TNB (Tenaga National Bhd.) 1 TNB Substation Trenches Details Submitted Approved (Upon Approval of Building Plan) Approved 2 TNB Power Supply Application (Upon Submitted Approved Approval of Building Plan) Approved 3 TNB Trenches Inspection Letter Submitted TNB substation work start January 2018 tentatively. (Upon trenches form work TNB Visited To submit after trenches completion) form work done. 4 TNB Substation Handover and Submitted Inspection Complete Handover (Upon TNB Substation overall work completion) 5 Contractor A Form Submission and Submitted TNB E Application for Developer Approved/Registered 6 TNB A Form, 20k BG, Land Geran and Surveyor Plan Submission Submitted (Before completion of project to form land transfer agreement of substation) 7 TNB Contribution Obtained (Contractor A Form and TNB E Informed Client Application of Developer must be Contribution Payment completed for TNB Contribution Payment) 8 TNB MSC MCCB Setting Letter Submitted Approved 9 TNB Meter Installation Meter Deposit Calculation Meter Deposit Payment Meter Installation 10 TNB Clearance Letter Submitted (Upon completion of all TNB cable Obtained laying/cable termination works.)