Download as pdf or txt
Download as pdf or txt
You are on page 1of 145

OPTIMIZATION OF SPAN-TO-DEPTH RATIOS IN HIGH-STRENGTH

CONCRETE GIRDER BRIDGES

by

Sandy Shuk-Yan Poon

A thesis submitted in conformity with the requirements


for the degree of Master of Applied Science
Graduate Department of Civil Engineering
University of Toronto

© Copyright by Sandy Shuk-Yan Poon (2009)


Optimization of Span-to-Depth Ratios in High-Strength Concrete Girder Bridges

Sandy Shuk-Yan Poon


Master of Applied Science
Graduate Department of Civil Engineering
University of Toronto
2009

ABSTRACT

Span-to-depth ratio is an important bridge design parameter that affects structural behaviour,

construction costs and aesthetics. A study of 86 constant-depth girders indicates that conventional

ratios have not changed significantly since 1958. These conventional ratios are now questionable,

because recently developed high-strength concrete has enhanced mechanical properties that allow

for slenderer sections.

Based on material consumption, cost, and aesthetics comparisons, the thesis determines optimal

ratios of an 8-span highway viaduct constructed with high-strength concrete. Three bridge types are

investigated: cast-in-place on falsework box-girder and solid slabs, and precast segmental span-by-

span box-girder. Results demonstrate that total construction cost is relatively insensitive to span-to-

depth ratio over the following ranges of ratios: 10-35, 30-45, and 15-25 for the three bridge types

respectively. This finding leads to greater freedom for aesthetic expressions because, compared to

conventional values (i.e. 18-23, 22-39, and 16-19), higher ranges of ratios can now be selected

without significant cost premiums.

ii
ACKNOWLEDGEMENTS

I would like to express my deepest gratitude to my supervisor, Professor Paul Gauvreau, whose
encouragement, guidance, and support enabled me to complete this thesis.
I am also indebted to my research colleagues for their insightful advice and assistance
throughout my graduate studies: Cathy Chen, Billy Cheung, Davis Doan, Negar Elhami Khorasani,
Eileen Li, Kris Mermigas, Jason Salonga, Jimmy Susetyo, Brent Visscher, and Ivan Wu.
Lastly, I would like to thank my family for their support and encouragement over these past two
years.

iii
TABLE OF CONTENTS
Abstract .............................................................................................................................................. ii
Acknowledgements........................................................................................................................... iii
Table of Contents ............................................................................................................................. iv
List of Figures ................................................................................................................................. viii
List of Tables .................................................................................................................................... xi
List of Symbols ............................................................................................................................... xiii

1 Introduction ............................................................................................................................... 1
1.1 The Significance of Optimizing Span-to-Depth Ratio ........................................................ 1
1.2 Objectives and Scope .......................................................................................................... 5
1.3 Thesis Structure................................................................................................................... 6

2 Typical Span-to-Depth Ratios of Existing Bridges................................................................. 7


2.1 Cast-in-Place Box-Girder .................................................................................................... 7
2.2 Cast-in-Place Slab ............................................................................................................. 12
2.3 Precast Segmental Box-Girder .......................................................................................... 16
2.4 Concluding Remarks ......................................................................................................... 18

3 Analysis Overview ................................................................................................................... 19


3.1 Analysis Model ................................................................................................................. 19
3.2 Materials............................................................................................................................ 21
3.2.1 Prestressing Tendons ................................................................................................. 21
3.2.2 Concrete Covers ........................................................................................................ 22
3.3 Loads ................................................................................................................................. 22
3.3.1 Load Combinations and Load Factors ...................................................................... 22
3.3.2 Live Loads................................................................................................................. 23
3.4 Design Requirements ........................................................................................................ 24
3.4.1 Ultimate Limit States Design Requirements ............................................................. 24
3.4.1.1 Flexural Strength ................................................................................................... 24
3.4.1.2 Shear Strength ....................................................................................................... 25
3.4.2 Serviceability Limit States Design Requirements ..................................................... 26
3.4.2.1 Stress ..................................................................................................................... 26
3.4.2.2 Vibration ............................................................................................................... 26
3.4.2.3 Deflection .............................................................................................................. 27
iv
3.5 Other Preliminary Analysis Assumptions ......................................................................... 27

4 Analysis of Cast-in-Place on Falsework Bridges .................................................................. 28


4.1 Cast-in-Place on Falsework Construction ......................................................................... 28
4.2 Cast-in-Place on Falsework Box-Girder ........................................................................... 28
4.2.1 Model ........................................................................................................................ 28
4.2.1.1 Cross-Section ........................................................................................................ 29
4.2.1.2 Prestressing Tendon Layout .................................................................................. 30
4.2.2 Analysis Results ........................................................................................................ 31
4.2.2.1 Structural Behaviour and Dimensioning ............................................................... 31
4.2.2.2 Vibration Limits .................................................................................................... 32
4.2.2.3 Deflections ............................................................................................................ 33
4.2.2.4 Material Consumption........................................................................................... 34
4.2.2.5 Limiting Factors of Span-to-Depth Ratios ............................................................ 36
4.3 Cast-in-Place on Falsework Solid Slab ............................................................................. 38
4.3.1 Model ........................................................................................................................ 39
4.3.1.1 Cross-Section ........................................................................................................ 39
4.3.1.2 Prestressing Tendon Layout .................................................................................. 39
4.3.2 Strip Method versus Beam Model ............................................................................. 40
4.3.3 Analysis Results ........................................................................................................ 42
4.3.3.1 Structural Behaviour and Dimensioning ............................................................... 42
4.3.3.2 Maximum Reinforcement Criterion ...................................................................... 43
4.3.3.3 Vibration Limits .................................................................................................... 44
4.3.3.4 Deflections ............................................................................................................ 45
4.3.3.5 Material Consumption........................................................................................... 46
4.3.3.6 Limiting Factors of Span-to-Depth Ratios ............................................................ 47

5 Analysis of Precast Segmental Span-by-Span Box-Girder .................................................. 48


5.1 Precast Segmental Span-by-Span Construction ................................................................ 48
5.2 Model ................................................................................................................................ 49
5.2.1 Cross-Section ............................................................................................................ 50
5.2.2 Elevation and Prestressing Tendon Layout ............................................................... 50
5.3 Longitudinal Bending Moments ....................................................................................... 51
5.3.1 Construction Moments .............................................................................................. 51
5.3.2 Moments due to Thermal Gradient ........................................................................... 54
v
5.4 Loss of Prestress................................................................................................................ 57
5.4.1 Friction Losses .......................................................................................................... 57
5.4.2 Creep and Shrinkage Losses ..................................................................................... 58
5.4.3 Losses due to Relaxation of Prestressing Steel ......................................................... 59
5.4.4 Total Prestress Losses ............................................................................................... 59
5.5 Behaviour of Unbonded Tendons at Ultimate Limit States .............................................. 60
5.6 Analysis Results ................................................................................................................ 61
5.6.1 Structural Behaviour and Dimensioning ................................................................... 61
5.6.2 Vibration Limits ........................................................................................................ 61
5.6.3 Deflections ................................................................................................................ 62
5.6.4 Material Consumption............................................................................................... 63
5.6.5 Limiting Factors of Span-to-Depth Ratios ................................................................ 64

6 Cost Comparisons ................................................................................................................... 65


6.1 Material Costs ................................................................................................................... 65
6.1.1 Material Unit Prices .................................................................................................. 65
6.1.1.1 Concrete Material Unit Price ................................................................................ 65
6.1.1.2 Cast-in-Place versus Precast Concrete .................................................................. 66
6.1.1.3 Falsework versus Erection Truss........................................................................... 67
6.1.1.4 Formwork .............................................................................................................. 67
6.1.1.5 Prestressing Tendons............................................................................................. 67
6.1.2 Material Cost Comparisons ....................................................................................... 67
6.1.2.1 Concrete Cost Comparison ................................................................................... 68
6.1.2.2 Prestressing Cost Comparison............................................................................... 69
6.1.2.3 Reinforcing Steel Cost Comparison ...................................................................... 70
6.1.2.4 Total Superstructure Cost ...................................................................................... 73
6.2 Overall Construction Costs ............................................................................................... 76
6.2.1 Construction Cost Breakdown .................................................................................. 76
6.2.2 Total Construction Cost Comparison ........................................................................ 77
6.3 Other Cost Factors ............................................................................................................ 78
6.4 Sensitivity Analysis........................................................................................................... 79
6.4.1 Sensitivity with Respect to Changes in Material Unit Prices .................................... 79
6.4.2 Sensitivity with Respect to Changes in Construction Cost Breakdown .................... 83
6.5 Concluding Remarks ......................................................................................................... 85

vi
7 Aesthetics Comparisons .......................................................................................................... 86
7.1 Visual Impact of Span-to-Depth Ratio .............................................................................. 86
7.1.1 Effects of Viewing Points ......................................................................................... 92
7.1.2 Other Factors that Affect Visual Slenderness ........................................................... 94
7.2 Evolution of the Visually Optimal Span-to-Depth Ratio .................................................. 97
7.3 Concluding Remarks ....................................................................................................... 102

8 Conclusions ............................................................................................................................ 103


8.1 Conventional Span-to-Depth Ratios ............................................................................... 103
8.2 Maximum Span-to-Depth Ratios .................................................................................... 103
8.3 Material Consumption Comparisons............................................................................... 104
8.4 Total Construction Cost Comparisons ............................................................................ 104
8.5 Aesthetic Comparisons.................................................................................................... 105
8.6 Optimal Span-to-Depth Ratios ........................................................................................ 105

Reference........................................................................................................................................ 107

Appendix A: Chapter 2 Supplementary Information ................................................................ 111


A.1 Cast-in-Place on Falsework Box-Girder ............................................................................ 112
A.2 Cast-in-Place on Falsework Solid Slab .............................................................................. 116
A.3 Precast Segmental Span-by-Span Box-Girder.................................................................... 118

Appendix B: Supporting Calculations ........................................................................................ 119


B.1 Flexural Strength for Bonded Tendons at ULS .................................................................. 119
B.2 Shear Strength at ULS ....................................................................................................... 120
B.3 Thermal Gradient Moments................................................................................................ 122
B.4 External Tendon Force ....................................................................................................... 124
B.5 Total Construction Cost ...................................................................................................... 125

Appendix C: Summary of Results ............................................................................................... 126


C.1 Cast-in-Place on Falsework Box-Girder............................................................................. 127
C.2 Cast-in-Place on Falsework Solid Slab .............................................................................. 128
C.3 Precast Segmental Span-by-Span Box-Girder .................................................................... 129
C.4 Sensitivity with Respect to Changes in Construction Cost Breakdown ............................. 130

vii
LIST OF FIGURES
Figure 1-1. Recommended ratios for cast-in-place box-girder ......................................................... 2
Figure 1-2. Recommended ratios for cast-in-place slab .................................................................... 2
Figure 1-3. Recommended ratios for precast segmental box-girder ................................................. 2
Figure 2-1. Span-to-depth ratios of cast-in-place box-girders ........................................................ 10
Figure 2-2. Span-to-depth ratios of cast-in-place box-girders ........................................................ 11
Figure 2-3. Span-to-depth ratios of cast-in-place slabs ................................................................... 13
Figure 2-4. Span-to-depth ratios of cast-in-place slabs ................................................................... 14
Figure 2-5. Span-to-depth ratios of precast segmental box-girders ................................................ 17
Figure 2-6. Span-to-depth ratios of precast segmental box-girders ................................................ 17
Figure 2-7. Span-to-depth ratios for all bridge types ...................................................................... 18
Figure 3-1. Typical plan and elevation ........................................................................................... 19
Figure 3-2. Typical deck arrangement ............................................................................................ 19
Figure 3-3. Summary of analysis cases ........................................................................................... 20
Figure 3-4. Live loads: CL-625 truck load (top); CL-625 lane load (bottom) ................................ 23
Figure 3-5. Flexural resistance: a) cross-section, b) concrete stains, c) equivalent concrete stresses,
d) concrete forces .............................................................................................................................. 24
Figure 3-6. Construction cost economy from increasing the number of stirrup spacing ................ 25
Figure 3-7. Deflection limits for highway bridge superstructure vibration (CHBDC 2006) .......... 26
Figure 4-1. Moment comparison of bridges with constant and reduced end span length ............... 29
Figure 4-2. Typical cross-section for cast-in-place on falsework box-girder ................................. 29
Figure 4-3. Typical reinforcing steel layout .................................................................................... 30
Figure 4-4. Typical tendon profile .................................................................................................. 30
Figure 4-5. Changes in sectional modulus and cross-sectional depth ............................................. 32
Figure 4-6. Deflection for superstructure vibration limitation ........................................................ 33
Figure 4-7. Deflections: a) dead load, b) long-term, c) short-term ................................................. 33
Figure 4-8. Material consumptions for cast-in-place on falsework box-girder ............................... 35
Figure 4-9. Tendon arrangement that limits further increase in span-to-depth ratio....................... 36
Figure 4-10. Interior box cavity limitation ...................................................................................... 37
Figure 4-11. Height of access diminishes as span-to-depth ratio increases .................................... 37
Figure 4-12. Concrete reduction due to increase in L/h ratio for solid slab and box-girder ........... 38
Figure 4-13. Voided slab ................................................................................................................. 38
Figure 4-14. Typical cross-section for cast-in-place on falsework solid slab ................................. 39

viii
Figure 4-15. Typical reinforcing steel layout .................................................................................. 39
Figure 4-16. Transverse distribution of longitudinal bending moment in slabs.............................. 41
Figure 4-17. Maximum reinforcement criterion: a) concrete stains, b) equivalent concrete stresses,
c) concrete forces .............................................................................................................................. 44
Figure 4-18. Deflection for superstructure vibration limitation ...................................................... 44
Figure 4-19. Deflections: a) dead load, b) long-term, c) short-term ............................................... 45
Figure 4-20. Material consumptions for cast-in-place on falsework solid slab .............................. 47
Figure 5-1. Precast segmental span-by-span construction method ................................................. 49
Figure 5-2. Span-by-span erection girder: a) overhead truss, b) underslung girder ........................ 49
Figure 5-3. Typical cross-section for precast segmental span-by-span box-girder ......................... 50
Figure 5-4. Typical reinforcing steel layout .................................................................................... 50
Figure 5-5. Typical tendon profile .................................................................................................. 51
Figure 5-6. Construction moments for segmental span-by-span method........................................ 52
Figure 5-7. Redistribution of dead load moments due to creep ...................................................... 54
Figure 5-8. Redistribution of dead load and prestress moments due to creep................................. 54
Figure 5-9. Thermal gradient effects ............................................................................................... 55
Figure 5-10. Moments due to thermal gradient ............................................................................... 56
Figure 5-11. Intentional angle changes ........................................................................................... 57
Figure 5-12. Long-term loss of prestress due to relaxation (Menn 1990) ....................................... 59
Figure 5-13. Compatibility conditions for bonded and unbonded tendons ..................................... 60
Figure 5-14. Deflection for superstructure vibration limitation ...................................................... 62
Figure 5-15. Deflections: a) dead load, b) long-term, c) short-term ............................................... 62
Figure 5-16. Material consumptions for precast span-by-span box-girder ..................................... 63
Figure 5-17. Access limited by height of interior box cavity.......................................................... 64
Figure 5-18. Access limited by height of interior box cavity and external tendons ........................ 64
Figure 6-1. Concrete material unit price ......................................................................................... 66
Figure 6-2. Concrete material cost comparison .............................................................................. 68
Figure 6-3. Total concrete cost comparison .................................................................................... 68
Figure 6-4. Prestressing tendon cost comparison ............................................................................ 69
Figure 6-5. Cost comparison of stirrups and minimum reinforcing steel ....................................... 71
Figure 6-6. Cost distribution of stirrups and minimum reinforcing steel ........................................ 72
Figure 6-7. Total reinforcing steel cost comparison ....................................................................... 73
Figure 6-8. Total superstructure material cost comparison ............................................................. 74
Figure 6-9. Total superstructure cost comparison (including cost of concrete placement)............. 75
ix
Figure 6-10. Total construction cost comparison ............................................................................ 78
Figure 6-11. Total construction cost comparison (+50% concrete unit price) ................................ 80
Figure 6-12. Total construction cost comparison (-50% concrete unit price) ................................. 80
Figure 6-13. Total construction cost comparison (+50% prestressing tendon unit price)............... 81
Figure 6-14. Total construction cost comparison (-50% prestressing tendon unit price) ............... 81
Figure 6-15. Total construction cost comparison (+50% reinforcing steel unit price) ................... 82
Figure 6-16. Total construction cost comparison (-50% reinforcing steel unit price) .................... 82
Figure 6-17. Total construction costs under changes in construction cost breakdown ................... 84
Figure 7-1. Cast-in-place on falsework box-girder with L=50m .................................................... 87
Figure 7-2. Cast-in-place on falsework solid slab with L=30m ...................................................... 88
Figure 7-3. Precast segmental span-by-span box-girder with L=50m ............................................ 89
Figure 7-4. Visual effects of increasing span-to-depth ratios from 10 to 35................................... 90
Figure 7-5. Effect of increasing span length (box-girder with h=2.5m) ......................................... 91
Figure 7-6. Viewed from 300m ....................................................................................................... 92
Figure 7-7. Viewed from 150m ....................................................................................................... 92
Figure 7-8. Viewed from 75m ......................................................................................................... 92
Figure 7-9. Effects of pier width-to-height ratio and span-to-depth ratio ....................................... 93
Figure 7-10. Effect of span-to-depth ratio as viewing angle becomes less oblique ........................ 94
Figure 7-11. Effect of bridge height on perceived superstructure slenderness ............................... 95
Figure 7-12. Effect of pier configuration on perceived superstructure slenderness ........................ 95
Figure 7-13. Effect of deck cantilever length on perceived superstructure slenderness ................. 96
Figure 7-14. Glenfinnan Viaduct, 1901 (Cortright 1997) ............................................................... 97
Figure 7-15. Slender bridges by Maillart ........................................................................................ 98
Figure 7-16. Waterloo Bridge over the Thames (Darger 2002) ...................................................... 99
Figure 7-17. Changis-sur-Marne Bridge, 1948 (Mossot 2007) ....................................................... 99
Figure 7-18. Sketches to evaluate aesthetic impact of span-to-depth ratios (O'Connor 1991) ....... 99
Figure 7-19. Neckar Valley Viaduct, 1977 (Leonhardt 1982) ...................................................... 100
Figure 7-20. Kocher Valley Viaduct, 1979 (Leonhardt 1982) ...................................................... 100
Figure 7-21. Pregorda Bridge, 1974 (Menn) ................................................................................. 101
Figure 7-22. Felsenau Bridge, 1974 (Menn) ................................................................................. 101
Figure C-1. Cast-in-place on falsework box-girder with L=50m.................................................. 130
Figure C-2. Cast-in-place on falsework solid slab with L=25m ................................................... 130
Figure C-3. Precast segmental span-by-span box-girder with L=40m.......................................... 130

x
LIST OF TABLES
Table 1-1. Description of recommended ratios ................................................................................. 3
Table 2-1. Summary of cast-in-place box-girders............................................................................. 7
Table 2-2. Summary of cast-in-place slabs (continued) .................................................................. 13
Table 2-3. Summary of precast segmental box-girders................................................................... 16
Table 3-1. Material properties ......................................................................................................... 21
Table 3-2. Material resistance factors (CSA 2006) ......................................................................... 21
Table 3-3. Prestressing tendon properties (CSA 1982) ................................................................... 21
Table 3-4. Corrugated metal duct properties (DSI 2008)................................................................ 21
Table 3-5. Concrete cover requirements (CSA 2006) ..................................................................... 22
Table 3-6. Load combination .......................................................................................................... 22
Table 3-7. Load factors ................................................................................................................... 22
Table 3-8. DLA factor (CSA 2006) ................................................................................................ 23
Table 3-9. Multi-lane loading modification factor (CSA 2006) ..................................................... 23
Table 4-1. Summary of structural response and dimensioning of cast-in-place on falsework box-
girder ................................................................................................................................................. 31
Table 4-2. Summary of material consumptions for cast-in-place on falsework box-girder ............ 34
Table 4-3. Results from beam model and strip method .................................................................. 42
Table 4-4. Summary of structural response and dimensioning of cast-in-place on falsework solid
slab .................................................................................................................................................... 43
Table 4-5. Concrete strengths required to satisfy maximum reinforcement criterion ..................... 44
Table 4-6. Summary of material consumption for cast-in-place on falsework solid slab ............... 46
Table 5-1. Prestress losses due to friction ....................................................................................... 58
Table 5-2. Prestress losses due to anchorage set ............................................................................ 58
Table 5-3. Prestress losses due to creep and shrinkage ................................................................... 59
Table 5-4. Effective prestress after all losses .................................................................................. 59
Table 5-5. Prestress at ULS............................................................................................................. 61
Table 5-6. Summary of structural response of precast span-by-span box-girder ............................ 61
Table 5-7. Summary of material consumption for precast span-by-span box-girder ...................... 63
Table 6-1. Material unit prices ........................................................................................................ 65
Table 6-2. Concrete material unit price........................................................................................... 66
Table 6-3. Comparison of changes in cross-sectional depth and prestressing demand................... 70
Table 6-4. Total superstructure cost variations ............................................................................... 76

xi
Table 6-5. Construction cost breakdown (Menn 1990)................................................................... 77
Table 6-6. Material unit price changes ............................................................................................ 79
Table 6-7. Summary of material unit price sensitivity analysis ...................................................... 83
Table 6-8. Summary of cost study .................................................................................................. 85
Table C-1. Summary of results of cast-in-place on falsework box-girder analysis ...................... 127
Table C-2. Summary of results of cast-in-place on falsework solid slab analysis ........................ 128
Table C-3. Summary of results of precast segmental span-by-span box-girder analysis.............. 129

xii
LIST OF SYMBOLS

A Gross cross-sectional area


Ac Area of concrete
Ap Area of prestressing steel
As Area of reinforcing steel
Av Stirrup area
C Compressive force
c Depth of compression region
e(x) Eccentricity of tendon at location x
Ec Concrete elastic modulus
Ep Prestressing tendon elastic modulus
Es Reinforcing steel elastic modulus
f’c Concrete compressive strength
fcr Concrete tensile strength
fpu Prestressing tendon ultimate strength
fpy Prestressing tendon yield stress
fr Free stress due to temperature gradient
fy Reinforcing steel yield stress
h Girder depth
I Moment of inertia
Ic Moment of inertia of gross uncracked concrete section
L Span length
L/h Span-to-depth ratio
lp Arc length of tendon between anchors
mop Moment when qp is applied to prestressing band
mp Moment when qp is applied to slab
Mr Flexural resistance
Mr Restraint moment
MSLS SLS moment demand
msp Self-equilibrating moment in strip method
MULS ULS moment demand
n Distance from base of cross-section to neutral axis (Section 5.3.2); Ep/Ec (Section
5.4.2)

xiii
P Prestressing force
P0 Jacking force
Pr Axial restraint force
qp Prestressing deviation force
S Sectional modulus
s Stirrup spacing
T Tensile force
z Moment lever arm
α(x) Sum of angle changes of tendon between stressing locations and point x
αc Thermal coefficient of concrete
αD Dead load factor
αp Prestress load factor
αx Intentional angle change of tendon
∆ Deflection
∆P Loss of prestress force
∆α Unintentional angle change of tendon
∆σp,rel Prestress loss due to relaxation of steel
ε0 Final strain
εc Concrete strain
εcs (t) Time-varying shrinkage strain
εcu Ultimate strain for concrete
εf Free strain due to temperature gradient
θ(y) Thermal differential
μ Coefficient of friction
σp0 Jacking stress
σp∞ Effective prestress after all losses
φ(t) Creep coefficient
φc Concrete resistance factor
φp Prestressing tendon resistance factor
φs Reinforcing steel resistance factor
ψ Final curvature of bending

xiv
1 INTRODUCTION
1.1 The Significance of Optimizing Span-to-Depth Ratio
Span-to-depth ratio, also known as slenderness ratio (L/h), is an important bridge design
parameter that relates a bridge’s span length to its girder depth. In the industry, this ratio is usually
used to establish the superstructure depth and is chosen during the conceptual design phase before
detailed calculations are performed. Selecting the ratio at an early stage of the design process
permits approximate dimensional proportioning which is needed for preliminary analysis to
evaluate the feasibility, cost-efficiency, and aesthetic merits of the design in comparison with
alternative design concepts (ACI-ASCE 1988). The ratio is commonly chosen based on experience
and typical values used in previously constructed bridges with satisfactory performance in order to
ensure that the design does not deviate drastically from past successful practice. The ratio can also
be determined by optimizing the combination of span length and superstructure depth to create a
cost-efficient and aesthetically-pleasing structure, but this generally involves an iterative process.
Therefore, instead of optimizing the span-to-depth ratio for every design concept, it is more
common to select ratios from a range of conventional values.
The choice of slenderness ratio is particularly critical in the design of girder-type bridges,
because it directly affects the cost of materials and construction of the superstructure. For instance,
using a high ratio (i.e. slender girder) reduces the concrete volume, increases the prestressing
requirement, and simplifies the construction due to a lighter superstructure. Moreover, slenderness
ratio has significant aesthetic impact, because the overall appearance of a girder-type bridge is
highly dependent on the proportion of the superstructure (Leonhardt 1982).
As stated previously, despite the significance of span-to-depth ratio, the industry has generally
relied on the same proven range of ratios over the past decades. Figures 1-1 to1-3 show the
recommended ranges of slenderness ratios outlined in different publications for three types of
prestressed concrete constant-depth girders: cast-in-place box-girder, cast-in-place slab, and precast
segmental box-girder. A brief description of the recommendations from each publication is given in
Table 1-1.

1
2

40

ACI-ASCE 1988
30
AASHTO 1994
Duan et al. 1999
Span-to-
depth Leonhardt 1979
20 Hewson 2003
ratio
Menn 1990
Leonhardt 1979 Cohn & Lounis 1994
10

Multiple-cell box-girder
Incremental launching method
0
1975 1980 1985 1990 1995 2000 2005 2010
Year
Figure 1-1. Recommended ratios for cast-in-place box-girder

50

40 ACI-ASCE 1988
AASHTO 1994
Cohn & Lounis 1994
30
Span-to- Menn 1990
depth
Cohn & Lounis 1994
ratio 20 Hewson 2003
Leonhardt 1979

10
Voided slab

Solid slab
0
1975 1980 1985 1990 1995 2000 2005 2010
Year
Figure 1-2. Recommended ratios for cast-in-place slab

25

ACI-ASCE 1988
20

AASHTO-PCI-ASBI 1997 Gauvreau 2006


15
Span-to-
depth Duan et al. 1999
ratio 10

0
1975 1980 1985 1990 1995 2000 2005 2010
Year

Figure 1-3. Recommended ratios for precast segmental box-girder


3

Table 1-1. Description of recommended ratios


Author Year Description
Leonhardt 1979 Fritz Leonhardt, a Professor of Civil Engineering at the University of Stuttgart, suggests ratios
based on values from previously constructed prestressed concrete bridges with good
performance. For cast-in-place single-cell box-girder, a ratio of 21 is recommended. The
suggested ratio is lowered to around 12 to 16 when incremental launching method is used due
to the large negative construction moments associated with this construction method. For cast-
in-place slab, he suggests values from 18 to 36, with the higher values used for longer spans
and for bridges with lighter traffic.
ACI-ASCE 1988 The American Concrete Institute-American Society of Civil Engineers (ACI-ASCE) Committee 343
on Concrete Bridge Design defines span-to-depth ratio recommendations for common bridge
types based on typical values. These recommendations are intended to provide general
guidelines for preliminary design. For cast-in-place, post-tensioned multiple-cell box-girder,
ACI-ASCE recommends ratios from 25 to 33. The recommended ratio for precast multiple-cell
continuous box-girder is around 22. These ratios are higher than the ones for single-cell box-
girder, because a multiple-cell box section has more webs to accommodate tendons compared
to a single-cell section with similar width. The recommended range of ratios is between 24 and
40 for cast-in-place, post-tensioned slab.
Menn 1990 Christian Menn is a Professor of Structural Engineering at the Institute of Structural Engineering
in Zurich. His suggestions are based on existing bridges with satisfactory performance in terms
of structural behaviour, aesthetics, and economics. He recommends ratios between 17 and 22
for cast-in-place box-girders, because girders with ratios below 17 would appear too heavy. On
the other hand, girders with ratios above 22 have substantial cost increase due to the
significantly higher longitudinal prestressing demand. Menn also suggests a maximum practical
limit of 25 for solid slab and a maximum cost-effective slab depth of 0.8m.
AASHTO 1994 The American Association of State Highway and Transportation Officials (AASHTO) defines
optional criteria for span-to-depth ratios in Cl.2.5.2.6.3 of the LRFD Bridge Design
Specifications. These values are based on traditional maximum ratios of constant-depth
continuous highway bridges with adequate vibration and deflection response. To ensure
proper vibration and deflection behaviours, the maximum ratios are determined to be 25 for
cast-in-place box-girder and 37 for cast-in-place slab.
Cohn & 1994 M.Z. Cohn is a Professor of Civil Engineering at the University of Waterloo and the span-to-
Lounis depth ratios suggested in this paper are part of the results of a Ph.D. thesis prepared by Z.
Lounis. These ratios are established from a systematic, multi-level optimization approach that
determines the ideal cross-sectional dimensions, span layouts and superstructure system based
on cost, material consumption, and aesthetics. For cast-in-place single-cell box-girder, the
optimum ratio is found to range from 12 to 20. The ratio increases with span length and
decreases with bridge width (e.g. a ratio of 12 corresponds to a span of 20m and a width of
16m while a ratio of 20 corresponds to a span of 50m and a width of 8m). This range of ratios is
slightly lower relative to the ones from other publications, because this study investigates a
simply-supported system while the ratios from other publications are mostly based on
continuous systems. A simply-supported girder tends to be deeper since it experiences greater
moments at midspan compared to a continuous structure. Cohn & Lounis also suggest the
range of optimum ratios for voided and solid slabs are 22 to 29 and 28 to 33 respectively.
AASHTO- 1997 The American Segmental Bridge Institute (ASBI) has established various standard precast
PCI-ASBI sections for segmental construction to enhance uniformity and simplicity for forming and
production methods. Using these standard sections generally lead to practical and cost-
effective solutions. The ranges of span-to-depth ratios obtained from these standard sections
are 17 to 19 for span-by-span method and 17 to 20 for balanced cantilever method.
Duan et al. 1999 Lian Duan is a Senior Bridge Engineer with the California Department of Transportation and a
Professor of Structural Engineering at Taiyuan University of Technology in China. A span-to-
depth ratio of 25 is recommended for cast-in-place multiple-cell box-girder based on typical
values from existing bridges. A range of ratios from 12.5 to 20 is recommended for precast
segmental box-girder. This range is based on frequently used standard precast sections from
Federal Highway Administration (FHWA).
4

Table 1-1. Description of recommended ratios (continued)


Author Year Description
Hewson 2003 Nigel Hewson is a recognized expert in the design and construction of prestressed bridges and
is an Associate Lecturer at the University of Surrey on this subject. He suggested a span-to-
depth ratio of 20 for cast-in-place single-cell box-girder and a maximum ratio of 20 for cast-in-
place voided slab. Both of these recommendations are based on typical values.
Gauvreau 2006 A span-to-depth ratio of 17 is recommended for precast segmental span-by-span constructed
box-girder. This value corresponds to the lower limit of span length used for this construction
method (30m) and the minimum height requirement of a box section to provide sufficient
access space within the box (1.8m). The recommended ratio is lower than the one for cast-in-
place box-girder, because a larger depth is needed to compensate for the reduced tendon
eccentricity due to the use of external unbonded tendons.

