WEEKLY-22

11 – 17 Januari 2021

ICB-Package Lms-02 : Upgrading Utara Main


Canal Rentang Irrigation Modernization Project
DAFTAR ISI

1. QUANTITY
2. QUALITY CONTROL
3. PROGRESS LAPANGAN
4. MONITORING PRODUKSI CONCRETE BLOCK LINING
5. RENCANA MINGGU - 22
6. PERMASALAHAN
1. QUANTITY

1.1. Physical Progress of Main Canal System Works Period up to J 29th, 2020

Physical Progress Towards The


No Project Contract (%)
Plan Actual Deviation
I ICB Package LMS-02: Utara
Main Canal Upgrading Works
for Rentang Irrigation
Modernization Project

1.2. Physical Progress against the 2020 budget of Main Canal System Works Period up to November
29th, 2020
Physical Progress Towards The
Contract (%)
No Project
Plan Actual Deviation
% % %
I ICB Package LMS-02: Utara
Main Canal Upgrading Works
for Rentang Irrigation
Modernization Project
1.3.Realisasi dilapangan

Bobot
Progress Sampai
Presentasi
No Item Nama Item Satuan Minggu Ke- Minggu
(%)
15 Ke-15
(%)
Contractor's
temporary
I-1 Ls 0 0.384 70.000
facilities: Office,
Quarters
Contractor's
laboratory and
I-2 Ls 0 0.189 70.000
laboratory
equipment
Assistance to
Engineer's staff
I-3 and site survey Ls 0.006 0.0602 11.1157
and setting out of
the works
Construction
I-4 drawings and as - Ls 0.006 0.0428 11.1157
built drawings
Reports and
I-5 Ls 0 0.014 22.000
photographs
Furnishing steel-
sheet piles for
Temporary
I-8 Coffering for m 0 2.404 83
canal works
(Type-II, width =
400 mm)
'Furnishing steel-
sheet piles Type-II
(for temporary
I - 10 m 6551.00 1.042 100
works of
dewatering of
structures)
2-1-1 Clearing and
grubbing type - A M2 5.000 0.041 83.101
Bobot
Progress Sampai
Presentasi
No Item Nama Item Satuan Minggu Ke- Minggu
(%)
15 Ke-15
(%)
2-1-4 Stripping of top
soil including M3 300 0.018 8.726
disposal

Excavation type -
2-1-6 m3 0 8.436 8.4362801
B
Hauling materials
on the land with
2-1-11 m3 0 0.018 4.3038335
hauling distance 1
- 3 km
2-1-14 Earthfill type - B m3 0 0.215 5.799459
Hauling materials
on the land with
2-1-19 0 0.473 22.037316
hauling distance
30 - 40 km
Hauling materials
on the land with
2-1-20 m3 0 0.236 5.7561556
hauling distance
40 - 50 km
Reinforcement
2-2-9 steel bar, ton 0 0.226 3.2574141
deformed bar
Fabrication of
concrete block,
2-2-13 m2 120 0.2645 2.138
1.00m x1.00m x
0.07m
Furnishing steel-
3-4-7 sheet piles type-II m 0 0.048 100
for structures
2. QUALITY CONTROL
Paket : LMS-02
Contractor : PT. Hutama Karya

2.1.Penyerahan Sampel Borrow Area


Dokumentasi

Penyerahan sampel borrow


area ex. Palasah dan ex.
Munjul untuk diuji di
Politeknik Negeri Bandung
tanggal 15 Januari 2021.
C.1. Pengambilan Sampel Aggregat Beton
Dokumentasi

Pengambilan sampel
aggregate kasar (split) dan
agregat halus (pasir) di
Batching Plant PT.
HAKAASTON tanggal 14
Januari 2021.
2.2.Concrete Block Lining
• Pengujian Kuat Tekan Umur 7 Dan 28 Hari
Tabel 1.1. QC Chart 7-days And 28-days Compressive Strength Test.
Test Result
7 Days (Kgf/cm2) 28 Days (Kgf/cm2)
Date of
Sampling Slump Slump
X1 X2 X3 Average (cm) X1 X2 X3 Average (cm)

