Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

No.

Authority Submission Check List Status Remark


TNB (Tenaga National Bhd.)
1 TNB Substation Trenches Details Submitted Approved
(Upon Approval of Building Plan) Approved
2 TNB Power Supply Application (Upon Submitted Approved
Approval of Building Plan) Approved
3 TNB Trenches Inspection Letter Submitted TNB substation work start
January 2018 tentatively.
(Upon trenches form work TNB Visited To submit after trenches
completion) form work done.
4 TNB Substation Handover and Submitted
Inspection Complete Handover
(Upon TNB Substation overall work
completion)
5 Contractor A Form Submission and Submitted
TNB E Application for Developer Approved/Registered
6 TNB A Form, 20k BG, Land Geran and
Surveyor Plan Submission Submitted
(Before completion of project to
form land transfer agreement of
substation)
7 TNB Contribution Obtained
(Contractor A Form and TNB E Informed Client
Application of Developer must be Contribution Payment
completed for TNB Contribution
Payment)
8 TNB MSC MCCB Setting Letter Submitted
Approved
9 TNB Meter Installation Meter Deposit Calculation
Meter Deposit Payment
Meter Installation
10 TNB Clearance Letter Submitted
(Upon completion of all TNB cable Obtained
laying/cable termination works.)

You might also like