As shown in the previous graphs, there has been no significant increase in the recommended
span-to-depth ratio since 1979 despite the advancement in material strengths and construction
technologies. Recent developments have resulted in high-strength materials which theoretically
should lead to more slender structural components and longer span lengths. In particular, high-
strength concrete with compressive strength of 40 to 140 MPa has been achieved by lowering the
water-to-cement ratio and incorporating chemical admixtures (Kosmatka et al. 2002). Because of
their enhanced mechanical properties like higher ultimate strengths and modulus of elasticity, high-
strength concrete structures can resist the same level of loads using slenderer sections, resulting in
lightweight structures. The reduction in self-weight is especially critical in long-span bridges,
because the dead load consumes approximately 75% of the load-bearing capacity in long-span
bridges constructed with normal-strength concrete (TRB 1990). High-strength concrete lowers the
dead load contribution by using thinner sections and improves the load-bearing capacity by
increasing strength, thus slenderer bridges with longer spans can be attained.
High-strength concrete has been applied to various types of structures. For instance, concrete
with compressive strength of 60 MPa is commonly used for large bridges in Europe (Muller 1999)
while the building industry has been using concrete with strengths of over 100 MPa for years
(Hassanain 2002). However, most short- and medium-span bridges are being constructed with
concrete strengths of less than 50 MPa, because high-strength concrete is more expensive,
especially if the designer still uses the typical span-to-depth ratios as defined decades ago based on
normal-strength concrete (Hassanain 2002). For instance, the unit price of concrete rises by about
68% when the compressive strength changes from 30 MPa to 60 MPa (Dufferin Concrete 2009).
This indicates a substantial material cost increase if the same guidelines for superstructure
proportioning of normal-strength concrete bridges are applied to high-strength concrete bridges,
causing the application of high-strength concrete in bridges to be economically unfeasible.
Therefore, with the advent of high-strength materials, recommended span-to-depth ratios need to be
5

updated to match the improvement in material strength and stiffness and to provide an economic
incentive for the application of these materials in bridges.

1.2 Objectives and Scope


The purpose of this thesis is to determine the ideal range of span-to-depth ratios for post-
tensioned girder bridges constructed with current high-strength materials based on aesthetic
comparisons and optimization parameters such as material consumption and total construction cost.
The three bridge types considered in this study are cast-in-place on falsework box-girder and solid
slab, and precast segmental span-by-span box-girder. The objectives of this study are summarized
as follows:
 Provide a study on the evolution of span-to-depth ratios in concrete girder bridges
constructed over the past 50 years and establish a range of conventional ratios.
 Determine the amount of prestressing and the concrete strength needed to satisfy safety
and serviceability requirements as a function of span-to-depth ratio for the three types
of bridge considered.
 Compare the material consumptions and total construction costs for bridges with
different slenderness ratios and determine the most cost-effective ratios.
 Investigate the sensitivity of the construction cost results with respect to changes in
material unit cost and construction cost breakdown.
 Examine the visual impact of different span-to-depth ratios and especially evaluate the
aesthetic influence of using the cost-effective ratios instead of conventional ones.
 Update the recommendations for span-to-depth ratios based on economic and aesthetic
considerations.
The results of this research are expected either to confirm that the conventional ratios are already
optimal for new high-strength materials or to demonstrate that more slender sections can be attained.
The study focuses on the superstructure only while the prestressing and concrete strength
demands for the substructure are not explicitly accounted for. Also, only bridges with typical span
lengths are analyzed in this study: 35m to 75m for cast-in-place box-girder, 20m to 35m for cast-in-
place solid slab, and 30m to 50m for precast segmental box-girder.
6

1.3 Thesis Structure


The thesis is organized in eight chapters:
Chapter 1 provides the background and motivation of optimizing span-to-depth ratio.
Chapter 2 examines the span-to-depth ratios of existing bridges and discusses their changes over
the past 50 years. This information along with the span-to-depth ratio recommendations described
in Chapter 1 leads to values for conventional slenderness ratios. These conventional ratios serve as a
basis for cost and aesthetic comparisons in the later chapters.
Chapter 3 outlines the general analysis model and method used for all three bridge types. It also
provides a breakdown on all the analysis cases that need to be considered and discusses specific
design criteria that must be satisfied.
The specific analysis models and analysis results for cast-in-place on falsework box-girder and
solid slab, and precast segmental span-by-span box-girder are described in Chapter 4 and 5
respectively. Analysis results include structural responses, material consumptions, and factors that
limit further increase in slenderness ratio. The construction method and design issues unique to each
bridge type are also discussed.
Chapter 6 compares the material costs and total construction costs for bridges with varying
span-to-depth ratios for the three bridge types. Optimal ratios with the lowest costs are determined
and in particular, cost savings associated with using the optimal ratios instead of conventional ones
are examined. Furthermore, a sensitivity analysis is performed to demonstrate the effects of
changing unit costs and total construction cost breakdown on the analysis results.
Chapter 7 explores the aesthetic impacts of varying span-to-depth ratios and discusses the
public perception on visually optimal ratios.
Chapter 8 provides a conclusion for this study by summarizing the optimal span-to-depth ratios
for the three bridge types as well as their improvement over conventional ratios in terms of material
consumptions, construction costs, and aesthetics. These optimal ratios lead to updated span-to-depth
ratio recommendations for bridges constructed with current high-strength materials.
2 TYPICAL SPAN-TO-DEPTH RATIOS OF EXISTING BRIDGES
This chapter describes a study of 86 existing constant-depth girder bridges and presents a
compilation of their span-to-depth ratios. Specifically, the study determines the range of ratios
typically used in the industry and examines its variations over the past 50 years. Three bridge types
are considered: cast-in-place box-girder, cast-in-place slab, and precast box-girder. A majority of
these bridges has span-to-depth ratios within the suggested ranges discussed in Chapter 1, indicating
that a representative sample of bridges has been used.

2.1 Cast-in-Place Box-Girder


First, the study investigates 44 constant-depth cast-in-place box-girders. Table 2-1 provides the
basic information as well as a cross-sectional drawing for each bridge. Additional information,
including the span arrangement, girder dimensions, designer and references, is given in Appendix
A.1. Figure 2-1 shows the span-to-depth ratios with respect to the span lengths and compares these
ratios with the recommended values described in Section 1.1. Figure 2-2 plots the ratios with
respect to the completion years in order to illustrate the trend in slenderness ratio over time.
Table 2-1. Summary of cast-in-place box-girders
Bridge Span-to- Construction
Name Location Cross-section
no. depth ratio method

1 Grenz Bridge at Basel Switzerland 17.7 N/A

Incremental
2 Sart Canal-Bridge Belgium 12.0 N/A
launching

Weyermannshaus
3 Switzerland 18.9 N/A
Bridge

Eastbound Walnut
4 U.S.A. 23.0 CIP on falsework
Viaduct

Taiwan High Speed


5&6 Taiwan 11.4 Span-by-span
Rail (1) & (2)

Span-by-span on
7 Pregorda Bridge Switzerland 22.2
falsework

Almese Viaduct & Balanced


8&9 Italy 18.2
Condove Viaduct cantilever

Balanced
10 Gravio Viaduct Italy 18.2
cantilever

Legend:
N/A = no data Split cross-section:
CIP = cast-in-place

7
8

Table 2-1. Summary of cast-in-place box-girders (continued)


Bridge Span-to- Construction
Name Location Cross-section
no. depth ratio method

Balanced
11 Borgone Viaduct Italy 18.2
cantilever

Span-by-span on
12 Quadinei Bridge Switzerland 20.0
falsework

13 Altstetter Viaduct Switzerland 21.6 N/A

14 Reuss Bridge Switzerland 17.7 CIP on falsework

Balanced
15 Cerchiara Viaduct Italy 18.5
cantilever

Balanced
16 Castello Viaduct Italy 18.5
cantilever

Balanced
17 Costacole Viaduct Italy 18.5
cantilever

Ferroviario Overpass
18 Italy 28.1 N/A
at Bolzano

Incremental
19 Krebsbachtal Bridge Germany 12.9
launching

Incremental
20 Shatt Al Arab Bridge Iraq 12.8
launching

21 Ancona Viaduct Italy 20.7 Segmental

Felsenau Bridge Span-by-span on


22 Switzerland 16.0
(approaches) falsework

23 La Molletta Viaduct Italy 20.8 Segmental

Fosso Capaldo
24 Italy 20.8 Segmental
Viaduct

Sihlhochstrasse
25 Switzerland 29.5 N/A
Bridge

Grosotto Viaduct,
26 to Balanced
Grosio Viaduct, Italy 20.0
28 cantilever
Tiolo Viadut

29 Denny Creek Viaduct U.S.A. 20.9 N/A

Woronora River Incremental


30 Australia 14.7 N/A
Bridge launching
9

Table 2-1. Summary of cast-in-place box-girders (continued)

Bridge Span-to- Construction


Name Location Cross-section
no. depth ratio method

Balanced
31 Valentino Viaduct Italy 20.0
cantilever

Balanced
32 Giaglione Viaduct Italy 20.0
cantilever

Balanced
33 Venaus Viaduct Italy 20.0
cantilever

34 Passeggeri Viaduct Italy 20.0 Segmental

35 Brunetta Viaduct Italy 20.0 Segmental

36 Pietrastretta Viaduct Italy 20.0 Segmental

37 Deveys Viaduct Italy 20.0 Segmental

38 Gruyère Lake Viaduct Switzerland 15.1 Span-by-span

Interstate 895 Bridge


Balanced
39 over James River U.S.A. 21.3 N/A
cantilever
(approaches)

40 Lätten Bridge Switzerland 18.1 N/A

Savona Mollere
41 Italy 22.5 Segmental
Viaduct

42 Ruina Viaduct Italy 19.3 N/A

Span-by-span
43 Weinland Bridge Switzerland 22.6
on falsework

Balanced
44 Kocher Valley Bridge Germany 21.2
cantilever
10

Bridge No. 1 5 20 30 40 42 43 44
35 ||||||||| | ||| | || ||||| || | | | |

30 1974 ―

25 (Lian et al. , AASHTO,
and minimum value of
25
1958 ACI-ASCE)
1971 ―

1974 1994 ―

1984 ―

20 1992 20 (Hewson) ―

1967 ―
Span-to- ―

1992 1980 ―
depth 1992 1972
ratio 15 1975 1978 ―

2002 2001
1975 ―


10 2000

Incremental launching
5
*Shaded region = Menn's
range (17 to 22)
0
20 40 60 80 100 120 140 160
Span length (m)
Figure 2-1. Span-to-depth ratios of cast-in-place box-girders

Figure 2-1 demonstrates that all 44 cast-in-place box-girders have span lengths between 35.4m
and 138m as well as span-to-depth ratios that range from 11.4 to 29.5. The frequency plot on the top
shows that 42 out of 44 bridges (95%) investigated have span lengths from 35m to 75m which is the
typical range for constant-depth box-girders as suggested by Hewson (2003). Above the frequency
plot are bridge numbers that relate each data point to its corresponding bridge in Table 2-1. The
frequency plot on the right shows a large concentration of bridges that have span-to-depth ratios
between 17.7 and 22.6. In fact, 33 out of 44 bridges (75%) have ratios within the range of values
recommended by Menn (17 to 22) and Hewson (20) which are based on existing bridges with
satisfactory performance, indicating that the study sample is representative of typical bridges.
Most bridges have ratios below 25 which is the traditional maximum value that ensures
adequate vibration and deflection responses in cast-in-place box-girders according to American
design standards (AASHTO 1994). Only 2 bridges (i.e. bridge no. 18 and 25), one with a multiple-
cell box-girder and the other with twin parallel box-girders, have ratios above 25. These two bridges,
however, are within the range of ratios recommended by ACI-ASCE (1988) for post-tensioned cast-
in-place multiple-cell box-girders (25 to 33). Higher ratios are expected for these types of cross-
sections, because additional webs can help accommodate the large amount of prestressing tendons
associated with slender girders without sacrificing the efficiency of the tendon layout (i.e. lowering
the tendon eccentricity by placing tendons in vertical layers within the webs). Also, the decrease in
spacing between webs causes considerable reduction in transverse bending for wide cross-sections,
thus lowering the transverse prestressing requirement.
11

Furthermore, 6 bridges have ratios of less than 15. Out of these 6 bridges, 4 are constructed
with incremental launching which generally requires a deeper cross-section to resist the large
negative moments during construction. They have ratios between 12 and 16 which is the typical
range for incrementally launched single-cell box-girders recommended by Leonhardt (1979). The
other two are railway bridges which also need a larger depth due to the greater live loads and more
stringent serviceability requirements. For instance, ACI-ASCE (1988) suggested a typical span-to-
depth ratio of approximately 16 for cast-in-place multiple-cell box-girders that carry railroads.
Figure 2-2 describes the variation in span-to-depth ratios over time. Only 37 out of the 44
bridges investigated are included in this graph due to the lack of data on completion year. These 37
bridges were completed between 1958 and 2002, and no significant variation in span-to-depth ratios
is observed within this time span. The slenderness ratios commonly used by the industry have not
increased over time despite the improvements in material strengths and advancements in
construction technologies. As stated previously, 75% of these bridges follow the same guidelines
recommended by Menn in 1986 and Hewson in 2003.
35

30 ―

25 (Lian et al. , AASHTO,
25 and minimum value of
ACI-ASCE) ―





20 20 (Hewson) ―

Span-to- ―



depth

ratio 15 ―




10

Incremental launching
5
*Shaded region = Menn's
range (17 to 22)
0
1955 1965 1975 1985 1995 2005
Year
Figure 2-2. Span-to-depth ratios of cast-in-place box-girders
12

2.2 Cast-in-Place Slab


In addition to cast-in-place box-girders, 28 cast-in-place constant-depth slab bridges are also
investigated. Table 2-2 provides basic information as well as a cross-sectional drawing for each
bridge and the detailed bridge information is given in Appendix A.2. Figure 2-3 and 2-4 relate the
span-to-depth ratios to the span lengths and to the completion dates.
Table 2-2. Summary of cast-in-place slabs
Bridge Span-to- Construction
Name Location Cross-section
no. depth ratio method
45 Khandeshwar Bridge India 20.3 N/A N/A
Spadina Ave. Bridge #16, Hwy
46 Canada 22.2 CIP on falsework
401
Spadina Ave. Bridge #18A, Hwy
47 Canada 22.2 CIP on falsework
401

Spadina Ave. Bridge #18B, Hwy


48 Canada 22.2 CIP on falsework
401
Spadina Ave. Bridge #19, Hwy
49 Canada 22.2 CIP on falsework
401
Spadina Ave. Bridge #21A, Hwy
50 Canada 22.2 CIP on falsework
401

Spadina Ave. Bridge #21B, Hwy


51 Canada 22.2 CIP on falsework
401

52 Sindelfingen Footbridge Germany 55.7 N/A

53 L 333 Overpass at Bassum Germany 21.9 N/A N/A

54 Waiblingen Footbridge Germany 42.5 N/A N/A


Incremental
55 Mako Bridge Senegal 23.9 N/A
launching
56 Kittelbaches Bridge Germany 19.3 N/A N/A

57 San Francisco Airport Viaduct U.S.A. 19.2 N/A N/A

58 St. Vincent Street Overpass Canada 35.6 CIP on falsework

59 Bridge across Jan-Wellen-Platz Germany 25 N/A N/A

Spadina Ave. Bridge #14, Hwy


60 Canada 38.6 CIP on falsework
401

Spadina Ave. Bridge #15, Hwy


61 Canada 38.6 CIP on falsework
401

Spadina Ave. Bridge #12, Hwy


62 Canada 38.6 CIP on falsework
401

63 Saale Bridge at Rudolphstein Germany 20 N/A N/A


Bridge #20 at Hwy 401/427
64 Canada 31.7 CIP on falsework
Interchange

Spadina Ave. Bridge #5, Hwy


65 Canada 35.0 CIP on falsework
401

Spadina Ave. Bridge #11 Hwy


66 Canada 30 CIP on falsework
401
13

Table 2-2. Summary of cast-in-place slabs (continued)


Bridge Span-to- Construction
Name Location Cross-section
no. depth ratio method

Spadina Ave. Bridge #22, Hwy


67 Canada 30.5 CIP on falsework
401

Spadina Ave. Bridge #23, Hwy


68 Canada 31.2 CIP on falsework
401

69 Hundschipfen Bridge Switzerland 40.5 N/A N/A

70 McCowan Road Underpass Canada 37.9 CIP on falsework

Spadina Ave. Bridge #24, Hwy


71 Canada 33.4 CIP on falsework
401

Spadina Ave. Bridge #4, Hwy


72 Canada 34.7 CIP on falsework
401

Bridge No. 45 52 56 58 60 63 68 70 72
| | || ||| || | || || | | | |
60
1986

50
1996
2000 ―
1963 ―
40
1964

Span-to- 1963 37 (AASHTO)
1963 ―

depth 1963 1963 30.5 (Cohn & Lounis ―
1963 ―
ratio 30 for solid slab) ―
1961 1963
1975 25 (Menn, Cohn &
1993 ―
2000 Lounis for voided slab) ―
1992 1994 ―
20 1967 20 (Hewson for ―

voided slab)

10 Voided slab *Shaded region =


Leonhardt's range (18 to 36)
Solid slab
0
0 10 20 30 40 50 60
Span length (m)
Figure 2-3. Span-to-depth ratios of cast-in-place slabs

As shown in Figure 2-3, the 28 bridges have span lengths between 13.2m and 47.5m and span-
to-depth ratios from 19.2 to 55.7. The sample consists of 14 solid slabs and 14 voided slabs. Out of
the 14 solid slabs, 7 that were mostly built in the 1960s have span lengths greater than 20m which is
the current maximum economic span length for this type of slab (Gauvreau 2006). All voided slabs,
except for bridge no. 72, have spans of less than the maximum typical span length of 46m as
suggested by ACI-ASCE (1988). Also, most of the bridges (79%) have span-to-depth ratios that are
within Leonhardt’s recommended range of 18 to 36 and are below AASHTO’s maximum value for
14

adequate deflection and vibration behaviour. Since the majority of the sample has span-to-depth
ratios within Leonhardt’s suggested range and spans similar to conventional values, the sample is
fairly representative of typical slab bridges.
60

50


40 ―
Span-to- ―
37 (AASHTO)
depth ―

30.5 (Cohn & Lounis

ratio ―

30 for solid slab)
25 (Menn, Cohn & ―
Lounis for voided slab) ―

20 20 (Hewson for ―

voided slab)

10 Voided slab *Shaded region =


Leonhardt's range (18 to 36)
Solid slab
0
1960 1970 1980 1990 2000 2010
Year
Figure 2-4. Span-to-depth ratios of cast-in-place slabs

As shown in Figures 2-3 and 2-4, most of the bridges have span-to-depth ratios that cluster
around two ranges: 13 bridges (46%) have ratios between 19 and 25 while 13 bridges have ratios
between 30 and 40.5. The first range is composed of 7 solid slabs built in the 1960s and 6 voided
slabs built after 1970. The latter range consists of 6 solid slabs and 7 voided slabs which are all
constructed in the 1960s except for bridge no. 69. The remaining two bridges (bridge no. 52 and 54)
with higher ratios of 42.5 and 55.7 are both pedestrian bridges which can be more slender due to the
lower live load requirements. Therefore, there is a noticeable variation in the typical range of span-
to-depth ratios depending on the construction year and function of the bridge.
Figure 2-4 clearly illustrates the changes in typical span-to-depth ratios with respect to
construction year. Out of the 19 bridges completed prior to 1975, 12 (63%) have slenderness ratios
greater than 30 and 12 (63%) are solid slabs. Newer bridges are mainly voided slabs with lower
slenderness ratios at around 20 due to the stricter code requirements in recent years. For instance,
the Ontario Ministry of Transportation (MTO) sets the minimum non-prestressed reinforcement
clear cover to be 70±20 for the top surface of voided slabs in the MTO Structural Manual (2003)
while the value is only 50±20 in the Ontario Highway Bridge Design Code (OHBDC 1983).
Likewise, the MTO Structural Manual limits the maximum span-to-depth ratio to 28 for all post-
tensioned slabs while no such provisions existed prior to 1975 (Scollard and Bartlett 2004). As
shown in Figure 2-4, the first generation post-tensioned voided slabs constructed in the 1960s have
15

span-to-depth ratios of over 30 which required large amount of longitudinal prestressing. This
resulted in the formation of longitudinal cracks above the voids due to the large concentrated post-
tensioning forces near the abutments, which created transverse splitting stresses, and due to the
restraint of transverse concrete shrinkage imposed by the steel void forms. To solve this cracking
problem, MTO recommended the addition of transverse prestressing to prevent shrinkage cracking
and a decrease in span-to-depth ratio in 1975 in order to reduce the required prestressing force,
which eventually led to the current maximum span-to-depth ratio limit of 28 (Scollard and Barlett
2004). As a result, in this study, 6 out of the 9 bridges built after 1975 have span-to-depth ratios
below 28; the remaining 3 bridges are pedestrian bridges or European bridges.
As stated before, the typical span-to-depth ratios for slab bridges vary considerably with time
and bridge function. The impact of slab type (i.e. solid or voided), on the other hand, is not as
significant. According to the literature discussed in Chapter 1, the conventional span-to-depth ratios
for solid slab are expected to be higher than the ones for voided slab, because voided slabs are
commonly used to reduce self-weight for longer spans that require slabs thicker than 800mm (Menn
1990). In fact, the study by Cohn and Lounis (1994) suggested that the optimum depth for voided
slab is 12% to 20% thicker than the one for solid slab, resulting in optimum ratios of approximately
30.5 for solid slab and 25 for voided slab. The sample in this study indicates a small difference in
span-to-depth ratios between the two slab types. Voided slabs have ratios that range from 19 to 35
while the range is from 22 to 39 for solid slabs (excluding the pedestrian bridges). These results are
reasonable, because a voided slab is theoretically an intermediate cross-section between a solid slab
and a box-girder and its range of ratios is expected to be in between the ones from solid slab and
box-girder (i.e. 17 to 22 as determined in Section 2.1). The typical ratios of the voided slab might be
closer to those of the solid slab or of the box-girder depending on its component dimensions. For
instance, if the void diameter is less than 60% of the total slab depth, the longitudinal behaviour
would resemble a solid slab (O'Brien and Keogh 1999). In this sample, the mean ratio for solid slab
is 30 which is only slightly higher than the 27 for voided slab if all the bridges from 1960 to 2000
are considered. If only recently constructed bridges are considered (i.e. built after 1990), the
conventional ratio for voided slab would decrease to around 20 which is the same as Hewson’s
suggested value. There is no data for recently constructed solid slabs, but the conventional ratio for
solid slab is expected to follow the same trend when the entire sample is considered and be only
slightly higher than the value for voided slab.
16

2.3 Precast Segmental Box-Girder


In this section, 14 precast segmental box-girders are examined. Table 2-3 provides basic
information as well as a cross-sectional drawing for each bridge and the detailed bridge information
is given in Appendix A.3. Figures 2-5 and 2-6 relate the span-to-depth ratios to the span lengths and
the completion dates.
Table 2-3. Summary of precast segmental box-girders
Bridge Span-to-
Name Location Construction method Cross-section
no. depth ratio

Bukit Panjang LRT Segmental span-by-


73 Singapore 15.7
System 801 span

Segmental with
74 Wiscasset Bridge U.S.A. 17.5 N/A
launching girder

75 Chiovano Viaduct Italy 17 Segmental

76 Collecastino Viaduct Italy 17 Segmental

77 Fiumetto Viaduct Italy 17 Segmental

78 San Leonardo Viaduct Italy 17 Segmental

79 Petto Viaduct Italy 17 Segmental

80 Cadramazzo Viaduct Italy 16.7 Balanced cantilever

81 Fella IX Viaduct Italy 16.7 Balanced cantilever

82 Malborghetto Viaduct Italy 16.1 Balanced cantilever

83 Val Freghizia Viaduct Italy 16.8 Balanced cantilever

84 Fella IV Viaduct Italy 17.6 Balanced cantilever

Ngong Shuen Chau


85 China 18.8 Balanced cantilever
Viaduct

Sutong Bridge Approach


86 China 18.8 Balanced cantilever
(Nantong side)
17

Bridge No. 73 75 83 84 86
25 | | || | | | |

20 2007
2007 ―
1981
1992 1988 1985 ―
17 (Gauvreau) ―

1986


1986
15 1998
Span-to-
depth
ratio
10

*Shaded region = range from


Duan et al. (12.5 to 20)
0
0 10 20 30 40 50 60 70 80 90
Span length (m)
Figure 2-5. Span-to-depth ratios of precast segmental box-girders

25

20

17 (Gauvreau)




15
Span-to-
depth
ratio
10

*Shaded region = range from


Duan et al. (12.5 to 20)
0
1980 1985 1990 1995 2000 2005 2010
Year
Figure 2-6. Span-to-depth ratios of precast segmental box-girders

According to Figure 2-5, all 14 bridges have slenderness ratios between 15.7 and 18.8 which are
within the range of frequently used ratios suggested by Duan et al. (1999). Also, 13 bridges have
spans between 30m and 60m which is a feasible and cost-effective span range for precast segmental
constructed constant-depth girders recommended by ASBI (1997). Since most of the bridges in this
study sample have span-to-depth ratios and span lengths within standard ranges, these bridges are
assumed to be representative of typical precast segmental box-girders.
18

Moreover, out of the 14 bridges, 10 bridges (71%) have ratios within 5% from 17 which is the
recommended value for precast segmental span-by-span construction from Gauvreau (2006). The
lowest ratio is 15.7 for bridge no. 70 which is a railway bridge that requires a deeper girder to
satisfy the more stringent serviceability requirements. Also, Figure 2-6 indicates that the typical
span-to-depth ratios did not vary significantly from 1981 to 2007.

2.4 Concluding Remarks


This study examines the span-to-depth ratios of 86 constant-depth girder bridges in order to
determine the range of ratios typically used by the industry over the past 50 years. The slenderness
ratios with respect to span lengths for all of these bridges are illustrated in Figure 2-7. The average
span-to-depth ratio and the typical span lengths for each bridge type are also indicated on the graph.
70 Typical span lengths: CIP box-girder
35 to 75m (CIP box-girder)
CIP voided slab
30 to 60m (precast segmental box-girder)
60 15 to 48m (CIP slab) CIP solid slab

Precast segmental
50 box-girder

Span-to-
depth 40
ratio
Average ratios:
30 30 (CIP solid slab)
27 (CIP voided slab)

20 20 (CIP box-girder)
17 (precast
segmental
10 box-girder)

0
0 20 40 60 80 100 120 140
Span length (m)
Figure 2-7. Span-to-depth ratios for all bridge types

The primary findings of this investigation are summarized in Table 2-4. Average ratios within
the typical ranges are considered as the conventional ratios and are used as a basis of comparison in
this thesis.
Table 2-4. Summary of conventional span-to-depth ratios
Bridge type Range of span- Number of bridges Average Notes
to-depth ratios within this range ratio
Cast-in-place box-girder 17.7 to 22.6 33 out of 44 (75%) 20 Range varies little between 1958
and 2002
Cast-in-place voided slab 19 to 35 13 out of 14 (92%) 27 Conventional ratio is closer to 20
for bridges completed after 1990
Cast-in-place solid slab 22 to 39 12 out of 14 (86%) 30 Used mainly from 1961 to 1975
Precast segmental box- 15.7 to 18.8 14 out of 14 (100%) 17 Range varies little between 1981
girder and 2007
3 ANALYSIS OVERVIEW
This purpose of this analysis is to compute the amount of prestressing and the concrete strength
needed to satisfy design requirements for bridges with varying span lengths and span-to-depth ratios.
These material consumption results are then used to compute construction cost as a function of
span-to-depth ratio. By examining the variations in construction cost and aesthetic impacts, the
study determines the most cost-optimal ratios for different bridge types. The three post-tensioned
bridge types considered are cast-in-place on falsework box-girder, cast-in-place on falsework solid
slab, and precast segmental span-by-span box-girder.
This chapter describes the analysis model, material properties, applied loads, ultimate and
serviceability limit states design requirements, as well as some preliminary analysis assumptions.
The analysis is performed using the program SAP2000 and spreadsheet calculations.

3.1 Analysis Model


The analysis model is an 8-span highway viaduct with a straight profile. Typical plan and
elevation are shown in Figures 3-1.

Abutment Pier 1 Pier 2 Pier 3 Pier 4 Pier 5 Pier 6 Pier 7 Abutment

Design lane 1
Bridge Design lane 2
width CL Bridge
b Design lane 3
Design lane 4

Lend L L L L L L Lend
PLAN

Depth
h

ELEVATION

Figure 3-1. Typical plan and elevation

Two types of constant-depth cross-sections are investigated: single-cell box-girder and solid
slab. Both types have 0.5m wide barriers, 90mm thick wearing surface and 3.5m wide design lanes
as shown in Figure 3-2. Proportions of other cross-sectional components vary for different
construction methods and are discussed in greater details in Sections 4.2.1.1, 4.3.1.1, and 5.2.1.
Barrier CL
90mm thick wearing surface
Design Lane 1 Design Lane 2 Design Lane 3 Design Lane 4

500 3500 3500 3500 3500 500

Figure 3-2. Typical deck arrangement

19
20

In the analysis, the span length and span-to-depth ratio are varied in the model to generate the
analysis cases illustrated in Figure 3-3. It should be noted that for cast-in-place on falsework box-
girders, cases with spans of 75m are included in the study mainly for comparison purposes. In the
industry, however, such long spans are generally constructed with cantilever method in regions
where high labour costs deter the extensive use of falsework.
L = 35m
L/h = 10, 15, 20, 25

L = 50m
L/h = 10, 15, 20, 25, 30
Cast-in-place on falsework
box-girder
L = 60m
L/h = 10, 15, 20, 25, 30, 35

L = 75m
L/h = 10, 15, 20, 25, 30, 35

L =20m
L/h = 30, 35, 40, 45

L = 25m
L/h = 30, 35, 40, 45
8-span highway viaduct Cast-in-place on falsework
solid slab
L = 30m
L/h = 30, 35, 40, 45, 50

L = 35m
L/h = 30, 35, 40, 45, 50

L = 30m
L/h = 15, 20, 25

Precast segmental, span-by- L = 40m


span box girder L/h = 15, 20, 25, 30

L = 45m
L/h = 15, 20, 25, 30
Legend:
L = span length
L/h = span-to-depth ratio

Figure 3-3. Summary of analysis cases


21

3.2 Materials
Tables 3-1 and 3-2 summarize the material properties and resistance factors used in the analysis.
To illustrate the effects of high-strength materials on span-to-depth ratios, a concrete compressive
strength of 50 MPa is used in the analysis, because this value is the minimum strength requirement
of high performance concrete as defined by MTO (OPSS 2007).
Table 3-1. Material properties
Material Property Value
1
Concrete
Compressive strength f’c = 50 MPa
Tensile strength fcr = 2.8 MPa = 0.4 fc′ (CSA 2006)
Elastic modulus Ec = 28100 MPa
γc 1.5
= 3000 fc′ + 6900 (CSA 2006)
2300
2
Prestressing tendons
Ultimate strength fpu = 1860 MPa
Yield stress fpy = 0.9 fpu = 1670 MPa
Effective prestress after all losses σp∞ = 0.6fpu = 1120 MPa
Elastic modulus Ep = 200000 MPa
2
Reinforcing steel bars
Yield stress fy = 400 MPa
Elastic modulus Es = 200000MPa
1
For solid slab analysis, higher concrete strengths (i.e. up to 80 MPa) are used for slender cases.
2
For prestressing tendons and reinforcing steel bars, a bilinear stress-strain relationship is used:
fp = Ep εp ≤ fpy
fs = Es εs ≤ fy

Table 3-2. Material resistance factors (CSA 2006)


Material Resistance factor φ
Concrete φc = 0.75
Prestressing strands φp = 0.95
Reinforcing steel bars and wires φs = 0.90

3.2.1 Prestressing Tendons


All analysis cases utilize size 15 seven-wire low-relaxation strands as prestressing tendons and
standard size corrugated metal ducts with properties summarized in Tables 3-3 and 3-4.