26/11/ 2020 226.71 251.05 234.36 237.37 12.00 340.07 339.38 321.99 333.81 12.00
27/11/ 2020 245.49 250.36 221.85 239.23 12.00 319.21 330.33 315.04 321.53 12.00
28/11/ 2020 285.13 284.44 277.48 282.35 12.00 315.73 317.12 347.03 326.63 12.00
29/11/ 2020 385.27 392.92 395.71 391.30 12.00 326.16 332.42 333.12 330.57 12.00
30/11/ 2020 266.35 246.19 262.88 258.47 12.00 571.65 454.12 379.71 468.49 12.00
01/12/ 2020 228.10 217.67 258.70 234.82 12.00 355.37 346.33 358.85 353.52 12.00
02/12/ 2020 232.28 269.83 273.31 258.47 12.00 328.94 324.77 317.12 323.61 12.00
03/12/ 2020 276.09 255.23 257.31 262.88 9.00 346.33 337.29 336.59 340.07 12.00
04/12/ 2020 219.06 212.81 200.29 210.72 12.00 350.50 341.46 353.98 348.65 12.00
07/12/ 2020 250.36 241.32 226.02 239.23 12.00 349.11 335.20 351.20 345.17 12.00
08/12/ 2020 269.14 280.26 262.18 270.53 12.00 350.50 356.07 343.55 350.04 12.00
10/12/ 2020 244.80 241.32 243.40 243.17 12.00 356.76 342.16 345.63 348.18 12.00
11/12/ 2020 242.01 213.50 226.71 227.41 12.00 340.77 345.63 338.58 341.66 12.00
12/12/ 2020 216.98 214.89 220.46 217.44 12.00 345.63 367.89 338.68 350.73 12.00
13/12/ 2020 221.85 218.37 236.45 225.56 12.00 390.14 353.28 392.92 378.78 12.00
14/12/ 2020 242.71 256.62 250.36 249.90 12.00 404.75 413.79 468.03 428.86 12.00
15/12/ 2020 246.88 246.19 246.19 246.42 12.00 376.23 409.62 536.88 440.91 12.00
16/12/ 2020 211.41 219.06 225.32 218.60 12.00 362.33 363.72 283.04 336.36 12.00
17/12/ 2020 224.63 229.50 237.84 230.66 12.00 502.80 505.59 520.19 509.53 12.00
18/12/ 2020 235.75 232.97 230.89 233.20 12.00 0.00
19/12/ 2020 225.32 222.54 220.46 222.77 12.00 0.00
20/12/ 2020 244.80 253.84 255.23 251.29 12.00 0.00
21/12/ 2020 255.23 246.19 202.37 234.60 12.00 0.00
22/12/ 2020 235.06 239.93 230.19 235.06 12.00 0.00
23/12/ 2020 234.36 231.58 223.24 229.73 12.00 0.00
24/12/ 2020 230.19 235.06 232.28 232.51 12.00 0.00
26/12/ 2020 216.98 228.10 218.37 221.15 12.00 0.00
27/12/ 2020 231.58 243.40 237.84 237.61 12.00 0.00
28/12/ 2020 249.66 235.75 243.40 242.94 12.00 0.00
29/12/ 2020 237.15 256.62 272.61 255.46 12.00 0.00
30/12/ 2020 215.59 240.62 207.94 221.38 12.00 0.00
02/01/ 2021 307.39 301.82 338.68 315.96 12.00 0.00
3. Soil Investigation
• Boring
Tabel 1.2. Hasil Laporan Harian Pekerjaan Boring.
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (N) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
B.Ut.2 x 9273961.18 PT. Suwanda
19/12/2020 22/12/2020 Divission Structure With Off-take y 202712.79 20 m 50 Karya Mandiri
z 13936
B.Ut.3 x 9275700.1 PT. Suwanda
19/12/2021 22/12/2021 Divission Structure With Off-take y 203111.48 20 m 43 Karya Mandiri
z 11.865
B.Ut.4 x 9277220.49 PT. Suwanda di kedalaman
22/12/2020 23/12/2020 Divission Structure With Off-take y 203554.228 20 m 14 Karya Mandiri 13.56 - 14.02 m nilai
z 10.571 N mencapai > 50
B.Ut.9.1c x 9283704.8 PT. Suwanda
22/12/2020 23/12/2020 Road bridge + Washing step y 201051.449 20 m 42 Karya Mandiri
z 7.092
B.Ut.9.1n x 9283884.78 PT. Suwanda
24/12/2020 26/12/2020 Road bridge + Washing step y 200927.696 20 m 37 Karya Mandiri
z 7.037
B.Ut.10.1p x 9286230.41 PT. Suwanda
24/12/2020 26/12/2020 Road bridge + Washing step y 200260.407 20 m 20 Karya Mandiri
z 6.223
B.Ut.10.1ay x 9287435.63 PT. Suwanda
27/12/2020 28/12/2020 Road bridge + Pipe crossing y 200441.283 20 m 43 Karya Mandiri
z 6.107
26/12/2020 28/12/2020 B.Ut.10.1aab x 9287435.63 20 m 16 PT. Suwanda
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (N) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
Road bridge + Pipe crossing y 200425.956 Karya Mandiri
z 6.107
B. Ut. 10 x 9288811.73 PT. Suwanda
28/12/2020 31/12/2020 Divission Structure y 199993.02 20 m 30 Karya Mandiri
z 5.358
B.Ut.11.1c x 9288811.73 PT. Suwanda
29/12/2020 31/12/2020 Road bridge + Washing step y 199455.665 20 m 29 Karya Mandiri
z 5.077
B. Ut. 11. 1e x 9290146.84 PT. Suwanda
1/12/2020 2/1/2021 Road Bridge y 199450.441 20 m 45 Karya Mandiri
z 4.786
B. Ut. 11. 1f x 9290320.18 PT. Suwanda
2/12/2020 2/1/2021 Road Bridge y 199447.311 20 m 19 Karya Mandiri
z 4.786
B. Ut. 11. 1h x 9290993.46 PT. Suwanda
2/1/2021 4/1/2021 Road Bridge y 199430.306 20 m 172 Karya Mandiri
z 5.033
B. Ut. 16a x *hasil PT. Argopitu
7/1/2021 9/1/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut. 15 x *hasil PT. Argopitu
9/1/2021 11/1/2021 Divission structure + Road bridge y 20 m belum Ishana
z diperoleh
B. Ut. 12. 1j x 9291656.22 PT. Suwanda
2/1/2021 4/1/2021 Road Bridge y 199414.817 20 m 15 Karya Mandiri
z 4.814
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (N) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
B. Ut. 12. 1t x 9291838.75 PT. Suwanda
5/1/2021 6/1/2021 Road bridge + Pipe crossing y 199494.828 20 m 34 Karya Mandiri
z 4.249
B. Ut. 12. 1u x 9291922.97 PT. Suwanda
5/1/2021 6/1/2021 Road Bridge y 199538.417 20 m 16 Karya Mandiri
z 4.462
B. Ut. 12. 1w x 9292040.45 *hasil PT. Suwanda
6/1/2021 8/1/2021 Road Bridge y 199598.346 20 m belum Karya Mandiri
z 4.355 diperoleh
B. Ut. 12 b x 929144.67 *hasil PT. Suwanda
6/1/2021 8/1/2021 Road bridge + Pipe crossing y 199663.762 20 m belum Karya Mandiri
z 3.933 diperoleh
B. Ut. 12 d x *hasil PT. Argopitu
11/1/2021 13/01/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut. 12 h x 9292551.7 *hasil PT. Suwanda
6/1/2021 8/1/2021 Road bridge + Pipe crossing y 199875.206 20 m belum Karya Mandiri
z 4.035 diperoleh
B. Ut. 12 x *hasil PT. Suwanda
8/1/2021 10/1/2021 Road bridge + Pipe crossing y 20 m belum Karya Mandiri
z diperoleh
B. Ut. 13i x *hasil PT. Suwanda
8/1/2021 10/1/2021 Road Bridge y 20 m belum Karya Mandiri
z diperoleh
B. Ut. 14e x PT. Suwanda
8/1/2021 10/1/2021 20 m
Road bridge + Washing step y Karya Mandiri
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (N) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai
*hasil
belum
z diperoleh
B. Ut. 14i x *hasil PT. Argopitu
10/1/2021 12/1/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut.14k x *hasil PT. Argopitu
10/1/2021 12/1/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut. 14l x *hasil PT. Argopitu
10/1/2021 12/1/2021 Road Bridge y 20 m belum Ishana
z diperoleh
B. Ut. 17ai x 9295276.37 PT. Argopitu
4/1/2021 6/1/2021 Road bridge + Pipe crossing y 200048.792 20 m 4/30 Ishana
z 2.771
B. Ut. 18 x 9296770.89 PT. Argopitu
2/1/2021 6/1/2021 Divission structure + Road bridge y 199589.418 20 m 4/30 Ishana
z 2.643
• DCPT
Tabel 1.3. Hasil Laporan Harian Pekerjaan DCPT.
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai

