *
UT. 32 250 100 210 100 150 100 150 100 * *
UT. 33 130 100 210 100 110 100 160 100 * *
Catatan:
Untuk titik 3 masih belum dapat dilakukan PRP tes karena muka air masih
(*) tinggi
(#) Tidak dapat dilakukan PRP tes karena terhalang pasangan batu lama
Belum dilakukan PRP tes (menyusul)
cm Kedalaman alat
kgf Satuan pembacaan alat
a dan b Beda beberapa cm
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
ZONA 2 (L)
UT. 118 290 100 290 100 190 100 190 100
UT. 119 270 100 270 100 230 100 250 100
UT. 120 250 100 300 90 300 55 290 100
UT. 121 150 100 80 100 290 100 250 100
1 15/01/2021
UT. 122 280 100 250 100 260 100 280 100
UT. 123 260 100 210 100 250 100 250 100
UT. 124 300 100 300 100 250 100 290 100
UT. 125 300 100 260 100 210 100 230 100
UT. 126 280 100 250 100 270 100 280 100
UT. 127 290 100 300 100 280 100 270 100
UT. 128 250 100 250 100 270 100 260 100
UT. 129 300 58 300 58 300 30 300 29
UT. 130 180 100 260 100 180 100 170 100
2 16/01/2021 UT. 131 270 100 290 100 280 100 300 55
UT. 132 300 100 270 90 140 100 300 100
UT. 133 110 100 300 74 300 70 300 90
UT. 134 270 83 270 100 300 100 300 90
UT. 135 190 100 190 100 300 65 300 40
UT. 136 300 96 300 85 210 100 260 100
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
ZONA 2 ('R)
UT. 118 190 100 120 100
UT. 119 220 100 180 100 160 100
1 13/01/2021 UT. 120 180 100 160 100 160 100
UT. 121 270 100 200 100 210 100
UT. 122 300 100 290 100 260 100
UT. 123 240 100 260 100
UT. 124 50 100 250 100
UT. 125 50 100 60 100
UT. 126 80 100 280 100
UT. 127 160 100 150 100
2 14/01/2021 UT. 128 290 100 170 100
UT. 129 150 100 210 100
UT. 130 120 100 290 100
UT. 131 150 100 210 100
UT. 132 130 100 120 100
UT. 133 220 100 290 100
Dokumentasi Pekerjaan
32
Dokumentasi Pekerjaan
33
Dokumentasi
34
Dokumentasi
5. Kendala Lapangan
• Dalam pekerjaan tes PRP untuk titik 3 tidak dapat dilakukan karena muka air masih tinggi.
• Terdapat beberapa titik dalam tes PRP yang tidak dapat dilakukan karena terdapat pasangan batu
lama disepanjang
35
3.PROGRESS DILAPANGAN
AREA 1
STA UT. 0 UT. 2 UT. 5 UT. 25 UT. 62 UT. 68
PEKERJAAN
Clearing and Grubbing
Stripping of Top Soil
Earthfill Type B
KIRI
Excavation Slope
Dasar
Lining Canal
Clearing and Grubbing
Stripping of Top Soil
KANAN
Earthfill Type B
Excavation Slope
Dasar
Lining Canal
AREA 2
UT. UT. UT. UT. UT. UT. UT. UT.
STA 118 122 125 130 138 141 150 173
PEKERJAAN
Clearing and
Grubbing
Stripping of
Top Soil
Earthfill Type B
KIRI
Excavati Slop
on e
Das
ar
Lining Canal
Clearing and
Grubbing
Stripping of
KANAN
Top Soil
Earthfill Type B
Excavation Slope
Dasar
Lining Canal
36
3.1. Kegiatan Senin, 11 Januari 2021
Kegiatan :
Penutupan celah celah pada ssp di aUT.118-122
Kegiatan :
Proses dewatering dengan menggunakan pompa
37
3.2.Selasa , 12 Januari 2021
Kegiatan :
Penambalan kebocoran disela sela SSP
Kegiatan
Menggunakan 4 pompa untuk proses dewatering
Kegiatan :
Proses dewatering
38
3.4. Kamis, 14 Januari 2021
Kegiatan :
Proses dewatering di UT.118-122 R
Kegiatan
Dewatering SSP
Kegiatan :
Proses dewatering di UT.118-122 R
39
3.5. Jum’at 15 Januari 2021
Kegiatan :
Proses penambalan sela-sela SSP
Kegiatan :
Proses dewatering di UT.118-122 R
Kegiatan :
Galian struktur di UT.118-122 R
40
3.6. Sabtu, 16 Januari 2021
Kegiatan :
Proses dewatering di UT.118-122 R
Kegiatan :
Proses dewatering di UT.118-122 R
Kegiatan :
Proses dewatering di UT.118-122 R dengan
menggunakan pompa
41
4. MONITORING PRODUKSI CONCRETE BLOCK LINING
PENGIRIMAN
REALISASI
Cetak Lining Block 1x1x0.07 m (m2)
HAKAA-SIS
Reject Jumlah Kom
Solid Hole Hole ᴓ Ratio Harian Kom Solid Hole Hole ᴓ
42
PENGIRIMAN
REALISASI
Cetak Lining Block 1x1x0.07 m (m2)
HAKAA-SIS
HAKAA-SIS
Reject Jumlah Kom
Solid Hole Hole ᴓ Ratio Harian Kom Solid Hole Hole ᴓ
HAKAA-SIS
HAKAA-SIS
Reject Jumlah Kom
Solid Hole Hole ᴓ Ratio Harian Kom Solid Hole Hole ᴓ
40 4-Jan-21 0 0 0 8739
41 5-Jan-21 0 0 0 8739
42 6-Jan-21 0 0 0 8739
43 7-Jan-21 0 0 0 8739
44 8-Jan-21 0 0 0 8739
45 9-Jan-21 0 0 0 8739
46 10-Jan-21 0 0 0 8739
47 11-Jan-21 0 0 0 8739
48 12-Jan-21 0 0 0 8739
49 13-Jan-21 0 0 0 8739
50 14-Jan-21 0 0 0 8739
51 15-Jan-21 0 0 0 8739
52 16-Jan-21 0 0 0 8739
53 17-Jan-21 0 0 0 8739
44
5. PERMASALAHAN DILAPANGAN
cuaca suka berubah-rubah, hujan dan cerah mengakibatkan pekerjaan berhenti dan akses
jalan kerja tidak bisa dilewati
45
6. RENCANA MINGGU ke-23
46