Table 3-3. Prestressing tendon properties (CSA 1982)


Property Value
Nominal diameter 15.24 mm
2
Nominal Area 140 mm
Mass 1.109 kg/m

Table 3-4. Corrugated metal duct properties (DSI 2008)


# strands Outer diameter (mm) Minimum block-out diameter (mm) Transition length (mm)
12 94 254 508
15 97 279 575
19 106.3 305 640
27 121.4 343 702
37 138.4 407 890
22

The minimum clear distance between adjacent ducts is 40mm according to the Canadian
Highway Bridge Design Code (CHBDC) (CSA 2006). A horizontal spacing of about the duct
diameter is used between tendons to provide sufficient space for concrete placement and vibration.

3.2.2 Concrete Covers


Concrete cover requirements and tolerances from CHBDC are used (Table 3-5). The bridge is
assumed to be exposed to the most severe environmental category (i.e. de-icing chemicals, spray or
surface runoff containing de-icing chemicals, marine spray).

Table 3-5. Concrete cover requirements (CSA 2006)


Component Reinforcement or steel ducts Concrete covers (mm)
Cast-in-place Precast
Reinforcing steel 40 ± 10 40 ± 10
Top surface of bottom slab
Post-tensioning ducts 60 ± 10 60 ± 10
Top surface of top slab Post-tensioning ducts 130 ± 15 120 ± 10
Reinforcing steel 50 ± 10 45 ± 10
Soffit of top and bottom slabs
Post-tensioning steel 70 ± 10 65 ± 10
Reinforcing steel 70 ± 10 60 ± 10
Vertical surfaces
Post-tensioning ducts 90 ± 10 80 ± 10

3.3 Loads
Dead loads, live loads (truck and lane), and prestress loads based on CHBDC are used in the
analysis. Thermal gradient effects are considered only in the precast segmental box-girder analysis
because they are more critical for precast girders which do not have continuous bonded steel.

3.3.1 Load Combinations and Load Factors


The load combinations and load factors used in the analysis under ultimate and serviceability
limit states are summarized in Table 3-6 and Table 3-7 (CSA 2006). Fatigue limit state is not
considered in the analysis, because the concrete is kept uncracked at service and the steel does not
experience large stress cycles.

Table 3-6. Load combination Table 3-7. Load factors


Permanent loads Transitory loads Dead load Load factor αD
Loads D P L K Precast concrete 1.10
Ultimate limit states Cast-in-place concrete 1.20
ULS1 αD αP 1.70 0 Barriers 1.20
ULS2 αD αP 0 0 Wearing surfaces 1.50
Serviceability limit states
SLS1 1.00 1.00 0.90 0.80 Prestress load Load factor αP
SLS2 0 0 0.90 0 Secondary prestress 0.95
SLS3 1.00 1.00 0 0 effects

Legend:
D = dead load L = live load
P = secondary prestress effects
K = effects of strains due to temperature differential
23

As shown in Table 3-6, load combinations ULS2 and SLS3 only consider permanent loads.
Without live loads, longitudinal tendons push the bridge upward while there might not be enough
dead load to weigh the bridge down. Therefore, this load combination must be checked to ensure
ULS and SLS requirements are satisfied when the bridge is hogging. This is particularly critical for
slender bridges since they have large prestressing forces and small dead loads. On the other hand,
load combination SLS2 considers pure live loads when the bridge is loaded with only one CHBDC
CL-625 truck; this combination is used for superstructure vibration check.

3.3.2
Axle no. Live1 Loads 2 3 4 5
Axle loads, kN 50 125 125 175 150
The live loads considered in the analysis comprise of CL-625 truck and CL-625 lane loads as
illustrated in Figure 3-4.
3.6 m 1.2 m 6.6 m 6.6 m
Axle no. 1 2 3 4 5
18 m
Axle loads, kN 50 125 125 175 150
CL-625 Truck Load

3.6 m 1.2 m 6.6 m 6.6 m

18 m
CL-625 Truck Load
Uniformly distributed load 9kN/m

Axle loads, kN 40 100 100 140 120

3.6 m 1.2 m 6.6 m 6.6 m


Uniformly distributed load 9kN/m
18 m
Axle loads, kN 40 100 100 140 120
CL-625 Lane Load
Figure 3-4. Live loads: CL-625 truck load (top); CL-625 lane load (bottom)

The CL-625 truck


3.6 m load is1.2increased
m by a 6.6
dynamic
m load allowance (DLA)
6.6 m factor for SLS1 and

ULS load combinations as shown in Table 3-818(CSA


m
2006, Cl. 3.8.4.5.3). This DLA factor accounts
CL-625 Lane Load
for the load increase due to impact from truck vibrations and it depends on the number of axles that
are loaded to produce the maximum force effect. The more the axles, the lower is the DLA factor,
because the probability of all of the axles being in phase is low. Furthermore, the model is under
multi-lane loading and the traffic load moments are modified according to the number of design
lanes loaded to produce maximum force effects as shown in Table 3-9. These modification factors
account for the probability of simultaneously loading more than one lane.
Table 3-8. DLA factor (CSA 2006) Table 3-9. Multi-lane loading modification factor (CSA 2006)
# of axles loaded DLA factor # of loaded design lanes Modification factor
1 1.40 1 1.00
2 1.30 2 0.90
3 or more 1.25 3 0.80
4 0.70
5 0.60
6 or more 0.55
24

3.4 Design Requirements


All analysis cases are designed to satisfy CHBDC ULS and SLS requirements by increasing the
amount of prestressing tendons and stirrups. Also, for the solid slab analysis, concrete strengths are
increased (up to 80 MPa) in order to reduce the prestressing demands in slender cases since the
dimensions of such cases cannot accommodate the large amount of tendons required to satisfy ULS.
The ULS check consists of flexural and shear strength requirements while the SLS check includes
stress, vibration and deflection limitations. In the analysis, such design checks only consider
longitudinal behaviour and ignore transverse behaviour based on the assumption that transverse
reinforcement demands remain constant for analysis cases with the same span lengths and bridge
type. This assumption is valid, because transverse behaviour depends highly on live loads which are
the same for cases with the same span lengths. Although dead loads vary for these analysis cases,
they contribute very little to the transverse calculations due to the small influence lengths. This
assumption does not affect the results of this comparative study in which comparisons are made
between bridges with the same span length but different span-to-depth ratios, and the relative values
of material consumptions and construction costs are more important than the actual values.

3.4.1 Ultimate Limit States Design Requirements


This section describes the ultimate limit states design requirements which include flexural and
shear strength checks.

3.4.1.1 Flexural Strength


In ULS, the flexural resistance (Mr) is a pure couple between compression in the concrete and
tension in the longitudinal prestressing tendons. The analysis assumes that other non-prestressed
reinforcements do not contribute to flexural strength and that cracked concrete has no tensile
strength. Also, an equivalent rectangular concrete stress distribution is used as shown in Figure 3-5.

εc = 3.5x10-3 α1fc’
φ a= C
c β1c
z Mr = Tz

fpy T = φpApfpy
Strain Stress Forces

Figure 3-5. Flexural resistance: a) cross-section, b) concrete stains, c) equivalent concrete stresses, d) concrete forces

Therefore, Mr = T∙z = φpfpyApz for cases with bonded tendons in which the changes in tendon
strain are assumed to be equal to the changes in strain of the surrounding concrete. A sample
calculation is shown in Appendix B.1. For cases with unbonded tendons (i.e. span-by-span box-
girders), this assumption is no longer valid and a different approach is used (refer to Section 5.5).
25

Furthermore, since the analysis model is a statically indeterminate system, negative bending
moments exist around the supports. In such regions, the bottom slab thickness of the box-girder is
proportioned such that the compressive depth c is within the bottom flange.
Other flexural requirements that are considered include minimum and maximum reinforcement
requirements. The first requirement states that the flexural resistance must be greater than 1.2 times
the cracking moment (Mcr) or 1.33 times the moment demand at ULS, whichever value is smaller
(CSA 2006, Cl. 8.8.4.3). The second requirement states that c/d should be less than 0.5 (refer to
Figure 3-5) (CSA 2006, Cl. 8.8.4.5). This requirement ensures that the steel has yielded when the
concrete crushes at a strain of 0.0035 at the extreme compression fibre and that significant plastic
deformation has developed prior to failure.

3.4.1.2 Shear Strength


The CHBDC sectional design model is used to compute shear strengths and a sample shear
calculation is shown in Appendix B.2. Shear resistance (Vr) comprises of three components:
concrete, prestressing tendons, and stirrups. Concrete shear resistance depends on the cross-section
while the prestressing shear resistance depends on the vertical component of prestressing force
which is determined by flexural requirements. Therefore, the only independent variable that can
increase shear strength is the amount of stirrups. In the analysis, the stirrups are at least 20M and the
minimum spacing of stirrups is 300mm as required by CHBDC to support longitudinal tendon ducts
and this spacing is reduced if it does not provide sufficient shear resistance (CSA 2006, Cl. 8.14.6).
Each analysis case uses at most two different stirrup spacing since further discretization yields little
changes in the final results as shown in Figure 3-6.

$2,500 $2,290 $2,273 $2,271 $2,270

$2,000

$1,500
Cost per Steel cost
deck area
$1,000
($/m2)
Total construction cost
$500 $277 $260 $258 $257

$0
1 2 3 4
Number of stirrup spacing
Figure 3-6. Construction cost economy from increasing the number of stirrup spacing

Figure 3-6 compares the cost results of for an analysis case when the number of stirrup spacing
increases from one to four. The graph is obtained by computing the material consumption and total
construction cost for a span-by-span constructed, precast segmental box-girder with a span length of
40m and span-to-depth ratio of 20. As the number of stirrup spacing increases, the amount of
26

stirrups needed decreases, because the stirrup layout is further refined to match the shear demand.
This trend is illustrated in the graph, but the graph also indicates that the savings in steel diminishes
as the number of stirrup spacing increases beyond two. For instance, the steel cost decreases by 6%
when two spacing instead of one spacing are used. On the other hand, the steel cost decreases by
only 1% when the number of spacing increases from two to four. Therefore, only two different
stirrup spacing are used in the analysis.

3.4.2 Serviceability Limit States Design Requirements


This section describes the serviceability limit states design requirements which comprise of
stress, vibration and deflection limitations.

3.4.2.1 Stress
For SLS stress checks, CHBDC poses crack width limitations if the stress exceeds concrete
cracking stress. This study, however, uses a more conservative approach in which cracking is not
permitted during service in order to minimize durability issues. The concrete stress needs to be less
than the tensile strength of concrete in order to avoid cracking:
M SLS P [3-1]
S
− A < fcr
where S = sectional modulus
P = prestressing force
A = gross cross-sectional area

3.4.2.2 Vibration
Vibration limitations are checked according to CHBDC (CSA 2006, Cl.3.4.4) which states that
the deflections under load combination SLS2 must be less than the value described in Figure 3-7.
All analysis cases are assumed to experience frequent pedestrian use which requires the most
stringent vibration criterion.

Figure 3-7. Deflection limits for highway bridge superstructure vibration (CHBDC 2006)
27

3.4.2.3 Deflection
The CHBDC does not have actual deflection restrictions and the limits used in American codes
are optional, because deflections in highway bridges generally do not pose a severe serviceability
problem as in railway bridges. However, excessive deflections affect rider confidence and cause
durability issues such as ponding (MacGregor and Bartlett 2000).
The analysis considers both long-term and short-term deflections due to permanent loads. Long-
term deflection ∆long-term should not exceed 1/750 of the span length (Menn 1990). Any deflection
that exceeds the limit needs to be balanced by camber imposed during construction such that long-
term deflection reduces to zero (Chen and Duan 1999). Long-term deflection accounts for the
minimum upward deflection due to prestress after all losses and the maximum downward deflection
due to creep:
∆long −term = ∆elastic + ∆creep [3-2]
∆elastic = ∆dead load + ∆prestress after all losses
∆creep = ϕ ∙ ∆elastic
where ϕ = creep coefficient
2.0 for CIP
=
1.5 for precast

On the other hand, short-term deflection accounts for the maximum upward deflection due to
prestress before losses and the minimum downward deflection due to instantaneous dead load:
∆short −term = ∆prestress before losses + ∆instantaneous dead load [3-3]

This check is particularly critical for cases with slender cross-sections in which large prestress
forces can cause the bridge to hog when there is no live load. Excessive camber poses a problem
and cracking might occur at regions that are originally designed to resist compression.
Live load deflections are considered under the vibration requirement. The actual live load
deflections have less impact on rider comfort compared to the acceleration of motion that riders feel
on the bridge.

3.5 Other Preliminary Analysis Assumptions


Other analysis assumptions include:
 Tendon eccentricity in duct is neglected. The centre of gravity of tendons is assumed to
be at the centroid of the duct.
 The increase in concrete to accommodate intermediate tendon anchors and deviators is
assumed to be negligible compared to the concrete volume of the entire superstructure.
 Every span is assumed to have the same number of prestressing tendons. The amount of
prestressing does not vary to suit the demand for each span.
 Substructure design is not considered in the analysis.
4 ANALYSIS OF CAST-IN-PLACE ON FALSEWORK BRIDGES
This chapter discusses the analysis of cast-in-place on falsework box-girder and solid slab. First,
Section 4.1 examines this construction method. The subsequent sections describe the analysis
models for the two bridge types by considering the cross-sections as well as the prestressing tendon
layouts. Lastly, this chapter summarizes the analysis results including structural behaviours,
vibration limits, deflections, material consumptions, and the factors that restrict further increase of
slenderness ratios.

4.1 Cast-in-Place on Falsework Construction


In cast-in-place on falsework construction, falsework for the entire bridge is assembled first.
The falsework needs to support concrete formwork as well as the full dead load of the bridge during
construction. After concrete is placed, longitudinal internal tendons are installed into ducts and
grout is placed inside the ducts such that tendons become bonded to the concrete. When the
concrete gains sufficient strength, tendons are stressed and as a result, the girder hogs and is
released from the formwork. The formwork and falsework are then removed. This is a labour-
intensive and slow method because it requires not only falsework erection but also on-site
placement of reinforcing steel and concrete. Falsework is also expensive and it can disrupt traffic
below the bridge. Moreover, cast-in-place concrete is subjected to on-site temperature and humidity
changes, so greater effort is needed to ensure good quality compared to precast concrete which is
manufactured in a controlled environment.
Despite these disadvantages, the cast-in-place on falsework method is still used today,
especially in regions where labour is inexpensive, primarily due to its simplicity (Gauvreau 2006).
This flexible construction method can also be applied to bridges with tight curves and complex
geometry (Hewson 2003). Furthermore, it provides opportunities for aesthetic expression since it
can readily accommodate different geometries.

4.2 Cast-in-Place on Falsework Box-Girder

4.2.1 Model
Analysis is performed on 21 cases with interior span lengths of 35m, 50m, 60m, and 75m and
span-to-depth ratios of 10, 15, 20, 25, 30, and 35. This set of span lengths is chosen because cast-in-
place on falsework box-girders are economical for spans up to about 80m according to Menn (1990)
and bridges with longer span lengths need to be haunched in order to reduce dead loads. The end
spans are made 10m shorter than interior spans to balance moments along the entire bridge and to
simplify the treatment of prestressing in the study. If the same span length is used throughout the

28
29

bridge, the end spans have greater moments than interior spans. A comparison of the moments
obtained from the two span arrangements is shown in Figure 4-1.
-300

-200

-100 0 50 100 150 200 250 300 350 400


Moment 0
Distance (m)
(kNm)
100

200
Constant span length
300 Reduced span length at end spans

Figure 4-1. Moment comparison of bridges with constant span length and reduced end span length

Typical span-to-depth ratios for this type of bridge range from 12 to 35 (Menn 1990). Therefore,
a similar range is used in the analysis. According to Menn (1990), the most economical ratio is 15,
but if both economic and aesthetic impacts are considered, the most optimal range becomes 17 to 22.

4.2.1.1 Cross-Section
A typical cross-section used in the analysis is shown in Figure 4-2. Dimensions for the box
components are based on values suggested by Gauvreau (2006). The deck is 15m wide and supports
four 3.5m wide design lanes and two 0.5m wide barriers. A minimum thickness of 225mm is used
for the top slab. This thickness is assumed to be sufficient to accommodate transverse tendons and
to resist punching shears from wheel loads. The top slab thickness increases to 375mm near the
webs such that the deck slab cantilever has enough strength and stiffness to resist transverse
bending. The intersection of the top slab and web occurs at the quarter point of the deck slab in
order to reduce transverse bending in the web. The web width is 450mm in order to accommodate
reinforcing bars, internal bonded tendons, concrete clear covers and the spacing required to
facilitate concrete placement and vibration. This width remains constant along the entire girder. On
the other hand, the bottom slab thickness varies from a minimum of 200mm at midspan to the depth
of the compressive stress zone created by negative moments at the supports.

Figure 4-2. Typical cross-section for cast-in-place on falsework box-girder


30

The reinforcement arrangement illustrated in Figure 4-3 is used and is assumed to be adequate
in resisting transverse bending moments for all analysis cases. The stirrup spacing varies based on
shear requirements; the remaining reinforcing steel is defined as “minimum reinforcing steel” in
this study and the layout is the same for all analysis cases.

Figure 4-3. Typical reinforcing steel layout

4.2.1.2 Prestressing Tendon Layout


The parabolic tendon layout used for this type of bridge is shown in Figure 4-4. The tendon is at
the highest possible location at the supports and the lowest possible location at midspan as allowed
by clear cover requirements of the webs. At the abutments, however, the tendon is located at the
centroidal axis of the cross-section in order to eliminate unbalanced prestress moments. Ideally, the
tendon layout should be parabolic between adjacent supports to provide maximum upward
deviation forces, but this layout results in abrupt corners over the supports. For practical purposes,
the tendon profile needs to be concave downward at the supports and the inflection point occurs at
one-fifteenth of the span length (L/15).

Figure 4-4. Typical tendon profile

In this study, the tendon is assumed to extend from one end of the bridge to another and be
stressed in one operation in order to simulate non-segmental construction. However, this layout is
generally not feasible in actual construction, because the installation is difficult and the prestress
loss due to friction is excessive for long bridges. In a real situation, segmented construction with
staged prestressing is required. This results in a more practical tendon layout in which adjacent
tendons would overlap at intermediate anchors. For the purpose of estimating loss of prestress, the
more practical layout is used and the tendon is assumed to extend over one span only. The
31

overlapping of tendons between adjacent spans is not considered. Based on this layout, the effective
prestress after all losses is estimated to be 60% fpu (1120MPa).

4.2.2 Analysis Results


This section summarizes the analysis results which include the structural response under ULS
and SLS, the material consumptions, and the factors that limit further increase of slenderness ratios.

4.2.2.1 Structural Behaviour and Dimensioning


Table 4-1 describes the ULS strength and SLS stress at the most critical location, the
dimensioning of shear reinforcement, and the factor that determines the amount of prestress
required for each analysis case. The sizing of prestressing tendons is described in Section 4.2.2.4.

Table 4-1. Summary of structural response and dimensioning of cast-in-place on falsework box-girder
Ultimate limit states Serviceability limit states Governing
L L/h __Flexural strength__ __Shear strength__ __Stresses__ factor for
(m) MULS Mr MULS/Mr Av smin % of girder σSLS (MPa) σSLS/fcr prestress
2
(kNm) (kNm) (mm ) (mm) @ smin requirement
10 37000 38200 97% 1200 - - 0.80 29% ULS flexural
15 35100 35600 99% 2000 - - 0.86 31% ULS flexural
35
20 33600 34800 97% 2000 243 9.0% 1.07 38% ULS flexural
25 32100 32400 99% 2000 200 22% 1.66 59% ULS flexural

10 75100 78400 96% 1200 224 5.4% 1.12 40% ULS flexural
15 67400 68600 98% 1200 147 6.2% 1.91 68% ULS flexural
50 20 63300 70700 90% 1200 102 17% 1.71 61% SLS stress
25 61200 69900 88% 2000 133 16% 2.10 75% SLS stress
30 60300 73600 82% 2000 106 18% 2.47 88% SLS stress

10 115000 118000 98% 1200 219 5.0% 1.16 41% ULS flexural
15 99100 99700 99% 1200 138 8.0% 1.83 65% ULS flexural
20 90200 96500 94% 1200 99 23% 2.01 72% SLS stress
60
25 85100 92800 92% 1200 76 29% 2.46 88% SLS stress
30 81300 88900 91% 1200 63 33% 2.33 83% SLS stress
35 73500 83300 88% 1200 52 30% 2.45 87% SLS stress

10 190000 199000 100% 1200 182 7.2% 1.46 52% ULS flexural
15 161000 164000 98% 1200 112 13% 1.84 66% ULS flexural
20 155000 173000 90% 1200 79 24% 2.10 75% SLS stress
75
25 142000 147000 97% 1200 59 29% 1.97 70% SLS stress
30 149000 166000 90% 1200 47 37% 2.17 78% SLS stress
35 143000 146000 98% 2000 60 28% 2.09 75% SLS stress

First, under ULS, the table describes the relationship between the flexural strength demand
(MULS) and resistance (Mr). Table 4-1 also summarizes the stirrup requirements for satisfying shear
demand by listing the stirrup area (Av), minimum stirrup spacing (smin) as well as the percentage of
girder that needs stirrups to be placed at a spacing of smin. The remainder of the girder requires
stirrups spaced at every 300mm which is the minimum spacing prescribed by CHBDC (CSA 2006,
32

Cl.8.14.3). All analysis cases, except for the cases with span of 35m and ratios of 10 and 15, need
stirrup spacing of less than 300mm near the supports where shear forces are greatest. Cases with
larger span lengths and span-to-depth ratios require small stirrup spacing of less than 100mm which
should be increased by using a bigger reinforcement bar (i.e. larger than 20M) for construction
purposes. However, the spacing described in Table 4-1 is used in this study, because the required
volume of stirrup varies little with respect to stirrup spacing and it is of greater concern than the
spacing in cost comparisons.
Table 4-1 also compares SLS stresses with the factored cracking stress. SLS stresses (σSLS)
cannot exceed the concrete tensile stress (fcr = 2.8 MPa) to avoid cracking during service.
Lastly, the table shows the factor that governs the amount of prestress needed for each analysis
case. The governing factor is either ULS flexural strength or SLS stress; ULS shear strength does
not govern since stirrups are added to resist any extra shear that is not balanced by the tendons and
concrete. The ULS flexural resistance is proportional to the cross-sectional depth while the SLS
stress depends on the sectional modulus which is related to the second power of the depth. For cases
with low span-to-depth ratios, the sectional moduli are large and the SLS stresses are relatively
small, thus ULS flexural strength governs the prestress requirement. However, as span-to-depth
ratio increases, the sectional modulus decreases at a faster rate than the cross-sectional depth
(Figure 4-5). As a result, SLS stress becomes more critical for slender girders and thus, it governs
the prestress requirement for these cases.
35
Stop fibre
30

25

Sectional modulus S (m3) 20 Sbottom fibre


or depth h (m)
15

10
h
5

0
5 10 15 20 25 30 35 40
L/h
Figure 4-5. Changes in sectional modulus and cross-sectional depth

4.2.2.2 Vibration Limits


Figure 4-6 describes the vibration deflection limits for bridges with frequent pedestrian use and
the truck load deflections under SLS2. The truck deflections are acceptable for all analysis cases
and vibration limits do not govern the prestressing requirement. The truck deflections are at least
58% less than the vibration limits.
33

80
L=75m Limit

60
L=60m Limit
Truck load
deflection 40
(mm)
L=50m Limit
L=75m
20 L=60m
L=35m Limit L=50m
L=35m
0
5 10 15 20 25 30 35 40
L/h
Figure 4-6. Deflection for superstructure vibration limitation

4.2.2.3 Deflections
The following graphs summarize the dead load, long-term and short-term deflections in terms of
span length over deflection (L/∆). As expected, deflection increases with increasing span lengths
and span-to-depth ratios. The maximum camber required is 0.5m for the case with a span of 75m
and span-to-depth ratio of 35 such that the long-term deflection essentially becomes zero.
12000

Dead load 8000 L=35m


deflection
(L/∆)
[down] 4000 L=50m
L=60m
L=75m

0
5 10 15 20 25 30 35 40
L/h
6000 L=35m
Long-term
deflection 4000
(creep +
elastic)
(L/∆) 2000
L=50m
[down] L=60m
L=75m
0
5 10 15 20 25 30 35 40
L/h
15000
L=35m
Short-term
deflection 10000
(dead load+ L=50m
prestress
before loss) 5000
(L/∆) L=60m
L=75m
[down]
0
5 10 15 20 25 30 35 40
L/h
Figure 4-7. Deflections: a) dead load, b) long-term, c) short-term
34

4.2.2.4 Material Consumption


Table 4-2 and Figure 4-8 summarize the material consumption for each analysis case as well as
their variations from the baseline case (i.e. L/h=20, which is the conventional ratio defined in
Chapter 2). These results are also illustrated in cross-section drawings in Appendix C.1.

Table 4-2. Summary of material consumptions for cast-in-place on falsework box-girder


Concrete Prestressing tendon Reinforcing steel
L
L/h Volume % change from Number of % change from Mass % change from
(m) 3
(m ) baseline case tendons baseline case (ton) baseline case
10 2700 +19% 52 -52% 216 +16%
15 2410 +6.5% 76 -30% 193 +3.8%
35
20 2260 0% 108 0% 186 0%
25 2174 -3.9% 136 +26% 187 +0.5%

10 4450 +25% 76 -47% 360 +18%


15 3860 +8.1% 100 -31% 314 +3.2%
50 20 3570 0% 144 0% 304 0%
25 3420 -4.0% 184 +28% 306 +0.7%
30 3350 -6.0% 240 +67% 315 +0.4%

10 5890 +28% 92 -43% 476 +18%


15 5000 +8.9% 120 -25% 410 +1.5%
20 4600 0% 160 0% 404 0%
60
25 4380 -4.7% 192 +20% 405 +0.2%
30 4270 -7.1% 248 +55% 415 +2.7%
35 4190 -8.8% 300 +88% 416 +3.0%

10 8290 +31% 136 -43% 674 +18%


15 6970 +9.9% 184 -23% 585 +2.5%
20 6340 0% 240 0% 571 0%
75
25 6030 -4.9% 300 +25% 579 +1.4%
30 5850 -7.7% 384 +60% 618 +8.2%
35 5910 -6.8% 528 +120% 621 +8.8%

As shown in the graphs, when the girder becomes more slender, concrete volume decreases
gradually at a decreasing rate. This trend exists because concrete volume depends highly on the
cross-sectional depth which also decreases at a declining rate as span-to-depth ratio increases
(Figure 4-8 a & b). Also, at higher span-to-depth ratios, the concrete volume varies less since the
reduction in web concrete is counterbalanced by the increase in bottom slab thickness. For instance,
for the cases with span length of 50m, concrete volume decreases by 880m3 as span-to-depth ratio
increases from 10 to 20, but concrete volume only decreases by 220m3 as span-to-depth ratio
increases from 20 to 30. In the latter case, the concrete reduction in the webs is 284m3, but the total
concrete reduction is only 220m3 due to increase in bottom slab thickness.
On the contrary, the amount of prestress increases as span-to-depth ratio increases, because
slender bridges have lower flexural resistances and require larger prestress forces (Figure 4-8 c).
35

The number of tendons increases at an increasing rate because for slender cases with large prestress
demand, the tendons need to be placed in more than one layer within the webs, thus lowering the
resistance moment lever arm. The prestress layout becomes more inefficient as slenderness
increases, resulting in an even greater demand for tendons to provide the same level of prestress.
Reinforcing steel mass is attributed to the longitudinal and transverse steel reinforcing bars as
well as the stirrups. The amount of steel reinforcing bars needed is proportional to the cross-
sectional area because they are placed according to Figure 4-3. Consequently, the graph for
reinforcing steel mass follows the trend of concrete volume for cases with low span-to-depth ratios
(Figure 4-8 d). These cases have deep girders that can resist shear using mostly stirrups installed
with the minimum spacing needed to support the tendons (i.e. 20M bars spaced at 300 mm), so the
required amount of reinforcing steel depends on the concrete volume. For the more slender girders,
more stirrups are needed to resist shear and thus the reinforcing steel graph no longer follows the
same trend as the concrete volume graph at higher span-to-depth ratios.
a) Concrete volume b) Cross-sectional depth
10000 8.0

8000
6.0

6000 L=75m
Concrete
volume Depth
4.0
(m3) h (m)
4000 L=60m
L=50m
2.0 L=75m
2000 L=35m L=60m
L=50m
L=35m
0 0.0
5 10 15 20 25 30 35 40 5 10 15 20 25 30 35 40
L/h L/h

c) Number of prestressing strands d) Reinforcing steel mass


600 800
L=75m
500 L=75m
600
400
Prestress Reinforcing
L=60m steel mass 400 L=60m
strands 300
(ton)
L=50m L=50m
200
L=35m 200 L=35m
100

0 0
5 10 15 20 25 30 35 40 5 10 15 20 25 30 35 40
L/h L/h

Figure 4-8. Material consumptions for cast-in-place on falsework box-girder


36

4.2.2.5 Limiting Factors of Span-to-Depth Ratios


The upper bound of span-to-depth ratio for cast-in-place on falsework box-girders is restricted
by the number of prestressing tendons that can fit inside the webs and by the minimum height of the
interior box cavity. First, the maximum feasible span-to-depth ratio for cases with span lengths of
75m is limited to 35 due to the tendon arrangement within the webs. This case requires sixteen 37-
strand ducts arranged in four layers in the webs (current tendon arrangement in Figure 4-9). For
cases having ratios beyond 35, more tendons are needed due to the reduced moment lever arm and
section modulus, but they cannot be accommodated efficiently within the 450mm thick webs
according to the current tendon arrangement. This inefficient arrangement of tendons decreases the
eccentricity of tendons, thus further increasing the prestressing demand. Figure 4-9 compares the
current tendon arrangement to a more efficient arrangement in which three ducts are placed in one
layer in each web, thus increasing the eccentricity (i.e. h1 > h2). However, since the web thickness is
kept constant for all cases in this study, the more efficient tendon arrangement is not used. The
current arrangement cannot efficiently accommodate tendons needed for the cases with span lengths
of 75m and slenderness ratios beyond 35.