B.Ut.2 x 9273956508 qc 200 PT. Argopitu

19/12/2020 21/12/2020 Divission Structure With Off-take y 202735757 19.20 m qt 210 Ishana

z 13.83

B.Ut.3 x 9275699948 qc 155 PT. Argopitu *

23/12/2020 23/12/2020 Divission Structure With Off-take y 203090909 15.60 m qt 210 Ishana

z 11.859

B.Ut.1 x 9273292975 qc 155 PT. Argopitu *

22/12/2020 23/12/2020 Off-take y 202808712 16.20 m qt 200 Ishana

z 13958

B.Ut.4 x 9277232246 qc 215 PT. Argopitu

23/12/2020 23/12/2020 Divission Structure With Off-take y 203524328 12.60 m qt 245 Ishana

z 10553

B.Ut.5.1 x 9279060469 qc 225 PT. Argopithu


24/12/2020 24/12/2020 10.60 m
Off-take y 202929450 qt 240 Ishana
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai

z 9.128

B.Ut.9.1c x 9283711.267 qc 178 PT. Suwanda *

24/12/2020 24/12/2020 Road bridge + Washing step y 201049.463 15.40 m qt 205 Karya Mandiri

z 7.117

B.Ut.6 x 9281287.937 qc 215 PT. Argopithu

24/12/2020 24/12/2020 Divission Structure y 201881730 11.40 m qt 230 Ishana

z 8.486

B.Ut.9.1n x 9283879.961 qc 190 PT. Suwanda *

24/12/2020 24/12/2020 Road bridge + Pipe crossing y 200932.193 17.80 m qt 209 Karya Mandiri

z 7.141

B.Ut.10.1p x 9286262470 qc 220 PT. Suwanda

26/12/2020 26/12/2020 Road bridge + Washing step y 200281701 10.00 m qt 225 Karya Mandiri

z 6.24

B.Ut.9 x 9285718.46 qc 204 PT. Suwanda

27/12/2020 27/12/2020 Divission Structure With Off-take y 200049.128 14.40 m qt 210 Karya Mandiri

z
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai

B.Ut.8 x qc 215 PT. Argopithu

27/12/2020 27/12/2020 Off-take y 12.20 m qt 225 Ishana

B.Ut.10.1ay x qc 203 PT. Suwanda

27/12/2020 27/12/2020 Road bridge + Pipe crossing y 15.60 m qt 210 Karya Mandiri

B. Ut. 10 x qc 200 PT. Argopithu

27/12/2020 27/12/2020 Divission Structure y 15.40 m qt 210 Ishana

B.Ut. 10.1. aab x 9287673.119 qc 210 PT. Suwanda

28/12/2020 28/12/2020 Road bridge + Pipe crossing y 200443.63 14.80 m qt 215 Karya Mandiri