More efficient tendon arrangement Current tendon arrangement

h1 h2

Figure 4-9. Tendon arrangement that limits further increase in span-to-depth ratio

If the more efficient tendon arrangement from Figure 4-9 is used, the prestressing demand is
expected to decrease. For example, for the case with span length of 75m and ratio of 35, using the
more efficient arrangement increases the eccentricity by 89mm and decreases the prestressing
demand by 3.0%. This decrease in tendon is relatively minor, because the advantage from
additional tendon eccentricity is offset by the increase in dead load (i.e. concrete volume increases
by 4.3% due to the thicker webs). With thicker webs, the maximum feasible span-to-depth ratio for
cases with span lengths of 75m becomes 40 at which point the limiting factor is the minimum
height requirement of the interior box cavity. Therefore, the results of this analysis depend on the
assumed web thickness. Using thinner webs requires more prestressing tendons and reduces the
maximum feasible span-to-depth ratio while larger web thickness reduces prestressing demand and
expands the feasible range of ratios.
37

Another factor that restricts span-to-depth ratios is the minimum height requirement for the
interior box cavity. As shown in Figure 4-10, the interior box cavity needs to be at least 1.0m such
that workers have enough space to strip forms, stress tendons and perform maintenance and repairs.

height
of h
access

Figure 4-10. Interior box cavity limitation

Although this height limit is not required by CHBDC, it is often used as good construction
practice. This height requirement restricts the ratio for cases with span lengths of 35m, 50m, and
60m to 25, 30, and 35 respectively. As span-to-depth ratio increases, more tendons are used and the
bottom slab becomes thicker in order to accommodate the compressive stress zone in negative
moment regions. As the bottom slab thickness increases, the height of interior box cavity shortens.
If this minimum height restriction does not exist, the box would essentially turn into a solid slab for
the more slender cases (Figure 4-11).

Figure 4-11. Height of access diminishes as span-to-depth ratio increases


38

4.3 Cast-in-Place on Falsework Solid Slab


As shown in the previous analysis, box-girders are not feasible for slender cases (i.e. span-to-
depth ratio greater than 30) due to practical construction considerations. Any further reduction in
cross-sectional depth essentially turns the box into a solid slab. This finding leads to the analysis of
cast-in-place on falsework solid slabs described in this section.
From the aspect of construction cost optimization, investigating span-to-depth ratios for solid
slabs is valuable, because concrete savings as a result of reduced depth in solid slabs would be more
than those in box-girders. As indicated by the shaded areas in Figure 4-12, reducing depth in solid
slab eliminates a strip of concrete as wide as the soffit while reducing depth in box-girder only
removes the web concrete.

Figure 4-12. Concrete reduction due to increase in span-to-depth ratio for solid slab and box-girder

Cast-in-place on falsework solid slabs are economical for short-span bridges due to simple
formwork, prestress layout and concreting operations (Hewson 2003). The straightforward
construction does not require a high level of technology or an extensive amount of labour. However,
solid slabs are inefficient in terms of structural behaviour, because they result in relatively large
dead loads and need more prestressing to get sufficient flexural stiffness and resistance compared to
box-girders (Menn 1990).
Due to its excessive dead load, solid slabs are generally used for shorter spans of less than 20m
(Gauvreau 2006). To reduce the dead load for long span cases, voided slabs (Figure 4-13) are used
instead of solid slabs. In voided slabs, stay-in-place forms are used to create the hollow cores. These
forms must be anchored against uplift during concreting and they need vents and drainage openings,
thus complicating the construction process. The voids also pose durability issues since inspection is
not possible inside the voids. Due to the construction complications and durability concerns, voided
slabs are not considered in the analysis despite the savings in concrete and reinforcing steel.

Figure 4-13. Voided slab


39

4.3.1 Model
The analysis considers 18 cases with span lengths of 20m, 25m, 30m, and 35m and span-to-
depth ratios of 30, 35, 40, 45, and 50. According to Gauvreau (2006), the maximum cost-effective
slab depth is 0.8m and the maximum practical span-to-depth ratio is 25, resulting in a maximum
span of 20m. This analysis uses a higher range of spans and ratios in order to demonstrate the
impacts of slenderness. Bridges with spans shorter than 20m cannot achieve the proposed span-to-
depth ratios because the girders would be too slender to accommodate sufficient reinforcement (e.g.
a 15m long span with a ratio of 35 only has a depth of 0.43m). Also, this set of ratios is chosen
since the commonly used value is 30 based on the review of existing bridges in Chapter 2.
Furthermore, span-to-depth ratios below 30 are not investigated, because a deep cross-section with
a depth greater than approximately 0.8m has large dead loads and is not economical (Menn 1990).

4.3.1.1 Cross-Section
A typical cross-section and reinforcement layout are shown in Figures 4-14 and 4-15. Compared
to the box cross-section considered previously, the solid slab model has a wider deck (i.e. 22m) that
supports six design lanes and shorter deck cantilevers (i.e. 3.75m) in order to emphasize slab
behaviour. Also, the deck cantilevers are tapered to reduce dead load which is much higher in solid
slabs than in box-girders. Longitudinal internal bonded tendons are grouped in bands over support
lines based on recent practices in North America (Park and Gamble 2000). To simplify analysis, a
solid wall pier is assumed and thus, only one band of tendons that spread over the entire “spine” of
the cross-section is used. To carry loads into the longitudinal tendon band, transverse tendons are
uniformly distributed along the length of the bridge.

Figure 4-14. Typical cross-section for cast-in-place on falsework solid slab

Figure 4-15. Typical reinforcing steel layout

4.3.1.2 Prestressing Tendon Layout


The model has the same tendon layout as the one from the box-girder model (Figure 4-4).
40

4.3.2 Strip Method versus Beam Model


Designing reinforcement based on elastic sectional forces only is complicated in slabs, because
bending moments exist in two orthogonal directions. To simplify the design, two methods are
considered: strip method and beam model. Results from these two methods are compared in this
section for three analysis cases: 1) L=25m, L/h=30; 2) L=30m, L/h=40; 3) L=35m, L/h=50.
The strip method, proposed by Hillerborg (1996), generates lower bound solutions of the theory
of plasticity. In contrast to yield line theory, the strip method solution provides adequate flexural
safety at ULS. This method states that if the moments can be distributed such that equilibrium
equations are satisfied and the reinforcements are designed for these moments, then the slab is safe
at ULS. The solution only needs to fulfill equilibrium equations and not necessarily the
compatibility criteria. More than one solution is possible since the slab is statically indeterminate.
For design purposes, the solution that yields reinforcement economy and favorable behaviour under
service conditions is used.
In the simple strip method, load is assumed to be carried by strips that run in the longitudinal
and transverse reinforcement directions. These strips are treated as beams and the moment in each
strip can be solved using simple statics. To further simplify analysis, torsional moments are
assumed to be zero in these strips. This moment distribution is preferred because torsional moments
require more reinforcement. One way to apply the simple strip method in prestressed slabs is to
divide the slab into strips that contain one tendon each. Since all the tendons are equal, strip width is
varied in order to balance the load.
Menn (1990) proposed a straightforward way to redistribute moments in slabs. In order to
minimize cracking, the prestressing deviation forces (qp) are chosen to be 60-80% of the total dead
load. To simplify analysis and construction, parallel prestressing tendons are arranged into narrow
bands. These bands of tendons are idealized as beams in the longitudinal direction and slabs can
redistribute moments onto the bands to reduce peak stresses. To account for this moment
redistribution onto these reinforcement bands, a self-equilibrating moment (msp) is used:
msp = mp − m0p [4-1]
where mp = moment where q p is applied to the original slab
-m0p = moment when-qp is applied to the idealized slab in which
the prestressing bands act as individual beams

This self-equilibrating moment varies across the width of the cross-section since additional
positive moments are concentrated at the reinforcement bands. Reinforcements are designed for the
final moments after redistribution.
Design moments in the analysis are computed based on Menn’s prestressing concept. First, the
structure is divided into two 3.75m wide edge strips and one 14.5m wide prestress band as shown in
41

Figure 4-16 b. Longitudinal tendons are distributed evenly in the prestress band. The two edge
strips are narrow relative to the prestress strip in order to ensure the deck cantilever load would
b
travel into the prestress band due to the short load path. To compute –m0p, - qp b0
is applied to the

prestress band where qp is 80% of the total dead load, b is the total slab width and b0 is the width of
prestress band. Likewise, mp is obtained by applying qp to the entire slab. The redundant moment
(msp) is the difference between mp and m0p. The redundant moment transfers forces from the edge
strips to the prestress band. Since this moment is self-equilibrating, the total moment remains
Support
Support
the
Support Support
Support Support
same after redistribution as shown in Figure 4-16 g. Reinforcement is then designed such that the
A
A
Support is satisfied the factored moment (Figure 4-16
following A h): Support
A
A
Support αDL mDL + αLL mLL + αp msp < Mr A Support
[4-2]
where α=load factor
Support Mr =moment resistance A Support
The transverse distribution of longitudinal bending moment
A
across the slab and the final design
Support A Support
b == 22m
b 22m
moment are illustrated in Figure 4-16. b = 22m
A
A
a) Elevation: Edge strip
Edge strip Prestress band
Prestress band bb0 == 14.5m
14.5m Edge strip
Edge strip
Support b = 22m 0 Support
Edge strip Prestress band b0 = 14.5m Edge strip
Support A Support
Edge strip Prestress bandA b0 = 14.5m
b = 22m Edge strip
A
b = A
22m
Edge strip Prestress band b0 = 14.5m Edge strip
A
b) Section A-A: 2.00
2.00
Edge strip Prestressb band
= 22mb0 = 14.5m Edge strip 2.00

2.00
Edge strip Prestress band b0 = 14.5m Edge strip
b = 22m
c) Dead load and live load moments mDL + mLL (assumebm= 22m = m ): 1.21 2.00
DL LL 1.21
Edge strip 1.21
Prestress band b0 = 14.5m Edge strip
Edge strip Prestress band b0 = 14.5m Edge strip 2.00
1.21
d) -m0P due to application of deviation forces qp on prestress band:
2.00
0.80
0.80
1.21 0.80
e) mP due to application of deviation forces qp on the entire slab width:
1.21 0.80
2.00
2.00
f) Self-equilibrating moment mSP = -m0P + mP: 1.21 0.80
0.80
0.80
0.41 0.80
0.41 0.80
0.41
g) Unfactored design moment = mDL + mLL + msp: 1.21
0.80
1.20
1.20 1.21
0.41 0.80m +m
1.20 2.41 mDL +mLLLL
2.41 0.80m DL
+mLL
2.41 == 2.00
2.00
DL
0.41 = 2.00
h) 1.20= αDLmDL + αLLmLL + αpmsp:
Design moment
0.80m +m
0.80
2.41 2.14 DL LL
2.14
3.29 0.80
2.14= 2.00
1.20 0.41
3.29
3.29 m +m
2.41 0.80 DL LL
Figure 4-16. Transverse distribution of longitudinal bending moment in slabs (values are0.41
divided by m2.14= 2.00
DL)
1.20 3.29
2.41 mDL+mLL
0.80= 2.00
2.14
1.20 3.29
0.41 0.80m +m
2.41 DL LL
0.41 2.14= 2.00
3.29
1.20
1.20 2.41 2.14 mDL+mLL
3.29 m= 2.00
+m
42

The three analysis cases are also investigated under the assumption that the slab behaves like a
beam, so there is no moment redistribution. The longitudinal tendon requirements for ULS flexure
determined from the two methods are summarized in Table 4-3.

Table 4-3. Results from beam model and strip method


L=25m, L/h=30 L=30m, L/h=40 L=35m, L/h=50
Beam Strip % diff. Beam Strip % diff. Beam Strip % diff.
Tendon requirement 230 176 23% 360 351 2.5% 500 486 2.8%
Total construction cost per deck area $ 2170 $ 2110 2.8% $ 2480 $ 2540 2.4% $ 2580 $ 2570 0.4%

The table shows that the prestress requirements and total construction costs obtained from the
two methods are similar. Strip method does not change the results significantly because the analysis
model is predominantly a simple, one-way system, so the moment distribution is similar to that of a
beam. Therefore, the simpler beam assumption is used for the analysis.

4.3.3 Analysis Results

4.3.3.1 Structural Behaviour and Dimensioning


Table 4-4 describes the ULS strengths and SLS stress at the most critical location and the
dimensioning of shear stirrups for each analysis case. The sizing of prestressing tendon is described
in Section 4.3.3.5. For all cases, the ULS flexural resistance (Mr) is at least 27% greater than the
demand (MULS), so flexural strength does not govern the prestress requirement. However, to satisfy
the maximum reinforcement criterion, larger concrete compressive strengths (f’c) are needed. This
criterion is discussed in greater details in Section 4.3.3.2. On the other hand, shear strength
requirements can be fulfilled with the listed stirrup areas (Av) distributed at a minimum spacing of
300mm as described in CHBDC. Only minimum stirrups are needed because the cross-sectional
widths and concrete strengths are large, thus resulting in high concrete shear resistances. Lastly,
SLS stresses govern the prestressing requirement for all cases. Critical stress occurs at the top fibre
of the support which is subjected to large negative moments.
43

Table 4-4. Summary of structural response and dimensioning of cast-in-place on falsework solid slab
Ultimate limit states Serviceability limit states
L (m) L/h __Flexural strength__ _Shear strength_ __Stresses__
2
MULS (kNm) Mr (kNm) MULS/Mr f’c (MPa) Av (mm ) σSLS (MPa) σSLS/fcr
30 17500 20000 86% 50 600 2.50 89%
20 35 15900 19100 83% 50 600 2.63 93%
40 14800 18900 78% 75 600 3.04 88%
30 28600 34000 84% 50 600 2.54 90%
25 35 25500 31600 81% 50 1000 2.42 85%
40 23400 30000 79% 60 1000 2.64 85%
30 43900 49600 89% 50 600 2.67 94%
35 39300 45800 86% 50 1000 2.75 97%
30
40 36500 44300 82% 60 1000 3.03 98%
45 32800 42900 76% 75 1000 3.03 87%
30 68900 81100 85% 50 600 2.79 98%
35 61200 74300 82% 50 1000 2.54 90%
35
40 55900 68100 82% 60 1000 2.92 94%
45 51800 64100 81% 80 1000 3.48 97%

4.3.3.2 Maximum Reinforcement Criterion


According to the maximum reinforcement criterion in CHBDC (CSA 2006, Cl.8.8.4.5), the
flexural resistance at ULS should be developed with a c/d of less than 0.5 at regions where the
moment capacity is close to the demand (c is the height of compressive stress region while d is the
distance between the extreme compressive fibre and the tendon as shown in Figure 4-17). This
ensures that the tendons would already be yielding and significant plastic deformations have
occurred when concrete crushes such that the structure would fail in a ductile manner. This
limitation is not satisfied for the more slender analysis cases. Slender bridges have short moment
lever arms and thus large prestress requirements. A large tensile force in the tendon needs to be
balanced by an equally large concrete compressive force, meaning that c is large. Slender bridges
have small d due to physical limitation and large c due to moment requirements, resulting in large
c/d ratios. For cases that do not satisfy this criterion, concrete strengths are increased such that
prestress requirement and c decrease. Concrete strengths that are needed to satisfy the maximum
reinforcement limit are summarized in Table 4-5. These higher strength concretes are more
expensive and the additional expenses will be accounted for in the cost comparative studies in
Chapter 6. For the cases that are crossed out in the table, concrete with strengths greater than 80
MPa are needed to fulfil the criterion. Such high strengths are not widely used in today’s bridge
industry and hence, the maximum span-to-depth ratio is limited by the maximum reinforcement
criterion and the maximum practical concrete strength.
44

Table 4-5. Concrete strengths required to satisfy


εcu = -3.5x10 -3 0.85f’c maximum reinforcement criterion

c C f’c required to satisfy c/d<0.5 limit (MPa)


d
z L/h 20m 25m 30m 35m
∆εp fp T 30 50 50 50 50
Figure 4-17. Maximum reinforcement criterion: a) 35 50 50 50 50
concrete stains, b) equivalent concrete stresses, c) concrete
40 75 60 60 60
forces
45 150 90 75 80
50 ― ― 135 115

4.3.3.3 Vibration Limits


Figure 4-18 describes the vibration deflection limits for bridges with frequent pedestrian use
and the truck load deflections under SLS2. The truck deflections are acceptable for all analysis
cases and vibration limits do not govern the prestressing requirement. The truck deflections are at
least 52% less than the vibration limits. The deflection increases as the girder becomes more slender
until the span-to-depth ratio reaches 35 for span lengths of 20m and 25m, and 40 for span lengths of
30m and 35m. These cases use larger concrete strengths as described previously (Section 4.3.3.2),
resulting in greater stiffness as well as lower deflections and flexural frequencies (indicated by
triangular markers on Figure 4-18).
50

40

Truck load 30
deflection L=35m limit
(mm)
20 L=30m limit
L=25m limit
10 L=20m limit L=35m
L=25m L=30m
L=20m
0
25 30 35 40 45 50
L/h
Figure 4-18. Deflection for superstructure vibration limitation
45

4.3.3.4 Deflections
The following graphs summarize the dead load, long-term and short-term deflections in terms of
span length over deflection (L/∆). The maximum camber required is 0.075m such that the long-term
deflection essentially becomes zero for the case with a span of 35m and slenderness ratio of 40. As
explained previously, cases with increased concrete strengths have lower deflections; these cases
are indicated by triangular markers.
12000

L=20m
Dead load 8000
deflection L=25m
(L/∆) L=30m
[down] 4000 L=35m

0
25 30 35 40 45 50
L/h
12000

Long-term
deflection 8000 L=20m
(creep + L=25m
elastic) L=30m
(L/∆) 4000 L=35m
[down]

0
25 30 35 40 45 50
L/h
30000
Short-term
deflection
20000
(dead load +
prestress L=20m
before loss) 10000 L=25m
L=30m
(L/∆) L=35m
[up]
0
25 30 35 40 45 50
L/h
Figure 4-19. Deflections: a) dead load, b) long-term, c) short-term
46

4.3.3.5 Material Consumption


Table 4-6 and Figure 4-20 summarize the material consumption for each analysis case and its
variation from the baseline case (i.e. L/h=30, which is the conventional ratio defined in Chapter 2).
The cases with higher concrete strengths are italicized in the table and are indicated by triangular
markers in the graphs. These results are also illustrated in cross-section drawings in Appendix C.2.
Table 4-6. Summary of material consumption for cast-in-place on falsework solid slab

Concrete Prestressing tendon Reinforcing steel


L
L/h Volume % change from Number of % change from Mass % change from
(m) 3
(m ) baseline case tendons baseline case (ton) baseline case
30 2150 0% 210 0% 85.7 0%
20 35 1930 -10% 264 +26% 86.9 +1.4%
40 1770 -18% 322 +53% 88.0 +2.7%

30 3210 0% 260 0% 111 0%


25 35 2860 -11% 312 +20% 113 +1.7%
40 2600 -19% 364 +40% 114 +2.5%

30 4270 0% 300 0% 124 0%


35 3790 -11% 350 +17% 130 +4.8%
30
40 3430 -20% 414 +38% 131 +5.4%
45 3160 -26% 480 +60% 132 +5.8%

30 5710 0% 414 0% 148 0%


35 5050 -12% 480 +16% 156 +5.0%
35
40 4550 -20% 528 +28% 156 +5.2%
45 4170 -27% 576 +39% 156 +5.3%

Contrary to the non-linear decline in box-girders, concrete volume decreases at a relatively


steady rate as slenderness increases for solid slabs (Figure 4-20 a). In box-girders, concrete volume
diminishes at a decreasing rate since web concrete reduction is offset by bottom slab thickening. In
contrast, increasing span-to-depth ratio in solid slabs simply removes an entire strip of slab, so the
concrete volume reduction is directly proportional to the decrease in girder depth (Figure 4-20 b).
The amount of prestressing is expected to increase at an increasing rate as slenderness rises
based on observations described in Section 4.2.2.4 for box-girder. However, Figure 4-20 c shows
that the prestress increases linearly with slenderness since larger concrete strengths are used and
fewer tendons are needed for the slender cases. Also, solid slabs can accommodate a large number
of tendons at the same elevation, so the tendons do not need to be placed in layers which reduce the
prestressing efficiency.
As shown in Figure 4-20 d, the amount of reinforcing steel remains relatively constant as span-
to-depth ratio varies. For the cases with spans of 20m, the stirrup requirement is the same for all
three cases. For the cases with the other span lengths, as span-to-depth increases from 30 to 35, the
required stirrup area increases from 600mm2 to 1000mm2 but spacing remains at 300mm. This
47

increase in stirrup area has little effect because stirrups account for less than 10% of the total
amount of reinforcement steel. As a result, the amount of reinforcement steel does not deviate more
than 5% from the baseline case.

a) Concrete volume b) Cross-sectional depth


6000 1.2

4000 L=35m 0.8 L=35m


Concrete L=30m
volume L=30m Depth (m) L=25m
(m^3) L=25m L=20m
2000 0.4
L=20m

0 0
25 30 35 40 45 50 25 30 35 40 45 50
L/h L/h

c) Number of prestressing strands d) Reinforcing steel mass


800 200

600 150 L=35m


L=35m
L=30m
Prestress L=30m Reinf.
steel L=25m
strands
400 100
L=25m mass
L=20m
L=20m (ton)

200 50

0 0
25 30 35 40 45 50 25 30 35 40 45 50
L/h L/h

Figure 4-20. Material consumptions for cast-in-place on falsework solid slab

4.3.3.6 Limiting Factors of Span-to-Depth Ratios


Maximum span-to-depth ratio in solid slabs is limited by the maximum reinforcement criterion
which states that the height of the compressive stress region should be less than half the distance
from the extreme compressive fibre to the centroid of tensile force (i.e. c/d < 0.5). This criterion is
not satisfied for cases with ratios as low as 35 if a concrete strength of 50 MPa is used. In order to
fulfil the criterion, cases with higher ratios use larger concrete strengths which reduce prestress
demands (i.e. results in a smaller compressive stress region) and improve ductility. The maximum
concrete strength used in the analysis is 80 MPa which limits the span-to-depth ratio to 40 for cases
with spans of 20m and 25m, and to 45 for cases with spans of 30m and 35m.
5 ANALYSIS OF PRECAST SEGMENTAL SPAN-BY-SPAN BOX-
GIRDER
This chapter examines the optimization of span-to-depth ratio for precast segmental span-by-
span constructed box-girders. Section 5.1 provides a general description of the construction method;
Section 5.2 discusses the analysis model; Section 5.3 examines the construction moments and
moments due to thermal gradients; Section 5.4 explores the loss of prestress; Section 5.5 discusses
the behaviour of unbonded tendons at ultimate limit states; and Section 5.6 summarizes the analysis
results.

5.1 Precast Segmental Span-by-Span Construction


Precast segmental span-by-span construction method is ideal for long bridges with many short-
to-medium spans, because it has a high speed of construction when repetitive spans are used. For
instance, a typical 40m span can be erected every 2 to 3 days using this method (Hewson 2003).
Also, this method can be used for bridges that require access beneath the superstructure since the
erection equipment is mainly above ground and the disruption to traffic below the bridge is
minimized (Sauvageot 1999).
The construction sequence is illustrated in Figure 5-1. In this method, an erection girder, either
an overhead truss or underslung girder, is first supported on a previously completed deck or
adjacent piers. Then precast segments are transported from the completed span and a crane located
at the edge of the completed deck stacks the segments loosely on the erection girder. If an overhead
truss is used, the segments are hanged with cables (Figure 5-2 a). If an underslung girder is used,
segments are supported under the deck cantilevers or soffit (Figure 5-2 b). After all the segments of
an entire span are placed, they are connected together with temporary prestress. A cast-in-place
closure joint next to the pier segment stitches the new span with the previously completed span
(Hewson 2003). Then permanent longitudinal external tendons, which overlap the previous span,
are installed and the new span becomes continuous with the completed structure. The erection
girder then launches forward to erect the next span.
Since precast segments are used and tendons are only stressed once for the entire span, this
method increases the ease and speed of construction. Efficiency in construction is further enhanced
with the use of external tendons which increases the speed of precasting (Sauvageot 1999).

48
Direction of Construction
49
Precast segments are placed onto erection girder
Direction of Construction Erection girder

Direction of Precast segments are placed onto erection girder


Construction
Erection girder
Precast segments are placed onto erection girder
Erection girder

Prestressing tendons are installed

Prestressing tendons are installed

Prestressing tendons are installed

Erection girder launches forward

Erection girder launches forward

Erection girder launches forward


Figure 5-1. Precast segmental span-by-span construction method

Figure 5-2. Span-by-span erection girder: a) overhead truss, b) underslung girder (NRS 2008, OSHA 2006)

5.2 Model
Analysis is performed on 11 cases with span lengths of 30m, 40m and 50m and span-to-depth
ratios of 15, 20, 25, and 30. This set of span lengths is chosen based on lengths of erection girders
that are typically used in the industry today. The maximum length is 50m because longer erection
equipment would become too heavy and this method would no longer be economical (Sauvageot
1999).
The range of slenderness ratios chosen for analysis is based on the conventional optimal ratio of
17 and the minimum cross-sectional depth of 1.8m (Gauvreau 2006). This depth is larger than the
minimum depth used in cast-in-place on falsework box-girder analysis (i.e. 1.4m) since the precast
bridge is longitudinally post-tensioned with external unbonded tendons which shorten the moment
lever arm compared to internal tendons.
50

5.2.1 Cross-Section
A typical cross-section and reinforcement layout are shown in Figures 5-3 and 5-4. They are
modified from AASHTO-PCI-ASBI standard sections (1997). Except for box height and bottom
slab thickness, all other dimensions remain the same for every analysis case. The box webs are
more slender compared to those for cast-in-place on falsework because they do not need to
accommodate internal tendons. As a result, web thickness depends only on shear and transverse
bending requirements. The bottom slab thickness depends on the thickness of the compressive stress
zone at negative moment regions. The deck is 15m wide and can support four lanes of traffic which
is the same as the cast-in-place on falsework case.

Figure 5-3. Typical cross-section for precast segmental span-by-span box-girder

Figure 5-4. Typical reinforcing steel layout

5.2.2 Elevation and Prestressing Tendon Layout


In precast segmental span-by-span construction, the girder is composed of interior segments,
pier segments, and closure joints. The maximum length of interior segment is chosen to be 3m
based on limitations of transporting segments from casting yard to construction site. The pier
segments are 1m long and they support the anchorages of all longitudinal tendons. The 150mm long
51

cast-in-place closure joint fills the gap between the pier segments and interior segments and it
allows for adjustments during placement of segments. Elevation and typical tendon layout of an end
span is illustrated below.

Figure 5-5. Typical tendon profile

As shown in the diagram, longitudinal tendons are continuous between adjacent piers and they
connect the precast segments of each span. Since the tendons are externally unbonded, a straight
tendon profile is used instead of a parabolic profile. Each tendon begins at the centroidal axis of the
girder for end spans or directly below the top slab for the interior spans. The tendon then continues
within the box cavity towards the bottom slab. It is deviated at 1/3 of the span and assumes a
horizontal profile. When the tendon reaches 2/3 of the span, it deviates again and continues towards
the top slab of the pier segment. The tendon is then anchored at the exterior side of the pier segment.
This anchorage location allows tendons from adjacent spans to overlap at the pier segments, thus
providing continuity throughout the superstructure.

5.3 Longitudinal Bending Moments


This section discusses two types of longitudinal bending moments that are particularly critical
in precast segmental bridges: construction moments and thermal gradient moments.

5.3.1 Construction Moments


Because a segmental method is used, the structural system changes during construction and the
final moments are affected by the stress history. Therefore, the moments at each stage of
construction is computed to obtain the final moments at completion. The following illustration
describes the dead load and prestressing moments (MDL and MP,tot) for a case with span of 40m and
ratio of 20 at various construction stages. The first eight graphs show the moments caused by the
additional new span at each construction stage. The last graph shows the final moments at the
instant of completion which are obtained by summing the construction moments at all construction
stages.
Figure 5-6. Construction moments for segmental span-by-span method
Stage 1: Stage 2:

-40000 MP,tot -40000


MP,tot
-20000 0 40 -20000 0 40 80
Moments 0 Distance (m) Moments 0 Distance (m)
(kNm) (kNm)
20000 MDL 20000
MDL
40000 40000
Stage 3: Stage 4:

-40000 -40000 MP,tot


MP,tot
-20000 0 40 80 120 -20000 0 40 80 120 160
Moments 0 Moments 0
(kNm) (kNm)
20000 20000
MDL MDL
40000 Distance (m) 40000 Distance (m)

Stage 5:

-40000
MP,tot
-20000 0 40 80 120 160 200
Moments 0 Distance (m)
(kNm)
20000
MDL
40000

52
Figure 5-6. Construction moments for segmental span-by-span method (continued)
Stage 6:

-40000
MP,tot
-20000 0 40 80 120 160 200 240
Moments 0 Distance (m)
(kNm)
20000
MDL
40000
Stage 7:

-40000
MP,tot
-20000 0 40 80 120 160 200 240 280
Moments 0 Distance (m)
(kNm)
20000
MDL
40000
Stage 8:

-40000
MP,tot
-20000 0 40 80 120 160 200 240 280 320
Moments 0 Distance (m)
(kNm)
20000 MDL
40000
Final moments at the instant of completion:
The final moments are the sum of all the construction moments.
-40000
MP,tot
-20000 0 40 80 120 160 200 240 280 320
Moments 0 Distance (m)
(kNm)
20000
MDL
40000

53
54

In the span-by-span method, the dead load moments at the instant of completion are biased
towards positive moment due to stress history compared to the same bridge built on falsework.
However, the instantaneous span-by-span moments (MSBS) would redistribute over time and shift
towards falsework moments (MFAL) because of creep. This redistribution of moments is
approximated by the following formula (Menn 1990):
M∞ = MSBS + α(MFAL + MSBS ) [5-1]

The factor α is chosen to be 0.7 for precast concrete. If cast-in-place concrete is used, α would
be 0.8 since it is more susceptible to effects of creep than precast concrete. The following graph
shows the redistribution of dead load moments for a case with L=40m and L/h=20.
-40000

-20000
0 40 80 120 160 200 240 280 320
Dead load
moment 0 Distance (m)
(kN)
20000

40000 Falsework Span-by-span M at infinity


Moment at infinity
Figure 5-7. Redistribution of dead load moments due to creep

When considering dead load moment only, significant redistribution of moments causes the
moment demand at midspan to decrease and demand at supports to increase. However, prestress
moments should also be included in the redistribution as shown in the following graph.
-40000

-20000
Dead load + 0 40 80 120 160 200 240 280 320
prestressing
0 Distance (m)
moments
(kN)
20000

Falsework Span-by-span M at infinity


Moment at infinity
40000
Figure 5-8. Redistribution of dead load and prestress moments due to creep

As illustrated in the graph, redistribution of the sum of prestress and dead load moments is
negligible. Therefore, moment redistribution is not considered in the analysis and the instantaneous
moments are used as moment demands for ULS and SLS checks.