B. Ut. 11. 1c x qc 198 PT. Suwanda

28/12/2020 29/12/2020 Road bridge + Washing step y 16.40 m qt 220 Karya Mandiri

28/12/2020 28/12/2020 B.Ut. 18 x 9296788.217 20 m qc 47 PT. Argopithu


Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai

Divission Structure y 199534.17 qt 55 Ishana

B. Ut. 17. ai x 9293124 qc 50 PT. Argopithu

28/12/2020 29/12/2020 Road bridge + Pipe crossing y 200057 20 m qt 58 Ishana

z 4.25

B. Ut. 17. s x 9295124 qc 50 PT. Argopithu

28/12/2020 29/12/2020 Road bridge y 201057 20 m qt 63 Ishana

z 4.75

B. Ut. 11. 1e x 9290161.133 qc 209 PT. Suwanda

29/12/2020 30/12/2020 Road bridge y 19904501250 16.40 m qt 218 Karya Mandiri

B. Ut. 16. a x 9293189.975 qc 63 PT. Argopithu

29/12/2020 29/12/2020 Road bridge y 200204.932 20 m qt 70 Ishana

z 4.575

B. Ut. 11. 1f x 9290332.361 qc 198 PT. Suwanda


30/12/2020 30/12/2020 17.60 m
Road bridge y 199446.916 qt 218 Karya Mandiri
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai

z 4.797

B. Ut. 11. 1h x qc 198 PT. Suwanda

30/12/2020 30/12/2020 Road bridge y 17.40 m qt 218 Karya Mandiri

B. Ut. 16 x 9293827 qc 47 PT. Argopithu

30/12/2020 30/12/2020 Off-take y 199638 20 m qt 53 Ishana

z 4.1

B. Ut. 15 x qc 55 PT. Argopithu

30/12/2020 30/12/2020 Divission structure + Road bridge y 20 m qt 62 Ishana

B. Ut. 14e x 9293147.398 qc 65 PT. Argopithu

30/12/2020 30/12/2020 Road bridge + Washing step y 200144.531 20 m qt 76 Ishana

B. Ut. 14i x 9293085.861 qc 65 PT. Argopithu

30/12/2020 31/12/2020 Road bridge y 200135.846 20 m qt 75 Ishana

z 4.578
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai

B. Ut. 14k x 9293108.41 qc 66 PT. Argopithu

30/12/2020 30/12/2020 Road bridge y 200146.855 20 m qt 78 Ishana

z 4.523

B. Ut. 14l x 9293133.404 qc 53 PT. Argopithu

31/12/2020 31/12/2020 Road bridge y 200161.069 20 m qt 59 Ishana

z 4.604

B. Ut. 14b x 9292894.367 qc 56 PT. Argopithu

31/12/2020 31/12/2020 Road bridge y 208037.362 20 m qt 62 Ishana

z 4.727

B. Ut. 13 x 9292915.839 qc 55 PT. Argopithu

31/12/2020 31/12/2020 Off-take y 20036.946 20 m qt 65 Ishana

z 4.614

B. Ut. 11 x 9291253.708 qc 144 PT. Suwanda

31/12/2020 31/12/2020 Off-take y 189435.708 20 m qt 150 Karya Mandiri

z 4.846

1/1/2021 1/1/2021 B. Ut. 12. 1j x 20 m qc 105 PT. Suwanda


Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai

Road bridge y qt 110 Karya Mandiri

B. Ut. 12. 1t x qc 28 PT. Suwanda

1/12/2021 1/12/2021 Road bridge + Pipe crossing y 20 m qt 35 Karya Mandiri

B. Ut. 12b x 9292138.133 qc 65 PT. Argopithu

2/12/2021 2/12/2021 Road bridge + Pipe crossing y 199636.711 20 m qt 75 Ishana

z 4.271

B. Ut. 12. 1u x qc 31 PT. Suwanda

2/12/2021 2/12/2021 Road bridge y 20 m qt 38 Karya Mandiri

B. Ut. 12d x 9292244 qc 55 PT. Argopithu

2/12/2021 2/12/2021 Road bridge y 199666 20 m qt 63 Ishana

z 4.14

B. Ut. 12. 1w x qc 35 PT. Suwanda


2/12/2021 2/12/2021 20 m
Road bridge y qt 41 Karya Mandiri
Waktu Pengerjaan
Lokasi Koordinat Kedalaman Hasil (kg/cm²) Sub. Contractor Catatan
Waktu Mulai Waktu Selesai

B. Ut. 12h x 9292540 qc 63 PT. Argopithu

2/12/2021 2/12/2021 Road bridge + Pipe crossing y 199826 20 m qt 72 Ishana

z 4.21

B. Ut. 13i x 9292780.762 qc 65 PT. Argopithu

2/12/2021 2/12/2021 Road bridge y 199971.733 20 m qt 73 Ishana

z 4.312

B. Ut. 12 x qc 205 PT. Suwanda

3/12/2021 3/12/2021 Divission structure y 18.80 m qt 215 Karya Mandiri

(*) : Pekerjaan Tes DCPT tidak dapat dilanjutkan karena pipa alat tidak dapat menembus kedalaman berikutnya (Jika dipaksa, resiko
pipa alat dapat rusak/bengkok).
• Hand Auger
Tabel 1.4. Hasil Laporan Harian Pekerjaan Hand Auger.

Waktu Kedalaman
Lokasi Koordinat (R/L) Progress Keterangan
Pengerjaan (m)

B.Ut.1.1a x 9271207.264 Pengambilan sampel UDS. kedalaman 3.5


27/12/2020 ('R) 5
Road Bridge y 200168.732 m, berat +/- 5 kg.
Tecapai
z 34.800
28/12/2020 (L) 5 Pengambilan sampel UDS. kedalaman 4 m

B.Ut.1.1k x 9272042.138
27/12/2020 Road Bridge y 200851.368 (L) 5 Tercapai Pengambilan sampel UDS. kedalaman 3.5 m
z 38.000
B.Ut.1.1t x 9272525.190
28/12/2020 Off-take y 201083.422 (L) 1.5 Tercapai Pengambilan sampel UDS. kedalaman 1 m
z 34.470
B.Ut.1.1 x 9272731.663
29/12/2020 Off-take y 201222.956 (L) 2.2 Tercapai Pengambilan sampel UDS. Kedalaman 1.5 m
z 35.750
B. Ut. 1 x 9273327.148
30/12/2020 Road Bridge y 201824.526 (L) 2.3 Tercapai Pengambilan sampel UDS. Kedalaman 1.5 m
z 39.370
B. Ut. 2f x 9273459l612
30/12/2020 Road Bridge y 202161.495 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 4 m
z 30.310
B. Ut. 2g x 9273466.767
31/12/2020 Foot Bridge + Off take y 202280.215 (L) 4.2 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 29.500
Waktu Kedalaman
Lokasi Koordinat (R/L) Progress Keterangan
Pengerjaan (m)

B. Ut. 5.1 x 9279065.911


3/1/2021 Off-take y 202933.638 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 27.890
B. Ut. 5.2 x 9280579.971
4/1/2021 Off-take y 201910.322 ('R) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 25.680
B. Ut. 5 x 9280902.602
4/1/2021 Off-take y 201894.354 ('R) 4 Tercapai Pengambilan sampel UDS. Kedalaman 3 m
z 25.910
B. Ut. 6 x 9281349.031
4/1/2021 Divission Structure y 201886.605 ('R) 4.25 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 27.640
B. Ut. 7 x 9282135.200
4/1/2021 Off-take y 201569.533 ('R) 4 Tercapai Pengambilan sampel UDS. Kedalaman 3 m
z 24.070
B. Ut. 8 x 9283606.738
5/1/2021 Off-take y 201082.482 (L) 4 Tercapai Pengambilan sampel UDS. Kedalaman 2.5 m
z 30.570
B. Ut. 9.1 x 9284423.839
5/1/2021 Off-take y 200487.235 ('R) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z
B. Ut. 9 x 9285718.870
5/1/2021 Divission Structure with Off take y 200050.382 ('R) 3 Tercapai Pengambilan sampel UDS. Kedalaman 2 m
z 19.850
5/1/2021 B. Ut. 10.1 n x 9286172.700 (L) 4.25 Tercapai Pengambilan sampel UDS. Kedalaman 3 m
Waktu Kedalaman
Lokasi Koordinat (R/L) Progress Keterangan
Pengerjaan (m)

Washing step + Off take y 200249.080


z 25.120
B. Ut. 10. 1 w x 9286779.995
6/1/2021 Drain inlet + Off take y 200252.073 ('R) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 81.070
B. Ut. 10. 1 x 928810.997
6/1/2021 Off-take y 200351.654 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 20.880
B. Ut. 11. 1 x 9290948.209
6/1/2021 Off-take y 199432.624 ('R) 4 Tercapai Pengambilan sampel UDS. Kedalaman 2.5 m
z 28.580
B. Ut. 11 x 9291247.535
6/1/2021 Off-take y 199418.948 (L) 4.2 Tercapai Pengambilan sampel UDS. Kedalaman 3 m
z 20.490
B. Ut. 12. 1m x 9291681.128
6/1/2021 Road Bridge y 199408.083 ('R) 4 Tercapai Pengambilan sampel UDS. Kedalaman 2.5m
z 17.920
B. Ut. 12. 1 x 9292138.155
6/1/2021 Off-take y 199618.175 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 19.380
B. Ut. 13 x 9292895.822
7/1/2021 Off-take y 20015.199 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 24.540
B. Ut. 14 b x 9292909.336
7/1/2021 ('R) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
Road Bridge y 200027.827
Waktu Kedalaman
Lokasi Koordinat (R/L) Progress Keterangan
Pengerjaan (m)