5.3.2 Moments due to Thermal Gradient


For heavy bridges exposed to solar radiation, thermal gradients exist across the cross-section
depths, meaning that the top deck is warm while the bottom flange is cold. As a result, the girder
deflects upward under no external loads.
55

In a simply-supported girder, thermal gradient only causes deflection and not moments. On the
other hand, it imposes a moment on continuous girders since there are internal restraints. These
thermal gradient moments are directly proportional to the flexural stiffness. Therefore, thermal
gradient is a particularly important issue for span-by-span constructed bridges in which cross-
sections are generally stiffer. Thermal gradient causes positive moments, which can crack the
bottom flange, so additional bottom tendons are required in order to prevent such cracking. Also,
thermal gradient moments are considered only in serviceability design checks, because the cracked
flexural stiffness is small in ultimate limit states and thus thermal gradient moments are negligible.
In the analysis, thermal gradient effects are considered for serviceability limit states and are
obtained using the method described as follows. First, the continuous girder is made statically-
determinate by removing internal restraints. A thermal differential θ(y) of 10°C is then applied
between the 225mm thick top deck and the rest of the box (CSA 2006, Cl.3.9.4.4). The free strain
due to this temperature change is obtained by the following formula:
εf = αc θ(y) [5-2]
where αc = thermal coefficient of concrete
= 10 × 10−6 /℃ [CSA 2006, Cl.8.4.1.3]

This free strain profile follows the shape of the temperature change and is non-linear if
unrestrained expansion is allowed at all elevations. However, the final strain profile ε(y) needs to be
linear since plane section remains plane. The difference between the free strain and final strain
profiles gives the restraint strain which is needed to restore compatibility. The thermal gradient and
strain profiles are illustrated in the following diagram.

Figure 5-9. Thermal gradient effects

These self-equilibrating, restraint stresses due to non-linear thermal profile on a statically-


determinate structure causes the primary temperature stresses fr(y):
fr y = Ec ε y − εf [5-3]
= Ec ε y − α c θ y
56

The axial restraint force Pr and restraint moment Mr can then be computed from fr (y):
h h [5-4]
Pr = fr y b y dy = Ec ε y − αc θ y b y dy
0 0
h h [5-5]
Mr = fr y b y y − n dy = Ec ε y − αc θ y b y y − n dy
0 0

However, both Pr and Mr are equal to zero because there are no external forces and internal
redundancies have been removed to make the structure statically-determinate. By setting Equations
5-4 and 5-5 to zero, the final curvature of bending (ψ) and final strain (ε0) at elevation y=0 are
obtained as follows. A complete derivation is shown in Appendix B.3.
h
αc [5-6]
ψ= θ y b y y − n dy
I 0
h
αc [5-7]
ε0 = θ y b y dy − nψ
A 0

According to the final strain profile, the final strain at elevation y can be obtained by:
ε y = ε0 + ψy [5-8]

As a result, the primary thermal stresses become:


fr y = Ec ε0 + ψy − αc θ(y) [5-9]

In a statically-determinate structure, these primary stresses only cause the girder to hog, but
there is no net moment. However, in a continuous structure, the curvature Ψ created by primary
stresses is incompatible and are restrained by piers. In order for the structure to maintain
compatibility while a thermal deformation is imposed, positive restraint moments are needed at
each end of the span:
M = -Ec Iψ [5-10]

The final moment Mfinal is obtained using moment distribution (Figure 5-10). This positive
restraint moment causes tensile stresses at the bottom fibre near the piers where the post-tensioning
are arranged to resist negative moments. If the positive restraint moments are large enough to crack
the bottom flange, additional bottom tendons would be required near the piers such that the resultant
moments become negative.
Distance (m)
0 40 80 120 160 200 240 280 320
0

Moments due to 2000


thermal gradient
(kNm) 4000

6000

Figure 5-10. Moments due to thermal gradient


57

Furthermore, secondary thermal stresses fs are induced by Mfinal:


Mfinal (y − n) [5-11]
fs y =
I
The total thermal stresses that need to be considered in design checks are computed with the
following equation:
ftemp y = fr y + fs y [5-12]
Mfinal (y − n)
= Ec ε0 + ψ ∙ y − αc θ(y) +
I
5.4 Loss of Prestress
Since external, unbonded tendons are used, the loss of prestress due to friction is lower and the
effective prestress after all losses is expected to be greater than 60%fpu (1120 MPa) which is the
estimated value used for the cast-in-place on falsework analyses. Therefore, an explicit calculation
of prestress losses is performed. With a more detailed calculation, the increase in prestress is less
than 6% compared to the assumed value of prestress after all losses (1120 MPa = 60% fpu). This
increase in stress is not significant enough to reduce the prestressing requirement.

5.4.1 Friction Losses


Friction losses are proportional to the deviation angles of tendons. Thicker sections have larger
deviation angles and thus higher friction losses. The decrease in prestressing force due to friction
losses ∆P(x) are computed with the following formulae (Menn 1990).
P0 1 − e−μα x if μα x ≥ 0.2 [5-13]
∆P x =
P0 μα x if μα x < 0.2

where x=distance from stressing location


P0 =jacking force
σp0 =jacking stress=80%fpu =1490MPa
μ=coefficient of friction=0.25 for external ducts
α x =sum of angle changes between stressing location and point x
=αx +x∆α
αx =intentional angle changes refer to Figure 5-11
=α1 +α2 +…+αn
∆α=unintentional angle change due to construction tolerances and
displacement of tendon during concreting
=0° for external tendons

Figure 5-11. Intentional angle changes


58

The friction losses are summarized in the Table 5-1. The maximum loss is only 5% of fpu.

Table 5-1. Prestress losses due to friction Table 5-2. Prestress losses due to anchorage set
Friction losses (% of fPu) Anchorage set losses (% of fPu)
L/h 30m 40m 50m L/h 30m 40m 50m
15 4.33% 4.91% 5.09% 15 6.11% 5.63% 5.12%
20 2.70% 3.30% 3.56% 20 4.68% 4.62% 4.29%
25 − 2.37% 2.62% 25 − 3.76% 3.68%

The loss of prestress due to anchorage set is a function of friction losses. The anchorage set
is assumed to be 6mm and the prestress loss due to anchorage set is computed using Equation 5-14.
(Collins and Mitchell 1997). The prestress losses due to anchorage set are summarized in Table 5-2.
[5-14]
∆set Ap Ep
∆P x = 2p
p
where p= friction loss per unit length [kN/m]
∆set =anchorage set = 6mm

5.4.2 Creep and Shrinkage Losses


Creep and shrinkage losses for girders with external, unbonded tendons are computed using
Equation 5-15 which is modified from Menn’s formula for bonded tendons using new compatibility
conditions (Menn 1990).
1 [5-15]
nρ Ac φ t σc0 x dx + εcs t Ec Ac
lp
∆P t =
Ac
1 + nρ 1 + μφ t 1+ e2 x dx
l p Ic

where t = time measured from initial loading


e(x) = distance from centroid of gross uncracked concrete section
to centroid of tendon
Ec = modulus of elasticity of concrete at time of initial loading
Ep = modulus of elasticity of prestressing tendon
n = Ep /Ec
Ac = area of gross uncracked concrete section
Ap = area of tendon
Ic = moment of inertia of gross uncracked concrete section
ϕ t = time-varying creep coefficient
= 1.5 for precast concrete
= 2.0 for cast-in-place concrete
μ = aging coefficient = 0.8 (Menn 1990)
εcs t = time-varying shrinkage strain under relative humidity of 60%
Toronto value from CHBDC
σc0 x = concrete stress at tendon level due to initial load
lp = arc length of tendon between anchors
Integrations are made over length of tendon from anchors to anchors

The creep and shrinkage losses are summarized in Table 5-3.


59

Table 5-3. Prestress losses due to creep and shrinkage


Creep and shrinkage losses (% of fPu)
L/h 30m 40m 50m
15 7.85% 6.24% 2.10%
20 6.30% 9.71% 6.11%
25 − 5.91% 4.35%

5.4.3 Losses due to Relaxation of Prestressing Steel


Prestress loss due to relaxation of steel (∆σp,rel) is estimated to be 59.3 MPa (3.19% fpu) for all
cases according to the following relationship suggested by Menn (1990).
10

6
∆σp,rel /σp0
[%] 4

0
0.5 0.55 0.6 0.65 0.7 0.75
σp0/fpu
Figure 5-12. Long-term loss of prestress due to relaxation (Menn 1990)

5.4.4 Total Prestress Losses


The effective prestress after all losses for every case is summarized in the following table. It is
the average value along the length of the tendon.
Table 5-4. Effective prestress after all losses
Effective prestress after all
losses (% of fPu)
L/h 30m 40m 50m
15 61% 62% 66%
20 64% 60% 63%
25 − 64% 66%

As shown in the table, compared to the estimated value of effective prestress (60% fPu), the gain
in stress is less than 6% after an explicit calculation. This gain in stress has an insignificant impact
on prestress requirements, so an effective prestress after all losses of 60% fpu is used in
serviceability checks.
60

5.5 Behaviour of Unbonded Tendons at Ultimate Limit States


The ULS flexural strength calculations for span-by-span method differ from those for previous
analyses. Previously, strain in bonded tendons can be directly solved with compatibility equations at
the specific section of interest. In contrast, span-by-span method uses unbonded tendons, the tendon
strain does not equal to the concrete strain at the same elevation and plane, and thus the tendon
stress cannot be determined locally. Furthermore, since strains in unbonded tendons are averaged
out between the anchorages, girders with unbonded tendons often have lower flexural resistances
compared to girders with bonded tendons. Figure 5-13 compares the behaviours of the two types of
tendons.

Figure 5-13. Compatibility conditions for bonded and unbonded tendons (Collins and Mitchell 1997)

To solve this problem, the unbonded tendon stress at ULS can be assumed to equal to the
effective prestress after all losses (60%fpu) instead of the yielding stress (90%fpu), because girders
with unbonded tendons often have lower flexural resistances than those with bonded tendons (Menn
1990). This conservative assumption causes the ULS be a governing factor for the prestress
requirement and results in extra tendons that are unnecessary for satisfying ULS limits.
In order to compute the actual prestress force in unbonded tendons at ULS, an iterative process
is used. This process computes the global deformation of the entire tendon instead of just the strains
61

at one plane. The iterative method is explained in greater details in Appendix B.4. The prestress at
ULS obtained from explicit calculations are summarized in the following table:

Table 5-5. Prestress at ULS


Prestress at ULS (% of fPu)
L/h 30m 40m 50m
15 73% 75% 69%
20 75% 76% 75%
25 − 82% 75%

These prestress at ULS are larger than the effective prestress after all losses, meaning that fewer
tendons are needed compared to the conservative method proposed previously.

5.6 Analysis Results


This section summarizes the analysis results including structural behaviours at ULS and SLS,
material consumptions to satisfy design requirements as well as the factors that limit the slenderness
of span-by-span precast box-girders.

5.6.1 Structural Behaviour and Dimensioning


The following table describes the ULS flexural strength and SLS stress at the most critical
location as well as the stirrup spacing requirement to satisfy ULS shear. The sizing of prestressing
tendons is discussed in Section 5.6.4. ULS flexural strength demand governs the prestress
requirement for all cases because unbonded tendons result in a lower tendon stress that is averaged
over the entire tendon length. Moreover, thermal gradient moments are not large enough to cause
overall positive moments at the piers, thus bottom tendons are not needed at these regions.
Table 5-6. Summary of structural response of precast span-by-span box-girder
Ultimate limit states Serviceability limit states
L L/h __Flexural strength__ __Shear strength__ __Stresses__
2
(m) MULS (kNm) Mr (kNm) MULS/Mr Av (mm ) smin (mm) % of girder @ smin σSLS (MPa) σSLS/fcr
15 38700 42900 90% 1200 207 15% 0.58 21%
30
20 38700 43300 89% 2000 247 4.5% -0.22 -
15 79400 83600 95% 1200 141 21% 1.81 67%
40 20 65500 68600 95% 1200 165 27% 1.99 71%
25 65400 71000 92% 1200 119 32% 1.95 70%
15 101000 102000 99% 1200 189 23% -0.10 -
50 20 97800 99400 98% 1200 149 29% 1.49 53%
25 97900 99700 98% 1200 116 33% 1.96 70%

5.6.2 Vibration Limits


As shown in the following graph, vibration limits are satisfied for all analysis cases and do not
affect tendon requirements. The truck deflections are at least 40% lower than the vibration
deflection limits.
62

40

30 L=50m Limit

L=40m Limit
Truck load
deflection 20
(mm) L=50m
L=40m
10
L=30m Limit L=30m

0
10 15 20 25 30
L/h
Figure 5-14. Deflection for superstructure vibration limitation

5.6.3 Deflections
Deflection is not a limiting factor since the cross-sections are stiff and the resulting deflections
are insignificant. The maximum camber required is 93mm.
20000
L=30m
15000 L=40m
Dead load
L=50m
deflection
(L/∆) 10000
[down]
5000

0
10 15 20 25 30
L/h

15000
L=30m
Long-term
deflection 10000 L=40m
(creep + L=50m
elastic)
(L/∆) 5000
[down]

0
10 15 20 25 30
L/h

60000
Short-term L=40m
deflection
(dead load+ 40000 L=30m
prestress L=50m
before loss)
(L/∆) 20000
[up]

0
10 15 20 25 30
L/h
Figure 5-15. Deflections: a) dead load, b) long-term, c) short-term
63

5.6.4 Material Consumption


The following table and graphs summarize the material consumption for each analysis case as
well as their variations from the baseline case (i.e. L/h=15). These results are also illustrated in
cross-section drawings in Appendix C.3. Like the cast-in-place box-girder case, as slenderness ratio
increases, concrete volume less compared to the increase in tendons. For instance, when the
concrete volume decreases by only 4% from the baseline case, the number of prestressing tendons
increases by 52% for the case with span of 30m and ratio of 20. On the other hand, reinforcing steel
mass remains similar for all the cases with the same span length.
Table 5-7. Summary of material consumption for precast span-by-span box-girder
Concrete Prestressing tendon Reinforcing steel
L
L/h Volume % change from Number of % change from Mass % change from
(m) 3
(m ) baseline case tendons baseline case (ton) baseline case
15 1920 0% 138 0% 159 0%
30
20 1840 -4.0% 210 +52% 149 -5.8%

15 2780 0% 198 0% 236 0%


40 20 2660 -4.4% 224 +13% 227 -3.9%
25 2600 -6.6% 296 +49% 231 -2.2%

15 3640 0% 204 0% 307 0%


50 20 3400 -6.7% 256 +25% 294 -4.2%
25 3350 -8.1% 333 +63% 299 -2.5%

a) Concrete volume b) Number of prestressing strands


4,000 400

L=50m L=50m
3,000 300 L=40m
Concrete L=40m Prestress
volume strands 200 L=30m
2,000
(m3) L=30m

1,000 100

0 0
10 15 20 25 30 10 15 20 25 30
L/h L/h
c) Reinforcing steel mass
400

300 L=50m
Reinforcing
steel mass L=40m
200
(ton)
L=30m
100

0
10 15 20 25 30
L/h
Figure 5-16. Material consumptions for precast span-by-span box-girder
64

5.6.5 Limiting Factors of Span-to-Depth Ratios


For all three span lengths analyzed (i.e. 30m, 40m, and 50m), the maximum slenderness ratio is
limited by the minimum height of access inside the box. As stated previously in Section 4.2.2.5, a
minimum access height of 1.0m is used to allow for sufficient space for construction, inspection and
maintenance. The maximum slenderness ratios are restricted to 20 and 25 for the cases with spans
of 30m and 40m respectively. For these two extreme cases, the access height is determined by the
height of the interior box cavity as demonstrated in Figure 5-17 which shows the cross-section for
the case with span of 40m and ratio of 25.

Figure 5-17. Access limited by height of interior box cavity

For the case with a span of 50m, the maximum span-to-depth ratio is 25 as shown in Figure 5-
18. Compared to the previous two cases, the access height is further reduced due to the use of
external tendons. If the slenderness ratio is increased to 30, the height of the interior box cavity and
the access height would reduce to 1.24m and 0.83m respectively.

Figure 5-18. Access limited by height of interior box cavity and external tendons

This minimum access height limit is not a rigid design requirement and is used merely to ensure
ease of construction. Higher span-to-depth ratios can be achieved for all three span lengths if only
ULS and SLS requirements are considered. However, as shown in Figures 5-17 and 5-18, the
addition prestress associated with higher slenderness ratios can only be accommodated with a
second layer of tendons. Such tendon layout is less efficient, because it reduces the tendon
eccentricity and as a result, more prestressing is needed. Due to the inefficient tendon configuration,
these slender cases are expected to be less cost-effective. Nonetheless, these cases are not
considered in this study since the minimum access requirement is not satisfied.
6 COST COMPARISONS
This cost study investigates the changes in superstructure and total construction costs, which are
based on the previously described material consumption results, when span-to-depth ratio varies.
Comparison of these costs reveals the optimal span-to-depth ratio for each bridge type. The cost
study also demonstrates the cost benefits of using the optimal ratios instead of conventional ratios.
Furthermore, a sensitivity analysis is performed to examine the impacts of changing material unit
prices and construction cost breakdown.

6.1 Material Costs


This section describes the material unit prices and provides a material cost comparison of all the
analysis cases.

6.1.1 Material Unit Prices


The unit costs for concrete, prestressing tendons and reinforcing steel are listed in Table 6-1.
They are based on values obtained from cast-in-place post-tensioned highway bridges in Ontario
(SNC-Lavalin 2008). All unit prices include installation costs (i.e. concrete placement and vibration,
grouting of tendons).

Table 6-1. Material unit prices


Material Unit Unit price
3
Concrete (f’c = 50 MPa) per m $ 1500
3
Material only per m $ 250
3
Formwork, falsework, and labour per m $ 1250
Longitudinal prestressing tendons (including anchorages) per kg $ 8.5
Reinforcing steel per kg $ 5.0

6.1.1.1 Concrete Material Unit Price


Concrete unit price varies with compressive strength, because higher strengths require more
cementing material and admixtures. Material unit prices for concrete with strengths from 10 MPa to
60 MPa are summarized in Table 6-2. For strengths greater than 60 MPa, values are extrapolated
from Figure 6-1 as indicated by hollow points. These prices account for the material only and do not
include grouting, pumping, formwork, falsework, and labour (Dufferin Concrete 2009).

65
66

Table 6-2. Concrete material unit price


3 $500
Concrete compressive Unit price (per m )
strengths (MPa)
10 $ 149 $400
15 $ 154
Extrapolated
20 $ 158
$300 values
25 $ 164 Concrete
30 $ 171 material
35 $ 180 price ($/m3) $200
40 $ 192
45 $ 220
$100
50 $ 250
55 $ 262
60 $ 287 $0
65 $ 320 0 20 40 60 80 100
70 $ 353 Concrete strength (MPa)
75 $ 389
80 $ 428 Figure 6-1. Concrete material unit price

6.1.1.2 Cast-in-Place versus Precast Concrete


The final results of this cost study are insensitive to the cost of casting and erection equipment
since the study does not compare the costs between different construction methods and cost
comparisons are mainly performed for bridges of the same type with varying spans and slenderness
ratios. Therefore, in the analysis, the unit price of precast concrete is assumed to be the same as the
one for cast-in-place concrete.
In a real construction setting, the casting operation would cost relatively the same for different
span lengths and construction methods, but the initial cost of precast is generally higher than cast-
in-place concrete, because it needs to be custom-built and stored in a manufacturing plant. Yet,
precast segments are more economically competitive when they are mass-produced. So, the unit
price of precast concrete depends on the length of the bridge. Precast concrete would likely cost
more if a short, 2-span bridge is analyzed instead of a long, 8-span viaduct. However, precast
concrete increases the speed of construction and reduces the risk of downtime created by having
additional on-site operations (e.g. in cast-in-place construction, workers need to build formworks,
install rebars, pour and vibrate concrete on-site). Precasting also eliminates other construction
problems related to cast-in-place such as poor quality control. These advantages of precast concrete
cannot be easily quantified, so they are not considered in this cost study.
As stated previously, the unit cost of precast concrete depends on the total length of the bridge
due to the relatively high initial cost associated with precasting. This dependency becomes less
significant when precast concrete are more widespread and the level of standardization increases.
The study anticipates that precast segments will be readily available like standard I-sections, thus
the impact of initial costs is reduced. As a result, the unit price of precast concrete is assumed to be
the same as cast-in-place concrete in the cost analysis.
67

6.1.1.3 Falsework versus Erection Truss


Span-by-span method has a cost reduction compared to cast-in-place on falsework since it does
not require falsework. Some cost gain is expected because a multiple-span viaduct allows for the
reuse of erection truss for each span while falsework needs to be assembled for the entire structure.
This cost advantage only exists for long bridges with repetitive spans. For shorter bridges with
fewer spans, the use of falsework might be more economical since the initial cost of erection truss is
relative high. Another factor that affects the cost of span-by-span bridges is the span length, because
the cost of erection equipment increases as span length increases. The cost of erection truss
becomes prohibitive when the span length is greater than 50m due to the heavy dead load (Hewson
2003). On the other hand, the unit price for falsework remains relatively constant as span length
increases. Therefore, a more extensive study is needed to investigate the relationship between cost,
span length and number of spans for cast-in-place on falsework and span-by-span methods, but this
is beyond the scope of this research.

6.1.1.4 Formwork
The unit price of formwork increases as the cross-section becomes more complex. For instance,
solid slabs require less complicated formworks compared to box-girders which have more surfaces.
Likewise, formworks for bridges with external tendons are simpler because the cross-section has no
internal tendon ducts. Variation in formwork price with respect to cross-sectional complexity is not
considered in the cost analysis and a constant concrete unit price is used for all cross-sectional types.

6.1.1.5 Prestressing Tendons


Both internal bonded and external unbonded tendons have the same unit price of $8.5/kg.
Although external unbonded tendons are more expensive in terms of material costs, they require
less labour due to the simple and rapid assembly. As a result, the cost is assumed to be the same as
internal bonded tendons.

6.1.2 Material Cost Comparisons


This section compares the material costs per deck area for all the analysis cases. Only the
superstructure material costs are compared because they are directly related to the span-to-depth
ratios whereas other components of construction costs (i.e. mobilization, substructure, and
accessories) are assumed to be independent of superstructure slenderness. The comparisons are
illustrated using a series of graphs in which the maximum cost variation for each span length is
indicated as a percentage next to the label for each line.
68

6.1.2.1 Concrete Cost Comparison


Figure 6-2 summarizes the pure material cost of concrete of all the analysis cases evaluated. In
general concrete cost decreases with increasing slenderness ratio. For solid slabs, however, cost
increases drastically for the very slender cases which require concrete strengths higher than 50 MPa.
$300

L=35m, 29%
$250 L=30m, 43%
L=75m, 42%

L=60m, 40% L=20m,42%


$200 L=50m, 33%
Cost of concrete L=25m, 12%
L=35m, 24%
(material only)
per deck
area ($/m2) $150
L=50m, 8.8%
L=40m, 7.0%
L=30m, 4.2%

$100

$50
L=20m
CIP on falsework solid slab
L=35m
CIP on falsework box-girder
L=30m span-by-span box-girder
Precast
$0
5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-2. Concrete material cost comparison
$1,600

L=75m, 42%
$1,400
L=60m, 40%

$1,200 L=50m, 33% L=35m, 22%

L=35m, 24% L=30m, 24%


$1,000
Cost of concrete L=25m, 20%
per deck L=20m, 11%
L=50m, 8.8%
area ($/m2) $800 L=40m, 7.0%
L=30m, 4.2%

$600

$400

$200 L=20m
CIP on falsework solid slab
L=35m
CIP on falsework box-girder
L=30m span-by-span box-girder
Precast
$0
5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-3. Total concrete cost comparison
69

The cost effect of increasing concrete strength diminishes when the costs of formwork and
falsework or erection truss are included as shown in Figure 6-3. In general, concrete cost decreases
as span-to-depth ratio increases due to the reduction in superstructure depth. However, decrease in
concrete cost slows down at higher span-to-depth ratios, because the cost reduction is offset by the
increase in bottom slab thickness to accommodate compressive stress regions in box-girders or by
the increase in concrete strengths to satisfy maximum reinforcement criterion in solid slabs.
Concrete cost also varies substantially between different cross-section types even when the
same span length and span-to-depth ratio are used. For instance, for cases with a span of 35m, the
concrete costs are $1500/m2 for a solid slab with span-to-depth ratio of 30 and $836/m2 for a cast-
in-place box-girder with ratio of 25. Concrete cost for the thinner solid slab (depth = 1.2m) is 79%
more than the one for the deeper box-girder (depth = 1.4m) even though the cross-sectional depths
vary by only 17%. This comparison indicates a significant reduction in concrete consumption,
which translates into dead load reduction, occurs when a box section is used instead of a solid slab.

6.1.2.2 Prestressing Cost Comparison


Unlike concrete, the cost of prestressing tendons varies substantially as span-to-depth ratio rises
as shown in Figure 6-4.
$500

$450

$400
L=35m, 39%
$350

Cost of prestress L=30m, 60%


$300
steel per deck
area ($/m )2

$250
L=50m, 62% L=25m, 40%

$200 L=40m, 49% L=20m, 53%

$150 L=75m, 284% L=30m, 53%

$100 L=60m, 223%


L=20m
CIP on falsework solid slab
$50 L=50m, 209%
CIP on falsework box-girder
L=35m
L=35m, 161%
L=30m span-by-span box-girder
Precast
$0
5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-4. Prestressing tendon cost comparison

The maximum cost differences amongst cases with the same span length are 284% for cast-in-
place on falsework box-girder, 60% for cast-in-place on falsework solid slab, and 62% for precast
70

span-by-span box-girder. The increases in prestressing demand are significant because although the
dead load (i.e. concrete volume) decreases as girder becomes more slender, this load reduction
cannot compensate for the relatively large decline in moment resistance which is attributed to the
decrease in flexural stiffness of the cross-section and in efficiency of tendon layout (tendon
eccentricity is lower for slender sections). This problem is illustrated in Table 6-3 which shows the
maximum change in concrete volume, girder depth, moment of inertia (proportional to flexural
stiffness), and prestress demand between the case with the lowest span-to-depth ratio and the case
with the highest ratio for a particular span length for each bridge type. For all three bridge types, the
decrease in dead load is small relative to the decrease in girder depth and modulus of elasticity. As a
result, more prestressing steels are needed to offset the reduced load capacity.
Table 6-3. Comparison of changes in cross-sectional depth and prestressing demand
Factor CIP on falsework box-girder CIP on falsework solid slab Precast span-by-span box-girder
(L=75m) (L=30m) (L=50m)
Concrete volume -29% -26% -8.1%
Girder depth -71% -33% -40%
Moment of inertia -94% -70% -69%
Prestress demand +284% +60% +62%

A comparison of prestressing steel costs between bridge types confirms that solid slab is the
least efficient in resisting loads. For example, for a span length of 35m, the prestressing tendons
required for a solid slab with a span-to-depth ratio of 30 is $275/m2 which is 2.4 times greater than
the $117/m2 needed for a cast-in-place box-girder with span-to-depth ratio of 25. Solid slabs require
more prestressing per unit deck area because they are heavier than box-girders with the same span
lengths and depths. Precast span-by-span box-girder is more efficient than solid slabs but less
efficient than cast-in-place box-girder, because it uses external tendons which reduce tendon
eccentricities and thus lowers the prestress moments. For instance, for the cases with span length of
50m and span-to-depth ratio of 25, the prestressing tendons required in a precast box-girder
($215/m2) cost 30% more than the tendons needed in a cast-in-place box-girder ($165/m2) although
the precast case has 7.6% less dead load.