z 16.920
B. Ut. 14 x 9293128.259
7/1/2021 Off-take y 200152.487 ('R) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 16.920
B. Ut. 16 x 9293834.362
7/1/2021 Off-take y 199936.634 ('R) 4 Tercapai Pengambilan sampel UDS. Kedalaman 2.5m
z 23.710
B. Ut. 17 s x 9294431.754
8/1/2021 Road Bridge y 200102.514 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3 m
z 17.310
B. Ut. 17 x 9295323.942
8/1/2021 Off-take y 200032.149 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3 m
z 11.360
B. Ut. 18 c x 9295579.537
8/1/2021 Foot Bridge + Off take y 200063.673 (L) 5 Tercapai Pengambilan sampel UDS. Kedalaman 3.5 m
z 16.220
B. Ut. 18 d x 9296153.545
8/1/2021 Pump Outlet + Off take y 199601.434 ('R) 4 Tercapai Pengambilan sampel UDS. Kedalaman 2.5m
z 15.620
• Tes PRP
Tabel 1.5. Hasil Laporan Harian Pekerjaan Tes PRP.

Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
ZONA 1 (L)
UT. 0 190 100 # * *
1 13/01/2021 UT. 1 200 100 200 100 * *
UT. 2 220 100 200 100 * *
UT. 3 150 100 230 100 * *
UT. 4 130 100 150 100 * *
UT. 5 100 100 180 100 * *
UT. 6 150 100 200 100 * *
2 14/01/2021 UT. 7 140 100 230 100 * *
UT. 8 80 100 220 100 * *
UT. 9 220 100 220 100 * *
UT. 10 60 100 40 100 * *
UT. 11 80 100 # * *
UT. 12 200 100 260 100 # # * *
UT. 13 140 100 180 100 150 100 200 100 * *
UT. 14 250 100 230 70 210 100 220 100 * *
3 16/01/2021 UT. 15 170 100 180 100 270 100 210 100 * *
UT. 16 40 100 40 100 250 100 250 100 * *
UT. 17 70 100 70 100 90 100 140 100 * *
UT. 18 160 100 200 100 250 100 250 100 * *
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
UT. 19 60 100 60 100 170 100 170 100 * *

Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
ZONA 1 ('R)
UT. 0 60 95 200 100 * *
UT. 1 80 70 220 100 * *
UT. 2 200 99 130 100 * *
1 13/01/2021
UT. 3 200 100 200 100 * *
UT. 4 40 100 150 100 * *
UT. 5 70 100 220 100 * *
UT. 6 300 100 290 100 * *
2 14/01/2021 UT. 7 200 100 240 100 * *
UT. 8 270 100 230 100 * *
UT. 9 200 100 280 100 * *
UT. 10 170 100 290 100 * *
UT. 11 150 100 190 100 * *
3 15/01/2021
UT. 12 190 100 210 100 * *
UT. 13 # # * *
UT. 14 + 30 100 100 110 100 * *
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
UT. 15 # # * *
UT. 16 # # * *
UT. 17 250 100 220 100 * *
UT. 18 250 100 180 100 * *
UT. 19 230 100 240 100 * *
UT. 20 210 100 230 100 * *
UT. 21 190 100 180 100 * *
UT. 22 70 100 80 100 80 100 180 100 * *
UT. 23 180 100 210 100 220 100 190 100 * *
UT. 24 240 100 220 100 260 100 270 100 * *
UT. 25 60 100 70 100 230 100 260 100 * *
UT. 26 90 100 130 100 140 100 160 100 * *
UT. 27 90 100 100 100 120 100 110 100 * *
4 16/01/2021
UT. 28 130 100 130 100 230 100 220 100 * *
UT. 29 320 100 330 100 130 100 130 100 * *
UT. 30 180 100 170 100 220 100 210 100 * *
UT. 31 290 100 280 100 270 100 250 100 * *
UT. 32 250 100 210 100 150 100 150 100 * *
UT. 33 130 100 210 100 110 100 160 100 * *

Catatan:
Untuk titik 3 masih belum dapat dilakukan PRP tes karena muka air masih
(*) tinggi
(#) Tidak dapat dilakukan PRP tes karena terhalang pasangan batu lama
Belum dilakukan PRP tes (menyusul)
cm Kedalaman alat
kgf Satuan pembacaan alat
a dan b Beda beberapa cm
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
ZONA 2 (L)
UT. 118 290 100 290 100 190 100 190 100
UT. 119 270 100 270 100 230 100 250 100
UT. 120 250 100 300 90 300 55 290 100
UT. 121 150 100 80 100 290 100 250 100
1 15/01/2021
UT. 122 280 100 250 100 260 100 280 100
UT. 123 260 100 210 100 250 100 250 100
UT. 124 300 100 300 100 250 100 290 100
UT. 125 300 100 260 100 210 100 230 100
UT. 126 280 100 250 100 270 100 280 100
UT. 127 290 100 300 100 280 100 270 100
UT. 128 250 100 250 100 270 100 260 100
UT. 129 300 58 300 58 300 30 300 29
UT. 130 180 100 260 100 180 100 170 100
2 16/01/2021 UT. 131 270 100 290 100 280 100 300 55
UT. 132 300 100 270 90 140 100 300 100
UT. 133 110 100 300 74 300 70 300 90
UT. 134 270 83 270 100 300 100 300 90
UT. 135 190 100 190 100 300 65 300 40
UT. 136 300 96 300 85 210 100 260 100
Progress
Waktu
No Lokasi Ket.
Pengerjaan
Ia Ib IIa IIb IIIa IIIb
cm kgf cm kgf cm kgf cm kgf cm kgf cm kgf
ZONA 2 ('R)
UT. 118 190 100 120 100
UT. 119 220 100 180 100 160 100
1 13/01/2021 UT. 120 180 100 160 100 160 100
UT. 121 270 100 200 100 210 100
UT. 122 300 100 290 100 260 100
UT. 123 240 100 260 100
UT. 124 50 100 250 100
UT. 125 50 100 60 100
UT. 126 80 100 280 100
UT. 127 160 100 150 100
2 14/01/2021 UT. 128 290 100 170 100
UT. 129 150 100 210 100
UT. 130 120 100 290 100
UT. 131 150 100 210 100
UT. 132 130 100 120 100
UT. 133 220 100 290 100
Dokumentasi Pekerjaan

Boring B.Ut. 14.1 k dan B. Ut. 14 i

Boring B. Ut. 15 dan B. Ut. 14 l

32
Dokumentasi Pekerjaan

PRP tes UT 005 R

PRP Tes Ut. 007 L

PRP Tes Ut. 128 L dan UT. 31 L


4. Kegiatan Lain

33
Dokumentasi

Diskusi terkait pengisian form


quality control dengan Pak Eddy
Prasetyo di Kantor Jatibarang.

Pengarahan terkait swelling tes


bersama kontraktor LMS 01 dan
LMS 02 dengan Mr. Ueno dan Pak
Darman.

Penjelasan cara tes swelling


bersama kontraktor LMS 01 dan
LMS 02 dengan Mr. Ueno dan Pak
Darman.

34
Dokumentasi

Penjelasan cara pengambilan


sampel dengan alat hand auger
bersama kontraktor LMS 01 dan
LMS 02 dengan Mr. Ueno dan Pak
Darman.

5. Kendala Lapangan
• Dalam pekerjaan tes PRP untuk titik 3 tidak dapat dilakukan karena muka air masih tinggi.
• Terdapat beberapa titik dalam tes PRP yang tidak dapat dilakukan karena terdapat pasangan batu
lama disepanjang

35
3.PROGRESS DILAPANGAN
AREA 1
STA UT. 0 UT. 2 UT. 5 UT. 25 UT. 62 UT. 68
PEKERJAAN
Clearing and Grubbing
Stripping of Top Soil
Earthfill Type B
KIRI

Excavation Slope
Dasar
Lining Canal
Clearing and Grubbing
Stripping of Top Soil
KANAN

Earthfill Type B
Excavation Slope
Dasar
Lining Canal

AREA 2
UT. UT. UT. UT. UT. UT. UT. UT.
STA 118 122 125 130 138 141 150 173
PEKERJAAN
Clearing and
Grubbing
Stripping of
Top Soil
Earthfill Type B
KIRI

Excavati Slop
on e
Das
ar
Lining Canal
Clearing and
Grubbing
Stripping of
KANAN

Top Soil
Earthfill Type B
Excavation Slope
Dasar
Lining Canal

36
3.1. Kegiatan Senin, 11 Januari 2021
Kegiatan :
Penutupan celah celah pada ssp di aUT.118-122

Kegiatan :
Proses dewatering dengan menggunakan pompa

37
3.2.Selasa , 12 Januari 2021

Kegiatan :
Penambalan kebocoran disela sela SSP

Kegiatan
Menggunakan 4 pompa untuk proses dewatering

3.3. Rabu, 13 Januari 2021

Kegiatan :
Proses dewatering

38
3.4. Kamis, 14 Januari 2021
Kegiatan :
Proses dewatering di UT.118-122 R

Kegiatan
Dewatering SSP

Kegiatan :
Proses dewatering di UT.118-122 R

39
3.5. Jum’at 15 Januari 2021

Kegiatan :
Proses penambalan sela-sela SSP

Kegiatan :
Proses dewatering di UT.118-122 R

Kegiatan :
Galian struktur di UT.118-122 R

40
3.6. Sabtu, 16 Januari 2021
Kegiatan :
Proses dewatering di UT.118-122 R

Kegiatan :
Proses dewatering di UT.118-122 R

Kegiatan :
Proses dewatering di UT.118-122 R dengan
menggunakan pompa

41
4. MONITORING PRODUKSI CONCRETE BLOCK LINING

PENGIRIMAN
REALISASI
Cetak Lining Block 1x1x0.07 m (m2)

Moulding (set) Moulding (pcs) Cetak Lining Block 1x1x0.07m (m2)