6.1.2.3 Reinforcing Steel Cost Comparison


Cost of non-prestressed reinforcing steel depends on the shear stirrup requirement and concrete
volume. Figure 6-5 shows the cost of stirrups in solid lines and the cost of minimum reinforcing
steels in dashed lines. In this study, the minimum reinforcing steel is defined as all the non-
prestressed steels other than stirrups and is illustrated in Figures 4-3, 4-15 and 5-4.
71

$400
CIP on falsework solid slab
L=20m
L=35m
CIP on falsework box-girder
$350 L=30m
L=75m, 42% Precast span-by-span box-girder
Stirrups
L=50m
$300 L=60m, 40% Minimum
L=30m reinforcing steel
L=50m, 33%
Cost of $250 L=35m, 24%
reinforcing
steel per
deck area $200 L=50m, 8.8%
($/m2) L=40m, 7.0%
L=30m, 4.2%
$150
L=20m, 22%
L=25m, 23%
L=30m, 35%
$100 L=35m, 37%

L=75m, 110%
L=60m, 84% L=50m, 23% L=35m, 257%
$50 L=40m, 18% L=30m, 413%
L=50m, 76% L=25m, 180%
L=35m, 40% L=30m, 18% L=20m, 423%
$0
5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-5. Cost comparison of stirrups and minimum reinforcing steel

As shown in Figure 6-5, cost of stirrups generally increases with span-to-depth ratios since
more stirrups are needed for slender cases which have lower shear resistances. The increase in
stirrup cost for cast-in-place box-girders slows down for ratios beyond 30, because 25M bars, which
result in a more efficient stirrup layout for these cases, is used instead of 20M bars. Also, solid slabs
require fewer stirrups compared to box-girders because they have longer effective widths and
higher concrete strengths for slender cases which result in greater concrete shear resistances. The
large number of prestressing tendons, which are needed for adequate flexural resistances, further
helps in resisting shears. For instance, for the cases with a span length of 35m, the stirrups required
for a solid slab with a span-to-depth ratio of 30 cost $15/m2 while they cost 3.2 times more for a
box-girder with a ratio of 25 (i.e. $48/m2).
The dashed lines on Figure 6-5 show the costs of minimum reinforcing steel required for
stability of the steel bar cage and for crack control. The minimum requirement of reinforcing steel is
proportional to the concrete volume, so it decreases as span-to-depth ratio increases.
The total cost of reinforcing steel is the sum of the costs of stirrups and minimum reinforcing
steel and the contributions of these two cost components vary over different span-to-depth ratios.
Figure 6-6 illustrates the contribution of each component by comparing the percentage distributions
and the actual costs for the longest span case for each bridge type. As shown in Figure 6-6 a, the
impact of stirrups on the total reinforcing steel cost increases as the girder becomes more slender
72

regardless of bridge type. This trend is a result of the reduction in minimum reinforcement due to
decreasing concrete volume and the rise in shear demand due to increasing girder slenderness.
As shown in Figure 6-6 b, for both cast-in-place and precast box-girders, the total reinforcing
steel cost decreases as span-to-depth ratio increases until 20. For these cases, decrease in minimum
reinforcing steel is significant due to the large reduction in concrete volume (shown in Figures 4-8 a
and 5-16 a) while the increase in stirrups is relatively small. As a result, the total reinforcing steel
cost exhibits an overall decreasing trend. When span-to-depth ratio increases beyond 20, the
reduction in reinforcing steel diminishes and becomes insignificant compared to the increase in
stirrups, resulting in an overall increase in total reinforcing steel cost.
For solid slabs, the total reinforcing steel cost does not increase significantly even for span-to-
depth ratios above 20. Although the stirrups cost increases by more than two times over the entire
range of ratios, this increase is offset by the equally large decrease in minimum reinforcement cost.
The decrease in minimum reinforcement is relatively large compare to the one for box-girders with
the same slenderness ratios, because solid slabs experience constant volume reduction as span-to-
depth ratio increases whereas the volume diminishes at a decreasing rate for box-girders (discussed
previously in Section 4.3.3.5 and illustrated in Figure 4-20 a).
a) Percentage distribution of reinforcing steel cost
100%

80% Minimum
reinforcing
60% steel
Stirrups
40%

20%

0%
10 15 20 25 30 35 30 35 40 45 15 20 25

b) Distribution of reinforcing steel cost


$400

Minimum
$300
reinforcing
steel
$200 Stirrups

$100

$0
10 15 20 25 30 35 30 35 40 45 15 20 25
L=75m L=35m L=50m
CIP on falsework box-girder CIP on falsework solid slab Precast span-by-
span box-girder
Figure 6-6. Cost distribution of stirrups and minimum reinforcing steel
73

The total cost of reinforcing steel for all analysis cases is shown in Figure 6-7. The maximum
variations in total reinforcing steel cost over the analysis range of ratios are only 18% for cast-in-
place on falsework box-girder, 5.8% for cast-in-place on falsework solid slab, and 6.2% for precast
span-by-span box-girder.
$400 L=75m, 18%

$350 L=60m, 18%

L=50m, 18%
$300
L=35m, 17%

$250 L=50m, 4.3%


Cost of L=40m, 4.0%
reinforcing L=30m, 6.2%
steel per $200
deck area
($/m2)
$150 L=35m, 5.4%
L=30m, 5.8%
L=25m, 2.5%
L=20m, 2.7%
$100

CIP on falsework solid slab


L=20m
$50
L=35m
CIP on falsework box-girder
L=30m
Precast span-by-span box-girder
$0
5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-7. Total reinforcing steel cost comparison

6.1.2.4 Total Superstructure Cost


Figure 6-8 describes the total superstructure material cost, which consists of costs of concrete
(material only), prestressing tendon, and reinforcing steel. The contribution of these three
components are summarized in Figure 6-8 a. For deep box-girders, the superstructure material cost
is mainly governed by concrete and reinforcing steel costs which decrease as span-to-depth ratio
increases due to the reduction in concrete volume. The effect of increasing prestressing tendon cost
is relatively minimal and is overshadowed by the reduction in concrete and reinforcement costs.
Therefore, the total material cost exhibits an overall decreasing trend for low span-to-depth ratios.
For the slender box-girders, the costs of prestressing tendon and reinforcing steel rise as span-to-
depth ratio increases. This cost increase is greater than the concrete cost reduction since the
decreasing in concrete volume slows down at higher span-to-depth ratios. As a result, the total
material cost experiences a net increase at higher ratios. For slender solid slabs, increase in material
cost is also attributed to the increase in concrete cost from the use of higher strength concrete.
74

a) Percentage distribution of superstructure material cost


100%

80% Prestressing
tendon
60%
Reinforcing
40% steel

20% Concrete
(material only)
0%
10 15 20 25 30 35 30 35 40 45 15 20 25
L=75m L=35m L=50m
CIP on falsework box-girder CIP on falsework solid slab Precast span-by-
span box-girder

b) Total superstructure material cost


$2,000

$1,500

Total material
cost per deck
area ($/m2)
$1,000

L=75m, 42% L=35m, 27%


L=60m, 22% L=30m, 28%
L=50m, 19% L=50m, 12%
L=35m, 6.3% L=40m, 9.2% L=25m, 11%
$500 L=30m, 6.7% L=20m, 28%

CIP on falsework solid slab


L=20m
L=35m
CIP on falsework box-girder
L=30m span-by-span box-girder
Precast
$0
5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-8. Total superstructure material cost comparison

Figure 6-9 describes the total superstructure cost which includes the falsework and casting costs
of concrete in addition to the total material cost. As stated in Section 6.1.1, the cost of concrete
casting and falsework is a function of concrete volume and is not related to concrete strength, and
thus it generally decreases as span-to-depth ratio increases. This decreasing casting and falsework
cost amplifies the cost reduction for deep girders and dampens the cost increase for slender girders.
The dampening effect is especially obvious for solid slabs in which the concrete volume reduction
associated with rising span-to-depth ratio is significant.
75

a) Percentage distribution of superstructure cost


100%

80% Prestressing
tendon
60% Reinforcing
steel
40%
Concrete
20% (material and
placement)
0%
10 15 20 25 30 35 30 35 40 45 15 20 25
L=75m L=35m L=50m
CIP on falsework box-girder CIP on falsework solid slab Precast span-by-
span box-girder
b) Total superstructure cost
$2,000 L=75m, 18%

L=60m, 20% L=35m, 12%


L=50m, 17%
$1,500 L=30m, 12%
L=35m, 14%
L=50m, 3.3% L=25m, 9.6%
L=40m, 2.6%
L=20m, 3.6%
Superstructure L=30m, 0.3%
cost per $1,000
deck area
($/m2)

$500

CIP on falsework solid slab


L=20m
CIP on falsework box-girder
L=35m
L=30m span-by-span box-girder
Precast
$0
5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-9. Total superstructure cost comparison (including cost of concrete placement)

The optimal span-to-depth ratio in terms of superstructure costs is determined by balancing the
concrete cost reduction with the prestressing cost increase as span-to-depth ratio rises. In terms of
superstructure material costs only, the cost optimal ratios are 15, 30, and 15 for cast-in-place on
falsework box-girder, solid slab and precast span-by-span box-girder respectively. These optimal
ratios increase to 25, 40, and 20 if the total superstructure costs are considered. This improvement
in slenderness ratio demonstrates the construction economy related to slender and lighter
superstructures.
Although these optimal ratios based on total superstructure costs are higher than the
conventional ones, the changes in superstructure cost between these two sets of ratios are actually
76

minor (less than 11%) as shown in Table 6-4. Using the more cost-efficient ratios instead of
conventional ratios yields only insignificant total superstructure cost savings compared to the
changes in individual material costs. The table also shows the maximum cost variations within the
entire range of slenderness ratios analyzed in parentheses. Even if the least cost-efficient ratio is
used, the total superstructure cost increases by only 20%.
Table 6-4. Total superstructure cost variations
CIP on falsework box-girder CIP on falsework solid slab Precast span-by-span box-girder
Analysis range of ratios 10 - 35 30 - 50 15 - 30
Conventional ratio 20 30 17
Optimal ratio 25 40 20
Cost component
Concrete -5.1% (42%) -19% (24%) -4.1% (8.8%)
Prestressing tendon +28% (284%) +53% (60%) +26% (62%)
Reinforcing steel -1.3% (18%) -5.3% (5.8%) -3.6% (6.2%)
Total superstructure -0.6% (20%) -11% (12%) -1.8% (3.3%)

Furthermore, Figure 6-9 shows that instead of refining cross-sectional component dimensions,
using a more efficient structural system results in greater cost savings. For instance, for a span
length of 35m, a cast-in-place solid slab with a slenderness ratio of 30 costs 59% more than a cast-
in-place box-girder with a ratio of 25. Therefore, the superstructure cost savings associated with
optimizing the span-to-depth ratios are negligible compared to the savings from choosing the proper
bridge type for a given span length and girder depth.

6.2 Overall Construction Costs


This section discusses the impact of optimizing span-to-depth ratio on the total construction cost
which includes the costs of superstructure, substructure, mobilization and accessories such as
bearings. First, the percentage breakdown of these cost components with respect to the total
construction cost is described in Section 6.2.1. Section 6.2.2 then describes the total construction
costs for all analysis cases computed using this cost breakdown. The analysis results indicate that
varying the span-to-depth ratio has minor influence on the total construction cost, because only the
superstructure cost depends on span-to-depth ratio whereas the cost of substructure and accessories
are related more to the span length.

6.2.1 Construction Cost Breakdown


The construction cost breakdown used in the analysis is adopted from Menn’s cost study on 19
concrete highway bridges constructed between 1958 and 1985 in Switzerland (Table 6-5).
Mobilization comprises of all the work that needs to be completed prior to the onset of construction.
Such tasks include preparing site facilities, procuring equipments and establishing access to the
construction site. Some examples of accessories are bearings, expansion joints, and drainage
77

systems. These two factors are independent of span-to-depth ratio, but they are related to the bridge
site conditions, number of spans, and bridge length. Likewise, the substructure cost depends more
on geotechnical conditions and bridge height. Therefore, the costs for these three items are
computed for the baseline cases only and are assumed to be constant for all other analysis cases
with the same span length.
Table 6-5. Construction cost breakdown (Menn 1990)
Item Cost
(% of total construction cost)
Mobilization 8.0%
Structure
Substructure
Foundations 18.0%
Piers and abutments 5.5%
Total substructure 23.5% 23.5%
Superstructure
Total superstructure 54.5%
Total structure 78.0% 78.0%
Accessories 14.0%
Total construction cost 100.0%

6.2.2 Total Construction Cost Comparison


The total construction costs for all analysis cases are illustrated in Figure 6-10 and a sample
calculation is shown in Appendix B.5. The trend and the most cost-optimal ratios are the same as
the ones for superstructure cost, because the total construction cost is simply the sum of
superstructure cost and the costs of substructure, mobilization and accessories which are constant
amongst analysis cases with the same span length. However, factoring in this constant cost further
diminishes the economic incentive of optimizing span-to-depth ratios. In fact, the total construction
cost premiums of using the optimal ratios instead of conventional ratios are only 0.4% for cast-in-
place box-girder, 5.8% for cast-in-place solid slab, and 1.0% for precast span-by-span box-girder.
Even within the entire feasible range of span-to-depth ratios, maximum variations in total
construction cost are only 11%, 6.2% and 1.8% for the three bridge types respectively.
These cost reductions related to optimizing span-to-depth ratios for a given span are
insignificant compared to the cost reduction from choosing a suitable bridge type and span
arrangement. For instance, for a span length of 35m, using a cast-in-place box-girder with
slenderness ratio of 25 instead of a cast-in-place solid slab with a ratio of 30 reduces the total
construction cost by 37%. Cost improvement can also be attained by using shorter span lengths. For
instance, using a span length of 50m instead of 75m reduces the total construction cost by 20% in
cast-in-place box-girders.
78

$4,000

$3,500
L=75m, 10%
L=35m, 6.1%
$3,000 L=60m, 11%
L=30m, 6.2%
L=50m, 9.0%
Total
$2,500 L=25m, 5.0%
construction L=35m, 7.7% L=50m, 1.8%
cost per L=40m, 1.4% L=20m, 1.9%
deck area L=30m, 0.1%
$2,000
($/m2)

$1,500

$1,000

$500 CIP on falsework solid slab


L=20m
L=35m
CIP on falsework box-girder
L=30m span-by-span box-girder
Precast
$0
5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-10. Total construction cost comparison

6.3 Other Cost Factors


In addition to construction costs, bridge designers are also concerned with other cost factors
such as operation, maintenance, rehabilitation, and demolition costs. These factors are excluded in
this cost study, but changing span-to-depth ratio is expected to have minor effects on these costs.
These factors depend more on the overall design concept (e.g. structural system, cross-section type,
span arrangement) than on the dimensioning of structural components (Menn 1990).
79

6.4 Sensitivity Analysis


The purpose of the sensitivity study is to investigate how sensitive are the analysis results to
changes in material unit prices and in breakdown of construction costs. The material unit prices
vary in different locations due to differences in labour costs and technology levels. The construction
cost breakdown also changes depending on the site conditions.

6.4.1 Sensitivity with Respect to Changes in Material Unit Prices


The first aspect to investigate is the impact of changes in material unit prices. A new set of
superstructure costs are calculated based on the following variations in material unit prices:

Table 6-6. Material unit price changes


Material Unit Original price +50% -50%
3
Concrete per m $ 1,500 $ 2,250 $ 750
Prestressing tendon per kg $ 8.50 $ 12.75 $ 4.25
Reinforcing steel per kg $ 5.00 $ 7.50 $ 2.50

These changes in unit prices are drastic and are chosen for only illustrative purposes such that a
clear trend would be observed. A more realistic maximum price change would be around 20%.
The effects of changing unit prices on total construction costs are illustrated in the following
graphs. The maximum percentage differences in cost for each span length over the specified range
of span-to-depth ratios are also indicated on the graphs. The dashed lines represent the costs under
original unit prices while the solid lines represent the costs when the unit prices vary by 50%. The
impacts of altering unit prices are illustrated in Figures 6-11 and 6-12 for concrete, Figures 6-13 and
6-14 for prestressing tendons, and Figures 6-15 and 6-16 for reinforcing steel. The graphs show
that modifying concrete unit price has the greatest influence on the total construction cost, because
concrete cost constitutes a large portion of the superstructure cost. For example, for a cast-in-place
on falsework box-girder with span length of 75m and span-to-depth ratio of 10, increasing the
concrete unit cost by 50% raises the total construction cost by 35%. On the other hand, increasing
the prestressing cost by 50% only increases the total construction cost by 4.6%.
80

$5,000

L=75m, 12%
L=35m, 8.7%

$4,000 L=60m, 13% L=30m, 8.0%


L=50m, 11%
L=25m, 6.4%
L=35m, 9.1%
Total L=50m, 2.2%
$3,000 L=40m, 1.7% L=20m, 3.8%
construction
cost per L=30m, 0.5%
deck area
($/m2)
$2,000

$1,000
CIP on falsework solid slab
L=35m
L=75m
CIP on falsework box-girder
L=50m span-by-span box-girder
Precast
$0
0 5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-11. Total construction cost comparison (+50% concrete unit price)

$5,000

$4,000

Total
construction $3,000
cost per
deck area
($/m2)
L=75m, 12%
$2,000 L=35m, 3.8%
L=60m, 7.8% L=30m, 3.1%
L=50m, 6.6% L=50m, 3.1%
L=35m, 5.4% L=25m, 1.9%
L=40m, 2.8% L=20m, 2.8%
L=30m, 1.5%
$1,000
L=25m
CIP on falsework solid slab
L=75m
CIP on falsework box-girder
L=50m span-by-span box-girder
Precast
$0
0 5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-12. Total construction cost comparison (-50% concrete unit price)
81

$5,000

$4,000

L=75m, 11% L=35m, 5.5%


Total
construction $3,000 L=60m, 8.8% L=30m, 4.9%
cost per
L=50m, 7.4% L=25m, 3.5%
deck area L=50m, 2.7%
($/m2) L=35m, 6.0% L=40m, 2.3% L=20m, 2.4%
L=30m, 1.3%
$2,000

$1,000
L=25m
CIP on falsework solid slab
L=75m
CIP on falsework box-girder
L=50m span-by-span box-girder
Precast
$0
0 5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-13. Total construction cost comparison (+50% prestressing tendon unit price)

$5,000

$4,000

Total
construction L=75m, 13%
$3,000 L=35m, 9.3%
cost per L=60m, 13%
deck area L=50m, 12% L=30m, 8.3%
($/m2)
L=35m, 9.7% L=50m, 2.5% L=25m, 6.8%
L=40m, 1.9% L=20m, 3.9%
$2,000 L=30m, 1.1%

$1,000
L=35m
CIP on falsework solid slab
L=75m
CIP on falsework box-girder
L=50m
Precast span-by-span box-girder
$0
0 5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-14. Total construction cost comparison (-50% prestressing tendon unit price)
82

$5,000

$4,000

L=75m, 10%
L=35m, 6.7%
Total L=60m, 11%
construction $3,000 L=50m, 9.1% L=30m, 6.1%
cost per
deck area L=35m, 7.7% L=50m, 1.7% L=25m, 4.7%
L=40m, 1.5%
($/m2) L=20m, 2.9%
L=30m, 0.2%
$2,000

$1,000
L=35m
CIP on falsework solid slab
L=75m
CIP on falsework box-girder
Precast
L=50m span-by-span box-girder
$0
0 5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-15. Total construction cost comparison (+50% reinforcing steel unit price)

$5,000

$4,000

Total
construction L=35m, 7.4%
$3,000 L=75m, 10%
cost per
L=30m, 6.9%
deck area L=60m, 11%
($/m2) L=50m, 9.0% L=25m, 5.3%
L=50m, 1.8% L=20m, 3.2%
L=35m, 7.6% L=40m, 1.5%
$2,000
L=30m, 0.5%

$1,000
L=35m
CIP on falsework solid slab
L=75m
CIP on falsework box-girder
L=50m span-by-span box-girder
Precast
$0
0 5 10 15 20 25 30 35 40 45 50 55
L/h
Figure 6-16. Total construction cost comparison (-50% reinforcing steel unit price)

As shown in the graphs, the optimal span-to-depth ratios remain at 25, 40, and 20 for cast-in-
place box-girder, cast-in-place solid slab, and precast box-girder regardless of unit price changes.
Table 6-7 summarizes the maximum cost improvements of using these optimal span-to-depth ratios
83

instead of conventional ratios for the specified variations in unit price. Despite such drastic unit
price changes, the cost improvements are only 0.6% ± 1.1% for cast-in-place box-girder, 5.8% ±
2.3% for cast-in-place solid-slabs, and 1.0% ± 0.5% for precast span-by-span box-girder.
Table 6-7 also lists the maximum percentage changes in cost over the entire range of span-to-
depth ratio in parentheses. These values represent the maximum cost increase when the least cost-
efficient span-to-depth ratios are used instead of the optimal ratios. For instance, for a given span
length, using a span-to-depth ratio of 10 instead of the optimal ratio results in 11% increase in total
construction cost for cast-in-place box-girder. This increase in cost changes to 12% if the concrete
unit price is increased by 50%. For cases with altered unit prices, the changes in cost with respect to
span-to-depth ratios deviate less than 3% from the ones for cases with original unit prices. Since the
optimal ratios remain the same and the changes in cost improvements are negligible (less than 3%),
results from the cost study are insensitive to modifications in unit prices.
Table 6-7. Summary of material unit price sensitivity analysis
Unit cost change CIP on falsework box-girder CIP on falsework solid slab Precast span-by-span box-girder
Range of L/h ratio 10 - 35 30 - 50 15 - 30
Optimal ratio 25 40 20
Conventional ratio 20 30 17
Original unit prices 0.4% (11%) 5.8% (6.2%) 1.0% (1.8%)
+50% concrete 0.9% (12%) 7.9% (8.7%) 1.3% (2.2%)
-50% concrete 1.5% (12%) 3.6% (3.8%) 0.5% (3.1%)
+50% prestressing tendon 0.9% (11%) 5.2% (5.5%) 0.8% (2.7%)
-50% prestressing tendon 1.0% (13%) 8.1% (9.3%) 1.5% (2.5%)
+50% reinforcing steel 0.3% (11%) 6.3% (6.7%) 1.0% (1.7%)
-50% reinforcing steel 0.4% (11%) 6.9% (7.4%) 0.9% (1.8%)

6.4.2 Sensitivity with Respect to Changes in Construction Cost Breakdown


The purpose of this section of the sensitivity study is to investigate the impact of altering the
construction cost breakdown. Hitherto, the cost results are computed according to Menn’s
breakdown of construction costs as described in Section 6.2.1. This breakdown changes under
situations such as complications in geotechnical and hydraulic conditions, changes in bridge height
which affect pier costs, and variations in mobilization cost for different construction sites.
Previous cost calculations assume that the superstructure costs constitute 54.5% of the total
construction cost for the baseline cases. Costs for the remaining items (i.e. substructure,
mobilization and accessories) are computed based on the superstructure costs of the baseline cases
and are set to be constant for the other cases with the same span lengths. Therefore, altering only the
proportion of superstructure cost is sufficient in demonstrating the influence of different
construction cost breakdowns. The total construction costs obtained from varying the superstructure
component from 20% to 80% for cast-in-place on falsework box-girder with a span length of 50m
are plotted in Figure 6-17.
84

As shown in the graph, changing the superstructure percentage basically shifts the curves
vertically while the cost difference between cases with different span-to-depth ratios remains the
same for each curve. As a result, the optimal ratio remains at 25 regardless of changes in the cost
breakdown. The graph also shows the percentage cost improvements from conventional ratio to
optimal ratio on the left (maximum cost variations over the entire range of span-to-depth ratios are
shown in parentheses). Obviously, the cost improvement increases as superstructure percentage
increases because the effect of reducing superstructure cost on the total construction cost is greater
if superstructure cost forms a large portion of the total cost. Therefore, using optimal span-to-depth
ratios poses more economic incentive if the superstructure percentage is higher. However, in spite
of the changes in the cost breakdown, the saving from using the optimal ratio instead of
conventional ratio is still less than 0.5% while the maximum cost variation within the entire range
of ratio is less than 13%. The same pattern occurs in the other bridge types and span lengths as
shown in Appendix C.4. Therefore, the values for optimal span-to-depth ratio as well as the cost
variations between cases with optimal and conventional ratios are insensitive to changes in cost
breakdown.

$8,000

Cost variation Superstructure as % of


total construction cost
0.1% (3.4%)
20%

$6,000

Total construction
cost per deck area
0.2% (5.2%)
($/m2) 30%
$4,000
0.3% (6.9%)
40%
0.3% (8.6%)
0.4% (9.0%) 50%
0.4% (10%) 54.5% (Menn)
0.5% (12%) 60%
$2,000 0.5% (13%) 70%
80%

$0
0 5 10 15 20 25 30 35
L/h
Figure 6-17. Total construction costs under changes in construction cost breakdown
85

6.5 Concluding Remarks


The results of this cost study are summarized in Table 6-8 which shows the percentage changes
in cost when optimal ratios instead of the conventional ones are used. Cost variations over the
analysis range of ratios are also included within the parentheses. For all three bridge types, the cost-
effective ratios are higher than the conventional ratios, but the actual cost saving associated with
using optimal ratios is less than 5.8%. The cost study also determines that the maximum cost
variability is less than 11%, meaning that using the least cost-efficient ratio within the analysis
range would only incur a relatively small additional cost. The range of cost-optimal ratios is thus
expanded from the typical ranges defined in Chapter 2 to the analysis ranges of ratios indicated in
Table 6-8.

Table 6-8. Summary of cost study


CIP on falsework box-girder CIP on falsework solid slab Precast span-by-span box-girder
Analysis range of ratios 10 - 35 30 - 50 15 - 30
Typical range of ratios 17.7 - 22.6 22 - 39 15.7 - 18.8
Conventional ratio 20 30 17
Cost-optimal ratio 25 40 20
Cost component
Concrete -5.1% (42%) -19% (24%) -4.1% (8.8%)
Prestressing tendon +28% (284%) +53% (60%) +26% (62%)
Reinforcing steel -1.3% (18%) -5.3% (5.8%) -3.6% (6.2%)
Total superstructure -0.6% (20%) -11% (12%) -1.8% (3.3%)
Total construction cost -0.4% (11%) -5.8% (6.2%) -1.0% (1.8%)

The results in Table 6-8 are found to be insensitive to changes in material unit price and
construction cost breakdown. The optimal ratios, however, are determined based on parameters
defined specifically for this study such as cross-section dimensions and span arrangements. If these
parameters are altered, the optimums would likely be different. For example, the optimal ratios
might increase if thicker webs are used for box-girders, because the prestressing requirement is
reduced for slender cases due to the more efficient tendon layout as discussed in Section 4.2.2.5.
Therefore, the actual values of optimal ratios determined in this study are expected to change in a
real situation.
Yet, the general finding regarding the variability in cost is still valid for a broad range of
situations, because the study demonstrates that cost savings from the use of optimal ratios are minor
compared to other construction cost components which are independent of span-to-depth ratio (e.g.
costs of mobilization, substructure, and accessories). So, even if optimal ratio changes, the
variability in cost is expected to remain relatively insignificant over the analysis range of ratios.
7 AESTHETICS COMPARISONS
The selection of slenderness ratio has significant impact on the overall appearance of girder
bridges. In particular, the ratio is an especially important visual criterion for highway overpasses,
which are mostly observed from the highways passing beneath them, because the superstructure is
the “prime object of scrutiny” from this view point (Elliott 1991). The previous cost study
demonstrates that total construction cost varies by less than 11% over the range of span-to-depth
ratios investigated. This finding provides the designer with more freedom for aesthetic expressions
since he can choose from a wide range of slenderness ratios without much economic restrictions.
This chapter examines these aesthetic opportunities by comparing the visual impacts of different
span-to-depth ratios. This chapter also discusses some visually superior slenderness ratios by
exploring existing bridges, which have been considered by the general public as aesthetically
pleasing, and by examining some past studies on bridge aesthetics.

7.1 Visual Impact of Span-to-Depth Ratio


This section demonstrates the visual impact of altering slenderness ratios by comparing
drawings of bridges with various ratios as shown in Figures 7-1 to 7-3. These figures compare
bridges with: a) conventional ratio obtained from Chapter 2; b) optimal ratio in terms of cost
efficiency determined in Chapter 6; c) least cost-efficient ratio for each of the three bridge types
considered. The total construction cost and its percentage variation from the cost of the optimal
ratio are indicated in the parentheses. Each set of drawing includes a 3-D rendering from the
vantage point of a driver, who is passing under the overpass at 150m away from the bridge, as well
as 2-D elevation and cross-sectional views. The 2-D drawings are included to illustrate that
although changing the slenderness ratio results in clear visual differences on paper, such differences
might not be as apparent from the driver’s perspective in a real situation. The drawings do not
include barriers; the effect of barriers is discussed in Section 7.1.2. Also, all the 3-D drawings are
obtained under the same lighting condition.

86
87

a) Conventional L/h = 20 ($2450/m2, 0.4%)

b) Optimal L/h = 25 ($2460/m2)

c) Maximum cost L/h = 10 ($2670/m2, 9.0%)

Figure 7-1. Cast-in-place on falsework box-girder with L=50m


88

a) & c) Conventional and maximum cost L/h = 30 ($3000/m2, 5.8%)

b) Optimal L/h = 40 ($2830/m2)

Figure 7-2. Cast-in-place on falsework solid slab with L=30m


89

a) Conventional L/h = 17 ($2370/m2, 1.0%)

b) Optimal L/h = 20 ($2350/m2)

c) Maximum cost L/h = 25 ($2390/m2, 1.8%)

Figure 7-3. Precast segmental span-by-span box-girder with L=50m

As shown in Figures 7-1 and 7-3, using cost-effective span-to-depth ratios noticeably improves
visual slenderness compared to the conventional ratios for cast-in-place on falsework and precast
span-by-span box-girders. The visual difference is even more apparent when the optimal case is
compared to the case with maximum construction cost. This finding indicates that varying the span-
to-depth ratio can have a significant visual impact without substantial cost premiums (less than 11%
variation in cost for all the analysis cases considered).
90

However, the visual impact of changing span-to-depth ratio is less obvious for the solid slab
case, because visual difference diminishes as slenderness ratio increases beyond 25 as shown in
Figure 7-4.

a) L/h=10 b) L/h=15

c) L/h=20 d) L/h=25

e) L/h=30 f) L/h=35

Figure 7-4. Visual effects of increasing span-to-depth ratios from 10 to 35


91

As stated previously, increasing the span-to-depth ratio by reducing the girder depth can
enhance visual slenderness without incurring significant additional costs. Increasing the ratio by
extending the span length has similar visual effect as shown in Figure 7-5. Yet, the cost premium
associated with increasing span length is much more severe. For instance, for the cast-in-place box-
girder case depicted in the figure, increasing the span length from 50m to 75m adds 23% to the total
construction cost.
a) L/h=20, L=50m ($2450/m2) b) L/h=30, L=75m ($3020/m2, 23%)

Figure 7-5. Effect of increasing span length (box-girder with h=2.5m)


92

7.1.1 Effects of Viewing Points


The visual impact of altering span-to-depth ratio becomes more or less noticeable depending on
the location of the observer. First, as the observer approaches the bridge, the effect of changing
slenderness ratio is more obvious. Figures 7-6 to 7-8 demonstrate the influence of viewing distance
by comparing box-girders with span length of 50m and slenderness ratios of 10 and 20 when
viewed from distances of 300m, 150m, and 75m.
a) L/h=10 b) L/h=20

Figure 7-6. Viewed from 300m

a) L/h=10 b) L/h=20

Figure 7-7. Viewed from 150m

a) L/h=10 b) L/h=20

Figure 7-8. Viewed from 75m


93

In addition to viewing distance, the viewing angle also influences the impact of span-to-depth
ratio. Figure 7-9 shows that the pier width-to-height ratio has greater visual impact than the
longitudinal span-to-depth ratio when the bridge is viewed from beneath along the length of the
bridge. This viewing angle is of particular importance if pedestrians can walk below the bridge.

a) L/h=10 with wide wall piers b) L/h=20 with wide wall piers

c) L/h=10 with narrow piers d) L/h=20 with narrow piers

Figure 7-9. Effects of pier width-to-height ratio and span-to-depth ratio


94

As the viewing angle becomes less oblique, the impact of pier dimensions diminishes while the
span-to-depth ratio has growing influence on the perceived slenderness of the structure Figure 7-10.

a) L/h=10 b) L/h=20

Figure 7-10. Effect of span-to-depth ratio as viewing angle becomes less oblique

7.1.2 Other Factors that Affect Visual Slenderness


In addition to span-to-depth ratio, other factors also affect the perceived thickness of the
superstructure. These factors include the bridge height, pier configuration, length of deck slab
cantilevers in a box-girder, and railing type. In this section, each factor is investigated using a box-
girder model with a span length of 50m and slenderness ratio of 20.
95

First, Figure 7-11 compares a tall bridge with a low one. Although the span-to-depth ratios are
the same for both bridges, the tall one appears to be more slender due to the larger opening under
the bridge. This large opening contrasts with the slender superstructure, thus reducing the perceived
girder depth. The low bridge, on the other hand, appears heavy because the girder depth is similar to
the bridge height. In fact, to achieve sufficient slenderness and transparency, Menn (1990)
suggested that the bridge height needs to be at least four times greater than the girder depth. This
height suggestion ensures that there is a large contrast between the girder depth and the depth of the
opening under the bridge, thus lowering the perceived thickness of the superstructure.
a) Bridge height/girder depth = 5 b) Bridge height/girder depth = 1.75

Figure 7-11. Effect of bridge height on perceived superstructure slenderness

The pier configuration also affects the visual impact of span-to-depth ratio (Figure 7-12). More
pronounced piers clearly separate the individual span lengths. As a result, the perceived
superstructure thickness still depends on the span-to-depth ratio. Conversely, narrow piers that are
tucked in underneath the superstructure draw less attention and thus accentuate the continuity of the
entire girder. The perceived slenderness is then related to the ratio between the visually
uninterrupted length of the superstructure and the girder depth.
a) Pronounced piers b) Less obtrusive piers

Figure 7-12. Effect of pier configuration on perceived superstructure slenderness


96

Thirdly, the perceived slenderness of the superstructure is influenced by the length of deck slab
cantilever in box-girders. Figure 7-13 compares a bridge with short cantilevers to a bridge with
longer cantilevers. The latter bridge appears to be more slender because the long cantilevers cast
shadows onto the girder webs and these shadows conceal a portion of the girder depth. The
continuous shadow line along the girder also emphasizes the overall superstructure length. Hence,
slenderness depends more on the bridge length than the span length in this case.
a) Short deck cantilevers b) Long deck cantilevers

Figure 7-13. Effect of deck cantilever length on perceived superstructure slenderness

Lastly, the railing type contributes to the visual slenderness of the superstructure. Figure 7-14
shows two bridges with open-type metal railings and concrete barrier walls. Any railing increases
the perceived depth of the girder. However, the first case appears more slender because metal
railings are more transparent compared to concrete barriers. Concrete barriers add an extra depth of
solid concrete which represents a major visual bulk. These concrete barriers can be as tall as 1.37m
for highway bridges according to CHBDC (CSA 2006) and this height increases with increasing
traffic volume and speed (Dorton 1991).
a) Open-type metal railings b) Concrete barrier walls

Figure 7-14. Effect of railing type on perceived superstructure slenderness


97

7.2 Evolution of the Visually Optimal Span-to-Depth Ratio


As demonstrated previously, varying the span-to-depth ratio clearly has an impact on aesthetics.
Yet, visually optimal span-to-depth ratios cannot be easily defined because aesthetics is not a
quantifiable attribute. The ratio that yields the best-looking bridge changes over time and depends
on the background of the observer. This section explores the visually optimal slenderness ratio by
examining the works and design philosophies of various prominent bridge designers.
First, the aesthetically optimal slenderness ratio has changed throughout the history of concrete
bridges. This section traces the development of slenderness in concrete arch and girder bridges.
Arch bridges are considered, because early concrete bridges were mostly arches and the concept of
arch slenderness, which is generally associated with the arch thickness and deck depth with respect
to span length, is analogous to the influence of span-to-depth ratios on the slenderness of girder
bridges. Most importantly, although the representation of slenderness is different for the two bridge
types, both arch and girder bridges demonstrate evident improvement in slenderness due to
economic or aesthetic reasons.
In the 19th century, concrete bridges were generally deep and heavy because concrete was
regarded as artificial masonry and arch was the primary structural form for concrete bridges at that
time. Also, the society preferred the massiveness, rigidity, and embellishments associated with
traditional masonry arches. This trend can be seen in the Glenfinnan Railway Viaduct 1901 which is
one of the first major concrete bridges (Figure 7-14).