HAKAA-SIS
HAKAA-SIS Jumlah
No Tanggal
HAKAA-SIS

HAKAA-SIS
Reject Jumlah Kom
Solid Hole Hole ᴓ Ratio Harian Kom Solid Hole Hole ᴓ

1 26-Nov-20 15 150 147 ada ada 2.00 150 150


2 27-Nov-20 8 80 77 ada ada 3.75 80 230
3 28-Nov-20 19 190 186 ada ada 2.11 190 420
4 29-Nov-20 7 70 68 ada ada 2.86 70 490
5 30-Nov-20 22 220 217 ada ada 1.36 220 710
6 1-Dec-20 22 220 218 ada ada 0.91 220 930
7 2-Dec-20 19 190 186 ada ada 2.11 190 1120
8 3-Dec-20 18 180 176 ada ada 2.22 180 1300
9 4-Dec-20 12 120 117 ada ada 2.50 120 1420
10 5-Dec-20 0 0 0 0.00 0 1420
11 6-Dec-20 0 0 0 0.00 0 1420
12 7-Dec-20 14 140 138 ada ada 1.43 140 1560
13 8-Dec-20 13.9 139 136 ada ada 2.16 139 1699
14 9-Dec-20 0 0 0 ada ada 0.00 0 1699
15 10-Dec-20 55 550 548 ada ada 0.36 550 2249
16 11-Dec-20 25 250 247 ada ada 1.20 250 2499
17 12-Dec-20 35 350 345 ada ada 1.43 350 2849
18 13-Dec-20 18 180 170 ada ada 5.56 180 3029

42
PENGIRIMAN
REALISASI
Cetak Lining Block 1x1x0.07 m (m2)

Moulding (set) Moulding (pcs) Cetak Lining Block 1x1x0.07m (m2)


HAKAA-SIS
HAKAA-SIS Jumlah
No Tanggal

HAKAA-SIS

HAKAA-SIS
Reject Jumlah Kom
Solid Hole Hole ᴓ Ratio Harian Kom Solid Hole Hole ᴓ

19 14-Dec-20 6 60 60 ada ada 0.00 60 3089


20 15-Dec-20 28 280 271 ada ada 3.21 280 3369
21 16-Dec-20 6 60 57 ada ada 5.00 60 3429
22 17-Dec-20 32 320 311 ada ada 2.81 320 3749
23 18-Dec-20 17 170 157 ada ada 7.65 170 3919
24 19-Dec-20 58 580 563 ada ada 2.93 580 4499
25 20-Dec-20 32 320 306 ada ada 4.38 320 4819
26 21-Dec-20 52 520 508 ada ada 2.31 520 5339
27 22-Dec-20 54 540 525 ada ada 2.78 540 5879
28 23-Dec-20 16 160 ada ada 160 6039
29 24-Dec-20 60 600 ada ada 600 6639
30 25-Dec-20 0 0 0 6639
31 26-Dec-20 60 600 ada ada 600 7239
32 27-Dec-20 48 480 ada ada 480 7719
33 28-Dec-20 42 420 ada ada 420 8139
34 29-Dec-20 48 480 ada ada 480 8619
35 30-Dec-20 6 60 ada ada 60 8679
36 31-Dec-20 0 0 0 8679
37 1-Jan-21 0 0 0 8679
38 2-Jan-21 6 60 ada ada 60 8739
39 3-Jan-21 0 0 0 8739
43
PENGIRIMAN
REALISASI
Cetak Lining Block 1x1x0.07 m (m2)

Moulding (set) Moulding (pcs) Cetak Lining Block 1x1x0.07m (m2)


HAKAA-SIS
HAKAA-SIS Jumlah
No Tanggal

HAKAA-SIS

HAKAA-SIS
Reject Jumlah Kom
Solid Hole Hole ᴓ Ratio Harian Kom Solid Hole Hole ᴓ

40 4-Jan-21 0 0 0 8739
41 5-Jan-21 0 0 0 8739
42 6-Jan-21 0 0 0 8739
43 7-Jan-21 0 0 0 8739
44 8-Jan-21 0 0 0 8739
45 9-Jan-21 0 0 0 8739
46 10-Jan-21 0 0 0 8739
47 11-Jan-21 0 0 0 8739
48 12-Jan-21 0 0 0 8739
49 13-Jan-21 0 0 0 8739
50 14-Jan-21 0 0 0 8739
51 15-Jan-21 0 0 0 8739
52 16-Jan-21 0 0 0 8739
53 17-Jan-21 0 0 0 8739

44
5. PERMASALAHAN DILAPANGAN

cuaca suka berubah-rubah, hujan dan cerah mengakibatkan pekerjaan berhenti dan akses
jalan kerja tidak bisa dilewati

45
6. RENCANA MINGGU ke-23

kegiatan di Area 2 Ut.118 Sd Ut.173 )


• Rencana melanjutkan pekerjaan pemancangan dengan SSP di area u.118 sd
Ut.122
• Melanjutkan pekerjaan earthfill
• Hauling materials on the land with hauling distance 30 - 40 km
• Melanjutkan pekerjaan Borring dan sondir
• Melanjutkan produksi blok panel beton di BP - HK aston
• Pekerjaan uji tekan umur beton 7 hari dan 28 hari blok beton di batching plant
HK-aston
• Trial Job mix desgn untuk penambahan semen menjadi 360 kg
• PRV

Majalengka, 17 Januari 2021


Construction Engineer

Eggi Novan Hermawan

46