Figure 7-14. Glenfinnan Viaduct, 1901 (Cortright 1997)

Improvement in the slenderness of arches was evident by the late 19th century due to the
development of reinforced concrete which allowed arches to be thinner and flatter. Robert Maillart
utilized the new material and created the Stauffacher Bridge 1899 which is a slender three-hinged
arch concealed with stone-cladding and ornaments such that it resembles traditional masonry arches
(Figure 7-15 a). In his subsequent bridges, Maillart abandoned the traditional architectural forms
and began his pursuit for slenderness and simplicity (Figure 7-15). First, he eliminated the stone-
98

cladding in the Zuoz Bridge 1901 to reveal the slender arch. He further enhanced slenderness by
removing the spandrel walls in the Tavanasa Bridge 1906.

a) Stauffacher Bridge, 1899 (Billington 1997) b) Zuoz Bridge, 1901 (Billington 1990)

c) Tavanasa Bridge, 1906 (Billington 1990) d) Salginatobel Bridge, 1930 (Billington 1990)

Figure 7-15. Slender bridges by Maillart

One of the major breakthroughs in bridge aesthetics is Maillart’s Salginatobel Bridge 1930
which accentuates the simple three-hinged arch form devoid of any structurally unnecessary
components (Figure 7-15 d). The bridge’s exceptional slenderness contrasts with the traditional
masonry-like structures that were popular at Maillart’s time. The design was chosen mostly for its
economic efficiency instead of its aesthetic value. In fact, its aesthetic merit was not widely
recognized outside of Switzerland until decades after the bridge was constructed. The Salginatobel
Bridge is now praised as a masterpiece of structural art by scholars like Billington (1990) and Bill
(1955).
In the 1930s, the development of reinforced concrete also allowed for the construction of
concrete girder bridges which could reach spans of over 70m. However, long-span reinforced
concrete girders commonly had problems with deformations and cracking. To minimize these
problems, the girders needed to be very deep, with span-to-depth ratios of less than 10 (Menn 1990).
Constant-depth girders with such ratios would be heavy, so long-span reinforced concrete bridges
were usually haunched. Two examples of these variable-depth girders are the Villeneuve-St.
Georges Bridge 1939 and the Waterloo Bridge 1939 which are both haunched box-girders (Figure
7-16). Their span-to-depth ratios at the supports are 9.7 and 10 respectively while the midspan
ratios are 31 and 32 (Menn 1990).
99

Figure 7-16. Waterloo Bridge over the Thames, 1939 (Darger 2002) Figure 7-17. Changis-sur-Marne Bridge, 1948
(Mossot 2007)

Significant improvement in slenderness for girder bridges only began with the introduction of
prestressing technology to bridge construction in the 1940s. Prestressing enhances structural
behaviour by reducing tensile stresses in the concrete and increasing the load-carrying capacity with
the use of high-strength tendons. As a result, longer and more slender girder bridges were feasible.
Some notable examples of slender prestressed bridges include Eugene Freyssinet’s series of
post-tensioned bridges along the Marne River 1948 (Figure 7-17). These bridges achieved visual
slenderness with the use of prestressing technology, which allowed for longer spans and thinner
decks, and had a midspan span-to-depth ratio of up to 40. This is a large improvement in
slenderness compared to the previous examples of reinforced concrete girders which had a midspan
ratio close to 30. This improvement in slenderness through post-tensioning technology was mainly
driven by material economy, structural efficiency and construction speed.
The aesthetic value associated with slenderness was not fully
appreciated by society until the 1960s which marked the beginning of
an era that praised minimalism and simplicity. The public’s perception
on bridge slenderness was demonstrated in a bridge aesthetics survey
conducted in 1969 by A.G.D. Crouch under the supervision of Colin
O’Connor at the University of Queensland (Crouch 1974, O'Connor
1991). Crouch was an Engineer with the Canberra Department of
Works while O’Connor was a Professor of Civil Engineering and has
published a number of books and papers regarding bridge design. The
bridge aesthetics survey investigated the relative visual merits of
various substructure and superstructure proportion parameters (e.g.
span-to-pier thickness ratio, span-to-column height ratio, etc.) through
the use of simple sketches of bridges with varying proportions. The
Figure 7-18. Sketches to
survey sample included 170 civil engineers, architects, and people with evaluate aesthetic impact of
span-to-depth ratios
(O'Connor 1991)
100

no education in structural design (a control group). The civil and architecture groups consisted of
students, university staffs as well as people in practice. One particular superstructure proportion
parameter that was investigated was the span-to-depth ratio (Figure 7-18). The response
corresponded to a preferred ratio of 34.3 for engineers, 20.5 for architects and 24.4 for the control
group. The difference among the three groups demonstrated that the visually optimal ratio depends
on the background of the observer. Engineers preferred a higher ratio because they valued material
efficiency. The other groups, in contrast, preferred a deeper girder because they saw depth as a sign
of strength and visual elegance as a matter of good proportions. The sketches used in this survey
might be too simple to confidently yield specific values for visually-optimal span-to-depth ratios.
Nonetheless, the survey indicated that people in general preferred a more slender structure with a
minimum span-to-depth ratio of 20 (i.e. the top two sketches in Figure 7-18).
Since there was greater public resonance for visual slenderness, higher span-to-depth ratios
gained unprecedented popularity in bridge designs in the 60s and 70s. Bridge designers, therefore,
consciously pursued slenderness based on its aesthetic merits in addition to its material economy. In
particular, two renowned bridge engineers designed a number of girder bridges with exceptional
slenderness at this time: Leonhardt and Menn. Leonhardt believed that “the slender bridge looks
better than the clumsy one. A slender look is therefore a design feature well worth striving for”
(Leonhardt 1982). He also claimed that heavy bridges appear “depressing” whereas lighter bridges
are more elegant. His design philosophy was demonstrated in the Neckar Viaduct 1977 and the
Kocher Valley Viaduct 1979 (Figures 7-19 and 7-20). The former haunched girder has a
slenderness ratio of 56 at midspan and 25 at the supports while the latter constant-depth girder has a
ratio of 21.2. Both the haunched and constant-depth girders demonstrate significant improvement in
slenderness compared to bridges from the 30s which used span-to-depth ratios of 30 at midspan and
10 at the supports for haunched girders and a ratio of 10 for constant-depth girders.

Figure 7-19. Neckar Valley Viaduct, 1977 (Leonhardt Figure 7-20. Kocher Valley Viaduct, 1979 (Leonhardt
1982) 1982)
101

Menn, on the other hand, believed that visual elegance was related to the efficient use of
material which could be demonstrated by slenderness and lightness of a structure (Menn 1990).
Two of his designs that incorporated this concept of visual elegance are the Pregorda Bridge 1974
and the Felsenau Bridge 1974 (Figures 7-21 and 7-22). Like Leonhardt’s bridges, these two bridges
are considerably more slender than the girder bridges constructed in the previous decades. The
Pregorda Bridge is a constant-depth girder with a slenderness ratio of 22.2 while the main spans of
the Felsenau Bridge are haunched and has ratios of 48 at midspan and 18 at the supports.

Figure 7-21. Pregorda Bridge, 1974 (Menn) Figure 7-22. Felsenau Bridge, 1974 (Menn)

Other contemporary bridge experts are also strong advocates of bridge slenderness and they
have expressed the importance of slenderness in bridge aesthetics in a number of publications. One
of these bridge professionals is Edward Wasserman who is the Civil Engineering Director of the
Structures Division for the Tennessee Department of Transportation and has been involved in the
design of over 2200 bridges. He claimed that a span-to-depth ratio between 25 and 30 would
produce a well-proportioned superstructure that “appears to float gracefully” whereas a lower ratio
would result in a bridge that appears to “loom heavily upon the landscape” (Wasserman 1991).
Likewise, Arthur Elliott, Bridge Engineer responsible for all bridge planning and design with the
California Department of Transportation from 1953 to 1973, stated that a “blocky, heavy, and
poorly proportioned” bridge is simply not beautiful (Elliott 1991). Frederick Gottemoeller, who has
produced a number of publications regarding bridge aesthetics and has developed the aesthetic
design guidelines for Maryland and Ohio, also recognizes the visual benefits of slenderness. He
claimed that better-looking bridges are characterized by their “simplicity, thinness, and continuity”
(Gottemoeller 2004).
As shown in this historical study, the public perception of bridge aesthetics changes over time.
In the early 1900s, people preferred heavier bridges whereas slender bridges were appreciated in the
60s and 70s. Although the visually optimal span-to-depth ratio cannot be easily determined,
contemporary bridge designers generally favour a higher ratio and regard slenderness as a key
element in a good-looking bridge.
102

7.3 Concluding Remarks


This chapter demonstrates that span-to-depth ratio has direct impact on perceived superstructure
slenderness by comparing 3-D drawings of bridges with varying ratios. Bridges with the most cost-
effective ratio are visually more slender than those with conventional ratios. The visual difference
between the cost-effective ratio and conventional ratio is particularly noticeable for the cast-in-place
on falsework and precast span-by-span box-girders. For cast-in-place solid slab, the difference is
less obvious because the conventional ratio is already high (i.e. 30) and increasing the ratio beyond
25 is found to have negligible visual impact. This chapter further shows that the effect of varying
span-to-depth ratio reduces as the observer moves away from the bridge or as the viewing angle
becomes more oblique. Factors, such as low and protruding piers, short deck cantilever lengths, and
thick concrete railing, also reduce the perceived slenderness. Lastly, a historical study indicates that
the visually optimal slenderness ratio evolves over time and contemporary bridge engineers
appreciate the aesthetic merit of superstructure slenderness.
8 CONCLUSIONS
Girder-type bridges have commonly been designed using conventional span-to-depth ratios
which have not changed significantly despite recent development in material strengths and
construction technologies. This study determines the optimum slenderness ratios for three types of
girder bridges constructed with high-strength concrete: cast-in-place on falsework box-girder and
solid slab, and precast segmental span-by-span box-girder. The ratios are optimized based on
material consumption and total construction cost criteria. Aesthetic comparisons are also performed
to determine the visual impact of these optimum ratios. The primary results of this thesis are
summarized as follows.

8.1 Conventional Span-to-Depth Ratios


A study of 86 constant-depth girder bridges reveals that the typical ranges of span-to-depth
ratios are 17.7 to 22.6 for cast-in-place box-girder, 19 to 35 for cast-in-place voided slab, 22 to 39
for cast-in-place solid slab, and 15.7 to 18.8 for precast segmental box-girder. The study
demonstrates that the ratios for cast-in-place and precast segmental box-girders have not varied
significantly from 1958 to 2007. The study also indicates that cast-in-place slabs constructed after
1975 are mostly voided slabs with slenderness ratios below 25 due to the more stringent code
requirements in recent years.

8.2 Maximum Span-to-Depth Ratios


The maximum span-to-depth ratio, which satisfies safety, serviceability, and constructability
requirements, varies with bridge type and span length. For cast-in-place box-girder with spans of
35m, 50m, and 60m, the maximum ratios are 25, 30, and 35 respectively. These values are restricted
by the interior box cavity height requirement which is necessary to provide sufficient space for
workers. The maximum ratio is also 35 for the case with a span of 75m; it is limited by the number
of tendons that can fit inside the webs of the box section.
The maximum ratios for solid slab are 40 for spans of 20m and 25m, and 45 for spans of 30m
and 35m. These ratios are governed by the maximum reinforcement criterion which ensures
adequate ductile behaviour. This limitation is especially critical for solid slabs, because slabs have
heavier dead loads compared to box-girders with the same ratio, so more reinforcements are needed.
For precast segmental box-girder, the maximum ratios are 20 for a span of 30m, and 25 for
spans of 40m and 50m. Like cast-in-place box-girders, these ratios are limited by the minimum
height requirement for the interior box cavity. Even though the governing factor of maximum
slenderness ratio is the same for both bridge types, the ratios for precast box-girders are lower,
because external tendons are used, further reducing the height of the cavity within box-girders.

103
104

8.3 Material Consumption Comparisons


As slenderness increases, the prestressing and concrete strength demands increase while
concrete volume decreases. For both cast-in-place and precast segmental box-girders, the decrease
in volume is small compared to the increase in prestressing since only a small amount of concrete at
the webs is eliminated while the moment resistance is significantly lowered as the ratio increases.
Reduction in concrete volume further diminishes for higher ratios because the bottom slab thickness
needs to be increased to accommodate the larger compressive force in a slender girder. This
increase in slab thickness counteracts the decrease in web volume, thus the reduction in concrete
volume becomes less for higher ratios. Moreover, a concrete compressive strength of 50 MPa is
sufficient to satisfy design requirements in every analysis case for both of these bridge types.
Decrease in concrete volume in a solid slab is more significant since a large strip of concrete as
wide as the soffit is removed as the ratio increases. Therefore, this volume reduction is proportional
to the decrease in girder depth. On the other hand, prestressing demand increases with slenderness.
This increase in prestressing is less than the one for cast-in-place box-girders, because solid slabs
can accommodate many tendons at the same elevation while tendons in box-girders need to be
placed in multiple layers within the webs which reduces the prestressing efficiency. Also, higher
strength concretes (i.e. f’c = 50 to 80 MPa) are used for slender slabs to satisfy ductility requirement
by lowering the prestressing demand. As a result, prestressing consumption in solid slabs increases
with span-to-depth ratio at a slower rate relative to box-girders.
Material consumptions are compared on the basis of material costs. Considering only the pure
material costs without the cost of formworks, falsework or precasting operations, the most efficient
ratios are15 for both cast-in-place and precast box-girders and 30 for solid slabs. If the costs of
concrete fabrication and placement are included, the most cost-efficient ratios for the three bridge
types increase to 25, 40, and 20. This increase in cost-optimal ratios indicates that the construction
economy related to a slenderer and lighter structure is a crucial aspect in the optimization of span-
to-depth ratio. More importantly, over the entire range of ratios investigated (i.e. 10 to 35 for cast-
in-place box-girder, 30 to 45 for cast-in-place solid slab, and 15 to 25 for precast segmental box-
girder), the maximum variations in pure material cost are 42%, 28%, and 12% while the maximum
variations in total superstructure cost are only 20%, 12%, and 3.3% for each bridge type.

8.4 Total Construction Cost Comparisons


The total construction costs are computed assuming the superstructure accounts for 54.5% of
total construction cost. With the additional costs of mobilization, substructure, and accessories, the
most cost-efficient ratios remain the same as the ones based on superstructure costs only. However,
105

the economy of using these optimal ratios diminishes when the total construction costs are
considered; the maximum savings within the analysis range of ratios are reduced to less than 11%,
6.2%, and 1.8% for cast-in-place box-girder, cast-in-place solid slab, and precast segmental box-
girder respectively. This finding indicates that optimizing one particular structural component (i.e.
superstructure span-to-depth ratio) does not result in significant economy. Greater cost savings
emerge from the selection of an appropriate bridge type. For instance, within the same range of span
lengths and span-to-depth ratios, a cast-in-place on falsework box-girder is more economical than a
solid slab. Moreover, these findings are not sensitive to changes in material unit prices and in total
construction cost breakdown; the cost-optimal ratios remain the same regardless of these changes.
The variability in total construction cost over the analysis range of ratios is less than 13% when the
material unit price is altered by 50% or when the superstructure cost contribution in the total cost
breakdown rises from 54.5% to 80%.

8.5 Aesthetic Comparisons


Since the total construction cost does not vary significantly over the entire range of span-to-
depth ratios investigated, the designer has more freedom to select the slenderness ratio without
much economic constraints. Varying the ratio changes the superstructure slenderness which is
generally the most important visual component of a girder-type highway overpass. A historical
study indicates that although the public perception on slenderness has evolved over time,
contemporary bridge engineers, especially the ones from the 1960s and 1970s, recognize and
appreciate the aesthetic merit of slenderness associated with high span-to-depth ratios.
The visual impact of span-to-depth ratios is examined by comparing 3-D renderings of bridges
with different ratios. This comparison determines that using cost-optimal ratios instead of
conventional ones would result in considerable enhancement in the superstructure slenderness for
cast-in-place and precast box-girders. Yet, the aesthetic impact of using the optimal ratio in solid
slabs is negligible because increasing the ratio beyond 25 is found to have no apparent visual
difference. Furthermore, the visual effects of varying span-to-depth ratio reduce as the observer
moves away from the bridge or as the viewing angle becomes more oblique. In addition to lowering
the slenderness ratio, other factors that reduce perceived slenderness include a low bridge height,
protruding piers, short deck cantilever lengths, as well as solid concrete railing.

8.6 Optimal Span-to-Depth Ratios


Based on construction economy and aesthetics considerations, the optimal span-to-depth ratios
are established to be 25, 40, and 20 for cast-in-place on falsework box-girder, cast-in-place on
falsework solid slab, and precast segmental span-by-span box-girder. However, these optimums are
106

expected to change in a real situation because they are determined based on specific parameters
defined for this study such as cross-section dimensions and span arrangements.
More importantly, the study demonstrates that, within the analysis range of ratios, the total
construction cost is relatively insensitive to changes in the ratio. This finding is valid even if the
optimum ratio changes, because the study shows that cost savings from optimizing span-to-depth
ratio are generally minor compared to other construction cost components. The results of this study
indicate that, compared to conventional ratios defined for normal-strength concrete bridges, a
greater range of values can be used without significant cost premiums for high-strength concrete
bridges (i.e. f’c = 50 to 80 MPa): 10 to 35 for cast-in-place on falsework box-girder; 30 to 45 for
cast-in-place on falsework solid slab; 15 to 25 for precast segmental span-by-span box-girder.
REFERENCE
AASHTO-PCI-ASBI. (1997)."Segmental Box Girder Standards for Span-by-Span and Balanced
Cantilever Construction." American Segmental Bridge Institute, <www.asbi-assoc.org>
(Feb. 1, 2009).

AASHTO. (1994). AASHTO LRFD Bridge Design Specifications, American Association of State
Highway and Transportation Officials, Washington, D.C.

ACI-ASCE Committee 343. (1988). "Analysis and design of reinforced concrete bridge structures."
American Concrete Institute, Detroit.

Belli, A. (2003). "Interstate 895 Bridge, James River, Richmond, Virginia, USA." Structural
Engineering International:Journal of the International Association for Bridge and
Structural Engineering (IABSE), 13(3), 177-179.

Bennett, M. V., and Taylor, A. J. (2002). "Woronora River Bridge, Sydney." Structural
Engineering International: Journal of the International Association for Bridge and
Structural Engineering (IABSE), 12(1), 28-31.

Bill, M. (1955). Robert Maillart, Girsberger Zürich.

Billington, D. (1990). Robert Maillart and the Art of Reinforced Concrete, The MIT Press,
Cambridge.

Billington, D. (1997). Robert Maillart: Builder, Designer, and Artist, Cambridge University Press,
Cambridge.

Cao, S., Wu, W., Tu, J., and Wu, E. (2006). "Design & Construction of Ngong Shuen Chau
Viaduct." International Conference on Bridge Engineering-Challenges in the 21st Century,
Hong Kong.

Chen, W.-F., and Duan, L. (1999). Bridge Engineering Handbook, CRC Press, Boca Raton.

Collins, M. P., and Mitchell, D. (1997). Prestressed Concrete Structures, Response Publications,
Toronto.

Cortright, R. (1997)."Glenfinnan Viaduct." Nicolas Janberg's Structurae,


<en.structurae.de/photos/index.cfm?JS=54616> (June 1, 2009).

Cremer, J.-M., Counasse, C., and Delforno, J.-Y. (2003). "The Sart Canal-Bridge, houdeng -
Aimeries, Belgium." Structural Engineering International: Journal of the International
Association for Bridge and Structural Engineering (IABSE), 13(1), 19-22.

Crouch, A. G. D. (1974). "Bridge Aesthetics - A Sociological Approach." Civil Engineering


Transactions, CE16(2), 138 - 142.

CSA (1982). "Steel for Prestressed Concrete Tendons." CSA G279-M1982, Canadian Standards
Association, Rexdale.

CSA. (2006). Canadian Highway Bridge Design Code, C. S. Association, ed., Canadian Standards
Association, Mississauga, Ontario.

107
108

Darger, N. J. (2002)."Waterloo Bridge (1945)." Nicolas Janberg's Structurae,


<en.structurae.de/photos/index.cfm?JS=3502> (June 1, 2009).

Dorton, R. A. (1991). "Aesthetic Considerations for Bridge Overpass Design." Bridge aesthetics
around the world, Transportation Research Board, National Research Council, Washington,
D.C., 10-17.

DSI. (2008). "DYWIDAG Post-Tensioning Systems." D.-S. International, ed., DYWIDAG-Systems


International.

Duan, L., Chen, K., and Tan, A. (1999). "Design Practice in Europe." Bridge Engineering
Handbook, W.-F. Chen and L. Duan, eds., CRC Press Boca Raton, 10-11 to 10-37.

Dufferin Concrete. (2009)."2009 Price List." Dufferin Concrete, <www.dufferinconcrete.ca> (June


1, 2009).

Elliott, A. L. (1991). "Creating a Beautiful Bridge." Bridge aesthetics around the world
Transportation Research Board, National Research Council, Washington, D.C., 215-229.

Gauvreau, P. (2006). "Bridges." Post-Tensioning Manual, Post-Tensioning Institute, Phoenix, 195-


240.

Gottemoeller, F. (2004). Bridgescape : The Art of Designing Bridges, Wiley, Hoboken.

Hassanain, M. (2002). "Optimal Design of High-Performance Concrete Adjacent Precast Box


Girder Bridges." 6th International Conference on Short & Medium Span
Bridges:Developments in Short & Medium Span Bridge Engineering, CSCE, Vancouver.

Hewson, N. R. (2003). Prestressed Concrete Bridges : Design and Construction, Thomas Telford,
London.

Hillerborg, A. (1996). Strip Method Design Handbook, E & FN Spon, London.

Holgate, A. (1996). The Art of Structural Engineering: The Work of Jorg Schlaich and His Team,
Ed. Axel Menges, Stuttgart.

Holowka, M. (1979). "Deck Slab Investigation of a Voided Posttensioned Concrete Bridge Deck -
Bridge 20." Ontario Ministry of Transportation and Communications, St. Catharines.

Janberg, N. (2009)."Structurae." <en.structurae.de> (June 1, 2009).

Kosmatka, S. H., Kerkhoff, B., Panarese, W. C., MacLeod, N. F., and McGrath, R. J. (2002).
Design and Control of Concrete Mixtures, Cement Association of Canada, Ottawa.

Leonhardt, F. (1979). Grundlagen des Massivbrückenbaues, Springer-Verlag, Berlin/Heidelberg.

Leonhardt, F. (1982). Brücken : Ästhetik und Gestaltung = Bridges: Aesthetics and Design,
Deutsche Verlags-Anstalt, Stuttgart.

Linse, A., and Wössner, K. (1978). "Kochertalbrücke-Entwürfe einer Grossbrücke. " Bauingenieur,
53(12), 453-463.
109

Liu, X. P., Qin, Z. P., Leung, Y. W., and Yue, L. (2007). "Construction of the precast segmental
approach structures for Sutong Bridge." 5th International Conference on Current and
Future Trends in Bridge Design, Construction and Maintenance, Thomas Telford Ltd,
Beijing.

MacGregor, J., and Bartlett, F. M. (2000). Reinforced Concrete: Mechanics and Design, Prentice
Hall Canada, Scarborough.

Meades, P., and Green, R. (1974). "Model Studies for Voided Posttensioned Concrete Slab
Bridges." Ministry of Transportation and Communications, Ontario, Toronto.

Menn, C. Christian Menn, Consulting Engineer: Projects." <www.christian-menn.ch> (July 1,


2009).

Menn, C. (1990). Prestressed Concrete Bridges P. Gauvreau, ed., P. Gauvreau, translator,


Birkhäuser Verlag, Basel.

Mossot, J. (2007)."Changis-sur-Marne Bridge " Nicolas Janberg's Structurae, (June 1, 2009).

MTO (2003). "Structural Manual." Ontario Ministry of Transportation, Bridge Office, St.
Catharines.

Muller, J. (1999). "Design Practice in Europe." Bridge Engineering Handbook, W.-F. Chen and L.
Duan, eds., CRC Press Boca Raton, 64-61 to 64-37.

NRS. (2008)."Gantries-Guangzhou LRT Project." NRS Bridge Construction Equipment,


<http://www.nrsas.com/v2009/project/pro_gantries.php> (June 1, 2009).

O'Brien, E. J., and Keogh, D. L. (1999). Bridge Deck Analysis, E & FN Spon, London.

O'Connor, C. (1991). "Empirical Assessment of Bridge Aesthetics: An Australian View." Bridge


Aesthetics Around the World, Transportation Research Board, National Research Council,
Washington, D.C., 230-240.

OHBDC. (1983). Ontario Highway Bridge Design Code, Highway Engineering Division, Toronto.

OPSS. (2007). Material Specification for Concrete - Materials and Production, Ontario Provincial
Standard Specification.

OSHA. (2006)."Overhead Launching Gantry Crane Safety and Health Information Bulletin."
Occupational Safety & Health Administration, <www.osha.gov/dts/shib/shib050106.html>
(June 1, 2009).

Park, R., and Gamble, W. L. (2000). Reinforced Concrete Slabs, Wiley, New York.

PEER. (2005)."Neckar Valley Viaduct, Weitingen, Germany (1978)." Pacific Earthquake


Engineering Research Center, University of California,
<http://nisee.berkeley.edu/elibrary/getpkg?id=GoddenG43-50> (July 1, 2009).

Sauvageot, G. (1999). "Segmental Concrete Bridges." Bridge Engineering Handbook, W.-F. Chen
and L. Duan, eds., CRC Press, Boca Raton.
110

Scollard, C. R., and Bartlett, F. M. (2004). "Rehabilitation Criteria for Post-Tensioned Voided-Slab
Bridges." Canadian Journal of Civil Engineering, 31(6), 977-987.

SNC-Lavalin. (2008). "Highway 400 Major MacKenzie Drive to Highway 11 Heritage Bridge
Replacement Design Concept Study." Report prepared by SNC-Lavalin, submitted to
Ontario Ministry of Transportation.

TRB. (1990). Truck Weight Limits: Issues and Options, Transportation Research Board Washington,
D.C.

Vogel, T. (1997). Christian Menn-Brückenbauer, Birkhäuser Verlag, Basel, 57.

Wasserman, E. P. (1991). "Aesthetics for Short- and Medium-Span Bridges." Bridge aesthetics
around the world Transportation Research Board, National Research Council, Washington,
D.C., 58-66.

Weinlandbrücke (1958). "Die Weinlandbrücke in der Umfahrungsstrasse von Andelfingen."


Direktion der öffentlichen Bauten des Kantons Zürich (Administration of Public Buildings
of the Canton of Zürich).
APPENDIX A: CHAPTER 2 SUPPLEMENTARY INFORMATION

111
A.1 Cast-in-Place on Falsework Box-Girder
Table A-1. Cross-sectional drawings for cast-in-place on falsework box-girders in Chapter 2
Bridge no. Cross-section Bridge no. Cross-section Bridge no. Cross-section

1 13 23 & 24

3 14 25

4 15 26

5&6 16 27

7 17 28

8 18 29

9 19 31

10 20 32

11 21 33

12 22 34

112
Table A-1. Cross-sectional drawings for cast-in-place on falsework box-girders in Chapter 2 (continued)
Bridge no. Cross-section Bridge no. Cross-section Bridge no. Cross-section

35 38 42

36 40 43

37 41 44

Table A-2. Cast-in-place on falsework box-girders in Chapter 2


Span Span-to-
Bridge Completion Construction Depth
Name Location Span arrangement (m) length L depth Reference
no. year method h (m)
(m) ratio L/h
Grenz Bridge at
1 Switzerland 35.4 2 17.7 Drawing from Gauvreau
Basel
Incremental
2 Sart Canal-Bridge Belgium 2002 13 spans 36 3 12 (Cremer et al. 2003)
launching
Weyermannshaus
3 Switzerland 37.75 2 18.88 Drawing from Gauvreau
Bridge
24.4+35.4+38.1+
Designer: T.Y. Lin International for
Eastbound Walnut CIP on 38.1+34.4+37.16+
4 U.S.A. 1986 38.6 1.68 23.0 Department of Highways, Colorado
Viaduct falsework 38.1+38.6+38.6+
Drawing from Gauvreau
34.0+24.7 = 382
Taiwan High Speed CIP span-by- 3*25+25.5+40+25+2*30
5 Taiwan 2000 40 3.5 11.4 Drawing from Gauvreau
Rail (1) span +3*25 = 300.5
25+35+26.5+25+
Taiwan High Speed CIP span-by-
6 Taiwan 2000 40+24.5+26.5+4* (30) = 40 3.5 11.4 Drawing from Gauvreau
Rail (2) span
322.5
Designer: Christian Menn
Span-by-span
7 Pregorda Bridge Switzerland 1974 40 1.8 22.2 Drawing from Gauvreau
on falsework
(Vogel 1997)
Balanced 2*(21+ 3*40 + 20.7) =
8 Almese Viaduct Italy 1990 40 2.2 18.2 DEAL Job Report (Segmental Bridge Data)
cantilever 323.4
Balanced 2*(20.65+17*40+21.15)
9 Condove Viaduct Italy 1992 40 2.2 18.2 DEAL Job Report (Segmental Bridge Data)
cantilever = 1443.6

113
Table A-2. Cast-in-place on falsework box-girders in Chapter 2 (continued)
Span Span-to-
Bridge Completion Construction Depth
Name Location Span arrangement (m) length L depth Reference
no. year method h (m)
(m) ratio L/h
Balanced 2*(20.65+12*40+21.15)
10 Gravio Viaduct Italy 1992 40 2.2 18.2 DEAL Job Report (Segmental Bridge Data)
cantilever = 1043.6
Balanced 2*(19.40+26*40+19.15)
11 Borgone Viaduct Italy 1992 40 2.2 18.2 DEAL Job Report (Segmental Bridge Data)
cantilever = 2157.1
Span-by-span
12 Quadinei Bridge Switzerland 1967 40 2 20 (Menn 1990)
on falsework
13 Altstetter Viaduct Switzerland 41 1.9 21.6 Drawing from Gauvreau
CIP on 28.1+34+37.5+40*3+42. Drawing from Gauvreau
14 Reuss Bridge Switzerland 1972 42.5 2.4 17.7
falsework 5+40*2+37.5+32.5 = 412 Designer: Christian Menn
Balanced 40.30+28*42.50+34=
15 Cerchiara Viaduct Italy 1992 42.5 2.3 18.5 DEAL Job Report (Segmental Bridge Data)
cantilever 1264.3
Balanced 40.30+6*42.50+ 36 =
16 Castello Viaduct Italy 1992 42.5 2.3 18.5 DEAL Job Report (Segmental Bridge Data)
cantilever 331.3
Balanced
17 Costacole Viaduct Italy 1992 34+5*42.50+34 = 280.50 42.5 2.3 18.5 DEAL Job Report (Segmental Bridge Data)
cantilever
Ferroviario
Spans = 36.7 to 45
18 Overpass at Italy 1974 45 1.6 28.125 Drawing from Gauvreau
Total length = 134
Bolzano
Krebsbachtal Incremental
19 Germany 1975 45 3.49 12.9 (Menn 1990)
Bridge launching
Shatt Al Arab Incremental Spans = 38.25 to 46.90
20 Iraq 1978 46.9 3.65 12.8 Drawing from Gauvreau
Bridge launching Total length = 761
Spans = 21.76 to 47.50
21 Ancona Viaduct Italy Segmental 47.5 2.3 20.7 DEAL Job Report (Segmental Bridge Data)
Total length = 2015.9
Felsenau Bridge Span-by-span Designer: Christian Menn
22 Switzerland 1975 48*5 = 240 48.0 3.0 16.0
(approaches) on falsework (Menn 1990)
(40+2*50+40)
23 La Molletta Viaduct Italy 1988 Segmental 50 2.4 20.8 DEAL Job Report (Segmental Bridge Data)
+(40+2*50+40) = 360
Fosso Capaldo (40+11*50+40)
24 Italy 1988 Segmental 50 2.4 20.8 DEAL Job Report (Segmental Bridge Data)
Viaduct +(40+11*50+40) = 1260
Sihlhochstrasse
25 Switzerland 54.5 1.85 29.5 Drawing from Gauvreau
Bridge
Balanced
26 Grosotto Viaduct Italy 1992 45+15*55+45= 915 55 2.75 20 DEAL Job Report (Segmental Bridge Data)
cantilever
Balanced
27 Grosio Viaduct Italy 1994 45+24*55+45 = 1410 55 2.75 20 DEAL Job Report (Segmental Bridge Data)
cantilever
Balanced
28 Tiolo Viaduct Italy 45+9*55+45 = 585 55 2.75 20 DEAL Job Report (Segmental Bridge Data)
cantilever
29 Denny Creek U.S.A. 1980 Spans = 57.32 57.32 2.744 20.9 Drawing from Gauvreau

114
Table A-2. Cast-in-place on falsework box-girders in Chapter 2 (continued)
Span Span-to-
Bridge Completion Construction Depth
Name Location Span arrangement (m) length L depth Reference
no. year method h (m)
(m) ratio L/h
Woronora River Incremental
30 Australia 2001 Total length = 521 58.7 4 14.7 (Bennett and Taylor 2002)
Bridge launching
Balanced
31 Valentino Viaduct Italy 1990 30.80+6*60+31 = 421.8 60 3 20 DEAL Job Report (Segmental Bridge Data)
cantilever
Balanced 2*(30.9+9*60+31.05) =
32 Giaglione Viaduct Italy 1992 60 3 20 DEAL Job Report (Segmental Bridge Data)
cantilever 1143.90
(30.7+9*60+ 30.9) +
Balanced
33 Venaus Viaduct Italy 1992 (30.95 +7*60+ 30.7) = 60 3 20 DEAL Job Report (Segmental Bridge Data)
cantilever
1083.25
(30.9+5*60+31.05)+(30.
34 Passeggeri Viaduct Italy 1992 Segmental 60 3 20 DEAL Job Report (Segmental Bridge Data)
9+4*60+31.05) = 663.90
(30.85+11*60+31.30)+(3
35 Brunetta Viaduct Italy 1992 Segmental 1.05+ 9*60+59.05) = 60 3 20 DEAL Job Report (Segmental Bridge Data)
1352.25
(30.70+4*60+
Pietrastretta
36 Italy 1992 Segmental 30.80)+(30.70+3*60+30. 60 3 20 DEAL Job Report (Segmental Bridge Data)
Viaduct
90) = 543.10
(30.70+3*60+
37 Deveys Viaduct Italy 1992 Segmental 30.70)+(30.70+4*60+31. 60 3 20 DEAL Job Report (Segmental Bridge Data)
70) = 542.80
Gruyère Lake CIP span-by-
38 Switzerland 1978 Total length = 2043 60.48 4 15.12 Drawing from Gauvreau
Viaduct span

Interstate 895
Balanced
39 Bridge over James U.S.A. 2002 64 3 21.3 (Belli 2003)
cantilever
River (approaches)
40 Lätten Bridge Switzerland 65 3.6 18.1 Drawing from Gauvreau
Savona Mollere 35.3+67.5+36.5+67.5+35
41 Italy 1994 Segmental 67.5 3 22.5 DEAL Job Report (Segmental Bridge Data)
Viaduct .3 = 242.1
Spans = 44.5 to 73.5
42 Ruina Viaduct Italy 1984 73.5 3.8 19.3 Drawing from Gauvreau
Total length = 785
Span-by-span
43 Weinland Bridge Switzerland 1958 57+76+88+66 = 287 88 3.9 22.6 (Menn 1990, Weinlandbrücke 1958)
on falsework
Designer: Fritz Leonhardt
Kocher Valley Balanced
44 Germany 1971 81+7*138+81=1128 138 6.5 21.2 (Linse and Wössner 1978, PEER 2005)
Bridge cantilever
Drawing from Gauvreau

115
A.2 Cast-in-Place on Falsework Solid Slab
Table A-3. Cross-sectional drawings for cast-in-place on falsework solid slabs in Chapter 2
Bridge no. Cross-section Bridge no. Cross-section Bridge no. Cross-section Bridge no. Cross-section
46 51 64 70

47 58 65 71

48 60 66 72

49 61 67

50 62 68

Table A-4. Cast-in-place on falsework solid slabs in Chapter 2


Span Span-to-
Bridge Completion Construction Depth
Name Location Span arrangement (m) length depth Reference
no. year method h (m)
L (m) ratio L/h
Designer: Shirish Patel & Associates
45 Khandeshwar Bridge India 2000 N/A 13.2 0.65 20.3 Consultants Private Limited
(Janberg 2009)
Spadina Ave. Bridge #16, 12.192+15.24+12.192
46 Canada 1967 CIP on falsework 15.24 0.686 22.2 Department of Highways Ontario
Hwy 401 = 39.624
47 & Spadina Ave. Bridge #18A 12.192+15.24+12.192
Canada 1967 CIP on falsework 15.24 0.686 22.2 Department of Highways Ontario
48 & B, Hwy 401 = 39.624
Spadina Ave. Bridge #19, 12.192+15.24+12.192
49 Canada 1967 CIP on falsework 15.24 0.686 22.2 Department of Highways Ontario
Hwy 401 = 39.624
50 & Spadina Ave. Bridge #21A 12.192+15.24+12.192
Canada 1967 CIP on falsework 15.24 0.686 22.2 Department of Highways Ontario
51 & B, Hwy 401 = 39.624
Designers: Schlaich, Bergermann und
52 Sindelfingen Footbridge Germany 1986 N/A 16.7 0.3 55.7 Partner
(Holgate 1996, Janberg 2009)
Designer: Haas Consult and Ingenieurbüro
53 L 333 Overpass at Bassum Germany 1993 N/A 13.5+16.87+13.5 16.87 0.77 21.9 Perlebery
(Janberg 2009)

116
Table A-4. Cast-in-place on falsework solid slabs in Chapter 2 (continued)
Span Span-to-
Bridge Completion Construction Depth
Name Location Span arrangement (m) length depth Reference
no. year method h (m)
L (m) ratio L/h
Designer: Fischer + Friedrich Beratende
54 Waiblingen Footbridge Germany 1996 N/A 17 0.4 42.5 Ingenieure
(Janberg 2009)
Incremental Designer: SFEDTP
55 Mako Bridge Senegal 1975 16+3*21+16+3*21+16 21 0.88 23.9
launching (Janberg 2009)
Designer: Metz-Herder-Wendt und Billig,
56 Kittelbaches Bridge Germany 1992 N/A 21.65 1.12 19.3 Schüßler-Plan Ingenieurgesellschaft mbH
(Janberg 2009)
San Francisco Airport Spans = 18.3 to 22.25,
57 U.S.A. N/A 22.25 1.16 19.2 Drawing from Gauvreau
Viaduct Total length =1630
St. Vincent Street Department of Highways Ontario
58 Canada 1964 CIP on falsework 19.5+2*24.4+19.5 = 87.8 24.4 0.686 35.6
Overpass Drawing from Gauvreau
Bridge across Jan-Wellen- Designer: Fritz Leonhardt
59 Germany 1961 N/A Total length = 536 25 1 25
Platz (Leonhardt 1982, PEER 2005)
60 & Spadina Ave. Bridge #14 & 18.2+25.7+2*23.4+29. Department of Highways Ontario
Canada 1963 CIP on falsework 29.4 0.762 38.6
61 #15, Hwy 401 +18.2 = 138 Drawing from Gauvreau
Spadina Ave. Bridge #12, 18.2+26.0+24.0+23.4+29. Department of Highways Ontario
62 Canada 1963 CIP on falsework 29.4 0.762 38.6
Hwy 401 4+18.2 = 139 Drawing from Gauvreau
Saale Bridge at
63 Germany 1994 N/A 23.4+8*31.2+23.4 31.2 1.56 20 (Janberg 2009)
Rudolphstein
Bridge #20 at Hwy 16.4+23.2+21.9+31.4+24.
64 Canada CIP on falsework 31.4 0.99 31.7 (Holowka 1979)
401/427 Interchange 4= 117
Spadina Ave. Bridge #5, 15.24+2*32+23.17+32+1 Department of Highways Ontario
65 Canada 1963 CIP on falsework 32 0.914 35
Hwy 401 5.2 = 149.655 Drawing from Gauvreau
19.96+34.08+29.56+27.8
Spadina Ave. Bridge #11 8+36.57+34.13+25.50+26 Department of Highways Ontario
66 Canada 1963 CIP on falsework 38.1 1.27 30
Hwy 401 .43+38.1+2*35.05+36.27 Drawing from Gauvreau
+36.2+36.5+25.603 = 477
Spadina Ave. Bridge #22, 18.2+38.7+23.1+20.2+34. Department of Highways Ontario
67 Canada 1963 CIP on falsework 38.7 1.27 30.5
Hwy 401 4+18.2 = 153 Drawing from Gauvreau
Spadina Ave. Bridge #23, 27.4+36.5+39.6+27.432 = Department of Highways Ontario
68 Canada 1963 CIP on falsework 39.62 1.27 31.2
Hwy 401 131 Drawing from Gauvreau
Designer: Wolfgang Linder
69 Hundschipfen Bridge Switzerland 2000 N/A 40.465 40.46 1 40.5
(Janberg 2009)
70 McCowan Road Underpass Canada CIP on falsework 36+45.1+36=117 45.1 1.52 29.7 (Meades and Green 1974)
Spadina Ave. Bridge #24, 22.86+45.72+22.86 = Department of Highways Ontario
71 Canada 1963 CIP on falsework 45.72 1.37 33.4
Hwy 401 91.44 Drawing from Gauvreau
Spadina Ave. Bridge #4, 28.042+47.549+24.984 = Department of Highways Ontario
72 Canada 1963 CIP on falsework 47.54 1.372 34.7
Hwy 401 100.575 Drawing from Gauvreau

117
A.3 Precast Segmental Span-by-Span Box-Girder
Table A-5. Cross-sectional drawings for precast segmental span-by-span box-girders in Chapter 2
Bridge no. Cross-section Bridge no. Cross-section Bridge no. Cross-section
73 78 83

75 79 84

76 80 & 81 85

77 82 86

Table A-6. Precast segmental span-by-span box-girders in Chapter 2


Bridge Name Location Completion Construction Span arrangement (m) Span Depth Span-to- Reference
no. year method length h (m) depth
L (m) ratio L/h
Bukit Panjang LRT System Segmental span-
73 Singapore
801 1998 by-span Total length =7715.24 34 2.16 15.7 DEAL Job Report (Segmental Bridge Data)
Segmental with 27.5+21*36.85+27.5 =
74 Wiscasset Bridge U.S.A.
1981 launching girder 829 36.85 2.1 17.5 (Janberg 2009)
75 Chiovano Viaduct Italy 1993 Segmental 39+18*39+39 = 780 39 2.3 17 DEAL Job Report (Segmental Bridge Data)
76 Collecastino Viaduct Italy 1991 Segmental 39+25*39+39 = 1053 39 2.3 17 DEAL Job Report (Segmental Bridge Data)
77 Fiumetto Viaduct Italy 1992 Segmental 39+11*39+39 = 507 39 2.3 17 DEAL Job Report (Segmental Bridge Data)
78 San Leonardo Viaduct Italy 1992 Segmental 39+5*39+39 = 273 39 2.3 17 DEAL Job Report (Segmental Bridge Data)
79 Petto Viaduct Italy 1992 Segmental 39+11*39+39 = 507 39 2.3 17 DEAL Job Report (Segmental Bridge Data)
80 Cadramazzo Viaduct Italy 1985 Balanced cantilever 2*(35+13*40+35) = 1180 40 2.4 16.67 DEAL Job Report (Segmental Bridge Data)
2*(41+18*40+40.80) =
81 Fella IX Viaduct Italy Balanced cantilever
1986 1604 40 2.4 16.7 DEAL Job Report (Segmental Bridge Data)
DEAL Job Report (Segmental Bridge
82 Malborghetto Viaduct Italy Balanced cantilever
1986 2*(40+16*45+40) = 1604 45 2.8 16.1 Data)
83 Val Freghizia Viaduct Italy 1988 Balanced cantilever (36+15*47+36) *2 = 1554 47 2.8 16.8 DEAL Job Report (Segmental Bridge Data)
84 Fella IV Viaduct Italy 1985 Balanced cantilever 2*(45+6*60+45) = 960 60 3.4 17.6 DEAL Job Report (Segmental Bridge Data)
85 Ngong Shuen Chau Viaduct China 2007 Balanced cantilever 45+4*60+45 60 3.2 18.75 (Cao et al. 2006)
Sutong Bridge Approach
86 China Balanced cantilever
(Nantong side) 2007 50+19*75 75 4 18.75 (Liu et al. 2007)

118
APPENDIX B: SUPPORTING CALCULATIONS
B.1 Flexural Strength for Bonded Tendons at ULS

εc = 3.5x10-3 α1fc’
φ a= C
c β1c
z Mr = Tz

fpy T = φpApfpy
Strain Stress Forces

This calculation is performed for a cast-in-place on falsework box-girder analysis case with span
length L of 50m and span-to-depth ratio L/h of 20.
MULS = moment demand = 53 000 kNm

Concrete properties
f’c = 50 MPa
fcr = 2.8 MPa
φc = 0.75

Prestressing tendon properties


fpy = 1670 MPa
φp = 0.95
Number of strands = 136
2
Ap = area of prestressing tendons = (136 strands)(140 mm ) = 0.019 m

Cross-sectional properties
b = width of compressive component = 15 m
d = distance from extreme compression fibre to centroid = 2.19 m
y = distance from base to centroid = 1.69 m
4
Ig = moment of inertia = 6.06 m

Flexural strength requirements


α1 = 0.85 − 0.0015f ′ c = 0.78 [CHBDC, Cl. 8.8.3]
β1 = 0.97 − 0.0025f ′ c = 0.85

T = ϕp fpy A p
= 0.95 1670 MPa 0.019m2
= 30 200 kN

T
a=
ϕc α1 f ′ c b
30 200 kN
=
0.75 0.78 50 MPa 15 m
= 0.688 m

a
z= d−
2
0.0688 m
= 2.19 m −
2
= 2.16 m

119
120

Mr = T ∙ z
= 30 200 kN 2.16 m
= 65 100 kNm

Mr = 65 100 kNm > MULS = 53 000 kNm ∴ number of tendons is sufficient

Minimum reinforcement requirement


1.2 Mcr
Mr > 𝑚𝑖𝑛 [CHBDC, Cl.8.8.4.3]
1.33 MULS

fcr Ig
1.2 Mcr = = 12 000 kNm
y
1.33 MULS = 70 500 kNm

Mr = 53 000 kNm > 1.2 Mcr = 12 000 kNm ∴ requirement is satisfied

Maximum reinforcement requirement


c
< 0.5 [Cl.8.8.4.5]
d

a 0.0688 m
c= = = 0.081m
β1 0.85
c 0.081 m
= = 0.037 < 0.5 ∴ 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡 𝑖𝑠 𝑠𝑎𝑡𝑖𝑠𝑓𝑖𝑒𝑑
d 2.91 m

B.2 Shear Strength at ULS


This calculation is performed for a cast-in-place on falsework box-girder analysis case with span
length L of 50m and span-to-depth ratio L/h of 20. The following calculation aims to find the
minimum stirrup spacing s needed to satisfy shear requirements.

VULS = shear demand = 11 300 kN


MULS = moment demand = 5330 kNm
Vp = component of prestressing force in the direction of shear = -3000 kN
Mp = prestressing moment = 8300 kNm

Concrete properties
f’c = 50 MPa
fcr = 2.8 MPa
φc = 0.75
ag = aggregate size = 10 mm

Prestressing tendon properties


fpy = 1670 MPa
φp = 0.95
Ep = 200 000 MPa
Number of strands = 136
2 2
Ap = area of prestressing tendons = (136 strands)(140 mm ) = 0.019 m
2
Aps = area of prestressing tendons in the flexural tension side = 0.568 m

Non-prestressed reinforcement properties


fy = 400 MPa
φs = 0.90
121

Es = 200 000 MPa


2
Av = area of stirrup = 0.0012 m (4-20M stirrups)
2
As = area of longitudinal non-prestressed reinforcement = 0.01 m

Cross-sectional properties
b = width of compressive component = 15 m
d = distance from extreme compression fibre to centroid = 1.31 m
h = height of section = 2.5 m
0.72 h
dv = max = 1.8 m
0.9 d
bv = minimum web width within dv = 0.938 m

sz = crack spacing parameter = dv = 1.8 m


35sz
sze = = 2.52 m
15 + a g

0.7fpu for bonded tendons


fpo = = 1300 MPa
σp,∞ for unbonded tendons

Mf
+ Vf − Vp − Aps fp0
d
εx = v = −0.003 = 0, 0 < εx < 3.0 × 10−3
2 Es As + Ep Aps

s ze
θ = 29 + 7000εx 0.88 + = 55°
2500

0.4 1300
β= = 0.148
1 + 1500εx 1000 + sze

Vc = concrete shear resistance = 2.5βϕc fcr bv dv = 3550 kN

Vr = Vc + Vs + Vp
Vs = shear resistance provided by stirrups = Vr − Vc − Vp = 10 800 kN
∅s fy A v dv cotθ
Vs =
s
Av Vs
= = 0.0238 m
s ∅s fy A v dv cotθ
Av
s= = 420 mm > 𝑚𝑖𝑛𝑖𝑚𝑢𝑚 𝑠𝑝𝑎𝑐𝑖𝑛𝑔 𝑜𝑓 300 𝑚𝑚 ∴ 𝑠 = 300 𝑚𝑚 𝑖𝑠 𝑢𝑠𝑒𝑑
0.0238 m
122

B.3 Thermal Gradient Moments


This section describes the derivations of moments and stresses due to thermal gradients.

Final curvature of bending ψ:


ε y + ε0
ψ=
y
The primary stresses:
fr y = Ec ε y − εf
= Ec ε y − α c θ y
= Ec ε0 + ψy − αc θ(y)
where αc = thermal coefficient of concrete = 10 × 10−6 /℃ [CHBDC, Cl.8.4.1.3]

Axial restraint force Pr and restraint moment Mr:


h h
Pr = fr y b y dy = Ec ε y − αc θ y b y dy
0 0
h h
Mr = fr y b y y − n dy = Ec ε y − αc θ y b y y − n dy
0 0

Note the following relationships:


yb y dy = nA

y 2 b y dy = I + n2 A

b y dy = A

Now, equate both Pr and Mr to zero because there are no external forces and internal
redundancies have been removed to make the structure statically-determinate.
First, Pr is equated to zero to obtain the final strain at elevation y=0 (ε0):

Pr = 0
h
fr y b y dy = 0
0
h
Ec ε y − αc θ y b y dy = 0
0
h
ε0 + ψy − αc θy b y dy = 0
0
h h h
ε0 b y dy + ψyb y dy − αc θyb y dy = 0
0 0 0
h
ε0 A + ψnA − αc θyb y dy = 0
0
123

h
αc
ε0 = θ y b y dy − nψ
A 0

Similarly, Mr is equated to zero to obtain the final curvature of bending ψ:

Mr = 0
h
fr y b y y − n dy = 0
0
h
Ec ε y − αc θ y b y y − n dy = 0
0
h
ε0 + ψy − αc θ y b y y − n dy = 0
0
h h h h
ε0 yb y dy − ε0 b y ndy − αc θ y b y ydy + nαc θ y b y dy
0 0 0 0
h h
+ ψy 2 b y dy − ψyb y ndy = 0
0 0
h h
ε0 nA − ε0 nA − αc θ y b y ydy + nαc θ y b y dy + ψ I + n2 A − ψn2 A = 0
0 0
h h
nαc θ y b y dy − αc θ y b y ydy + ψI = 0
0 0
h
αc
ψ= θ y b y y − n dy
I 0

To remove this incompatible rotation, restraint moment M is needed at each end of the span:

M = −Ec Iψ

This restraint moment is distributed to obtain the final moments caused by thermal gradient Mfinal.
This final moment causes secondary stresses fs:

Mfinal (y − n)
fs y =
I

The total thermal stresses that need to be considered in design checks are computed with the
following equation:

ftemp y = fr y + fs y
Mfinal (y − n)
= Ec ε0 + ψ ∙ y − αc θ(y) +
I
124

B.4 External Tendon Force


This section describes an iterative process to calculate the prestressing force P in unbonded
tendons to equilibrate external load Q at ULS.
Q

x
P P

This method requires the knowledge of prestressing steel area and effective prestress after all
losses. First, the force in the unbonded tendons is assumed to be Pi. Pi must be less than the
Q Q
yielding force Py but greater than the minimum force Pmin needed to equilibrate the external load
Q. Then the change in length due to force ∆lPF is computed using:

(Pi − P∞ )
∆lPF = l
A P EP P0
where P∞ = effective prestress force after all losses = σp,∞AP = 60%fpu AP
lP0 = length of tendon when prestress force is P∞

The change in length due to deformation ∆lPD, which is the actual length of tendon when loaded by
εc εc
Q and Pi, is also computed:
C C
∆lPD = εcP x dx
εcp= ∆εp T=Apfpy when ∆εp+εp∞>εpy εcp≠∆εp T
where εcP = concrete strain at PT level due to Q and Pi

εcpIf the two changes in length are not equal, Pi is varied εcp and the calculations are performed again.
This process is iterated until ∆lPF equals ∆lPD, and Pi at this point is theεactual =∆εp
cp, average force in the tendons
at ULS. This iterative processε is illustrated
= ∆ε = totalindeformation/undeformed
the following figure.length of tendon
cp, average p
120
εcp
εcp, average=∆εp Py
100
εp∞ PULS εp∞
εp,total = ∆εp+ εp∞ = εcp+εp∞ 80 εp,total =∆εp+ εp∞ = εcp, average+εp∞
tal tendon strain varies along the tendon length Total tendon strain remains constant along the tendon length.
Deformation ∆l∆lPF
PF
Tendon stress is averaged out between adjacent anchorages.
(mm) 60 PTherefore,
min the flexural resistance is lower at critical locations ∆l∆lPD
PD
compared to the bonded case.
40

20

0
40000 42000 44000 46000 48000 50000
-20 P (kN)
125

B.5 Total Construction Cost


The following calculation is performed for a cast-in-place on falsework box-girder with span length
L of 35m and total bridge length of 260m.

Material unit prices


Concrete = $ 1500/m3
Prestressing tendons = $ 8.5/kg
Reinforcing steel = $ 5.0/kg

Other construction costs are more dependent on the span length and are assumed to be the same
for all cases. They are computed based on the total superstructure cost of the baseline case.

Item Unit L/h


10 15 20 (baseline) 25
3
Concrete Concrete volume m 2700 2410 2260 2170
3
($ 1500/m ) Total concrete cost $ 4,050,000 $ 3,610,000 $ 3,390,000 $ 3,260,000

Prestressing Tendon length per strand m 359 359 358 358


tendon Number of strands 52 76 108 136
($ 8.5/kg) Total tendon length m 18700 27300 38700 48700
Tendon mass kg 20600 30100 42600 53600
Total prestressing tendon cost $ 175,000 $ 255,000 $ 362,000 $ 456,000

3
Reinforcing Mass of reinforcing steel per kg/m 80.0 80.0 82.0 86.1
steel concrete volume
($ 5.0/kg) Reinforcing steel mass kg 216000 193000 186000 187000
Total reinforcing steel cost $ 1,080,000 $ 963,000 $ 928,000 $ 936,000

Total superstructure cost (54.5% of total $ 5,310,000 $ 4,830,000 $ 4,680,000 $ 4,650,000


construction cost)
Other construction cost (e.g. substructure, $ 3,910,000 $ 3,910,000 $ 3,910,000 $ 3,910,000
mobilization, accessories) (45.5% of total
construction cost)
Total construction cost $ 9,240,000 $ 8,740,000 $ 8,590,000 $ 8,560,000
2
Total construction cost per deck area per m $ 2,360 $ 2,240 $ 2,200 $ 2,200
APPENDIX C: SUMMARY OF RESULTS

126
C.1 Cast-in-Place on Falsework Box-Girder
Table C-1. Summary of results of cast-in-place on falsework box-girder analysis
Span-to- Span length (m)
depth ratio 35 50 60 75
10 $ 2370 (107%) $ 2670 (109%) $ 2890 (112%) $ 3280 (111%)
4 15-strand ducts 4 19-strand ducts 4 27-strand ducts 4 37-strand ducts

15 $ 2250 (102%) $ 2490 (102%) $ 2670 (103%) $ 3030 (103%)


4 19-strand ducts 4 27-strand ducts 4 31-strand ducts 8 27-strand ducts

20 $ 2210 (100%) $ 2450 (100%) $ 2590 (100%) $ 2950 (100%)


4 27-strand ducts 8 19-strand ducts 8 27-strand ducts 8 37-strand ducts

25 $ 2200 (99.4%) $ 2450 (100%) $ 2580 (99.5%) $ 2950 (100%)


8 19-strand ducts 8 27-strand ducts 8 27-strand ducts 12 27-strand ducts

30 $ 2490 (102%) $ 2600 (100%) $ 3020 (103%)


8 37-strand ducts 8 37-strand ducts 12 37-strand ducts

35 $ 2660 (103%) $ 3220 (109%)


12 27-strand ducts 16 37-strand ducts

127
C.2 Cast-in-Place on Falsework Solid Slab
Table C-2. Summary of results of cast-in-place on falsework solid slab analysis
Span-to- Span length (m)
depth ratio 20 25 30 35
30
$ 2270 (100%) $ 2650 (100%) $ 3000 (100%) $ 3450 (100%)
10 27-strand ducts 10 27-strand ducts 12 27-strand ducts 18 27-strand ducts

35
$ 2240 (98.1%) $ 2560 (96.6%) $ 2890 (96.3%) $ 3320 (96.3%)
12 27-strand ducts 12 27-strand ducts 14 27-strand ducts 20 27-strand ducts

40
$ 2240 (98.8%) $ 2520 (95.2%) $ 2830 (94.2%) $ 3250 (94.3%)
14 27-strand ducts 14 27-strand ducts 18 27-strand ducts 22 27-strand ducts

45
$ 2860 (95.4%) $ 3280 (95.1%)
20 27-strand ducts 24 27-strand ducts

128
C.3 Precast Segmental Span-by-Span Box-Girder
Table C-3. Summary of results of precast segmental span-by-span box-girder analysis
Span-to- Span length (m)
depth ratio 30 40 50
15
$ 2380 (100%)
$ 2040 (100%) $ 2280 (100%)
6 37-strand ducts
6 27-strand ducts 6 37-strand ducts

20
$ 2250 (98.6%) $ 2350 (98.4%)
$ 2040 (100%)
8 37-strand ducts 8 37-strand ducts
6 37-strand ducts

25
$ 2280 (100%) $ 2390 (100%)
8 37-strand ducts 9 37-strand ducts

129
130

C.4 Sensitivity with Respect to Changes in Construction Cost Breakdown


$8,000

Cost variation Superstructure as % of


total construction cost
0.1% (3.4%)
20%

$6,000

Total construction
cost per deck area 0.2% (5.2%)
30%
($/m2)
$4,000
0.3% (6.9%)
40%
0.3% (8.6%)
0.4% (9.0%) 50%
0.4% (10%) 54.5% (Menn)
0.5% (12%) 60%
$2,000 0.5% (14%) 70%
80%

$0
0 5 10 15 20 25 30 35
L/h
Figure C-1. Cast-in-place on falsework box-girder with L=50m
$8,000 Superstructure as % of
Cost variation
total construction cost
1.7% (1.7%) 20%

$6,000

Total construction
cost per deck area 2.6% (2.6%)
($/m2) 30%

$4,000
3.4% (3.5%) 40%
4.3% (4.5%) 50%
4.8% (5.0%) 54.5% (Menn)
5.1% (5.4%) 60%
$2,000 6.0% (6.4%) 70%
6.8% (7.3%)
80%

$0
25 30 35 40 45
L/h
Figure C-2. Cast-in-place on falsework solid slab with L=25m
131

$8,000

Superstructure as % of
Cost variation total construction cost
20%
0.3% (0.8%)
$6,000

Total construction
cost per deck area
($/m2)
0.5% (1.3%) 30%
$4,000

0.6% (1.7%) 40%

0.8% (2.1%) 50%


0.8% (2.3%) 54.5% (Menn)
$2,000 0.9% (2.5%) 60%
1.1% (3.0%) 70%
1.2% (3.4%) 80%

$-
10 15 20 25 30
L/h
Figure C-3. Precast segmental span-by-span box-girder with L=40m

You might also like